Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shetgiri & Associates vs Bank Of India & Anr
2025 Latest Caselaw 2856 Cal/2

Citation : 2025 Latest Caselaw 2856 Cal/2
Judgement Date : 28 October, 2025

Calcutta High Court

Shetgiri & Associates vs Bank Of India & Anr on 28 October, 2025

Author: Amrita Sinha
Bench: Amrita Sinha
                                                                           2025:CHC-OS:209
                          IN THE HIGH COURT AT CALCUTTA
                            Constitutional Writ Jurisdiction
                                     Original Side

Present :- Hon'ble Justice Amrita Sinha


                                  WPO 730 of 2025

                                Shetgiri & Associates
                                         Vs.
                                Bank of India & Anr.

For the writ petitioner             :-   Mr. Vibhakar Mishra, Adv.
                                         Mr. Ajay Chaubey, Adv.
                                         Mr. Vinayak Chaubey, Adv.
                                         Ms. Ritika Pipalwa, Adv.
                                         Mr. Prabhat Kumar, Adv.
                                         Mr. Utkarash Mishra, Adv.
                                         Ms. Ahona Majumder, Adv.

For the respondent                  :-   Mr. Debashis Saha, Adv.

Mr. Avirup Roy Sanyal, Adv.

Ms. Sucheta Pal, Adv.

Heard on                            :-   28.10.2025

Judgment on                         :-   28.10.2025


Amrita Sinha, J.:-

1. The petitioner is aggrieved by the cancellation of the tender process in

which it participated and emerged as the L-1 bidder. The cancellation

was communicated to the petitioner by a communicating letter dated

22nd July, 2025. The letter of cancellation mentions that due to some

technical reasons in the tender, the bank has decided to go for re-

tendering for the same. Necessary information will be published in the

newspaper, Bank's website and MSTC-E-tendering portal.

2025:CHC-OS:209

2. Learned advocate for the petitioner submits that the cancellation is

mala fide, arbitrary and bad in law. According to the petitioner, the

authority inspected the site in question and was satisfied with the

performance of the petitioner. After declaring the petitioner as L-1

bidder, the authority ought not to have cancelled the tender process.

3. It has been submitted that no reason has been prescribed for

cancellation of the tender process which stood concluded declaring the

petitioner as the L1 bidder.

4. Learned advocate for the petitioner relies on the judgment delivered by

the Hon'ble Supreme Court in the matter of Subodh Kumar Singh

Rathour Vs. Chief Executive Officer and Others reported in 2024

SCC OnLine SC 1682 paragraphs 123, 125 and 127. Relying on the

ratio laid down in the above decision it has been submitted that the

public authority ought to maintain the sanctity of tenders in public

private procurement processes. Public tenders are designed to provide a

level playing field for all potential bidders. The integrity of this process

ensures that public projects and services are delivered efficiently and

effectively, benefiting the society at large. The sanctity of contracts is a

fundamental principle.

5. The special reliance has been placed on the observation of the Hon'ble

Supreme Court mentioning that when public authorities enter into

contracts, they create legitimate expectations that the State will honour

its obligations. Arbitrary and unreasonable terminations undermine

2025:CHC-OS:209 these expectations and erode the trust of private players from the public

procurement processes and tenders.

6. Reliance has also been placed on the judgment delivered by the Hon'ble

High Court of Orissa, Cuttack on 8th September, 2017 in W.P.(C) No.

5272 of 2017 in the matter of M/s. Sical Logistics Ltd. Vs. Mahanadi

Coalfields Limited and others wherein the Court was of the opinion

that in view of the Central Vigilance Commission guidelines, the tender

accepting authority is not free to take any decision in an arbitrary

manner and is bound to record clear and logical reasons for any action

of rejection/recall of tenders.

7. Prayer has been made restraining the authority from floating fresh

tender and to direct the authority to award the contract in favour of the

petitioner.

8. Learned advocate representing the bank submits, upon instruction that,

the tender process was cancelled because of technical reasons. The fact

of cancellation has been made known to all the participants. The

participants have been intimated that they would be at liberty to

participate in the next tender that will be floated.

9. Learned counsel for the respondents relies on the decision delivered by

the Hon'ble Supreme Court in the matter of Principal Chief

Conservator of Forest and Others Vs. Suresh Mathew and Others

reported in 2025 SCC OnLine SC 933 paragraphs 20 and 21.

10. Learned counsel refers to the clause in the form for application in the e-

tendering process wherein it has been mentioned that the bank has

2025:CHC-OS:209 reserved the right to select or reject any or all the applications received

without any reason whatsoever. It has been submitted that because of

technical reasons, despite declaration of the L-1 bidder, the bank was

compelled to cancel the entire tender process.

11. Learned counsel for the bank submits, upon instruction that, notice of

re-tender was floated but the petitioner did not participate in the same.

Today, i.e. 28th October, 2025, is the date for opening of the bids.

12. I have heard the submissions made on behalf of both the parties and

have perused the documents placed before the Court.

13. Admittedly, in the instant case the petitioner was communicated the

reason for cancellation of the tender process. The authority found that

due to technical reasons in the said tender the same had to be cancelled

and decision was taken to re-tender the same. The petitioner, though

participated in the initial tender process, but for reasons best known,

did not participate in the re-tender process. The date for opening the

bids of the subsequent tender is today.

14. Though a participant legitimately expects that after emerging as the

successful bidder, the work order and the contract would be issued but

there may be genuine and valid reasons for the authority to cancel the

process and thereafter take decision whether and when to issue the

notice of re-tender.

15. Cancellation of a tender due to technical reasons is an internal policy

decision of the tender inviting authority. Till it is proved with sufficient

documents that the cancellation was indeed illegal and arbitrary, the

2025:CHC-OS:209 Court usually refrains from exercising judicial discretion in the matter.

Making out a case that the tender process was cancelled so as to

provide benefit or advantage to any other favourable candidate of the

authority may be a ground to exercise judicial review. No case of mala

fide exercise of power by the authority has been made out in the instant

writ petition.

16. Mere arriving at a decision that the petitioner is the L-1 bidder did not

create any right in favour of the petitioner for issuance of work order

and execution of the contract in between the parties. No positive

decision or action was taken by the authority in furtherance of the

declaration of the petitioner as the L1 bidder. On the contrary, due to

technical reasons the entire tender process got cancelled and the

cancellation was duly informed to all the participants. Notice of re-

tender was floated but the petitioner chose not to participate in the

process of re-tender. The petitioner cannot claim to be prejudiced due to

cancellation of the tender process as no further step was taken by the

authority after declaration of the result of the bid.

17. Had the work order been issued in favour of the petitioner and contract

been executed between the parties and thereafter the same cancelled

without assigning any reason, then the ratio laid down by the Hon'ble

Supreme Court in the matter of Subodh Kumar Singh Rathour (supra),

as relied upon by the petitioner, could have been applied.

18. In Subodh Kumar Singh Rathour (supra) the Court clearly laid down

that when public authorities enter into contracts, the State ought to

2025:CHC-OS:209 honour its obligations. In the instant case, the stage of entering into

contract between the parties did not arise at all. It was only after

declaration of the result of the bid that the bank detected technical

errors/ defects/ lapses and cancelled the entire tender process. The

bank also went to the extent of communicating the fact of cancellation

of the tender process to all the participants.

19. In M/s. Sical Logistics Ltd. (supra) the Court observed that there was an

obligation for recording clear and logical reasons for rejection/recall of

tender in accordance with Central Vigilance Commission guidelines. In

the instant case, the ground for cancellation of the tender process -

'technical reason', was communicated to all the participants. It is not

that no reason for cancellation was communicated. It may be that the

reason was not a detailed one, but at least, some reason was mentioned

for cancellation of the tender process.

20. Had the petitioner been genuinely aggrieved by the cancellation of the

tender process, then the petitioner ought to have rushed to the Court

immediately after communication of the cancellation on 22nd July, 2025.

It appears that the writ petition was filed only on 16th September, 2025.

By now, the bank has proceeded with the re-tender process and today is

the date fixed for opening the bids.

21. The Hon'ble Supreme Court in the matter of Suresh Mathew and Others

(supra) laid down that the equal opportunity to be given to the bidders

so that there would be fair play between them. Here, all the participants

were intimated about the reason for cancellation of the tender process

2025:CHC-OS:209 and everybody had the opportunity to participate in the re-tendering

process. The petitioner, in its discretion, did not avail the opportunity to

participate in the re-tender process.

22. There is no order passed by any competent forum restraining the bank

from proceeding with the re-tender process. The bank has, accordingly,

proceeded with the same and will take necessary steps to conclude the

same provided the process is in accordance with law. If the bank notices

any further discrepancy in the process of re-tender, the bank will take

necessary steps as per law.

23. The Court is not convinced that any legal right, far less; constitutional

or statutory right of the petitioner has been infringed by the act of the

respondent authority in any manner whatsoever. It does not appear that

the act of the authority is palpably arbitrary or illegal requiring

interference. The Court is not inclined to exercise the power of judicial

review in the instant case.

24. The writ petition, accordingly, fails and is hereby dismissed.

25. No costs.

26. Urgent photostat certified copy of this order, if applied for, be supplied

to the parties upon compliance of all legal formalities.

(Amrita Sinha, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter