Citation : 2023 Latest Caselaw 3597 Cal
Judgement Date : 19 May, 2023
IN THE HIGH COURT AT CALCUTTA
Constitutional Writ Jurisdiction
Appellate Side
Present :-
The Hon'ble Justice Moushumi Bhattacharya.
W.P.A 27132 of 2022
M/s. Navkar Global Infra
vs.
Damodar Valley Corporation
With
W.P.A 27137 of 2022
M/s. Navkar Global Infra
vs.
Damodar Valley Corporation
For the petitioner : Mr. Kishore Dutta, Sr. Adv.
Mr. Srijib Chakraborty, Adv.
Mr. Moyukh Mukherjee, Adv.
Mr. Aditya Mondal, Adv.
Ms. A. Bazaz, Adv.
For the DVC : Mr. Samrat Sen, Adv.
Mr. Swarajit Dey, Adv.
Ms. Riddhi Jain, Adv.
Last Heard on : 08.05.2023.
Delivered on : 19.05.2023.
2
Moushumi Bhattacharya, J.
1. The writ petitions involve similar facts and have been filed against the
Damodar Valley Corporation. Both the writ petitions are being disposed of
by the judgment. A few of the dates are different; the facts and dates in WPA
27132 of 2022 are being mentioned in the judgment.
2. The petitioner participated in a Tender floated by the respondent
Damodar Valley Corporation for empanelment of transportation agencies for
evacuation of ash from ash ponds of Durgapur Steel Thermal Power Station
of DVC. The Tender was dated 9.9.2022. The petitioner has challenged the
rejection of the petitioner's techno-commercial bid on 1.12.2022 on the
ground of being "Non Compliant".
3. At the time of moving the matter the petitioner's grievance was that
the petitioner's bid was admitted by the Tender Evaluation Committee on
the same day i.e. 1.12.2022 at 2:04 pm but was rejected 11 minutes later at
2:15 pm.
4. The petitioner was granted interim protection by an order dated
9.12.2022 noting the narrow-margin of 11 minutes and directing DVC to
keep any further evaluation of the Tender in abeyance until the matter is
heard out on the returnable date. The interim order was extended
thereafter. Affidavits are now complete in the matter.
5. Learned counsel appearing for the petitioner submits that the
petitioner was eligible under the Tender conditions and the techno-
commercial bid submitted by the petitioner was rejected without application
of mind and for extraneous considerations. Counsel puts emphasis on the
margin of 11 minutes between the petitioner's bid being accepted at 2:04pm
on 1.12.2022 but thereafter being rejected at 2:15 pm on the same day.
Counsel places documents to show that the reason given for the impugned
rejection, namely, "Techno Commercially Non Compliant" is not a ground of
rejection contemplated in the Notice Inviting Tender. Counsel submits that
the petitioner had submitted all documents as required by the NIT and no
reasons have been given in support of the impugned rejection.
6. Learned counsel appearing for the respondent DVC submits that the
scope of work in the NIT, namely, evacuation of ash from ash ponds of the
Durgapur Steel Thermal Power Station of DVC and nuisance-free
transportation along with disposal of the ash in designated places outside
the plant boundary requires uninterrupted and continuous operation.
Counsel submits that DVC is seriously prejudiced by the operation of the
interim order. Counsel seeks to dislodge the allegation of the 11 minutes
margin by stating that the bids were opened on 17.10.2022 and the Tender
Inviting Authority informed the petitioner on 1.12.2022 of the impugned
rejection. Counsel submits that the impugned decision is fundamentally
different from administrative orders issued by the authorities in the general
running of the Government and that the decision taken in the present
matter is in the realm of contracts. Counsel submits that the authority is
not required to give a reasoned order as long as the rejection does not suffer
from any irregularity. Counsel places the affidavit filed on behalf of DVC to
submit that the petitioner's techno-commercial bid was rejected for
justifiable reasons.
7. Upon considering the material on record in connection with the
submissions made on behalf of the parties, the Court arrives at the following
findings.
8. Although the primary contention at the time of interim relief was the
11 minutes difference in the admission and rejection of the petitioner's
techno commercial bid, a closer look at the documents reveals otherwise.
The petitioner's bid was opened on 17.10.2022 along with the bids of other
bidders who have participated in the tender. A host of correspondence
followed thereafter including on 15.11.2022, 17.11.2022, 24.11.2022,
28.11.2022 and 29.11.2022. The correspondences are part of the affidavit
filed by the DVC. The correspondence show that DVC sought for
clarifications on the documents submitted by the writ petitioner and that
the writ petitioner furnished documents to provide such clarifications. The
petitioner's techno-commercial bid was rejected on 1.12.2022 only after DVC
considered these documents.
9. Further, the tender process was admittedly conducted through the
Central Public Procurement Portal (CPPP) which generated a system-
generated mail whenever the Portal was accessed. This system-generated
mail was what the petitioner relied on as an "admission" of the petitioner's
bid at 2:04 P.M. on 1.12.2022 which was followed by the impugned rejection
at 2:15 P.M. on the same day. The documents also show that similar
system-generated mails were sent to all the participating bidders on
1.12.2022 at 2:04 P.M.
10. Therefore, the argument of rejection of the bid within the span of 11
minutes of admission of the same is belied from the documents on record.
11. It is also arguable whether the petitioner was qualified to submit the
bud under the eligibility criteria set out in clause 5.01 of the Detailed
Invitation For Bid of the NIT. Clause 5.01 requires the bidder to furnish
details of having completed "similar works" within India during the last 7
years ending the last day of the month previous to the one in which the offer
is invited.
12. Clause 5.01 contains three classifications of the works including two
similar completed works each costing not less than an amount equal to Rs.
15,08,48,404/-. The "Notes" for the technical criteria for clause 5.01 further
explains the meaning of "completed work" and "similar work".
13. The affidavit filed by DVC shows that the petitioner failed to furnish
details of similar or completed works of the financial parameters mentioned
in clause 5.01 of the NIT. The insufficiency of the documents includes the
petitioner's disclosing the Letter of Intent without submitting documents of
completion or the value of the work actually completed. In other cases where
the petitioner has disclosed Letters of Intent along with work done
supported by certificates of completion, the documents do not indicate
segregation of the value of work in relation to similar nature of work. DVC
has also given instances of requesting submission of appropriate documents
from the petitioner's employer Tata Project Limited but did not receive any
response from the petitioner's employer as to the value of work which could
be categorised as transportation which was the requirement of the NIT.
Moreover, the purchase orders submitted by the petitioner for different
items of work done are less than the minimum financial requirement in
clause 5.01.
14. The affidavit of DVC, which deals with the petitioner's documents in
detail, raises a doubt as to whether the petitioner was at all eligible to
participate in the Tender under the parameters including clause 5.01 (of the
Detailed Invitation For Bid of the NIT) or otherwise.
15. In Silppi Constructions Contractors v. Union of India; (2020) 16 SCC
489, the Supreme Court relied on Jagdish Mandal v. State of Orissa; (2007)
14 SCC 517 to hold that evaluating tenders and awarding contracts are
essentially commercial functions where the principles of equity and natural
justice stay at a distance. It was further held that while rejecting a tender,
the authority inviting the tenders is not required to give reasons even if it is
within a State under Article 12 of the Constitution. The Supreme Court took
a practical look of the matter to opine that giving of reasons at every stage
would disrupt the commercial activities of the State. In the present case, the
tender authority rejected the petitioner's techno-commercial bid by stating
that the bid was found to be techno commercially non-compliant at the
stage of evaluation by duly constituted Committee of DVC. The impugned
rejection cannot be interfered with on the ground of being insufficient or
arbitrary following the decisions of the Supreme Court in Silppi
Constructions and Jagdish Mandal.
16. The prohibition of Mohindhr Singh Gill v. Chief Election Commissioner;
New Delhi; (1978) 1 SCC 405 would apply when the authority tries to
supplement reasons already given with fresh reasons. This would further
not apply to the present case which involves the evaluation of a tender and
in light of the pronouncement of the Supreme Court in Silppi Constructions
where the Supreme Court held that the authority can provide the reasons
for rejection of a bid in the counter to the writ petition.
17. Even otherwise there are several decisions of the Supreme Court
which reiterate the limited power of judicial review in matters of tender
including N.G. Projects Limited v. Vinod Kumar Jain; (2022) 6 SCC 127 and
National High Speed Rail Corporation Limited v. Montecarlo Limited; (2022) 6
SCC 401. In the last decision, namely Montecarlo, the Supreme Court
observed that before interfering with a contract in exercise of the powers of
judicial review, the Court should ask itself whether the decision of the
authority is mala fide or intended to favour someone or whether the process
adopted is so arbitrary and irrational that no responsible authority acting
reasonably could have reached that decision.
18. The facts which emerge from the records and the settled law of the
subject persuade this Court to deny the relief prayed for.
19. The decisions cited on behalf of the petitioner namely Bharat Singh v.
State of Haryana; (1988) 4 SCC 534 required a party to complete and prove
facts by evidence and from the pleadings on record. Contrary to the
contentions of the petitioner, the present matter does not involve any point
of law which is required to be substantiated from the material on record. It
is essentially a factual dispute where DVC has brought the relevant facts
before the Court. A.K.K. Nambiar v. Union of India; (1969) 3 SCC 864 is on
verification of an affidavit/petition and its admissibility as evidence. The
petitioner has sought to dispute the authority of the deponent of the
affidavit filed by the DVC. The deponent of the affidavit is the Joint Director
(HR)- Law of DVC and there is nothing on record to raise doubts as to his
authority to verify and affirm the affidavit. M.P. Power Management Company
Limited, Jabalpur v. Sky Power Southeast Solar India Private Limited; (2023)
2 SCC 703 lays down the scope of judicial review at the post-contract stage.
Hence, this decision may not assist the petitioner at the stage of a tender
which is essentially pre-contract.
20. Both WPA 27132 of 2022 and WPA 27137 of 2022 are found to be
without merit for the reasons stated above. The writ petitions are hence
dismissed and the interim orders dated 9.12.2022 are accordingly vacated.
Connected applications, if any, are also disposed of. There shall be no order
as to costs.
Urgent Photostat certified copies of this judgment, if applied for, be
supplied to the parties upon fulfillment of requisite formalities.
(Moushumi Bhattacharya, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!