Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Zillion Infraprojects Private Limited vs Bridge And Roof Company India Limited
2026 Latest Caselaw 84 Cal/2

Citation : 2026 Latest Caselaw 84 Cal/2
Judgement Date : 15 January, 2026

[Cites 12, Cited by 0]

Calcutta High Court

Zillion Infraprojects Private Limited vs Bridge And Roof Company India Limited on 15 January, 2026

                      IN THE HIGH COURT AT CALCUTTA
                          (COMMERCIAL DIVISION)
                              ORIGINAL SIDE


                         RESERVED ON: 17.12.2025
                         DELIVERED ON: 15.01.2026
                                  PRESENT:
                       HON'BLE JUSTICE GAURANG KANTH
                              AP-COM 913 OF 2025
                   ZILLION INFRAPROJECTS PRIVATE LIMITED
                                  VERSUS
                    BRIDGE AND ROOF COMPANY INDIA LIMITED

Appearance:

Mr. Kishore Datta, Sr. Adv.
Mr. Soumen Das, Adv.
Ms. Aseyaa Chowdhury, Adv.
Mr. Altamas Alim, Adv.
                                                       ..... for the petitioner

Mr. Shounak Mukhopadhyay, Adv.
Mr. Amit Mehria, Adv.
Ms. Paramita Banerjee, Adv.
Mr. Rohan Raj, Adv.
Mr. Yash Mahmia, Adv.
                                                       ..... for the respondent

                                   JUDGMENT

Gaurang Kanth, J.:-

1. The Petitioner, by way of the present Petition under Section 34 of the

Arbitration and Conciliation Act, 1996 ("the Act"), has assailed the interim

arbitral award dated 28.08.2025 passed by the learned Sole Arbitrator,

whereby Claim Nos. 2 to 9 raised by the Petitioner were held to be barred by

limitation.

2. At the outset, learned counsel appearing for the Respondent raised a

preliminary objection with regard to the maintainability of the present

petition. Accordingly, the present judgment is confined solely to the

adjudication of the said preliminary objection.

3. The material facts necessary for the disposal of the preliminary objection

raised by the Respondent are set out hereinafter.

4. The present petition arises out of a tender issued for the structural works in

respect of the Alumina Refinery Project of Utkal Alumina International

Limited (UAIL) at Rayagada, Odisha. UAIL awarded the structural and

pipeline works to the Respondent, who, in turn, subcontracted the said

works to the Petitioner. The total contractual value of the subcontract works

was Rs. 11,82,90,150/-. There was a delay of 419 days in the completion of

the works, which, according to the Petitioner, was occasioned by defaults

attributable to the Respondent. Due to the non-payment of the outstanding

dues, the Petitioner invoked the arbitration clause. Upon a petition filed by

the Petitioner under Section 11 of the Act, this Court constituted the Arbitral

Tribunal. The Petitioner thereafter filed its Statement of Claim seeking an

award of Rs. 3,01,78,450/- under nine distinct heads.

5. The Respondent filed an application under Section 16 of the Act, contending

that Claim Nos. 2 to 9 raised by the Petitioner in the Statement of Claim

were barred by limitation.

6. By an interim award dated 28.08.2025, the Arbitral Tribunal allowed the

said application and held that Claim Nos. 2 to 9 raised by the Petitioner were

barred by limitation.

7. Aggrieved by the interim award dated 28.08.2025, the Petitioner has

preferred the present petition under Section 34 of the Act, assailing the said

interim arbitral award.

Submission on behalf of the Respondent

8. Mr. Shounak Mukhopadhyay, learned senior counsel for the Respondent

contended that, by the impugned interim award, the learned Sole Arbitrator

allowed the Respondent's application under Section 16 read with Section 17

of the Arbitration and Conciliation Act, 1996, and rejected Claim Nos. 2 to 9

of the Petitioner on the ground of limitation. It was submitted that such

determination constitutes a jurisdictional ruling within the meaning of

Section 16 of the Act. Consequently, according to the Respondent, the

statutory remedy available to the Petitioner lies by way of an appeal under

Section 37(2) of the Act, and not by invocation of Section 34 of the Act. In

support of this contention, reliance was placed on the judgments of the

Hon'ble Supreme Court in Deep Industries Ltd. v. ONGC reported as (2020)

15 SCC 706, Uttarakhand Purva Sainik Kalyan Nigam Limited v.

Northern Coalfields Limited, reported as (2020) 2 SCC 455, as well as the

decision of the Hon'ble Division Bench of this Court in Board of Trustees

for the Shyama Prasad Mukharjee Port v. Marincraft Engineers Pvt.

Ltd., APO 60 of 2022.

Submission on behalf of the Petitioner

9. Mr. Kishore Datta, learned Senior Counsel appearing for the Petitioner,

however, controverted the aforesaid objection. It was submitted that, by

virtue of the impugned award, the learned Sole Arbitrator has finally and

conclusively rejected Claim Nos. 2 to 9 raised by the Petitioner. It was argued

that, insofar as the said claims are concerned, the arbitral proceedings stand

terminated, and the impugned order, to that extent, amounts to a final

adjudication of the rights of the parties. Consequently, it was contended that

the impugned order answers the description of an "interim award" within the

meaning of Section 2(1)(c) of the Arbitration and Conciliation Act, 1996, and

is, therefore, amenable to challenge under Section 34 of the Act. In support

of the said contention, reliance was placed on the judgments of the Hon'ble

Supreme Court in BSNL v. Nortel Networks India Pvt. Ltd., reported as

(2021) 5 SCC 738, and Indian Farmers Fertilizers Co-operative Ltd. v.

Bhadra Products, reported as AIR 2018 SC 62.

Legal Analysis

10. This Court has considered the rival submissions advanced by the learned

counsel for the parties on the issue of maintainability and has perused the

judgments relied upon by them.

11. The preliminary objection raised by the Respondent necessitates an

examination of the true nature and legal character of the impugned order

dated 28.08.2025, and, consequently, the determination of the appropriate

statutory remedy available to the Petitioner under the scheme of the Act.

12. At the outset, it is well settled that the nomenclature assigned to an order by

the arbitral tribunal is not determinative; rather, it is the substance and

effect of the order that governs the issue of maintainability. The Court must

therefore ascertain whether the impugned determination is in the nature of a

jurisdictional ruling under Section 16 of the Act, amenable to an appeal

under Section 37(2), or whether it constitutes an interim award finally

deciding certain claims, thereby attracting a challenge under Section 34.

13. The Arbitral Tribunal while deciding the said application, held as under:

"It is clear to this Ld. Tribunal that since Claim No. 2 to 9 do not form part of the final and RA Bills pertaining to the Claim No. 1 and are separately distinguishable, the bar of limitation would apply, having expired three years, from the date of completion of the project on 30.10.2013, i.e, on and by 30.10.2016. Since the limitation expired much prior to the imposition of the Moratorium on 5th February, 2019, the Claim Nos 2 to 9 are precluded from obtaining the benefit of such Moratorium. This Tribunal is of the further view that Clause 35.1 of the GCC stating, inter alia, that the contract would be alive, would have arguably applied to Claim No. 2 to 9 if and only if (vide Table at paragraph B supra) comprising the totality of Claim No. 2 to 9 were not part of the Final Bill and RA Bills raised separately in this arbitration."

14. A plain reading of the aforesaid extract demonstrates that the Arbitral

Tribunal has not merely returned a prima facie or procedural finding, but

has undertaken a substantive adjudication on the issue of limitation, leading

to the outright rejection of Claim Nos. 2 to 9. The Tribunal has recorded a

definitive conclusion as to the commencement and expiry of the period of

limitation, rejected the applicability of the moratorium, and further

construed Clause 35.1 of the GCC to hold that the said claims stood

excluded from its protective ambit. The consequence of such determination

is that, insofar as Claim Nos. 2 to 9 are concerned, the rights of the parties

stand finally determined, leaving nothing further to be adjudicated by the

Tribunal in respect thereof.

15. The Respondent has placed reliance on the decisions of the Hon'ble Supreme

Court in Deep Industries Ltd. (supra) and Uttarakhand Purva Sainik

Kalyan Nigam Limited (supra) to contend that judicial interference at an

interlocutory stage of arbitral proceedings must be minimal and that orders

passed under Section 16 are specifically appealable under Section 37,

thereby impliedly excluding recourse under Section 34. In Deep Industries

Ltd. (supra), the Hon'ble Supreme Court underscored the legislative intent of

restricting court intervention during the pendency of arbitral proceedings

and cautioned against entertaining challenges that would derail the arbitral

process. Similarly, in Uttarakhand Purva Sainik Kalyan Nigam Limited

(supra), the Hon'ble Supreme Court reiterated that a party aggrieved by a

jurisdictional ruling of the arbitral tribunal must ordinarily avail the remedy

prescribed under Section 37, and that courts ought not to bypass the

statutory framework. Similarly, the decision of the Hon'ble Division Bench of

this Court in Board of Trustees for the Shyama Prasad Mukharjee Port

(supra), reiterates that orders passed by the arbitral tribunal which do not

finally determine the rights of the parties are ordinarily not amenable to

challenge under Section 34 of the Act.

16. There can be no quarrel with the aforesaid propositions. However, the said

judgments proceed on the premise that the order under challenge is a pure

jurisdictional ruling, whereby the arbitral tribunal either accepts or rejects

its competence to adjudicate the dispute, without finally determining the

substantive rights of the parties.

17. On the other hand, the Petitioner has relied upon the decisions of the

Hon'ble Supreme Court in Indian Farmers Fertilizers Co-operative Ltd.

(supra) and Nortel Networks India Pvt. Ltd. (supra), which elucidate the

legal contours of an "interim award" under Section 2(1)(c) of the Act. In

Indian Farmers Fertilizers Co-operative Ltd. (supra), the Hon'ble

Supreme Court authoritatively held that a determination on limitation which

finally disposes of a claim is not merely a procedural or interlocutory order,

but partakes the character of an interim award, since it conclusively

adjudicates the rights of the parties in respect of that claim. The Court

observed that when an arbitral tribunal decides an issue of limitation in a

manner that results in the rejection of claims, such determination is final

insofar as those claims are concerned.

18. The aforesaid principle was further reinforced in Nortel Networks India

Pvt. Ltd. (supra), wherein the Hon'ble Supreme Court held that a finding on

limitation that results in the termination of arbitral proceedings with respect

to certain claims constitutes an interim award amenable to challenge under

Section 34. The Court clarified that the decisive test is whether the order

finally determines the rights of the parties with respect to the subject-matter

of the claim, and not whether the arbitral proceedings continue in respect of

the remaining claims.

19. Applying the aforesaid principles to the facts of the present case, it is evident

that the impugned interim award does not merely decide the competence of

the arbitral tribunal in abstract terms. By allowing the Respondent's

application and holding Claim Nos. 2 to 9 to be barred by limitation, the

learned Sole Arbitrator has finally and conclusively rejected the said claims,

resulting in the termination of arbitral proceedings insofar as those claims

are concerned. No further adjudication survives in respect thereof.

20. While it is true that the objection was raised under Section 16 of the Act, the

mere invocation of Section 16 cannot be determinative of the nature of the

order. Once the tribunal's determination transcends a threshold

jurisdictional enquiry and culminates in the final disposal of substantive

claims, the order ceases to be interlocutory in nature and assumes the

character of an interim award within the meaning of Section 2(1)(c) of the

Act.

21. In such circumstances, the statutory appeal under Section 37(2) would not

be an efficacious or appropriate remedy, as Section 37 is designed to address

orders either accepting or rejecting jurisdiction at a preliminary stage, and

not awards, whether interim or final, that conclusively determine claims. The

Act expressly provides that an arbitral award, including an interim award,

may be challenged only under Section 34, and no appeal is maintainable

therefrom save as expressly provided.

22. Accordingly, this Court is of the view that the judgments relied upon by the

Respondent operate in a distinct factual and legal context, where the arbitral

tribunal had not finally adjudicated upon the claims themselves. In contrast,

the ratio laid down in Indian Farmers Fertilizers Co-operative Ltd. (supra)

and Nortel Networks India Pvt. Ltd. (supra) squarely applies to the present

case, where the impugned order results in the irreversible extinguishment of

Claim Nos. 2 to 9.

23. In view thereof, this Court is of the considered view that the impugned order,

to the extent it rejects Claim Nos. 2 to 9, partakes the character of an

interim award and is amenable to challenge under Section 34 of the

Arbitration and Conciliation Act, 1996. The preliminary objection raised by

the Respondent as to the maintainability of the present petition is therefore

rejected.

24. Upon rejection of the preliminary objection, list the matter in the monthly

list of March, for consideration on merits.

25. Both parties are at liberty to file the additional documents which were part of

the Arbitral Records.

(GAURANG KANTH, J.)

SAKIL AMED P.A.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter