Citation : 2025 Latest Caselaw 3370 Cal/2
Judgement Date : 4 December, 2025
IN THE HIGH COURT AT CALCUTTA
(COMMERCIAL DIVISION) 2025:CHC-OS:238
ORIGINAL SIDE
RESERVED ON: 13.11.2025
DELIVERED ON: 04.12.2025
PRESENT:
HON'BLE JUSTICE GAURANG KANTH
AP-COM 21 OF 2023
MANAGING DIRECTOR BIHAR STATE POWER
GENERATION CO LTD AND ANR
VERSUS
R S CONSTRUCTION AND ANR
Mr. U. P. Singh, Sr. Adv.
Mr. Kumar Manish, Adv.
Mr. S. K. Poddar, Adv.
Mr. Abin Lal Chakravarty, Adv.
..... for the petitioners
Mr. Prashant Kumar, Adv.
Ms. Bhawna Tekriwal, Adv.
..... for the respondent no. 1
JUDGMENT
Gaurang Kanth, J.:-
1. The Petitioner in the present Arbitration petition under Section 34 of the
Arbitration and Conciliation Act, 1996 is challenging the Award dated
17.09.2023 passed by the Learned Sole Arbitrator Mr. Justice D.K Seth
(Retd).
2. The facts relevant for adjudication of the present petition are as follows.
3. The Respondent was declared as the successful bidder in an e-auction
floated by the Petitioner through MMTC (proforma Respondent herein) for
the dismantling, demolition and disposal of unserviceable and obsolete
decommissioned 3 ×15 MW units of the Barauni Thermal Power Station at
Begusarai. Pursuant to the auction, the Respondent deposited a sum 2025:CHC-OS:238 of
Rs. 2,00,05,100/- on 06.12.2012, whereupon the Petitioner issued the
acceptance/sale order in favour of the Respondent.
4. As per the said contract, the Respondent had to complete the dismantling,
demolition and disposal of the said three obsolete thermal units within 356
days from the date of acceptance, i.e. by 05.12.2013.
5. Under the terms of the sale order, the total sale consideration was to be
paid in three instalments. The Respondent deposited the first instalment
on 27.12.2012, the second instalment on 25.02.2013, and the third
instalment on 25.03.2013. Consequent upon payment of the first
instalment, the Petitioner issued the first delivery order on 31.12.2012.
The site was handed over to the Respondent for the first time on
16.01.2013, and the Respondent commenced dismantling and disposal
activities pursuant to the dismantling-cum-disposal order issued by the
Petitioner.
6. During the execution of the contract, several disputes and differences
emerged between the parties. Ultimately, on 10.12.2013, the Petitioner
No.1 issued an order directing stoppage of all work.
7. It appears from the record that during the subsistence of the contract, the
Respondent repeatedly sought extension of the validity period of the
contract. The Petitioners, however, did not accede to any such request, nor
were the grievances raised by the Respondent addressed.
8. In view thereof, the Respondent thereafter invoked the arbitration clause
contained in the tender document (Buyer's Specific Terms and Conditions).
On 01.02.2014, the Respondent issued a notice invoking arbitration and
requested MMTC to appoint an arbitrator in terms of the arbitration
2025:CHC-OS:238 clause. Shri S.S. Choudhuri was appointed as the Sole Arbitrator, who
conducted the arbitral proceedings and published an award on
02.07.2019. Both parties assailed the said award before this Court. By
order dated 24.03.2022, this Court set aside the said award and appointed
Mr. Justice Dilip Kumar Seth (Retd.) as the Sole Arbitrator to adjudicate
the disputes afresh, with a direction to proceed on the basis of the
pleadings already filed by the parties in the earlier reference.
9. In compliance with the said direction, the newly appointed Sole Arbitrator
entered upon the reference and, after conclusion of the arbitral
proceedings, passed the impugned award dated 17.09.2023. By the said
award, the Sole Arbitrator awarded a sum of Rs. 29,96,18,025/- to the
Respondent together with future interest @ 9% per annum, subject to the
condition that if the awarded amount was paid within 120 days, no
interest would be payable.
10. Aggrieved thereby, the Petitioner has approached this Court by way of the
present petition under Section 34 of the Arbitration and Conciliation Act,
1996.
Submission on behalf of the Petitioner
11. Learned counsel for the Petitioner submits that the impugned award dated
17.09.2023 is liable to be set aside under Section 34(1)(a) and/or Section
34(2)(a)(iii) of the Arbitration and Conciliation Act, 1996 on the ground of
incapacity and misjoinder. It is urged that the Award has been made
against the Managing Director, Bihar State Power Generation Company
Limited and the Chairman, Bihar State Power Holding Company Limited,
persons who neither in their personal capacity nor in their official capacity
were parties to, or privy to, the arbitration agreement. Learned counsel
2025:CHC-OS:238 relies upon the pleadings to show that a specific objection as to misjoinder
was taken in the reply to the Statement of Claim but no amendment was
permitted or made in the Statement of Claim thereafter.
12. Learned counsel further points out that the first award rendered by Shri
S.S. Choudhuri, the earlier arbitrator, was an award against the Company.
That award was, by consent of the parties, set aside by this Court by order
dated 24.03.2022 and a fresh reference was directed to be adjudicated by
Mr. Dilip Kumar Seth (Retd.). Despite the setting aside of the earlier award
and the re-reference, the present Award has been rendered against
persons who were never proper parties to the arbitration.
13. Learned counsel further submits that no notice under Section 21 of the
Arbitration and Conciliation Act, 1996 was ever issued to or served upon
the Petitioners. In the absence of such mandatory notice invoking
arbitration, the arbitral proceedings stand vitiated at their very inception.
14. To support the proposition on incapacity and misjoinder, learned counsel
relied upon the judgments of the Hon'ble Supreme Court in Tata
Engineering & Locomotive Co. Ltd. Vs State of Bihar, reported as
1964 (6) SCR 885; S.N. Prasad Vs Monnet Finance Ltd., reported as
(2011) 1 SCC 320; and Deutsche Postbank Home Finance Ltd. Vs
Taduri Sridhar, reported as (2011) 11 SCC 375, West Bengal Power
Development Corporation Ltd Vs Sical Mining Ltd. pronounced on
30.09.2022, Adavya Projects Pvt Ltd Vs Vishal Structurals Pvt Ltd
reported as 2025, SCC OnlineSC 806, Vidya Drolia Vs Durga Trading
Corporation reported as 2021 (2) SCC 1.. Learned counsel submits that
the legal principles laid down in those decisions are attracted in the
present case and warrant the setting aside of the Award in question.
15. It is further contended by the Petitioner that the arbitration clause 2025:CHC-OS:238 is
narrowly worded and does not provide for reference of "all disputes arising
out of or in relation to the agreement". Reliance is placed on Oriental
Insurance Company Ltd. Vs Narbheram Power & Steel (P) Ltd.,
reported as (2018) 6 SCC 534, and United India Insurance Co. Ltd. Vs
Hyundai Engineering & Construction Co. Ltd., reported as (2018) 17
SCC 607, to submit that where the arbitration clause is restrictive in
scope, only those disputes expressly covered by the clause can be referred
to arbitration, and the Tribunal lacks jurisdiction to adjudicate issues
falling outside its explicit ambit.
16. It is next urged that the Sole Arbitrator misconstrued the contractual
timeline. Clause 7.3 of the tender documents and the acceptance
letter/sale order dated 06.12.2012 expressly provided for 365 days from
the date of the acceptance letter for taking delivery and removal of
materials by way of dismantling and demolition for all main packages; this
position is reiterated in the first Delivery Order dated 31.12.2012. On
these terms, the contractual tenure expired on 05.12.2013. The
Petitioner's stoppage-of-work order dated 10.12.2013 was therefore issued
five days after the expiry of the contractual period. Despite these clear
contract terms, the Sole Arbitrator erroneously held that the 365-day
period commenced from the date of the dismantling/demolition-cum-
disposal order on 02.04.2013/15.04.2013, and on that incorrect premise
concluded that the stoppage order was invalid and contrary to the
contract.
17. Learned counsel for the Petitioner submits that the Sole Arbitrator has
committed patent errors of fact and law by returning findings on the basis
2025:CHC-OS:238 of purported admissions that do not exist on record. It is urged that the
Arbitrator repeatedly used the expression "admittedly" to support
conclusions, despite there being no admission by the Petitioner in the
pleadings or evidence. Reliance is placed on National Textile
Corporation Ltd. Vs Naresh Kumar Badrikumar Jagad, reported as
(2011) 12 SCC 695, wherein the Supreme Court held that in the absence
of pleadings, no amount of evidence can be looked into, and any finding
based on non-existent or assumed admissions is legally unsustainable.
18. Learned counsel further submits that the Sole Arbitrator committed a
patent error in law by holding that "time was not the essence of the
contract", despite the contract expressly stipulating a defined
delivery/removal period and incorporating time bound obligations. It is
contended that the Arbitrator effectively re-wrote the terms of the contract
by unilaterally fixing 02.04.2013/15.11.2013 as the dates of
commencement of the contract, dates which find no basis in the
contractual framework and appear to have been inferred solely on the
Arbitrator's own assumptions. Reliance is placed on Indian Oil
Corporation Ltd. Vs Shree Ganesh Petroleum, reported as (2022) 4
SCC 463, and South East Asia Marine Engineering & Constructions
Ltd. Vs Oil India Ltd., reported as (2020) 5 SCC 164, wherein the
Supreme Court has reaffirmed that arbitral tribunals cannot re-write
contractual terms and must give effect to the express stipulations agreed
between the parties.
19. Learned counsel for the Petitioner submits that the Sole Arbitrator further
erred in law in concluding that a sum of Rs.14,29,22,468/- represented
the value of the materials allegedly remaining unlifted, despite the
complete absence of evidence on record to support such a determination.2025:CHC-OS:238 It
is contended that the finding is wholly conjectural and contrary to the
evidentiary record. Reliance is placed on Bharat Coking Coal Ltd. Vs
L.K. Ahuja, reported as (2004) 5 SCC 109, and Unibros Vs All India
Radio, reported as 2023 SCC OnLine SC 1366, which reiterate that
arbitral awards cannot be sustained where the findings are unsupported
by evidence or are based on mere assumptions. It is further urged that the
Sole Arbitrator erred in law in awarding interest @ 10% on the claim for
loss of profit; that rate and the manner of computation are contrary to the
ratio laid down by the Hon'ble Supreme Court and result in an award
unsupported by law and inconsistent with established principles relating
to damages and interest.
20. Finally, learned counsel submits that the Arbitrator determined the costs of
the arbitration without any evidentiary foundation and in the absence of
any pleading to justify the quantum of costs awarded. Such an exercise,
according to learned counsel, is arbitrary and contrary to law.
21. Learned counsel therefore prays that the Award dated 17.09.2023 be set
aside in its entirety as the sole Arbitrator exceeded his jurisdiction and
misconducted the proceedings.
Submission on behalf of the Respondent
22. Per contra, learned counsel for the Respondent supports the impugned
Award and submits that the Petitioner has failed to make out any ground
under Section 34 of the Arbitration and Conciliation Act, 1996, warranting
interference by this Court. It is submitted that the present Petition is
nothing but an attempt to re-argue the merits of the case, which is
impermissible in proceedings under Section 34.
2025:CHC-OS:238
23. Learned counsel for the Respondent submits that the objection regarding
misjoinder of parties is wholly misconceived. The claims were at all
material times directed against Bihar State Power Generation Company
Ltd. and Bihar State Power Holding Company, the principal contracting
entities, and the impleadment of their Managing Director and Chairman
was only in a representative capacity. No relief was sought against them in
their personal capacity, and the Award is enforceable solely against the
corporate entities. Learned Counsel places reliance on Bhupesh Rathod
Vs Dayashankar Prasad Chaurasia, reported as (2022) 2 SCC 355,
wherein the Hon'ble Supreme Court clarified that arraying a party in a
representative capacity does not vitiate the proceedings unless prejudice is
demonstrated. He further relies on OPG Power Generation Pvt. Ltd. Vs
Enexio Power Cooling Solutions India Pvt. Ltd., reported as (2025) 2
SCC 417, which reiterates that technical objections such as misjoinder
cannot defeat an otherwise valid arbitral proceeding where the real parties
to the dispute were properly before the arbitrator. Accordingly, the
objection raised by the Petitioner is without merit and deserves rejection.
24. Learned counsel further submits that the plea of absence of notice under
Section 21 is an afterthought. The Respondent states that the notice
invoking arbitration was duly issued on 01.02.2014 and was acted upon
by the Petitioner itself, as evidenced by the appointment of the first
arbitrator, Shri S.S. Choudhuri. Once the Petitioner voluntarily
participated in the proceedings and filed pleadings before both the earlier
and subsequent Arbitrators, it cannot now contend that no notice was
served. Participation in arbitration without demur constitutes valid waiver
within the meaning of Section 4 of the Act.
2025:CHC-OS:238
25. On the question of the contractual period of 365 days, learned counsel
submits that the Arbitrator's interpretation is both reasonable and
consistent with the conduct of the parties. The dismantling and demolition
work could commence only upon issuance of the dismantling-cum-
disposal order and actual handing over of the site. Therefore, the
Arbitrator correctly held that the period of 365 days would run from the
date on which effective possession and operative orders were issued. The
stop-work order dated 10.12.2013 was therefore premature and contrary
to the terms of the contract.
26. Learned counsel submits that the Petitioner's grievance regarding the
Arbitrator's use of the expression "Admittedly" is baseless. The Arbitrator
referred only to facts established either through documentary evidence or
through uncontroverted testimony. The mere use of the expression does
not vitiate the Award.
27. With regard to the issue of whether time was the essence of the contract,
learned counsel submits that the Arbitrator correctly applied the settled
principles of law. In contracts involving dismantling, demolition and
disposal of large industrial units, time is ordinarily not regarded as the
essence unless the contract expressly stipulates otherwise. No such
express stipulation exists in the present case.
28. With respect to the rate of interest, it is contended that the Arbitrator
exercised his discretion under Section 31(7) of the Act. Courts ought not to
interfere with the Arbitrator's discretion unless the rate awarded is
arbitrary or perverse, which the Petitioner has failed to demonstrate.
29. Learned counsel further argues that the fixation of costs by the Arbitrator
falls squarely within his jurisdiction under Section 31A of the Act. The
2025:CHC-OS:238 Petitioner has neither established illegality or shown any perversity in the
manner in which costs were awarded.
30. The Respondent submits that the present challenge is outside the narrow
scope of Section 34. The Hon'ble Supreme Court in Consolidated
Construction Consortium Ltd. Vs JMC Projects (India) Ltd., reported as
2025 (7) SCC 757 has reaffirmed that a court cannot re-appreciate
evidence or substitute its own view where the arbitrator's interpretation is
a plausible one. Likewise, in Ssangyong Engineering & Construction
Co. Ltd. Vs NHAI, reported as (2019) 15 SCC 131, the Hon'ble Supreme
Court held that interference is permissible only when the award is perverse
or patently illegal, not merely because another interpretation is possible. In
the present case, the learned Arbitrator has adopted a reasonable,
evidence based and commercially sensible view. The Petitioners are
essentially seeking a re-evaluation of facts and interpretation, which is
expressly impermissible under the law laid down in the above decisions.
The Award, therefore, warrants no interference.
31. Learned counsel submits that the Award is reasoned, internally consistent,
and founded on a proper appreciation of facts and evidence. No ground
under Section 34(2) or 34(2A) of the Arbitration and Conciliation Act,
1996, has been made out. Accordingly, the Petition deserves to be
dismissed.
Legal Analysis
32. This Court has heard the submissions advanced by learned counsel for
both parties and has meticulously examined the record, along with the
judicial precedents cited at the Bar. The objections raised by the
2025:CHC-OS:238 Petitioners are now considered under the respective heads outlined
hereinbelow.
Preliminary Objection Regarding Misjoinder of Parties and the Impermissible Passing of an Award Against Non-Signatories to the Arbitration Agreement.
33. The principal contention advanced by the Petitioners is that the Award
stands vitiated as it has been passed against individuals who were not
parties to the arbitration agreement, namely the Managing Director of
Bihar State Power Generation Company Ltd. and the Chairman of Bihar
State Power Holding Company Ltd. According to the Petitioners, the
impleadment of these officers, who had no privity to the arbitration clause,
renders the Award without jurisdiction.
34. This Court, upon considering the arbitral record, finds no merit in the
objection raised by learned counsel for the Petitioner. At the outset, the
Petitioners did not actively pursue this objection before the Arbitral
Tribunal. Although the issue of maintainability was framed, the Petitioners
confined their challenge to (i) the scope of the arbitration clause and (ii)
whether disputes arising after completion of the contract could be referred
to arbitration. No submissions were advanced with respect to alleged
misjoinder of parties. This omission amounts to a clear waiver of this
objection. Having failed to raise this plea at the appropriate stage, the
Petitioners cannot now be permitted to resurrect it in proceedings under
Section 34 of the Act.
35. Secondly, the pleadings unequivocally establish that the substantive
contractual relationship existed solely between the Respondent and Bihar
State Power Generation Company Ltd., while Bihar State Power Holding
Company Ltd. was arrayed as a party owing to its position as the holding
2025:CHC-OS:238 company. All claims were raised exclusively against these corporate
entities. Being juristic persons, they were necessarily represented through
their principal officers, i.e., the Managing Director and the Chairman, who
were impleaded merely in a representative capacity. Their inclusion did not
create any personal liability. The Award itself fastens liability exclusively
upon the corporate entities that were signatories to the arbitration
agreement and is neither directed against nor executable against the
individual officers in their personal capacity.
36. An examination of the relevant Supreme Court jurisprudence shows that in
Bhupesh Rathod (supra), the Court held that the impleadment of officials
in a representative capacity does not vitiate the proceedings unless specific
prejudice is demonstrated. No such prejudice has been shown in the
present case. Further, in OPG Power Generation Pvt. Ltd. (supra), the
Supreme Court reiterated that technical objections such as misjoinder or
non-joinder cannot defeat arbitral proceedings where the contracting
parties were before the arbitrator and the Award operates solely against
them. A pragmatic and non-technical approach is mandated under the
Arbitration and Conciliation Act, 1996.
37. Applying these principles, the Petitioners' argument that the Award has
been passed against "non-signatories" is untenable. The individuals named
in the arbitration were not independent parties but merely represented the
corporate entities that were privy to the arbitration agreement and were
the true subjects of the adjudication.
38. Learned counsel for the Petitioners has relied upon various judgments to
contend that arbitral proceedings can be initiated only against parties to
the arbitration agreement, and that the Managing Director and Chairman
2025:CHC-OS:238 were not such parties. This Court is in respectful agreement with the legal
principle laid down in those precedents. However, the reliance is misplaced
in the context of the present factual matrix. It is neither the Respondent's
case nor does the record suggest that arbitration was initiated against the
Managing Director or the Chairman in their personal capacity. The arbitral
proceedings were always directed against the corporate entities who were
signatories to the contract, and the officers were impleaded merely in a
representative capacity. Consequently, the cited judgments do not advance
the petitioners' case and have no application to the facts of the present
case.
39. Consequently, the contention that the Award is liable to be set aside on the
ground that it has been rendered against persons who are not parties to
the arbitration agreement is misconceived, unsupported by the record, and
contrary to established legal principles.
Objection Regarding Non-Compliance with the Mandatory Notice Requirement Under Section 21 of the Arbitration and Conciliation Act, 1996
40. Learned counsel for the Petitioner further contended that no notice under
Section 21 of the Arbitration and Conciliation Act, 1996 was issued, and
therefore the arbitral proceedings stand vitiated. This objection also
deserves rejection. The Petitioner never raised this plea before the Arbitral
Tribunal at any stage. The record indicates that arbitration was invoked by
notice dated 01.02.2014, pursuant to which the Arbitrator was appointed
in accordance with the contractual clause. The Petitioners participated
fully in the arbitral proceedings, the Sole Arbitrator rendered an Award,
and thereafter this Court on the consent of both parties set aside the
Award and appointed a fresh arbitrator. The Petitioners again participated
2025:CHC-OS:238 in the subsequent proceedings without ever raising an objection under
Section 21. Having consciously participated throughout without protest,
the Petitioner cannot now be permitted to raise this objection after the
Award has been rendered. The contention is therefore devoid of merit and
stands rejected.
Objection concerning Extension of the Contractual Timeline
41. Another point raised by the learned counsel for the Petitioners is that the
sole arbitrator misconstrued the contractual timeline. According to the
Petitioners, the Contractual period of 365 days was to be computed from
the date of issuance of the letter of acceptance, which would result in the
completion date being 05.12.2013. Whereas the Sole Arbitrator held that
the said time period of 365 days is to start from the date of issuance of the
dismantling/demolition-cum-disposal order 02.04.2013/15.04.2013.
42. This Court has carefully examined the Arbitral Award in detail. The Sole
Arbitrator analysed the issue comprehensively and arrived at his findings
upon a considered interpretation of the relevant contractual clauses.
Clause 7.3.1 of the contract stipulates that the duration of the contract
shall be 365 days from the date of issuance of the acceptance letter
and/the dismantling/demolition-cum-disposal order and/or up to the
validity period of the delivery order/release order. Further, Clause 7.3.3
provides that the contract shall remain valid up to the validity period of the
delivery order/release order or the extended period thereof, in the event
such extension is granted by the principal.
43. Having regard to these two clauses, the Sole Arbitrator observed that the
Letter of Acceptance (LOA) was not the sole basis for computing the 365-
2025:CHC-OS:238 day contractual period. The contract expressly permitted extension of time
at the discretion of the Respondent, and in the presence of such an
enabling provision, the contract could not be construed as one in which
time was the essence. The Arbitrator further held that the date of entering
into the contract is distinct from the validity period of the contract, which
is dependent upon the issuance of the acceptance letter and/the
dismantling/demolition-cum-disposal order. Consequently, the 365-day
period was required to be computed from the date of issuance of any of
these operative documents. Applying this interpretation, the Sole
Arbitrator concluded that the starting point for calculating the 365-day
period must be the date of the first dismantling/demolition-cum-disposal
order, since the buyer was contractually prohibited from commencing
dismantling/demolition activities without such an order. Prior to the said
order, the buyer had no opportunity to undertake any substantive activity
except mobilization of resources, notwithstanding that the site was handed
over on 13.01.2013. Given that the plant consisted of three units requiring
dismantling and demolition prior to removal from the site, the issuance of
the dismantling/demolition-cum-disposal order was the operative trigger.
Since the first such order was issued on 02.04.2013/15.04.2013, the sole
arbitrator correctly computed the 365-day period from that date. In light of
this well-reasoned interpretation, the Petitioner's objection to the
computation of the contractual period stands negated.
44. This Court finds that the reasoning adopted by the learned Arbitrator
constitutes a plausible and judicious view based on a proper interpretation
of the contractual clauses. No ground for interference is made out, and
hence, no intervention is warranted on this issue.
2025:CHC-OS:238 Objection concerning quantification of goods which are not lifted
45. The next objection advanced by the Petitioners is that the Learned Sole
Arbitrator erred in concluding that a sum of Rs. 14,29,22,468/-
represented the value of the materials alleged to have remained un-
uplifted, despite there being, according to the Petitioners, no evidence on
record to support such a finding.
46. This Court finds no merit in the submission advanced by learned counsel
for the Petitioner. The Learned Sole Arbitrator undertook a detailed
examination of this issue. It was noted that the underlying transaction was
a contract for the sale of goods, with the Petitioner as the seller and the
Respondent as the purchaser. The total value of materials agreed to be
dismantled and lifted under the contract was Rs. 21,21,54,087.52/-. The
Respondent led expert evidence through CW-2 to establish that materials
worth Rs. 6,99,37,000/- had in fact been lifted from the site. On the basis
of this evidence, and in the absence of any contrary evidence, the
Arbitrator concluded that the remaining materials valued at Rs.
14,29,22,468/- were lying un-lifted.
47. It is significant that no evidence whatsoever was led by the Petitioners, who
were in custody and control of the un-lifted materials, to demonstrate that
the value of the materials lying at site was different or lesser. The
Petitioners, having exclusive possession of the un-lifted goods, were in the
best position to place such evidence but failed to do so. Conversely, the
Respondent, not being in possession of the remaining goods, produced the
best possible evidence available to it, namely, the quantification of the
materials actually lifted. In these circumstances, the Arbitrator's reliance
on the Respondent's evidence was fully justified.
2025:CHC-OS:238
48. The Arbitral Tribunal also undertook a comprehensive analysis of the
contractual terms and held that the stoppage-of-work notice dated
10.12.2013 was illegal, as the 365-day contractual validity period had not
expired. The Tribunal recorded that the Respondent had already paid the
entire contract value and that its inability to lift the remaining materials
was directly attributable to obstructions created by the Petitioner. The
Tribunal further noted that although the site was formally handed over
only on 13.01.2013, the first dismantling/demolition-cum-disposal order
without which dismantling could not commence was issued only in April
2013. Thus, the Respondent could not undertake dismantling or lifting
before that date.
49. The Tribunal further observed that the Petitioner, instead of extending the
contractual period and permitting the Respondent to lift the materials for
which payment had already been made, chose to issue the stoppage-of-
work order on 10.12.2013, thereby preventing the removal of dismantled
goods. On these findings, the Arbitrator held that the Respondent was
entitled to refund of Rs. 14,29,22,468/-, being the value of the un-lifted
materials.
50. This Court finds that the conclusions drawn by the Learned Sole Arbitrator
constitute a plausible and well-reasoned view based on a proper
appreciation of evidence, including expert testimony. In a petition under
Section 34, this Court cannot re-appreciate evidence or substitute its own
conclusions for those of the Arbitral Tribunal. As the findings are neither
perverse nor contrary to the express terms of the contract, no ground for
interference is made out.
2025:CHC-OS:238 Objection concerning loss of profit and Cost of Arbitration.
51. The final objection raised by the learned counsel for the Petitioners pertains
to the award of Rs. 1,42,92,247/- towards loss of profit, which, according
to the Petitioners, has been granted in the absence of any specific
evidence. The Petitioners further challenge the award of costs, contending
that the fixation of arbitration costs lacks evidentiary basis and is
unsupported by any pleadings justifying the quantum awarded.
52. This Court has carefully examined the findings recorded in the Award. The
Arbitral Tribunal has returned a categorical finding of fact that the
Petitioner was responsible for the breach of contract. Consequently, the
Respondent became entitled to compensation/damages on account of loss
of business and loss of profit attributable to the Petitioner's breaches.
While the Tribunal noted the absence of direct evidence quantifying loss of
profit, it applied a reasonable measure by assessing loss of profit at 10% of
the value of the unlifted materials, thereby arriving at an amount of Rs.
1,42,92,247/-. This method of assessment is a recognised and judicially
accepted approach, particularly in cases involving breach by a seller in a
contract for the sale of goods.
53. With respect to costs, Section 31A(3) of the Arbitration and Conciliation
Act, 1996 expressly empowers the Arbitral Tribunal to determine the costs
of arbitration. Applying the principles underlying Section 31A, the Tribunal
found it appropriate to award the costs incurred by the Respondent in
conducting the arbitral proceedings, particularly as the Respondent had
been compelled to pursue arbitration owing to the Petitioner's refusal to
extend the time period for lifting the goods for which payment had already
2025:CHC-OS:238 been made. On this basis, the Tribunal awarded Rs. 27,76,000/- as costs
of arbitration.
54. This Court finds no infirmity in the approach adopted by the Tribunal. The
conclusions reached are based on a plausible appreciation of the facts and
the law governing quantification of damages and the award of costs. The
Petitioner has failed to demonstrate that the Tribunal's findings are
perverse, irrational, or contrary to the terms of the contract. Accordingly,
the objections raised on this ground are also rejected.
Conclusion
55. Having considered the rival submissions, examined the arbitral record,
and evaluated the findings recorded by the Learned Sole Arbitrator, this
Court is of the view that none of the objections raised by the Petitioners
fall within the limited grounds permissible for interference under Section
34 of the Arbitration and Conciliation Act, 1996. The judicial review
contemplated under Section 34 is supervisory and not appellate in nature,
and the Court cannot reappreciate evidence or substitute its own
conclusions merely because another alternative view may be possible.
56. The objections relating to alleged misjoinder of parties, absence of notice
under Section 21, erroneous interpretation of contractual clauses
governing to the validity period of the contract, assessment of the value of
unlifted materials, quantification of loss of profit, and award of arbitration
costs have all been duly considered and stand rejected. The findings of the
Arbitral Tribunal are based on a logical, reasoned, and plausible
interpretation of the contractual terms and on a proper appreciation of
both expert and documentary evidence. None of these findings can be said
to be perverse, irrational, or violative of the public policy of India.
2025:CHC-OS:238
57. This Court reiterates that an arbitral award is to be accorded finality and
minimal judicial interference is the governing principle. The Petitioners
have failed to establish that the award suffers from any patent illegality or
contravention of the fundamental policy so as to attract the provisions of
Section 34 of the Act.
58. For all the reasons discussed hereinabove, this Court holds that the
impugned award does not warrant interference. The petition under Section
34 of the Arbitration and Conciliation Act, 1996 is accordingly dismissed.
(GAURANG KANTH, J.)
Sakil Amed P.A.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!