Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Buildstar Infra Private Limited vs Utkarsh India Limited
2025 Latest Caselaw 1762 Cal/2

Citation : 2025 Latest Caselaw 1762 Cal/2
Judgement Date : 16 June, 2025

Calcutta High Court

Buildstar Infra Private Limited vs Utkarsh India Limited on 16 June, 2025

Author: Arijit Banerjee
Bench: Arijit Banerjee
OCD-10
                                  ORDER SHEET

                                AD-COM/2/2025
                                       WITH
                               CS-COM/432/2024
                      IN THE HIGH COURT AT CALCUTTA
                         Commercial Appellate Division
                               ORIGINAL SIDE

                     BUILDSTAR INFRA PRIVATE LIMITED
                                   VS
                          UTKARSH INDIA LIMITED

  BEFORE:
  The Hon'ble JUSTICE ARIJIT BANERJEE
                 AND
  The Hon'ble JUSTICE RAI CHATTOPADHYAY
  Date : 16th June, 2025.

                                                                          Appearance:
                                                      Mr. Rabindra Kumar Mitra, Adv.
                                                               Mr. Sourjya Das, Adv.
                                                         Ms. Poulami Bhowmick, Adv.
                                                                   ..for the appellant

                                                             Mr. Chayan Gupta, Adv.
                                                       Mr. Souryadeep Banerjee, Adv.
                                                             Mr. Dwip Raj Basu, Adv.
                                                                  ..for the respondent


                              Dictated by Arijit Banerjee, J.

The Court: This appeal is directed against a judgment and order dated

September 10, 2024, whereby the respondent's application for judgment upon

admission to the tune of Rs.25,20,606/- was allowed by a Learned Judge of

this Court along with interest at the rate of 18% per annum from May 1, 2021,

till realisation of the said amount.

The relevant facts of the case are that the respondent/plaintiff is engaged

in, inter alia, the business of manufacture and sale of Steel Structures, Crash

Barriers, Steel ERW Pipes etc., of diverse specifications. The

appellant/defendant is engaged in the manufacture and sale of construction

equipment including crash barriers of diverse specifications.

It appears that pursuant to negotiation, an agreement/arrangement was

arrived at between the parties hereto for supply of crash barriers along with

allied accessories by the plaintiff to the defendant as per the verbal purchase

orders placed by the defendant on the plaintiff. It, further, appears that the

defendant placed several orders on the plaintiff and received supply of the

relevant products. The parties appear to have maintained a running and

continuous account. Ad hoc payments were made from time to time by the

defendant to the plaintiff, which were adjusted in the running accounts.

It appears that on April 23, 2021, the defendant paid a sum of Rs.8.50

lakh to the plaintiff. Out of the said sum, an amount of Rs.12,195/- was

adjusted against the pending dues of the plaintiff and the balance

Rs.8,37,805/- was adjusted against four invoices raised by the plaintiff on the

defendant during March and April, 2021. After such adjustment, a sum of

Rs.25,20,606/- remained due and payable by the defendant to the plaintiff.

The plaintiff claimed the outstanding amount. The defendant issued a

communication dated January 4, 2022. This communication is important as

the same forms the fulcrum of the plaintiff's prayer for judgment upon

admission. The communication reads thus:-

"We will clear the pending amount i.e., INR 2520606/- lying in the ledger of Utkarsh India Ltd. From Buildstar Infra Pvt. Ltd. Will be cleared maximum by 6 months. We are not be able to clear the full amount at a glance as we have a huge financial crisis. We will pay the first payment in the month of Jan'22 appx. Upto 800000/- and the balance will be paid in the specified time frame mentioned above.

In between any requirement of the materials, we will lift those with the payment at the time of lifting. Please co- operate with us to revive the situation. Thanking you"

In spite of the aforesaid communication, nothing was paid by the

defendant. The plaintiff sent reminder e-mails on June 22 and June 25, 2022.

On July 6, 2022, the plaintiff sent a legal notice to the defendant which the

latter duly received. However, no further payment was made by the defendant.

According to the plaintiff, on August 5, 2022, the defendant approached

the plaintiff with a proposal to settle the disputes amicably. According to the

plaintiff, it was decided that the defendant will pay the sum of Rs.27,50,000/-

in full and final settlement of the plaintiff's claim, in two instalments within

September 15, 2022. The defendant issued a cheque for Rs.7.50 lakh, dated

August 23, 2022, in favour of the plaintiff and apparently assured the plaintiff

that another cheque for the balance amount would be issued within September

15, 2022. The cheque for Rs.7.50 lakh, when presented for payment, was

dishonoured by reason of there being insufficient funds in the concerned bank

account of the defendant.

In the aforesaid factual matrix, the plaintiff instituted the present suit.

In the suit, the plaintiff took out an application under Order XII Rule 6 of the

Code of Civil Procedure for judgment upon admission to the tune of

Rs.25,20,606/-

The Learned Single Judge noted the rival contentions of the parties in

great detail. The Learned Judge considered the legal precedents cited on behalf

of both the parties. His Lordship came to the conclusion that there was a clear

and unequivocal admission of liability to the tune of Rs.25,20,606/- in the

defendant's letter dated January 4, 2022. Accordingly, the Learned Judge

allowed the plaintiff's application. Hence this appeal at the instance of the

defendant.

Learned counsel appearing for the appellant/defendant argued that the

letter dated January 4, 2022, cannot be considered to be an unequivocal

admission of liability by the defendant. The defendant had issued that

communication only to persuade the plaintiff not to stop supplies to the

defendant. In fact, the supplies made by the plaintiff earlier were not as per

the specifications by reason of which the defendant has suffered huge loss and

damage. Exchange of WhatsApp messages would show that the letter dated

January 4, 2022, was not meant to be an admission of the defendant's liability.

Several triable issues have been raised by the defendant and unless the order

under appeal is set aside or stayed immediately, the defendant shall suffer

irreparable loss and prejudice.

We have not called upon the respondent's counsel to make submission.

We find no apparent infirmity in the order under appeal. The

authenticity of the letter dated January 4, 2022, emanating from the

defendant, is not disputed by the defendant. The defendant attempts to offer

an explanation as to why the letter was issued, which is not acceptable to us.

As regards the defendant's contention that the plaintiff supplied defective goods

to the defendant, we do not find any contemporaneous document on record to

that effect. If indeed the plaintiff failed in its contractual obligations, vis-à-vis

the defendant, nothing stopped the defendant from recording the same by

issuing appropriate letters. The defendant should not have, in that event,

issued the admission letter dated January 4, 2022, nor should it have issued

the cheque for Rs.7.50 lakh in favour of the plaintiff.

On an overall consideration of the facts of the case and the documents

on record, we have no doubt in our mind that the communication dated

January 4, 2022 amounts to a clear and unequivocal admission of liability by

the defendant to the tune of Rs.25,20,606/-.

The provision of Order XII Rule 6 of the Code of Civil Procedure has been

promulgated by the Parliament to enable plaintiffs with genuine and

undisputed and/or admitted claims to recover their dues without going

through an unduly long process of trial of the suit. In a case where the

defendant has clearly and unconditionally admitted its liability, as in this case,

it would indeed be unfair to subject the plaintiff to a long process of trial. The

purported defence sought to be raised by the present defendant appears to be

moonshine and an attempt in desperation to try and delay payment of the

plaintiff's claim.

We do not find any reason to interfere with the judgment and order

under appeal. The Learned Judge has rightly appreciated the scope of Order

XII Rule 6 of CPC and has rightly allowed the plaintiff's application.

In view of the aforesaid, this appeal stands dismissed.

There will be no order as to costs.

(ARIJIT BANERJEE, J.)

(RAI CHATTOPADHYAY, J.)

bp

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter