Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Eastern Coalfields Limited And Another vs M/S. Ucc-Rla-Sta (Jv) And Others
2024 Latest Caselaw 5031 Cal

Citation : 2024 Latest Caselaw 5031 Cal
Judgement Date : 27 September, 2024

Calcutta High Court (Appellete Side)

Eastern Coalfields Limited And Another vs M/S. Ucc-Rla-Sta (Jv) And Others on 27 September, 2024

Author: T.S. Sivagnanam

Bench: T.S. Sivagnanam

MAT NO. 719 OF 2024
  REPORTABLE

           IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
                       CIVIL APPELLATE JURISDICTION
                              APPELLATE SIDE



                          RESERVED ON: 18.09.2024
                          DELIVERED ON:27.09.2024

                                  CORAM:

          THE HON'BLE MR. CHIEF JUSTICE T.S. SIVAGNANAM

                                     AND

       THE HON'BLE MR. JUSTICE HIRANMAY BHATTACHARYYA


                            MAT NO. 719 OF 2024
                                    WITH
                           I.A. NO. CAN 1 OF 2024
                                      +
                           I.A. NO. CAN 2 OF 2024
                                      +
                           I.A. NO. CAN 3 OF 2024
                                      +
                           I.A. NO. CAN 4 OF 2024


              EASTERN COALFIELDS LIMITED AND ANOTHER

                                  VERSUS

                      M/S. UCC-RLA-STA (JV) AND OTHERS

Appearance:-
Mr. Jishnu Chowdhury, Adv.
Mr. Syed Nurul Arefin, Adv.
Mr. Rahul Singh, Adv.
Mr. Syed Moyeenul Arefin

                                                     ......For the Appellants

Mr. Subhabrata Datta, Adv.
Mr. Subhojit Seal, Adv.
Mr. Aranya Saha, Adv.
                                          ......For the Respondent Nos 1 & 2

                                  Page 1 of 37
      MAT NO. 719 OF 2024
       REPORTABLE

                                       JUDGMENT

(Judgment of the Court was delivered by T.S. Sivagnanam, CJ.)

1. This intra court appeal by the respondents in WPA No. 26622 of 2023

is directed against the judgment and order dated 13.03.2024 by which the

writ petition filed by the respondent herein was allowed in part directing the

appellants to pay the writ petitioners the amount of Rs. 2,96,94,618/-

within April 12, 2024 together with interest at 8% per annum on half of the

amount that is on Rs. 1,41,47,309/- from November 30, 2022 till the date of

payment and interest at the same rate to be paid on the balance amount of

Rs. 1,48,47,309/- from May 30, 2023 till date of payment. In so far as the

rest of the claim of the writ petitioners with regard to the contract in

question, including final bills and the purported additional performance

security as well as other components, the writ petitioners were granted

liberty to make such claim by instituting a civil suit before the competent

board having jurisdiction and if so instituted the same to be decided on its

own merits in accordance with law by the said court.

2. The appellants who are the respondents in the writ petition are

aggrieved by such direction and have preferred the present appeal. The facts

leading to the filing of the writ petition could be briefly stated as hereunder:-

3. The first writ petitioner is a Joint Venture Partnership constituted

under the relevant provision of the Indian Partnership Act, 1932 and the

second writ petitioner is the constituted attorney of the Joint Venture by

virtue of a power of attorney executed in his favour. The writ petitioner

participated in a e-tender called for by the appellants as published by a

Notice Inviting Tender (NIT) dated November 25, 2014 for a estimated

MAT NO. 719 OF 2024 REPORTABLE

contract value of Rs. 190,47,08,700.00/- ps. The appellant issued a letter of

approval to the first writ petitioner dated May 04, 2015 in respect of the

awarded work and work order and subsequently the work order dated June

26, 2015 was issued. The writ petitioner's would state that during the

execution of the project the appellant's required the Joint Venture to submit

a modified offer for the project and accordingly the same was made by offer

dated March 10, 2019 which was duly approved by the appellants by

issuing a supplementary work order dated June 21, 2019.

4. The writ petitioners submitted an Additional Performance

Security/Security Deposit (TSD) of an amount of Rs. 3,03,600/-. The writ

petitioners would state that they had successfully completed the project to

the satisfaction of the appellants. By letter dated May 31, 2022, the Joint

Venture had requested the appellant's for final measurement of the contract

as per NIT. Subsequently, a supplementary work order dated June 21, 2019

was issued for an additional quantity of OB and coal. The writ petitioner

would state that they completed the entire work awarded which could be

seen from the measurement done by the appellant on October 12, 2021 and

certified by the appellant by their letter dated January 29/31, 2022. On a

request made by the writ petitioner final measurement was done on June

09, 2022 and the same was certified on June 24, 2022. By letter dated June

24, 2022 the writ petitioner requested the appellant for final of OB and coal

and finalised total excavation duly done by the writ petitioner as per the NIT

followed by the work order, supplementary work order and further work

order so that the contract can be closed as per the extant terms and

conditions. By memo dated November 19, 2022 the appellant issued job

MAT NO. 719 OF 2024 REPORTABLE

completion certificate in favour of the writ petitioner certifying that the writ

petitioner duly executed and completed the project work. The writ petitioner

by letter dated April 28, 2023 requested the appellant to take steps for

closure of the contract and to release all dues/payments to the writ

petitioner namely Performance Security cum Additional Performance

Security and retention monies at the earliest. Since the request was not

complied with a legal notice dated November 27, 2023 was issued to the

appellant calling upon them to take immediate steps for closure of the

contract and release all payments to the writ petitioner. Since the demand

made by the writ petitioners were not complied with, they had filed the writ

petition.

5. In the writ petition, the appellant prayed for a direction upon the

appellant to issue closure of contract and release pending dues, as detailed

in the Annexure P14 to the writ petitioner along with interest cost etc; to

issue a writ of prohibition prohibiting the appellant from withholding the

pending dues of the writ petitioner as detailed in Annexure P14 to the writ

petition. The respondent contended that the action of the appellant in

denying the writ petitioner for closure of the contract is wholly arbitrary,

unreasonable and illegal and completely malafide and unsustainable in the

eye of law.

6. It was contended that in the absence of any allegations against the writ

petitioner in regard to the execution of the project and no defect was also

notified by the appellant to the writ petitioner in respect of the execution of

the project work and also the defect liability period from the date of

completion of the project was also over hence the action of the appellant is

MAT NO. 719 OF 2024 REPORTABLE

arbitrary and unreasonable. By referring to the memo dated November 19,

2022, the writ petitioner contended that the appellants having accepted that

the writ petitioners satisfactorily completed the project which was also

recorded in the memo dated January 18, 2023, there was no justification for

not releasing the pending payment etc. The appellants filed their affidavit-in-

opposition in the writ petition denying and disputing the allegations made in

the writ petition. It was contended that it is incorrect to state that there are

no dues/recovery to be made from the writ petitioner and on scrutiny which

has to be ascertained and other recovery are to be made from the writ

petitioner. Various other details were also set out alleging that various sums

have to deducted.

7. Clause 4.7 of the general terms and conditions of the contract was

referred to and contended that the refund of security deposit shall be

subject to the appellant right to deduct/appropriate its dues against the

contractor under the subject contract or under any other contract. The

averments made by the writ petitioner that they have no other alternate

efficacious remedy except to move the writ petition under Article 226 of the

Constitution of India was denied.

8. The learned Single Bench classified the claim made by the writ

petitioner under two heads namely the final bills raised by the writ

petitioners being the first component and the performance security and

retention bills which were put in by way of security deposit as a second

component. So far as the first component is concerned, the writ petitioners

were non suited and it was held that such claim cannot be adjudicated in

MAT NO. 719 OF 2024 REPORTABLE

the writ petition and the writ petitioner be best relegated to the competent

civil court.

9. With regard to the second component namely security deposits, the

learned writ court took into consideration the averments made by the

appellants in paragraph 20 of the affidavit-in-opposition wherein they have

stated that the writ petitioner/contractor had submitted Performance

Security Deposit and retention money however Additional Performance

Security Deposit was denied on the ground that there is no such clause in

the agreement. Therefore, the learned writ court held that the limited scope

of the writ petitioner claims can be decided within the scope of the writ

petition is the entitlement of the writ petitioners to be refunded the admitted

performance security deposit and retention money.

10. Further it held that since there is no dispute regarding the said

amounts having been paid by the writ petitioners in the first place, no

detailed adjudication by calling for evidence is required and what is

necessary is only to interpret the provisions of the contract and come to a

conclusion as to whether the appellants have arbitrarily and without any

reasonable excuse withheld such components of the writ petitioners claimed

which can very well be done within the confines of a writ petition. For such

limited purpose the learned Single Bench referred to clause 4.7 of the

general terms and conditions.

11. The learned Single Bench held that there is no dispute that the writ

petitioner completed the work in question and in terms of clause 4.7 half of

the security deposit was to be immediately refunded to the writ petitioner on

completion of the entire work. The entitlement petitioners to the other half of

MAT NO. 719 OF 2024 REPORTABLE

the security deposit was on expiry of six months performance guarantee

period from the date of completion. Thus, it was held that the appellants are

mandated since the term "shall be refunded" has been used to refund the

entire security deposit, half immediately on the completion of the work and

other half within 6 months thereof. The right of the appellant to

deduct/appropriate its dues has to be read not in isolation but in the

context of clause 4.7 as a whole. So construed such deduction or

appropriation had to be done within the outer limit of six months. However,

in the case on hand, no claim was raised by the appellants, admittedly

within the said six months.

12. Further it was held that the work was concluded on June 01, 2022

and the job completion certificate was issued on November 19, 2022 and

even if it is assumed that the entitlement of the writ petitioners to half of the

security deposit on certification, the date of issuance of the job completion

certificate is relevant date and hence half of the security deposit had to be

paid immediately after November 19, 2022 and the other half with or

without deductions within a further six months. With regard to the

maintainability of the writ petition both the writ petitioner as well as the

appellant relied upon the decision of the Hon'ble Supreme Court in M.P.

Power Management Company Limited Versus Sky Power Southeast

Solar India Private Limited and Others 1, it was held that going by the

said judgment, the principle that in the case of non-statutory contract, the

rights are governed only by the terms of the contract may not continue to

hold. Further it was held that the mere fact that the relief is sought under a

(2023) 2 SCC 703

MAT NO. 719 OF 2024 REPORTABLE

contract which is not statutory, will not entitle the state to ward off scrutiny

of its action or inaction under the contract. Further if the complaining party

is able to establish that the action/inaction, is perceived, arbitrary, the state

can indeed be called upon to honour its obligations of making payments

unless it be that there is a serious and genuine dispute raised regarding the

liability of the state to make the payment. Further the learned writ court

held that as per the language of clause 4.7, the appellant have the right to

deduct/appropriate its dues under the present or any other contract or from

that security deposit and not from the bill. Since clause 4.7 itself provides

that the security deposit has to be refunded within the outer limit of six

months performance guarantee period from the date of completion as such,

no such deduction/appropriation can be made after the said period. With

the above reasoning and certain other observations/findings, the writ

petition was partly allowed as indicated above.

13. The appellant is before us, contended that the prayer for recovery of

money in the writ petition enforcement of a contractual dispute of the

present nature is not permissible. The contract is non-statutory, the dispute

under reference are contractual disputes which arose in the course of

performance of a contract which is in the nature of the commercial contract

interference in writ jurisdiction that too for a money claim is not

maintainable. The claim of the writ petitioner is a matter of arbitration

before the civil court. In this regard reliance was placed on the decision in

State of Uttar Pradesh and Others Versus Bridge and Roof Company

MAT NO. 719 OF 2024 REPORTABLE

(India) Limited 2. Further the contract does not become a statutory

contract merely because it relates to construction of a public utility or has

been awarded by the statutory body. The ordinary principles of law of

contract would apply and dispute pertaining to a covenant in a contract or

its enforceability are to be determined according to the usual principles and

in support of such contention reliance was placed on the decision in Kerala

State Electricity Board and Another Versus Kurien E. Kalathil and

Others 3.

14. By referring to the decision in M.P. Power Management Company

Limited (supra), it is submitted that in the said decision, it has been held a

dressed up and disguise matter involving breach of contract cannot be said

to be arbitrary state action. It has also been held that mere allegations of

breach of contract would not suffice but there must be palpable,

unreasonable or absolutely irrational action/inaction part of any principle,

which is absent in case. Therefore, it is submitted that interference in

respect of non-statutory contract on a conspectus of the above decisions

leaving a very narrow ambit. Even if in the judgment of M.P. Power

Management Company Limited (supra) is followed there must be absolute

irrational act or an act bereft of reason. It is contended that in the present

case when the contract permits appropriation of dues arising under other

contract, this cannot be said to exists. It was further contended that

whether payment is required to be done or not requires interpretation of

clause 4.7 of the contract read with the other provision. Such interpretation

(1996) 6 SCC 22

(2000) 6 SCC 293

MAT NO. 719 OF 2024 REPORTABLE

would then be applicable to the facts of the case. The question of

interpretation of a commercial contract is not permissible in writ

jurisdiction. Relying upon the judgment in Bridge and Roof Company

India Limited (supra) it is submitted that in the said decision it has been

held that dispute relating to interpretation of the terms and conditions of a

contract cannot be agitated and could not have been agitated in a writ

petition.

15. Reliance was placed on the decision in ABL International Limited

and Another Versus Export Credit Guarantee Corporation of India

Limited and Others 4 wherein the Hon'ble Supreme Court held that a plain

interpretation of the clause itself was sufficient and it does not require any

aid much less the oral evidence to interpret the clause and therefore in the

said case, where the court found that what was required was a pure

interpretation of contract and no traverse to the facts of the case or anything

would effect. However, this is not the case of the writ petitioners as

interpretation of clause 4.7 and its applicability would require travelling to

the facts of the case namely dates when the claim arose, dates when cause

of action for recovery arose or all factual matters and therefore such

interpretation in a writ petition was not permissible.

16. Clause 4.7 is clear and unambiguous permitting a right of recovery

and courts will not permit rewriting or would not rewrite its contract. In

support of such proposition, reliance was placed on the decision in Orix

Auto Finance (India) Limited Versus Jagmander Singh and Another 5

(2004) 3 SCC 553

(2006) 2 SCC 598

MAT NO. 719 OF 2024 REPORTABLE

and Orissa State Financial Corporation Versus Narsingh Ch. Nayaki

and Others 6.

17. It is further submitted that there are two parts to clause 4.7. The first

part require that security deposit would be refunded, subject to the

company's right to deduction and appropriate its dues against the

contractor, under this contract or under any other contract. The second part

states that on completion of the entire work and certified as such by the

engineer in charge one half of the security deposit would be refunded and

the other half would be refunded after expiry of six months. The two parts of

the same clause are separate and the time limit prescribed in the second

part cannot be read into the first part and it would mean adding to the

clause which is impermissible; Clause 4.7 has no time limit; until the time

the payment is made by the appellant to the writ petitioners, its rights to

forfeit on account of the claim made under this contract or any other

contract remains enforce and cannot be curtailed. If the time limit is to be

read into such power of the appellant, the same would be adding to or

rewriting of contract, which the Hon'ble Court have said is impermissible.

Literal interpretation of a reasonable person is what is required for the

purpose of ascertainment of meaning. Arguments on contra proferentem may

not be accepted. There is no ambiguity in the contract without which this

principle has no application. There is no foundation for the argument of

unconscionable bargain a term has been made.

18. With regard to the findings rendered by the learned Single Bench

more particularly in paragraphs 29 to 31 and 36, it is contended that Order

(2003) 10 SCC 261

MAT NO. 719 OF 2024 REPORTABLE

8 Rule 6A CPC cannot be a bar. There was no opportunity in the writ

petition to file a counter claim. Therefore a analogy of filing the affidavit-in-

opposition to a writ petition, to a written statement, thereby preventing a

counter claim from being filed latter, is with respect in opposite. Further

even such provision allow an extension by court. Further the cause of action

has arisen in favour of the appellant and that would only merge in the

judgment. Just because the writ petition was filed, would not prevent the

appellant to proceed before the Civil Court and the analogy of the appellant

rights being barred because it has filed the affidavit-in-opposition, may be

an incorrect finding.

19. Further it is contended that clause 4.7 requires the security deposit to

be paid within six months along with the retention money. However, even if

it is not paid in time, because the accounts could not be finalised, if claims

arise prior to the payment which would entail recovery, the right of recovery

would not be abrogated. It was further contended that the claim and counter

claim of the present nature arising out of a commercial contract should

never be decided on affidavits and this prejudices the rights of parties

available before the civil court. In support of such contention, reliance was

placed on the decision in the State of Bihar Versus Jain Plastics and

Chemicals Limited 7. Therefore, it is submitted that the cause of action of

the appellant to recover in respect of the other contract accrued prior to

expiry of six months time from the date of certifications of Bills. In this

regard, the dates and events concerning the other Joint Venture's namely

ST- CC and STA-DGM (JV) were referred to.

(2002) 1 SCC 216

MAT NO. 719 OF 2024 REPORTABLE

20. It is further submitted that in respect of the other two contracts loss

and damages for breach were being constantly suffered from the date of

auction and therefore notice of demand is not relevant but what is relevant

is the date of sufferance of loss which gives the cause of action to recover. It

is submitted that the documents concerning the other two Joint Ventures

were enclosed along with CAN 2 of 2024 and leave was sought for to rely on

the documents and since both parties have referred to those documents it is

prayed that CAN 2 of 2024 may be allowed.

21. The learned advocate appearing for the respondent/writ petitioner

submitted that the appellants have broadly raised three issues for

consideration namely (i) whether the writ petition is maintainable owing to

the disputed question of facts and interpretations of the clauses of the

contract? (ii) whether the act on the part of the appellants in not disbursing

the security deposit can be termed as arbitrary, unfair and unreasonable

action or not? (iii) whether interpretation of clause 4.7 of the condition of

contract by the Hon'ble Single Bench while passing the impugned order can

be construed as rewriting of condition of the contract or not? and (iv)

whether the order impugned is sustainable or not?

22. The learned advocate appearing for the respondent referred to the

dates and event as to when they had completed the work, the date of

issuance of the job completion certificate, the date of completion of the

period since the date of obtaining the job completion certificate and the

dates of notice of termination and other contracts. It is submitted that in the

writ petition it had been clearly stated as to the what are the amounts

payable to the writ petitioner and for examining these issues in a proper

MAT NO. 719 OF 2024 REPORTABLE

perspective the interpretation of clause 4.7 is required to be made in the

light of text and context of the factual aspect of the matter. It is submitted

that a plain reading of clause 4.7, the following rights and obligations of the

parties to the contract are discernible. (a) A right has been conferred upon

the appellant to deduct/appropriate its dues against the writ petitioner

under this contract or any other contract from the security deposit of the

writ petitioner (b) the appellant are obliged to refund 50% of the security

deposit on the completion of the entire work certified by the engineer-in-

charge (c) the appellants are entitled to deduct/appropriate its dues against

the contract from the 50% of the security deposit lying with them within the

period of six months from the date of completion. Therefore, the appellant is

not obliged to refund the 50% of the security deposit within the six months

period from the date of completion. (d) the writ petitioner being the

contractor is entitled to refund on the remaining 50% of the security deposit

on expiry of six months performance guarantee period. (e) In the case on

hand, admittedly the appellant did not refund 50% of the security deposit on

completion of the entire work as certified or by the engineer-in-charge on

November 20, 2022. Therefore, non-payment of the 50% of the security

deposit in consonance of clause 4.7 is an arbitrary action of the appellants.

So far as the remaining 50% of the security deposit is concerned, the

appellant is under an obligation to ascertain whether there is any dues

against the contract under the present contract or any other contract to be

deducted/appropriated till May 30, 2023. In the case on hand, there were

no dues till May 30, 2023 and the appellant was not authorised to

deduct/appropriate any sum from the remaining 50% of the security

MAT NO. 719 OF 2024 REPORTABLE

deposit. Therefore, as on June 01, 2023, the writ petitioner is entitled to get

his refund of his security deposit which the appellants were obliged to

release and the remaining of the security deposit on June 01, 2023. Meres

issuance of show cause notice does not ipso facto be termed as dues to be

deducted/appropriated as no financial liability was accrued by issuance of a

show cause notice to any of the constituent parties of the joint ventures. (g)

the Hon'ble Single Bench carefully considered the attendant facts and

circumstances in construing clause 4.7 of the conditions of the contract.

Therefore, the appellant is obliged to release the security deposit on expiry of

six months performance guarantee period. (h) The interpretation and/or

construction of clause 4.7 cannot be said to be rewriting of the contract

rather using the work "within" in paragraph 24 of the impugned order while

construing clause 4.7 is mere error which is required to be

modified/rectified appropriately by this court. (i) Referring to the decision in

Subodh Kumar Singh Rathour Versus Chief Executive Officer and

Others 8 it is submitted that a decision has opened up a new vista where

each and every action of the instrument is the realm of contracts are tested

on the touchstone of justness, reasonableness and fairness and thus

ascertaining arbitrariness viewing through losses of the contracts and its

nuanced interpretation cannot be said to be outside the power of the judicial

review. (j) Reliance was placed on the decision in Nabha Power Limited

(NPL) Versus Punjab State Power Corporation Limited 9 for the

proposition that a commercial document must be interpreted in such a

2024 SCC Online SC 1682

(2018) 11 SCC 508

MAT NO. 719 OF 2024 REPORTABLE

manner as to give efficacy to the contract rather than to invalidate it. (k)

Reliance was placed on the decision in United India Insurance Company

Limited Versus Harchand Rai Chandan Lal 10 for the proposition that

terms and conditions of the contract has to be strictly read and natural

meaning be given to it. (l) Reliance was placed in DLF Universal Limited

and Another Versus Director, Town and Country Planning Department,

Haryana and Others 11 for the proposition that the contract is interpreted

according to its purpose (m) the interpretation of Clause 4.7 cannot be made

to invalidate the intendment of the parties to the contract (n) the Hon'ble

Single Bench while interpreting or construing clause 4.7 did not exercise its

discretion arbitrarily and nor capriciously. (o) the writ petition is

maintainable as the acts/omission on the part of the appellant in not

releasing the security deposit in both stages appears to be arbitrary. (p)

although the word used in paragraph 24 in the impugned order passed by

the learned Single Bench cannot be said to be correct, it cannot be termed

rewriting of the contract rather its mere error which needs to be

modified/rectified by this court in furthering the intendment of the parties

to the contract in construing clause 4.7 in the light of the attendant facts

and circumstances of the case.

23. By placing reliance on the decision in the case of Surya

Constructions Versus State of Uttar Pradesh and Others 12, it is

submitted that in the light of the principles propounded therein the writ

petitioners are entitled to get the refund of the security deposit along with

(2004) 8 SCC 644

(2010) 14 SCC 1

(2019) 16 SCC 794

MAT NO. 719 OF 2024 REPORTABLE

the interest awarded by the Hon'ble Single Bench. The learned Advocate

appearing for the appellant would submitted that the respondents have

relied on the decision in Subodh Kumar Singh Rathour (supra) and the

said decision will not assist the writ petitioner and in this regard, elaborately

referred to the facts of the said case more particularly the findings in the

paragraph 59 to 62 and 70 and wherein the Hon'ble Supreme Court came to

the conclusion that the decision to terminate the contract was beyond

purview of the clause of the contract.

24. It is further submitted in paragraph 69 of the said judgment the

Hon'ble Supreme Court has held that to ascertain whether the Act is

arbitrary or not the court must carefully attend to the facts the

circumstances of the case. It should be find out whether the impugned

decision is based on any principle. if not, it may unerringly point to

arbitrariness. If the act buttress or mere exhibition of the will of the

authority it would sufficiently bear the insignia of arbitrariness. Therefore it

is submitted that if the act of an authority is based on reason which is not

totally absurd and if it acts are based on a principle, the writ court would

not come to the conclusion of arbitrariness or caprice and would refuse to

interfere or go into the validity or legality of the decision leaving the same to

be done in a contractual forum or the civil court. In the case on hand,

decision to withhold is based on a principle that is clause 4.7 of the

contract. The writ court may not adjudicate whether the interpretation is

correct and leave the same for decision in an appropriate proceeding. Since

the action of the appellant is based on a contractual clause there is no

arbitrariness or capriciousness. Therefore it is submitted that the decisions

MAT NO. 719 OF 2024 REPORTABLE

relied on by the learned advocate appearing for the respondent does not

assist them in its endeavour to support money decree based on

interpretation of contract and the facts of the case and it cannot be called as

arbitrary action and the action of the appellant cannot be called as arbitrary

act.

25. Reliance was placed on the decision in State of Gujarat and

Another Versus Amber Builders 13 wherein it was held that the judgment

in Union of India Versus Raman Iron Foundry 14 was specifically

overruled on the issue on hand that the Government had no right to

appropriate the amount claimed without getting its first adjudicated was

overruled by three judge bench of the Hon'ble Supreme Court in H.M.

Kamalauddin Ansari and Company Versus Union of India 15. The

Hon'ble Supreme Court in the said case found that there was a general

condition which entitled the Government to recover the damages claimed by

appropriating any sum which may become due to the contractor under other

bills and the court disagree to the findings in Raman Iron Foundry and it

was held that the decision in Gangotri Enterprises Limited Versus Union

of India 16 is per incuriam because it relies upon Raman Iron Foundry

which has been specifically overruled by three judge bench in H.M.

Kamalauddin Ansari and Company.

26. We have heard Mr. Jishnu Chowdhury, learned Senior Advocate

assisted by Mr. Syed Nurul Arefin, Mr. Rahul Singh and Mr. Syed Moyeenul

Arefin learned advocates appearing for the appellants and Mr. Subhabrata

(2020) 2 SCC 540

(1974) 2 SCC 231

(1983) 4 SCC 417

(2016) 11 SCC 720

MAT NO. 719 OF 2024 REPORTABLE

Datta assisted by Mr. Subhojit Seal and Mr. Aranya Saha learned advocates

appearing for the respondents nos. 1 and 2.

27. The first issue to be decided is regards the maintainability of the writ

petition and to what extent the writ court can interfere in contractual

matters. In Bridge and Roof Company (India) Limited, the Hon'ble

Supreme Court pointed out that the contract which was subject matter of

the said case is a contract in the realm of private law; it is not a statutory

contract; it is the governed by the provisions of the Contract Act or may be,

also by certain provisions of the Sale of Goods Act. Any dispute relating to

the interpretation of the terms and conditions of such contract cannot be

agitated, and could not have been agitated in a writ petition, that is a matter

either for arbitration as provided by the contract or for the civil court as the

case may be.

28. It was further held that whether any money is due to the respondent

therein from the appellant Government therein under the contract and, if so,

how much and the further question whether retention or refusal to pay any

amount by the Government is justified or not are all matters which cannot

be agitated in or adjudicated upon in a writ petition. Further it was held

that the prayer in the writ petition to restrain the Government from

deducting a particular amount from the writ petitioner's bills was a prayer

which cannot be granted by the High Court under Article 226 of the

Constitution. Further whether there has been reduction in the statutory

liability on account of a change in law within the meaning of certain clauses

of the contract is again not a matter to be agitated in the writ petition. A

matter relating to interpretation of the terms of the contract should be

MAT NO. 719 OF 2024 REPORTABLE

agitated before the arbitrator or the civil court as the case may be; if any

amount is wrongly withheld by the Government, the remedy of the

respondent is to raise the dispute as provided by the contract or approach

the civil court as the case may be according to law. Similarly, if the

Government says that if any over payment has been made to the

respondent, the remedy is also the same.

29. In Kerala State Electricity Board, the Hon'ble Supreme Court held

that the interpretation and implementation of a clause in a contract cannot

be subject matter of a writ petition. Whether the contract envisages actual

payment or not is a question of construction of contract. If a term of a

contract is violated, ordinarily the remedy is not the writ petition under

Article 226. A contract would not become statutory simply because it is for

construction of public utility and it has been awarded by the statutory body.

Obligations imposed by the contract on the contracting parties come within

the purview of the Contract Act, that would not make the contract statutory.

It was further held that the disputes about the meaning of covenant in a

contract or its enforceability have to be determined according to the usual

principles of Contract Act. Every Act of a statutory body need not necessarily

involve an exercise of statutory power. Statutory bodies, like private parties,

have power to contract or deal with property. Such activities may not raise

any issue of public law. The contract being not a statutory contract the

dispute relating to the interpretation of the terms and conditions of such

contract could not have been agitated in a petition under Article 226 of the

Constitution of India.

MAT NO. 719 OF 2024 REPORTABLE

30. In ABL International Limited while considering the matter

pertaining to interpretation of a clause in the contract, the Hon'ble Supreme

Court held that a plain interpretation of the clause was sufficient and it does

not require any aid, much less oral evidence to interpret the clause.

31. In Jain Plastics and Chemical Limited, it was held that the writ is

not remedy for enforcing contractual obligations; writ petition under Article

226 is not the proper proceeding for adjudication of such disputes; the

existence of alternate remedy does not affect the jurisdiction of the court to

issue writ, but ordinarily that would be a good ground in refusing to exercise

the discretion under Article 226. In the facts of the said case, it was found

that many matters could be decided after referring to the contention raised

in the affidavits and counter affidavits, but that would hardly be the ground

to exercise of the extraordinary jurisdiction under Article 226 of the

Constitution in case of alleged breach of contract.

32. In The Union of India Versus D.N. Revri and Company and Others

17 it was held that the contract being a commercial document between

parties, it must be interpreted in such a manner as to give efficacy to the

contract rather than to invalidate it. It would not be right while interpreting

a contract entered into between two lay parties to apply strict rules of

construction which are ordinarily applicable to a conveyance and other

formal documents. The meaning for such a contract must be gathered by

adopting a common sense approach and it must not be allowed to be

thwarted by a narrow pedantic and realistic interpretation.

(1976) 4 SCC 147

MAT NO. 719 OF 2024 REPORTABLE

33. In United India Insurance Company Limited, the Hon'ble Supreme

Court held that it is a settled law that the terms of the contract have to be

strictly read and natural meaning to be given to it. No outside aid should be

sought unless the meaning is ambiguous.

34. In DLF Universal Limited, the Hon'ble Supreme Court while

considering how a contract should be interpreted held as follows"-

It is settled principle in law that a contract is interpreted according to its purpose. The purpose of a contract is the interests, objectives, values, policy that the contract is designed to actualize. It comprises joint intent of the parties. Every such contract expresses the autonomy of the contractual parties' private will. It creates reasonable, legally protected expectations between the parties and reliance on its results. Consistent with the character of purposive interpretation, the court is required to determine the ultimate purpose of a contract primarily by the joint intent of the parties at the time the contract so formed. It is not the intent of a single party; it is the joint intent of both parties and the joint intent of the parties is to be discovered from the entirety of the contract and the circumstances surrounding its formation.

As is stated in Anson's Law of Contract,

"a basic principle of the Common Law of Contract is that the parties are free to determine for themselves what primary obligations they will accept.... Today, the position is seen in a different light. Freedom of contract is generally regarded as a reasonable, social, ideal only to the extent that equality of bargaining power between the contracting parties can be assumed and no injury is done to the interests of the community at large."

The Court assumes:

MAT NO. 719 OF 2024 REPORTABLE

"that the parties to the contract are reasonable persons who seek to achieve reasonable results, fairness and efficiency.... In a contract between the joint intent of the parties and the intent of the reasonable person, joint intent trumps, and the Judge should interpret the contract accordingly. A party who claims otherwise, violates the principle of good faith.

(See Purposive Interpretation in Law by Aharon Barak: 2005 Princeton University Press).

35. The legal principle that could be culled out from the above decisions is

that in matter relating to the interpretation of the term of a contract it

should be agitated before the arbitrator or civil court as the case may be. If

the contractor alleges that the Government has wrongfully withheld certain

sums then the remedy is to approach the civil court and invoking Article

226 is not the proper remedy. External aids are not required to be applied

while interpreting the terms and conditions of a contract. The subsisting

contract cannot be rewritten in a writ proceeding. When serious disputed

questions or rival claims arising out of breach of contract are required to be

investigated and determined on the basis of evidence led in the civil court,

the writ petition is not maintainable. While interpreting a contract it must

be interpreted in such manner as to give efficacy to the contract rather than

to invalidated it. The terms of the contract have to strictly read and natural

meaning to given to it, no outside aid should be sought unless meaning is

ambiguous.

36. Consistent with the character of purposive interpretation, the court is

required to determine, the ultimate purpose of a contract primarily by the

joint venture of the parties at the time the contract so formed; it is not the

MAT NO. 719 OF 2024 REPORTABLE

intent of a single party; it is the joint intent of both parties and the joint

intent of the parties is to discover from the entirety of the contract and the

circumstances surrounding its formation.

37. If the above legal principle is applied to the facts of the case, we have

to necessary hold that a writ petition for enforcement of the terms and

conditions of a contract was not maintainable. Equally interpretation of the

terms and contract of a contract would also fall outside the jurisdiction of a

petition under Article 226 of the Constitution.

38. The learned advocate appearing for the respondent writ petitioner

placed heavy reliance on the decision in M.P. Power Management

Company Limited. The learned Advocate for the appellant endeavour to

distinguish the decision by referring to the various paragraphs. Thus, we are

required to consider as to whether the decision in M.P. Power Management

Company Limited would assist the case of the appellant or that of the

respondent. Paragraph 82 of the judgment would be relevant:-

We may cull out our conclusions in regard to the points, which we have framed:

i. It is, undoubtedly, true that the writ jurisdiction is a public law remedy. A matter, which lies entirely within a private realm of affairs of public body, may not lend itself for being dealt with under the writ jurisdiction of the Court.

ii. The principle laid down in Bareilly Development Authority (supra) that in the case of a non-statutory contract the rights are governed only by the terms of the contract and the decisions, which are purported to be followed, including Radhakrishna Agarwal (supra), may not continue to hold good, in the light of what has been laid down in ABL (supra) and as followed in the recent judgment in Sudhir Kumar Singh (supra).

MAT NO. 719 OF 2024 REPORTABLE

iii. The mere fact that relief is sought under a contract which is not statutory, will not entitle the Respondent-State in a case by itself to ward-off scrutiny of its action or inaction under the contract, if the complaining party is able to establish that the action/inaction is, per se, arbitrary.

iv. An action will lie, undoubtedly, when the State purports to award any largesse and, undoubtedly, this relates to the stage prior to the contract being entered into [See R.D. Shetty (supra)]. This scrutiny, no doubt, would be undertaken within the nature of the judicial review, which has been declared in the decision in Tata Cellular v. Union of India MANU/SC/0002/1996 MANU/SC/0002/1996 : (1994) 6 SCC 651.

v. After the contract is entered into, there can be a variety of circumstances, which may provide a cause of action to a party to the contract with the State, to seek relief by filing a Writ Petition.

vi. Without intending to be exhaustive, it may include the relief of seeking payment of amounts due to the aggrieved party from the State. The State can, indeed, be called upon to honour its obligations of making payment, unless it be that there is a serious and genuine dispute raised relating to the liability of the State to make the payment. Such dispute, ordinarily, would include the contention that the aggrieved party has not fulfilled its obligations and the Court finds that such a contention by the State is not a mere ruse or a pretence.

vii. The existence of an alternate remedy, is, undoubtedly, a matter to be borne in mind in declining relief in a Writ Petition in a contractual matter. Again, the question as to whether the Writ Petitioner must be told off the gates, would depend upon the nature of the claim and relief sought by the Petitioner, the questions, which would have to be decided, and, most importantly, whether there are disputed questions of fact, resolution of which is necessary, as an indispensable prelude to the

MAT NO. 719 OF 2024 REPORTABLE

grant of the relief sought. Undoubtedly, while there is no prohibition, in the Writ Court even deciding disputed questions of fact, particularly when the dispute surrounds demystifying of documents only, the Court may relegate the party to the remedy by way of a civil suit.

viii. The existence of a provision for arbitration, which is a forum intended to quicken the pace of dispute resolution, is viewed as a near bar to the entertainment of a Writ Petition (See in this regard, the view of this Court even in ABL (supra) explaining how it distinguished the decision of this Court in State of U.P. and Ors. v. Bridge & Roof Co.

MANU/SC/0969/1996MANU/SC/0969/1996 :

(1996) 6 SCC 22, by its observations in paragraph- 14 in ABL (supra)].

ix. The need to deal with disputed questions of fact, cannot be made a smokescreen to guillotine a genuine claim raised in a Writ Petition, when actually the resolution of a disputed question of fact is unnecessary to grant relief to a writ applicant.

x. The reach of Article 14 enables a Writ Court to deal with arbitrary State action even after a contract is entered into by the State. A wide variety of circumstances can generate causes of action for invoking Article 14. The Court's approach in dealing with the same, would be guided by, undoubtedly, the overwhelming need to obviate arbitrary State action, in cases where the Writ remedy provides an effective and fair means of preventing miscarriage of justice arising from palpably unreasonable action by the State.

xi. Termination of contract can again arise in a wide variety of situations. If for instance, a contract is terminated, by a person, who is demonstrated, without any need for any argument, to be the person, who is completely unauthorised to cancel the contract, there may not be any necessity to drive the party to the unnecessary ordeal of a prolix and avoidable round of litigation. The

MAT NO. 719 OF 2024 REPORTABLE

intervention by the High Court, in such a case, where there is no dispute to be resolved, would also be conducive in public interest, apart from ensuring the Fundamental Right of the Petitioner Under Article 14 of the Constitution of India. When it comes to a challenge to the termination of a contract by the State, which is a non-statutory body, which is acting in purported exercise of the powers/rights under such a contract, it would be over simplifying a complex issue to lay down any inflexible Rule in favour of the Court turning away the Petitioner to alternate Fora. Ordinarily, the cases of termination of contract by the State, acting within its contractual domain, may not lend itself for appropriate redress by the Writ Court. This is, undoubtedly, so if the Court is duty-bound to arrive at findings, which involve untying knots, which are presented by disputed questions of facts.

Undoubtedly, in view of ABL Limited (supra), if resolving the dispute, in a case of repudiation of a contract, involves only appreciating the true scope of documentary material in the light of pleadings, the Court may still grant relief to an applicant. We must enter a caveat. The Courts are today reeling under the weight of a docket explosion, which is truly alarming. If a case involves a large body of documents and the Court is called upon to enter upon findings of facts and involves merely the construction of the document, it may not be an unsound discretion to relegate the party to the alternate remedy. This is not to deprive the Court of its constitutional power as laid down in ABL (supra). It all depends upon the facts of each case as to whether, having regard to the scope of the dispute to be resolved, whether the Court will still entertain the petition.

xii. In a case the State is a party to the contract and a breach of a contract is alleged against the State, a civil action in the appropriate Forum is, undoubtedly, maintainable. But this is not the end of the matter. Having regard to the position of the State and its duty to act fairly and to eschew

MAT NO. 719 OF 2024 REPORTABLE

arbitrariness in all its actions, resort to the constitutional remedy on the cause of action, that the action is arbitrary, is permissible (See in this regard Kumari Shrilekha Vidyarthi and Ors. v.

               State         of        U.P.         and        Ors.
               MANU/SC/0504/1991MANU/SC/0504/1991                  :
               (1991) 1 SCC 212)). However, it must be made

clear that every case involving breach of contract by the State, cannot be dressed up and disguised as a case of arbitrary State action. While the concept of an arbitrary action or inaction cannot be cribbed or confined to any immutable mantra, and must be laid bare, with reference to the facts of each case, it cannot be a mere allegation of breach of contract that would suffice. What must be involved in the case must be action/inaction, which must be palpably unreasonable or absolutely irrational and bereft of any principle. An action, which is completely malafide, can hardly be described as a fair action and may, depending on the facts, amount to arbitrary action. The question must be posed and answered by the Court and all we intend to lay down is that there is a discretion available to the Court to grant relief in appropriate cases.

xiii. A lodestar, which may illumine the path of the Court, would be the dimension of public interest subserved by the Court interfering in the matter, rather than relegating the matter to the alternate Forum.

xiv. Another relevant criteria is, if the Court has entertained the matter, then, while it is not tabooed that the Court should not relegate the party at a later stage, ordinarily, it would be a germane consideration, which may persuade the Court to complete what it had started, provided it is otherwise a sound exercise of jurisdiction to decide the matter on merits in the Writ Petition itself.

xv. Violation of natural justice has been recognised as a ground signifying the presence of a public law element and can found a cause of action

MAT NO. 719 OF 2024 REPORTABLE

premised on breach of Article 14. [See Sudhir Kumar Singh and Ors. (supra)].

39. In the above decision the judgment in Radhakrishna Agarwal and

Others Versus State of Bihar 18 was held not to continue to hold good in

the light of the decision in ABL International Limited. Equally it has been

said that mere fact that the relief is sought under the contract, it is non

statutory, will not be entitle the respondent state in a case by itself to ward

off scrutiny of its action or inaction under the contract, if the complaining

party is able to establish that the action/inaction as per-se arbitrary.

Therefore, the scope of the interference in a matter where relief is sought for

in a non-statutory contract is available when the complaining party is able

to establish that the action/inaction is per-se arbitrary. It has also been held

that the state can be called upon to honour its obligations of making

payment however this will not be done when there is serious and genuine

dispute raised relating to the liability of the state to make payment and such

dispute ordinarily would include the contention that the aggrieved party has

not fulfilled its obligations and the court finds such a contention by the

state is a mere ruse or pretence. Ultimately it has been held that exercise of

jurisdiction depends upon the facts of each case as to whether having regard

to the scope of the dispute to be resolved, whether the court will still

entertain the petition under Article 226 of the Constitution. Therefore, the

respondent writ petitioner has to bring the relief sought for in the writ

petition which admittedly pertains to interpretation and a claim arising out

(1977) 3 SCC 457

MAT NO. 719 OF 2024 REPORTABLE

of non-statutory contract, within anyone of the parameters pointed out

above.

40. The learned Single Bench has interpreted clause 4.7 of the General

Terms and Conditions of the contract which reads as follows:-

For such limited enquiry, Clause 4.7 of the GTC is required to be set forth below:

"4.7 Refund of Security Deposit : The refund of Security deposit shall be subject to company's right to deduct/appropriate its dues against the contractor under this contract or under any other contract. On completion of the entire work and certified as such by the Engineer-In- Charge, one half of the security deposit remaining with the company shall be refunded. The other half shall be refunded to the contractor on the expiry of six months performance guarantee period from the date of completion as certified by the Engineer-In- Charge, subject to the following conditions:

a) Any defect/defects in the work, if detected after issue of completion certificate is/are rectified to the satisfaction of the engineer-In-

Charge within the said defect liability period of six months or on its due extension till completion of the rectification work as required.

b) In the case of building work or other work of similar nature the refund shall be made on the expiry of the said six months period or at the end of one full monsoon period i.e. June to September. Whichever is later in point of time and any defects such as leakages in roof effloresces in walls, dampness, defects in drainage etc. should be rectified to the satisfaction of the Engineer-In-Charge.

c) (i) In case of supply, installation and commissioning of equipment for electrical and

MAT NO. 719 OF 2024 REPORTABLE

mechanical works the refund shall be made on the expiry of defect liability period which will be one year from the date of commissioning of the equipment/completion of the work and/or rectification of any defect which may be detected in the individual equipment or the whole system under the contract, whichever is later.

(ii) All types of Manufacture's guarantee/warranty wherever applicable are to be issued/revalidated in the name of the owner by the Contractual agency and will be covered with relevant counter guarantee."

41. The writ petitioner has not challenged the above condition/clause nor

they are entitled to challenge after having participated in the tender and

come out successful. As pointed out above, the terms and conditions of the

contract have to be interpreted without applying any externally aids bearing

in mind that there are two parties to the contract and the question of

unilateral interpretation to favour one to be desisted. Furthermore, the

intention of the parties has to be culled out from the entirety of the contract

and the circumstances surrounding its formation.

42. The learned Single Bench was of the view that the right of the

appellant to deduct / appropriate its dues against the contractor under this

contract or under any other contract is exercisable within a period of 6

months. The question would be whether the Court would be justified in

reading the terms and conditions of the contract dehors than what has been

stated in the contract. Admittedly, the writ petitioner has accepted the

condition and performed the work allotted. Clause 4.7 consists of three

limbs, the first of such is that the refund of security deposit shall be subject

MAT NO. 719 OF 2024 REPORTABLE

to the company's right (appellant's right) to deduct / appropriate its dues

against the contractor under this contract or under any other contract. The

clause / sentence terminates with a "full stop".

43. The second limb is on completion of the entire work and certified as

such by the Engineer-in-charge one half of the security deposit remaining

with the company shall be refunded. A simple and natural meaning to be

given to the clauses that the second limb would be subject to the first limb,

if the appellant exercises its right to deduct/ appropriate its dues against

the contractor under this contract or under any other contract the second

limb will not come into operation. If the second limb does not come into

operation, it goes without saying that the third limb of the condition also

would not come into operation. Therefore, in our view the learned Single

Bench could not have super imposed the condition of 6 months which is

present in the second limb of Clause 4.7 into the first limb. This clearly

amounts to rewriting the contract which is impermissible.

44. We find from the pleadings in the writ petition that no such case was

canvassed by the writ petitioners themselves. Therefore, going by the

manner in which contracts have to be interpreted, the Court ought not to

add or substitute any words in a commercial contract which has been

entered into by both parties fully conscious of their rights and obligations. If

this is the correct interpretation to be given to Clause 4.7, then the

appellant has the right to deduct or appropriate its dues against the

respondent writ petitioner under any other contract and no time limit has

been prescribed for exercise of such right. Admittedly, there were two other

joint ventures in which the respondent is a party namely, STA-CC(JV) and

MAT NO. 719 OF 2024 REPORTABLE

STA-BGM(JV). So far as STA-CC(JV) is concerned, the last date for

completion of the work as per the NIT was 1.6.2022. Breach was committed

and notice was issued to the JV on 18.7.2022. On 19.1.2023 appellant

issued a letter to STA-CC(JV) to commence work failing which informed

them that in terms of Clause 6.1 of the GTC forfeiture of the security deposit

will be made. The said joint venture filed a writ petition before this Court

and the Court by order dated 15.5.2023 directed commencement of work

failing which the appellant is entitled to take penal action. The said JV did

not comply with the direction and ultimately notice of termination was

issued on 26.6.2023 and the matter is now pending before the Arbitration

Tribunal. So far as STA-BGM (JV) show-cause notice was issued on

18.7.2022 informing them that if they do not adhere to the terms and

conditions penal action will be taken as per the NIT. The contract was

terminated by notice of termination dated 1.1.2024 and damages of Rupees.

29,61,32,571/- has been claimed. We are informed that a suit was filed by

the said joint venture, the plaint was rejected and appeal is pending. The

contention of the respondent writ petitioner is that on the date when the

completion certificate was issued to the writ petitioner JV i.e. 19.11.2022

there was no enforceable demand. In our view, this would be and incorrect

manner in which the power of the appellant for deduction or appropriation

of its dues can be interpreted. Clause 4.7 does not give any such leverage. It

is plain and simple conferring power on the appellant to deduct /

appropriate its dues against the contractor under any other contract and the

refund of security deposit is subject to such exercise of power. Therefore, the

respondent writ petitioner cannot be heard to be said that on the date of

MAT NO. 719 OF 2024 REPORTABLE

issuance of completion certificate or on the expiry of the 6 months period

there was no crystallized demand and therefore such right cannot be

exercised at this juncture is an incorrect interpretation which would

frustrate the object of the contract. The notice of termination of the contract

should not be read in isolation but should be read along with the chain of

events which preceded the termination. Therefore, the date on which the

breach occurred at the first instance would be relevant for all purposes and

the same cannot be ignored. The document has to be interpreted in a

manner that conveys the proper meaning to a reasonable man.

Undoubtedly, the writ petitioner is a corporate entity and not an individual

and it is not the first time the writ petitioner have entered into contract with

the appellant and in respect of the two other joint ventures they are

defaulters and claims are pending. Therefore, we are of the view that the

appellant would be entitled to exercise its powers under Clause 4.7 and

withhold the payment under any other contract to which the writ petitioner

is a party and this alone will be the correct interpretation of the terms and

conditions of the contract as has been understood by the parties themselves

and acted upon.

45. The decision in Subodh Kumar Singh Rathour was heavily relied on

by the learned advocate appearing for the respondent writ petitioner. In fact,

a careful reading of the judgment would lend support to the case of the

appellant rather than the respondent. The Hon'ble Supreme Court after

referring to a catena of decisions some of which we have referred above held

that although disputes arising purely out of contracts are not amenable to

writ jurisdiction yet keeping in mind the obligation of the State to act fairly

MAT NO. 719 OF 2024 REPORTABLE

and not arbitrarily or capriciously, it is settled that when contractual power

is being used for public purpose, it is certainly amenable to judicial review.

After having rendered such a finding, the Hon'ble Supreme Court examined

the facts of the case and found that the cancellation of the tender in the said

case was influenced by extraneous consideration. The cancellation of the

tender fell outside the purview of the terms and conditions of the contract.

The Hon'ble Supreme Court on facts found that the matter is not purely a

contractual; it is not a breach of contract, rather a plain and simple exercise

of executive power. It was further held that the question whether an

impugned action is arbitrary or not is ultimately to be answered on the facts

and in the circumstances of a given case. The Court carefully attain to the

facts and circumstances of the case; it should find out whether the

impugned decision is based on any principle; if the act is capricious or

exhibits whims of the authority. then it would bear the insignia of

arbitrariness. The Court to assess whether an action complained of should

be termed as arbitrary is by way of scrutinizing the reasons that have been

assigned to such an action. Therefore, the Court had interfered in the said

matter because it was a mala fide and whimsical exercise of power and

admittedly exercise outside the scope of the contract. In the instant case the

appellant seeks to enforce its powers under clause 4.7 of the GTC which is

well within the scope of the contract.

46. Therefore, we are of the view that the power exercised by the appellant

to withhold the money is within the scope of the contract and therefore, the

learned writ Court could not have allowed the writ petition in part, could not

have interpreted the terms and conditions of the contract as has been done

MAT NO. 719 OF 2024 REPORTABLE

and eventually passed a money decree in a writ petition when admittedly the

power exercised by the appellant to deduct / appropriate its dues under any

other contract was in exercise of powers conferred under Clause 4.7 and

such exercise is neither extraneous nor arbitrary nor mala fide. As has been

held above, the learned Writ Court could not have imported the time period

of 6 months found in the second limb of Clause 4.7 to the first limb which is

independent of the second limb. In other words the second limb could come

into operation only if there are no circumstances warranting exercise of the

power by the appellant under the first limb of Clause 4.7.

47. Therefore, we have no hesitation to hold that the action of the

appellant is neither unfair nor unjust nor unreasonable nor arbitrary but an

exercise done under the terms and conditions of the contract. The Court

cannot fix a time limit within which period the deduction or forfeiture can be

done by the appellant either under the subject contract or under any other

contract and if such interpretation is made it would undoubtedly amount to

rewriting a contract which is impermissible under Article 226 of the

Constitution.

48. As mentioned above, the sufferance of loss is relatable to the date of

breach of other joint venture, and the question of a crystallized liability to be

in place on the date of issuance of completion certificate in the subject

contract is not required and if such interpretation is given, it would frustrate

the terms and conditions of the contract which cannot be done.

49. For all the above reasons, the appeal is allowed and the order and

direction issued by the learned Single Bench is set aside. The above decision

will not prevent the respondent with petitioner from availing other remedies

MAT NO. 719 OF 2024 REPORTABLE

before the appropriate forum in the appropriate manner and the findings

rendered above will not prejudice the rights of the respondent in such

proceedings that the appellant may avail. No costs.

50. CAN 4 of 2024 has been filed by the appellant on 26.09.2024 praying

for a direction upon the respondent writ petitioner to extend the bank

guarantee which was filed by the respondent writ petitioner.

51. In the light of the judgment allowing this appeal, no further orders are

required in CAN 4 of 2024 and the same stands disposed of along with the

connected applications.

(T.S. SIVAGNANAM, CJ.)

I Agree.

(HIRANMAY BHATTACHARYYA, J.)

(P.A.- SACHIN/PRAMITA)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter