Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Damodar Valley Corporation vs Bla Projects Pvt. Ltd
2024 Latest Caselaw 2588 Cal/2

Citation : 2024 Latest Caselaw 2588 Cal/2
Judgement Date : 13 August, 2024

Calcutta High Court

Damodar Valley Corporation vs Bla Projects Pvt. Ltd on 13 August, 2024

Author: Sabyasachi Bhattacharyya

Bench: Sabyasachi Bhattacharyya

                      In the High Court at Calcutta
                        Original Civil Jurisdiction
                           Commercial Division

The Hon'ble Justice Sabyasachi Bhattacharyya

                          AP-COM No. 231 of 2024

                      Damodar Valley Corporation
                                 Vs
                        BLA Projects Pvt. Ltd.


     For the petitioner       :    Mr. K. Kejriwal, Adv.
                                   Ms. Paramita Banerjee, Adv.
                                   Mr. Tamoghna Chattopadhyay, Adv.

     For the respondent       :    Mr. Jaydip Kar, Sr. Adv.

Mr. Suman Kr. Dutt, Adv.

Mr. S. Roy, Adv.

Mr. Debdeep Sinha, Adv.

     Hearing concluded on     :    08.08.2024

     Judgment on              :    13.08.2024

     Sabyasachi Bhattacharyya, J:-


1. The present challenge under Section 34 of the Arbitration and

Conciliation 1996 (hereinafter refer to as "the 1996 Act) has been

preferred against the award dated August 14, 2021 passed in an

arbitral proceedings between the parties. BLA Projects Private Limited

(the respondent herein) was the claimant. Out of the seven heads of

claim, four were allowed by the learned arbitrator. Counter claims on

two counts made by the Damodar Valley Corporation (DVC), the

respondent before the learned arbitrator and the petitioner herein,

were turned down.

2. Learned counsel for the petitioner argues that the award is contrary to

the terms of the contract. As per the contract, DVC was entitled to

terminate the contract if the claimant/BLA indulged in corrupt and

fraudulent practices. The relevant clauses relating to termination were

Clause 15 of the General Terms and Conditions, Clause 17 of the

General Conditions of Contract (GCC), Clause 14 of the Annual Rates

Contract (ARC) and Clause 24.2.1 of the Additional/Special

Conditions of Contract.

3. It is argued that all the clauses are almost identical and permit

termination in the event of corrupt or fraudulent practices in

executing the contract. Some of the said clauses also contemplate

termination at the sole discretion of the DVC, albeit with a 60 days‟

prior notice. It is argued that the learned arbitrator erred in holding

that „corrupt‟ and „fraudulent‟ practice were intended to cover

malpractice indulged in by the contractor in the matter of

procurement of the contract only and not activity in performance of

the contract. Thus, the other conditions of contract were overlooked

by the learned arbitrator.

4. In the present case, the first notice of termination was issued, after

which the matter came up to this Court and upon a direction being

passed by this Court, a hearing was given to both sides and a

reasoned order was passed by the Executive Director of the DVC. The

said reasoned order granted liberty to the DVC to issue termination

notice. In pursuance thereof, the termination notice was issued,

contemplating forthwith termination.

5. It is argued that the learned arbitrator failed to take into consideration

all the provisions of termination under the agreement between the

parties and stuck to Clause 24.2.1 only, thus rendering the award

contrary to the terms of the contract and violative of Section 21(3) of

the 1996 Act.

6. Learned counsel for the petitioner next argues that the

claimants/respondent indulged in corrupt and fraudulent practice.

The relevant documents show that fraud was perpetuated by the BLA

(claimant). The unloaded coal was contaminated with mud. The

contaminated coal was loaded at the siding. The defence taken by the

claimant was heavy rain, due to which the coal allegedly got mixed

with the mud and soil at the loading point (kaccha point). Thus,

inferior quality of coal was mixed with extraneous materials, which

was admitted by the claimant, thus making the claimant liable for

termination of its contract. It is argued that contamination of coal is

an admitted fact in the reply dated June 5, 2018 by the claimant to

the show- se notice dated June 2, 2018 and even in the statement of

claims and the cross-examination of the Claimant‟s Witness (CW).

7. With regard to claim nos.1 and 2, pertaining to the Running Account

(RA) bills, the learned arbitrator erroneously directed payment of such

bills since the BLA had indulged in a corrupt and fraudulent practice.

Under Clause 13 of the Annual Rates Contract, the DVC is, in fact,

entitled to impose penalty for carrying stones, shortages and in

respect of quantity etc, which was required to be adjusted from the

running bills.

8. Further, the Engineer-in-Charge of the DVC was to pass the bills after

scrutiny and final bill was to be made payable only after the

reconciliation of the bills, outstanding penalties etc. at the end of the

contract period. The running bills in the present case were not

processed by the DVC in terms of the contract and have not been

proved by the BLA.

9. The BLA, it is argued, did not raise the bills in terms of the contract.

Learned counsel appearing for the petitioner submits that it is

preposterous to contend that the claim can be allowed even without

proof merely because the provisions of the Evidence Act are not

applicable.

10. Regarding claim no.3 in respect of bank guarantee, since the claimant

indulged in corrupt and fraudulent practice, it is argued that the DVC

was entitled to retain the security deposit and bank guarantee.

11. Claim no.5 in respect of loss of profits was also erroneously awarded

by the arbitrator, it is contended. It is argued by the petitioner that

the contract was for a period of one year whereas it had to be

terminated after about two months‟ performance. However, BLA has

been awarded loss of profit for the entire balance period of the

contract which amounts to specific enforcement of the contract which

is determinable at the will of the DVC with 60 days‟ notice.

12. Learned counsel appearing for the petitioner argues that the learned

arbitrator has allowed the claim on the basis of the affidavit evidence

of CW which contains self-serving statements. A certificate by a

Chartered Accountant (CA) was relied upon, which was not proved

properly because the CA did not depose as witness. Mere production

of the certificate of a CA is not proved enough, it is argued.

13. Learned counsel submits that Question No. 500 was put to the CW in

cross-examination and the witness agreed that he cannot testify to the

contents of the CA certificate. As the BLA was under a legal obligation

to prove its claim with credible and adequate evidence, failure to do so

of its part made the claim of loss of profits liable to be rejected. The

statement of the CW simpliciter could not be sufficient basis to allow

the claim.

14. In respect of loss of reputation (claim no.6), it is argued that the BLA

itself had breached the contract, resulting in termination and

invocation of bank guarantee, and no evidence was led to prove that

the claimant suffered any loss of reputation. The said claim was

awarded as a matter of course.

15. The rejection of the counter claims of DVC, it is argued, was on the

sole basis that termination was held to be wrongful by the arbitrator.

However, the contamination of coal in at least 3 tippers was admitted.

The learned arbitrator also ignored that there was evidence of shortage

in the transported coal which was evinced from the cross-examination

of the CW. There was admitted shortage of about 1700 MT of coal

which equals to 1.14% of the coal delivered to the DVC.

16. Under Clause 13 of the ARC, the DVC is entitled to impose penalty for

slippage, carrying stone, shortage and for quantity etc.

17. Learned counsel for the DVC place reliance on Delhi Metro Rail

Corporation Ltd. v. Delhi Airport Metro Express (P) Ltd reported at

(2024) SCC Online SC 522, Ssangyong Engineering & Construction Co.

Ltd. v. National Highway Aruthority of India (NHAI) reported at (2019)

15 SCC 131 and Associate Builders v. Delhi Development Authority

reported at (2015) 3 SCC 49 for the proposition that an award that is

contrary to the terms of the contract is perverse and should be set

aside.

18. In order to substantiate the argument that if there is a contractual

clause allowing termination without reason, even if termination is held

to be wrongful/invalid on the basis of another clause, damages must

be limited to the notice period under the clause of termination at will,

learned counsel for the petitioner cites Indian Oil Corporation. Ltd. v.

Amritsar Gas Service and Others, reported at (1991) 1 SCC 533.

19. It is also argued that award for loss of profit should be based on

credible and adequate evidence and should not result in the

windfall/unjust enrichment of the claimant. In support of the said

contention, learned counsel cites Unibros v. All India Radio reported at

(2023) SCC OnLine SC 1366, Batliboi Environmental Engineers Ltd. v.

Hindustan Petroleum Corpn. Ltd. reported at (2024) 2 SCC 375 and

Executive Engineer v. Modi Project Ltd reported at (2024) SCC OnLine

Jhar 115.

20. Learned senior counsel for the claimant/respondent BLA, on the other

hand, argues that the scope of Section 34 of the 1996 Act after the

2015 amendment is extremely limited. It is argued that none of the

grounds of the said provision have been made out by the DVC.

21. An arbitral award cannot be challenged on its merits, it is argued, as

the court exercising power under Section 34 does not sit in appeal

over the order of the arbitral tribunal.

22. The 2015 amendment to the 1996 Act further narrowed the grounds

for setting aside the arbitral award. In Associate Builders (supra), it

was reiterated that merits of the decision rendered by an arbitral

award cannot be gone into in a challenge under Section 34. Only

when the award is in conflict with the public policy of India that the

merits can be looked into.

23. The Supreme Court, in its landmark judgments such as Renusagar

Power Co. Ltd. V. General Electric co. reported at (1994) Supp (1) SCC

644, etc. set out what would constitute a conflict with the

fundamental policy of Indian law, which is a sine qua non for an

award to be in conflict with the public policy of India.

24. It is argued that none of the said conditions are satisfied in the

present case. A possible view of the arbitrator on facts has necessarily

to pass muster as the arbitrator is the ultimate master of the quantity

and quality of evidence to be relied upon at the time of delivering the

arbitral award.

25. Learned senior counsel for the claimant next argues that in

Ssangyong Engineering (supra) it was recognised that the public policy

of India means the fundamental policy of Indian Law and the previous

tests of Associate builders (supra) will no longer apply.

26. Patent illegality has also been introduced as a ground by the 2015

amendment Act, under sub-section (2-A) of Section 34. However, such

patent illegality must go to the root of the matter and not amount to

mere erroneous application of the law.

27. The concept of patent illegality following the 2015 amendment has

been explained by the Supreme Court. Reappreciation of evidence is

specifically barred under the said ground.

28. Learned senior counsel next cites Patel Engineering Ltd. v. North

Eastern Electric Power Corporation. Ltd reported at (2020) 7 SCC 167

where a three-judge Bench of the Supreme Court dealt extensively

with the history of patent illegality as a ground for setting aside

domestic awards. The Supreme Court noted that the said ground is

available if the arbitrator‟s decision is found to be perverse or so

irrational that no reasonable person would have arrived at the said

decision.

29. In UHL Power Company Ltd. v. State of Himachal Pradesh reported at

(2022) 4 SCC 116, another three-judge Bench reiterated the settled

law that if there are two plausible interpretations of the terms and

conditions of the contract, the learned arbitrator can proceed to accept

one, which would not be interfered with under Section 34, unlike the

normal appellate jurisdiction.

30. Learned counsel next takes the court through the provisions of

termination of contract and argues that fraudulent or corrupt practice

as defined under the contract does not include contamination of coal,

which has been correctly explained by the learned arbitrator in his

award.

31. Learned senior counsel for the claimant/respondent submits that no

admission as to breach of contract has been made by the claimant in

any of its letters/documents, contrary to the arguments of the present

petitioner. In the two letters dated June 5, 2018 and June 29, 2018,

the respondent had only stated that the alleged incident of mixing of

mud with coal was due to circumstances beyond the control of the

respondent and that the contract contemplated such situation up to a

percentage. Mixing beyond the same might attract penalty if it is

found to be beyond the permissible level. The context of its admission

has been explained by the respondent in course of the arbitral

proceedings.

32. The view expressed by the learned arbitrator, being a plausible view

on appreciation of evidence, ought not to be interfered with under

Section 34.

33. With regard to the alleged corrupt/fraudulent practice, the

respondent argues that the DVC did not refer to any particular

phenomenon but to a sequence of isolated disjointed events. A single

test report of coal sample analysis has been produced by the

petitioner which indicates that coal was collected on June 2, 2018 but

was tested as late as on September 29, 2019, that is, after the first

sitting of the arbitrator, which palpably makes it clear that the same

was an afterthought.

34. Even the GCV (Gross Calorific Value) of coal was shown in the report

to be 3894. In a reply to a query made by the respondent under the

Right to Information Act, the DVC had admitted that the GCV of coal

received at the plant for the period April 2017 to December 2017 and

September 2018 was less than GCV 3894. Therefore, the quality of

coal received in the three tippers on June 2, 2018, by no stretch of

imagination, can be called "contaminated". If DVC could run the

Raghunathpur Thermal Power Plant with coal of GCV less than 3894

for the period from April to December 2017 without any complaint

and/or allegation of contamination, it is argued that it did not have

any case of contamination in respect of the test result of coal sample

with GCV 3894.

35. In the Statement of Claims, the claimant had also challenged the

order dated September 5, 2018 passed by the Executive Director

(Projects) of the DVC, in support of which various grounds and

pleadings were made. Upon considering the same, the learned

Arbitrator arrived at his findings and such appreciation of evidence

cannot be reopened under Section 34 of the 1996 Act.

36. Regarding the claim on account of unpaid RA Bills, that is, Claim No.

1, learned senior counsel for the claimant/respondent argues that the

works performed by the respondent had duly been certified by the

SDE (M) FM and SE (M) FM of the DVC. Despite the same, the DVC

released only a part of the claim, to the tune of Rs. 2,22,96,973/-,

withholding a sum of Rs. 3,38,31,962/- in violation of the contract.

DVC also failed to make out any case of short supply before the

learned Arbitrator. The learned Arbitrator, upon considering the

pleadings, RA Bills and the evidence on record, elaborately discussed

the same and rightly allowed the claim in favour of the claimant.

37. The respondent submits that the Claim No. 3 related to wrongful

invocation of bank guarantee. Since the termination of the contract

was held to be illegal and wrongful, the said claim was rightly allowed

by the Arbitrator.

38. The award on Claim No. 5 on account of the loss of profit, it is argued,

was justified. Oral evidence was adduced to substantiate the claim of

twenty per cent of the unexecuted work. Coupled with the oral

evidence, a chart showing the break-up of the price quoted and

approved by DVC was also produced, to which there was no cross-

examination of the witness. Learned senior counsel places reliance on

A.E.G. Carapiet Vs. A.Y. Derderian, reported at AIR 1961 Cal 359 for

the proposition that if the case of the defendant is not put in cross-

examination to the witness of the plaintiff, it has to be construed that

the case of the plaintiff has been admitted. That apart, the award on

the claim on account of loss of profit is also justified by several

judgments of the Supreme Court, it is argued, which are as follows:

i) A.T. Brij Paul Singh Vs. State of Gujarat, reported at (1984) 4

SCC 59;

ii) Mohd. Salamatullah Vs. Govt. Of A.P., reported at (1977) 3 SCC

590;

iii) Dwaraka Das Vs. State of M.P., reported at (1999) 3 SCC 500;

and

iv) MSK Projects (I) (JV) Ltd. Vs. State of Rajasthan, reported at

(2011) 10 SCC 573.

39. Thus, it is argued that the present challenge ought to be dismissed.

40. The first issue which falls for consideration here is whether the

learned Arbitrator acted with patent illegality in holding that the

termination by the DVC of the contract between the parties was

unlawful.

41. In this regard, the petitioner relies on four termination clauses from

different parts of the contract between the parties. Clause 15 of the

Special Conditions of the Contract, under the head "General Terms

and Conditions", Clause 17 of the GCC, Clause 14 of the ARC as well

as Clause 24.2.1 of the ASCC, all provide for termination. However,

none of the clauses apart from Clause 24.2.1 contemplate forthwith

termination of the contract. The rest of the abovementioned clauses

envisage either 30 or 60 days‟ notice.

42. In the present case, admittedly, the termination was forthwith,

simultaneously with the issuance of the notice. Hence, in any event,

the other clauses are not applicable and, as such, the learned

Arbitrator was perfectly justified in focusing on Clause 24.2.1 as the

relevant termination clause. The germane provision of the said clause

was that for such forthwith termination, the contractor, in the

judgment of the employer, had to be engaged in corrupt or fraudulent

practices. However, such expressions "corrupt" and "fraudulent"

practices have been clearly defined in sub-clause (c) of Clause 24.2.1.

The expression "in competing for or in executing the Contract"

qualifies such practices. Hence, per se, it is evident that the said

practice, to be corrupt or fraudulent, had to pertain to competing for

or executing the contract.

43. "Corrupt practice" according to the said sub-clause means the

offering, giving, receiving or soliciting of anything of value to influence

the action of a public official in the procurement process or in contract

execution. The said clause, on the face of it, is not applicable even as

per the allegations of DVC.

44. "Fraudulent practice" is defined in the clause as a misrepresentation

of facts "in order to influence a procurement process or the execution of

a contract" to the detriment of the Employer and also includes

collusive practice among Bidders (prior to or after bid submission)

"designed to establish bid prices at artificial non-competitive levels and

to deprive the Employer of the benefits of free and open competition".

45. Hence, the fraudulent practice contemplated in the said clause

pertains ex facie to the stage of the tender process, till the execution of

the contract. In the present case, the claimant succeeded in the

tender process and was awarded a contract, pursuant to which it

worked for approximately two months. Thus, the applicability of

Clause 24.2.1 is ruled out at the outset.

46. The argument of the petitioner to the effect that the expression

"executing the contract" also means the performance of the contract is

specious. A comprehensive but plain reading of the said clause clearly

indicates that the entire fraudulent practice envisaged therein revolves

around the bidding process, in order to obviate artificial non-

competitive pricing which would curtail free and open competition.

The said practice, as envisaged in the clause, has to be for the

purpose of influencing a procurement process or the execution of a

contract.

47. It is to be noted that the conscious expression used in the said clause

is "execution of a contract" and not "execution of the work". Hence, by

no stretch of imagination can it be construed that the fraudulent

practice overreaches the stage of execution of the contract and

transgresses into the domain of performance of the contract.

48. As such, the learned arbitrator was perfectly justified in holding that

the termination itself was unlawful.

49. With regard to the RA Bills, the claimant is justified in arguing that

the work done was approved from the end of the DVC itself. Moreover,

the learned arbitrator elaborately discussed the evidence on such

issue at length and came to the conclusion that only two elements

needed to be considered, being the quantity of coal covered by the four

RA Bills and any other factor which may have a bearing in the process

and quantification, such as moisture content or purity in the coal.

When the quantity had been ascertained, it was held, one only had to

apply the rates as per MT as provided in the agreement.

50. The arbitrator took into consideration the fact that the DVC had paid

a substantial amount out of the said total claim upon verifying and

being satisfied that the stipulated procedure or process of claim had

been adhered to by the claimant. The arbitrator also considered that

if bills had been raised in a regular fashion it was open to the

respondent (DVC) to question the correctness of it but here,

apparently no contemporaneous objection was raised by the DVC

showing why that amount claimed was not payable.

51. The learned arbitrator recorded that he raised a query with learned

counsel for the DVC to furnish the DVC‟s version as to the quantity of

coal supplied by the claimant, preferably with a breakup, to which

counsel submitted, unless in consultation with the claimant effort is

made for reconciliation, it might not be possible to give a precise

amount. The arbitrator thus rejected such contention since the DVC

in the natural course of things must be presumed to be in possession

of all bills and relevant document relating to such supply.

52. The Arbitrator further considered several other aspects of the matter

including the statements contained in the affidavit of evidence of the

DVC‟s witness, one Gupta Bhaya. The claimant‟s counsel put a

question to him in the course of cross-examination that he was the

responsible person entrusted to oversee the operations in connection

with the transportation of coal, regarding quantity or quality. In such

context, it was observed by the arbitrator that the DVC was

deliberately withholding relevant evidence and adverse inference was

drawn against the DVC.

53. The third RA Bill, it was recorded by the learned arbitrator, was

virtually admitted by the witness Gupta Bhaya in answer to Question

Nos. 358-359 and the quantity supplied under the fourth RA Bill was

also similarly admitted, which was clear from perusal of the relevant

documents appearing at page nos. 7, 8, 9, 11 and 16 of the claimant‟s

Compilation of Documents placed before the learned arbitrator. The

arbitrator thus came to the conclusion that there was no question of

short supply and no justification, accordingly, for the DVC to withhold

the claims on the RA Bills.

54. Insofar as the loss of profit is concerned, the learned arbitrator also

entered into elaborate details and relied on a Chart, being Annexure -

„A‟ to the Annual Rate Contract (ARC), showing how the agreed price of

Rs. 369.179 per MT was calculated by taking into consideration the

break-up of charges for transportation, unloading of rakes and loading

of vehicles and liaisoning.

55. The break-up of price calculation read with the calculation shown in

Paragraph 8 of the affidavit of evidence of one Indrajit Roy Sarkar, who

adduced evidence for the claimant, were considered to hold that the

rate of profit of 20 per cent was established.

56. The explanation as to the calculation, it was observed by the learned

arbitrator, was further elaborated in Paragraph nos. 9, 41 to 44, 46 to

52 in his affidavit of evidence, which testimony was not cross-

examined with any meaningful purpose and remained unchallenged.

Upon such elaborate consideration of the evidence, the learned

arbitrator came to its conclusions regarding loss of profit.

57. With regard to Claim no. 6, that is, loss of reputation and goodwill, the

arbitrator looked into several aspects of the matter. Also, fact remains

that the continuing commercial relation between the parties since long

was uncontroverted. The work was awarded to the claimant, also

after checking the claimant‟s credentials during the tender process.

Moreover, since the termination was held to be unlawful, it would

obviously affect the future business and goodwill of the claimant,

since it is common business practice that prior termination in earlier

contracts is to be disclosed in every commercial tender. The qualitative

aspect and the principle on which loss of reputation was awarded in

favour of the claimant, thus, cannot be disputed. Insofar as the

quantitative aspect is concerned, a mere token Re. 1/- was awarded

under the said head and, as such, the said aspect cannot be gone into

at all.

58. Insofar as the counter claims of the DVC are concerned, the learned

arbitrator based his findings on the fact that the termination itself was

bad, for which the claimant was not entitled to such counter claims.

The arbitrator also considered that an amount of Rs. 284.97 Crore

was claimed for loss of earning revenue on account of loss of

generation of electricity due to alleged failure on the part of the

claimant to transport for the target quantity contemplated in the

contract. As the basis of such assessment, as recorded by the learned

arbitrator, the respondent/petitioner-DVC relied on an order of the

Central Electricity Regulatory Commission (CERC) dated September

28, 2017 which was passed in a matter to which the claimant was not

a party.

59. Also, since the termination itself was wrongful, it was held that no

fault could be attributed to the claimant for not performing the

contract for its full tenure.

60. Also, the learned arbitrator held that the loss alleged to be suffered

was too remote in the sense that likelihood of such loss was not within

the reasonable contemplation of parties when the agreement was

made.

61. On such elaborate discussion only, the learned arbitrator turned down

the counter claims.

62. Thus, it is amply clear that the learned arbitrator gave elaborate

reasons and delved into a detailed factual appreciation of the entire

evidence on record and came to his findings as befits a reasonable and

prudent man.

63. This Court, as is well-settled by the Supreme Court in the several

judgments cited by the parties including Associate Builders (supra),

Ssangyong Engineering (supra), Patel Engineering Limited (supra) and

UHL Power Company Limited (supra), cannot enter into a

reappreciation of evidence like a regular first appellate court, sitting in

a challenge under Section 34 of the 1996 Act. The limited window

which could have been invoked by the DVC is found in sub-section

(2-A) of Section 34, which makes patent illegality a ground for

challenge. However, such patent illegality has to appear on the face of

the award. Also, the proviso to the sub-section stipulates that an

award shall not be set aside on the said score merely on the ground of

an erroneous application of law or by reappreciation of evidence.

64. In the present case, I do not even find any erroneous application of

law, let alone any occasion to reappreciate the evidence. The

judgment of the Arbitrator is perfectly well-reasoned and supported by

cogent evidence and, as such, none of the grounds of challenge under

Section 34 of the 1996 Act are established.

65. There is nothing in the award to attract the grounds of contravention

of the fundamental policy of Indian law or to hold that it is in conflict

with the basic notions of morality or justice.

66. Hence, the present challenge under Section 34 of the 1996 Act is

entirely misconceived and accordingly must fail.

67. Accordingly, AP-COM No. 231 of 2024 is dismissed on contest without

any order as to costs, thereby affirming the award dated August 14,

2021 passed by the learned arbitrator in the arbitral proceedings

between the present parties.

68. There will be no order as to costs.

69. Urgent certified server copies, if applied for, be issued to the parties

upon compliance of due formalities.

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter