Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kosc Industries Private Limited vs Lakhotia Infra Technologies Pvt. Ltd
2024 Latest Caselaw 145 Cal/2

Citation : 2024 Latest Caselaw 145 Cal/2
Judgement Date : 18 January, 2024

Calcutta High Court

Kosc Industries Private Limited vs Lakhotia Infra Technologies Pvt. Ltd on 18 January, 2024

Author: Moushumi Bhattacharya

Bench: Moushumi Bhattacharya

                          IN THE HIGH COURT AT CALCUTTA
                          Ordinary Original Civil Jurisdiction
                                  ORIGINAL SIDE
                               (Commercial Division)

Present :

Hon'ble Justice Moushumi Bhattacharya


                                    AP 70 of 2023
                                        with

                                    AP 71 of 2023

                       KOSC Industries Private Limited
                                         vs
                     Lakhotia Infra Technologies Pvt. Ltd.


     For the petitioner         :     Mr. Shounak Mukhopadhyay, Adv.
                                      Mr. Vishwarup Acharyya, Adv.


     For the respondent         :     Mr. Siddhartha Chatterjee, Adv.
                                      Mr. Abirlal Ghosh, Adv.


     Last heard on              :     10.01.2024


      Delivered on              :     18.01.2024


Moushumi Bhattacharya, J.

1. Both the applications have been filed under section 9 of the

Arbitration and Conciliation Act, 1996 for interim relief. In one of the

applications, the petitioner has prayed for a restraint on the respondent

from alienating or creating any third party rights in respect of the

equipments supplied by the petitioner to the respondent under four

Purchase Orders issued by the respondent. In that application, the

petitioner has also prayed for a direction on the respondent to furnish

security for Rs. 53,07,352/-. The relief sought for in the other application is

substantially the same except that the petitioner has claimed security of

Rs.7,93,268/- from the respondent.

2. The other difference is that the respondent in AP 71 of 2023 has taken

a point of pecuniary jurisdiction in that the Calcutta High Court lacks

jurisdiction to entertain the applications.

3. The Court proposes to dispose of the applications by way of this

judgment since both the applications involve the same facts and

substantially the same point of law.

AP 70 of 2023

4. The undisputed facts are that petitioner supplied 2200 units of MS

Props - construction scaffolding material - on rent to the respondent under

4 Purchase Orders. The rate of rent per piece on a monthly basis is an

admitted sum mentioned in the Purchase Orders. The figures mentioned in

the "Rental" column is a part of the Purchase Orders and has not been

disputed by the respondent.

5. The petitioner, through learned counsel, has also placed and relied on

a table which contains certain facts as per the affidavit-in-opposition of the

respondent. The table relates to "Duration of Use of Goods" from 12.9.2019

- 18.10.2019. A total of 2000 goods were supplied by the petitioner to the

respondent by October, 2019. The chart mentions the number of goods

returned by the respondent together with the dates of return and states that

the respondent admittedly withheld 600 units of goods. The dates of supply

and of return have reference to specific pages in the affidavit-in-opposition

filed by the respondent. Counsel has shared the chart with learned counsel

appearing for the respondent.

6. The chart also contains a calculation of admitted rent for the 600

units which the respondent has withheld. The petitioner describes the

figures as "admitted" on the basis of the calculation statement on the

duration of use of goods by the respondent. The total principal amount due

has been calculated at Rs. 22,29,120.00/- as the rent for the balance

withheld 600 goods from November, 2019 - July, 2023 + the rent for 900

goods used from November, 2019 - February, 2020 and for 500 goods used

from November, 2019 - June, 2020. The calculation also adjusts Rs.

4,90,880.00/- received by the petitioner from the respondent.

7. It is relevant to note that the petitioner's claim in the arbitration is in

excess of Rs. 70 lacs on account of the withholding of the petitioner's goods

by the respondent and the disposing of and alienating of the goods by the

latter.

8. Learned counsel appearing for the respondent has objected to the

maintainability of the application on the ground that the application was

made after constitution of the arbitral tribunal. However, the records show

that a Division Bench of this Court entertained the section 9 application by

its order dated 2nd March, 2023 and passed an injunction on the respondent

from transferring or alienating the material leased to the respondent for 3

months from the date of the order. The respondent, significantly did not

challenge this order.

9. Therefore, the objection made under section 9(3) of The Arbitration

and Conciliation Act, 1996 on the Court not having jurisdiction to entertain

an application under section 9(1) after constitution of arbitral tribunal, is no

longer acceptable : Arcelor Mittal Nippon Steel v. Essar Bulk Terminal Limited;

(2022) 1 SCC 712. It is also relevant that the respondent did not object to

the maintainability of the application before the Division Bench on 6th

September, 2023 when the Division Bench set aside the order dated 14th

July, 2023 and thought it fit to appoint a Receiver for taking inspection of

the units lying at the various sites of the respondent (appellant before the

Division Bench) and deliver the same to the petitioner. The Division Bench

was however pleased not to interfere with the interim order restraining the

respondent from dealing with the goods till the Receiver takes actual

physical position of the 800 units or lesser / greater number of units lying

with the respondent.

10. The respondent's resistance to the figures mentioned in the chart

relied on by the petitioner is without basis since the statement on the

duration of use of goods clearly refers to specific pages in the affidavit-in-

opposition of the respondent and the fact that 2000 units were admittedly

supplied by the petitioner to the respondent from 12.9.2019 - 18.10.2019

and that 600 units were admittedly withheld by the respondent. It is also

significant that the only reason apparent from the order of the Division

Bench dated 6th September, 2023 for remanding matter to the First Court

was that the respondent failed to indicate its stand on the contents of the

chart before the First Court.

11. Moreover, the Purchase Orders mention the admitted rate of rent

payable by the respondent to the petitioner with individual rates of rent for

the MS Props on a monthly basis. Hence, this sum cannot be disputed by

the respondent. The calculation of the admitted rent due to the petitioner at

the agreed rate mentioned in the Purchase Orders is hence merely a matter

of arithmetical calculation. The petitioner has simply calculated the agreed

rate of rent on the number of units used by the respondent from November,

2019 to July, 2023 including for the withheld 600 units.

12. The contention of the petitioner that the petitioner would have

received a much higher rent on the goods if the respondent had returned the

units to the petitioner within the stipulated time under the Purchase Order

cannot be ignored. In the present case, the petitioner has restricted its claim

of security to the aggregate sum payable by the respondent for continued

use of goods till July, 2023 together with the fact that a portion of the goods

has also been disposed of by the respondent despite the order of injunction

passed by the Division Bench on 2nd March, 2023.

13. The Court is also not in agreement with the respondent on the issue of

delay. In making such objection, the respondent has to first cross the hurdle

of giving a satisfactory explanation as to why the respondent held on to 600

units from July, 2020. This is the admitted case and would be reflected from

the respondent's affidavit-in-opposition. Further, the petitioner initiated to

proceed under the Micro, Small and Medium Enterprises Development Act,

2006 (MSMED) on 15th July, 2020. The records show that proceedings

initiated under the MSMED Act were prolonged due to the dilatory tactics of

the respondent and the conciliation proceedings were ultimately terminated

on 5th January, 2023. The application under section 9 was filed immediately

thereafter on 7th February, 2023.

14. Significantly, the respondent withheld 600 units of the petitioner

throughout this period which means that the cause of action continued on a

day to day basis and aggravated the petitioner's claim against the

respondent.

15. The powers conferred on a Court under section 9 of the 1996 Act

includes the power to make an order for securing the amount in dispute in

arbitration. It is also substantially settled that the Court can make such

orders as may appear to be just and convenient without being fettered by

the regime of Order XXXVIII Rule 5 of The Code of Civil Procedure, 1908

where the sum is admitted and the defence is prima facie untenable; Essar

House Private Limited v. Arcellor Mittal Nippon Steel India Limited; 2022 SCC

OnLine SC 1219 and Abheya Realtors Private Limited v. SSIPL Retail Limited;

(2010) 2 CHN 203.

16. Considering the relevant facts and circumstances and the admitted

amounts pertaining to the rent payable by the respondent for use of the

petitioner's goods from November, 2019 to July, 2023 including withholding

of 600 units of the petitioner's goods, the court accepts that the petitioner is

entitled to claim compensation and damages for the retention of the goods.

The respondent should accordingly secure the amount in aid of the interim

measure under section 9 of the Act.

17. AP 70 of 2023 is accordingly allowed and disposed of by directing the

respondent to furnish security for a sum of Rs. 53,07,352/- on the basis of

the tabulated calculation which is a part of the petition inclusive of the sum

received by the petitioner as advance from the respondent. The respondent

should furnish the amount, 50% by way of cash deposit and the remaining

50% by way of a bank guarantee, to be deposited to the Registrar, Original

Side of this Court within two weeks from date.

AP 71 of 2023

18. The petitioner has sought for a direction on the respondent to furnish

security for Rs. 7,93,268/- on the same ground and on the same facts as in

AP 70 of 2023. The undisputed facts which are relevant for the adjudication

has already been stated above in the first section of the judgment and are

not being repeated. The claim of the petitioner arises out of the MS Props

unit supplied by the petitioner to the respondent. The respondent used the

goods from July, 2019 - February, 2020 and also removed the units/goods

from its custody which would be evident from the Receiver's Report. The

Receiver was appointed by the Division Bench by its order dated 6th

September, 2023 in an appeal filed by the respondent from the order of the

First Court.

19. The first section of the judgment also refers to a chart handed up by

learned counsel appearing for the petitioner as per facts admitted in the

affidavit-in-opposition of the respondent with regard to the respondent's use

of the goods and duration thereof. A statement of the admitted rent due

from the respondent to the petitioner is also part of the chart. The petitioner

claims a total amount of Rs. 22,29,120.00/- in the other arbitration petition

being AP 70 of 2023.

20. As stated above the facts are not being repeated.

21. The only point which learned counsel appearing for the respondent

has raised in the present application is the lack of the pecuniary jurisdiction

for the Court to entertain the present matter. Counsel has argued that the

mail from the petitioner to the respondent dated 14th July, 2020 reflects the

value of the withheld goods to be lesser than Rs. 10 lacs which divests the

High Court of jurisdiction to entertain the matter.

22. However, the fact remains that the present application for interim

protection has already been entertained by the Court and was carried to the

Division Bench which proceeded to pass orders on 2nd March, 2023 and 6th

September, 2023 restraining the respondent from relying on the mail dated

14th July, 2020. Significantly, the Division Bench in its order dated 2nd

March, 2023, refused to accept the stand taken by the respondent on the

mail dated 14th July, 2020. The respondent has not challenged any of the

orders passed by the Division Bench.

23. Learned Counsel appearing for the petitioners has also relied on a

chart with a calculation of admitted rent due from the respondent as per the

purchase orders. The total rent of all goods per month is Rs. 35,297/- and

the outstanding principal sum of rent from July, 2019 to February, 2020 is

Rs. 2,02,376.00/-. The chart contains particularised statements of claim for

the goods withheld by the respondent from March, 2020 to July, 2023 which

is Rs. 40,000/- and also calculates the total amount due for the withheld

goods at Rs. 1,69,480.00/-. A sum of all these figures comes to

Rs.3,71,856.00/-. The chart was shared with learned counsel appearing for

the respondent.

24. On the point of law, the Court finds the contention made on behalf of

the petitioner to be of substance, namely, that the application has been filed

on the basis of the principles under section 12 of the Commercial Courts

Act, 2015 under which the relief sought in the arbitration are relevant for

determining the satisfied value. The petitioner has prayed for security in the

application for approximately an amount of Rs. 7.93 lacs along with

injuctive relief for withholding of the goods. The aggregate value of rent

hence comes to above Rs. 10 lacs. Reference in this context may be made to

section 12(a), (b) and (d) of The Commercial Courts Act, 2015 which takes

into account the money sought to be recovered being inclusive of interest

computed up to the date of filing of the application as well as the market

value of the immovable property on the date of the filing of the application.

Section 12(2) refers to the aggregate value of the claim and counter-claim as

set out therein in a commercial dispute which is to form the basis for

determining the jurisdictional Court.

25. Hence, the consideration which is germane to the argument of

pecuniary jurisdiction, or the lack thereof, is the correctness of the

petitioner's valuation of the reliefs sought in the application and in the

respondent's construction of the mail dated 14.7.2020.

26. Even if the specific contents of the mail are taken into consideration,

the relevant column pertaining to amounts pending from the respondent on

account of the materials lying at Naihati reflects the "cost" and not the value

of the balance goods. The cost referred to is that of refurbishment of goods

after their return to the petitioner so that the goods can be let out to other

clients. The fact that "cost" is not equivalent to the value of the goods would

also be evident from the respondent's purchase orders which provides for

the agreed monthly rental to be paid by the respondent for these goods. The

figure is slightly less than ½ of the alleged total value of the goods. Hence,

the construction given by the respondent to this mail and to the figures

contained therein is untenable and reflects an erroneous understanding of

the petitioner's mail. The object appears to be divesting the Court of

jurisdiction on a ground which is non-existent.

27. The pecuniary jurisdiction argument is hence answered against the

respondent.

28. The particulars of the basis of the petitioner's claim for security is

tabulated in the petition. The petitioner has claimed the amounts due

against the bills and invoices raised by the petitioner on the respondent for

the respondent's use of the petitioner's equipment on a compoundable-

interest basis. The petitioner has also claimed compensation and damages

for the respondent retaining 600 units / balance material and has adjusted

the sum of Rs. 80 lakhs received as advance from the respondent.

28. The Court, under section 9 of The Arbitration and Conciliation Act,

1996, has plenary powers - including the power to make an order for

securing the amount in dispute in the arbitration. The petitioner, as the

claimant in the arbitration and as a party to the arbitration agreement has a

statutory right to approach the Court for interim relief. The respondent's

action of withholding a substantial quantity of the petitioner's goods till

date, contrary to the agreement between the parties and alienating the

goods in the face of the order of injunction passed by the Division Bench,

are additional factors for the Court to pass interim measures of protection in

favour of the petitioner.

29. The Court finds no basis to refuse interim protection in view of the

above reasons. AP 71 of 2023 is accordingly allowed and disposed of by

directing the respondent to furnish security for the sum of Rs. 7,93,268/-,

50% of which shall be in the form of cash deposit and remaining 50% by

way of bank guarantee. Both the components should be furnished with the

Registrar Original Side within 2 weeks from date. The petitioner shall be

permitted to approach the Court for further and other injunctive reliefs

against the respondent in default of these directions.

30. Connected applications, if any, are also disposed of along with the two

arbitration petitions.

Urgent Photostat certified copies of this judgment, if any, be supplied

to the parties upon fulfillment of requisite formalities.

(Moushumi Bhattacharya, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter