Citation : 2023 Latest Caselaw 482 Cal
Judgement Date : 17 January, 2023
January 17, 2023
Item No. 1
Court No.1
PA(RB)
WPA (P) 238 of 2022
Tarakeswar Green Mates & Anr.
vs.
State of West Bengal & Ors.
Mr. Raghunath Chakraborty, Advocate
... for the petitioners
Mr. Rabindra Narayan Dutta,
Mr. Kakali Naskar, Advocates
... for the state respondents
In this public interest petition, the petitioner,
which is an NGO, has raised the issue relating to
felling of trees in the process of widening of
Tarakeswar-Chawkdighi Road. It is stated that 826
trees on both sides of the road will be cut in the
process of widening and such cutting of trees will
have adverse impact on environment and ecological
balance. Further plea has been raised that necessary
permissions have not been obtained and due
procedure has not been followed before starting the
process of cutting of the trees. In the writ petition,
the prayer is to restrain the concerned respondents
from cutting the trees.
Learned counsel for the respondent had assured
this Court on 25th of July, 2022 that till the nest
date of hearing, no trees in question will be cut.
Thereafter, the report in the form of affidavit on
behalf of the respondent no. 4 has been filed placing
on record the relevant documents. On the direction
of this Court, the original record relating to
permission to cut the trees in question has been
produced.
Submission of learned counsel for the petitioner
is that the due procedure was not followed and
relevant information was not disclosed while taking
the permission to cut the trees. Referring to the
document enclosed along with the report dated 29th
of July, 2022, he has submitted that the documents
enclosed with the application for felling of trees in
prescribed Form-I (B) have not been disclosed and
that certificate in connection with felling of trees in
Form-I (C) is signed by the Pradhan but it does not
disclose any resolution of the concerned Panchayat.
He has further submitted that in terms of the
notification dated 22nd of August, 2013, prior
clearance of the impact assessment authority is
required and that in the inquiry report Form-II, all
the columns have not been filled up. He has further
submitted that the concurrence of the West Bengal
Pollution Control Board has not been obtained and
provisions of Section 9 of the West Bengal Trees
(Protection and Conservation in Non-Forest Areas)
Act, 2006 have not been complied with and
provisions of the West Bengal Trees (Protection and
Conservation in Non-Forest Areas) Rules, 2007 (for
short, 'Rules of 2007') have not been adhered to.
Learned counsel for the State has submitted
that the trees are standing on the government land
and they are on both sides of the existing road.
Therefore, it is necessary to cut those trees for the
purpose of widening of the road. He submits that
due procedure has been followed and all requisite
permissions have been taken, therefore, there is no
legal impediment in cutting of those trees. He further
submits that compensatory plantation will be done
once the work of widening of road is complete and
the plan has already been placed on record in this
regard. He has also submitted that a declaration was
also filed before the competent authority giving time
limit for compensatory plantation and requisite
declaration will also be filed before this Court.
We have heard the learned counsels for the
parties and have perused the record. The original
record which is produced today has also been
perused.
The application in Form-I (B) for felling of trees
in non-forest areas/certificate of clearance in respect
of developer in terms of rule 4(2) and rule 7 (2) of the
Rules of 2007 was submitted for the purpose of
felling the trees in question. Along with the said
application, a list was enclosed disclosing the
species, approximate height, natural or planted,
physical condition, etc. of the trees. A compensatory
plantation plan duly approved by the Forest Range
Officer enclosed with the application, is available in
the original file. Certificate of clearance for developer
in Form-IV and permission for felling,
disposal/disposing of trees in non-forest area in
Form-III in terms of rule 5(2) is contained in the
original file. It has been pointed out that the
certificate in Form-I (C) is to be issued by the
Pradhan.
The notification dated 14th of September, 2006
has been placed on record, the schedule of which
contains the list of projects or activities requiring
prior environment clearance. The expansion of the
State highways, greater than 30 kms, is covered in
the said schedule. It has been pointed out by learned
counsel for the State that the expansion work in
question is not greater than 30 kms and that the
work relates to the State highways. Hence, we find
no error in the stand of the State that prior
environmental clearance is not required. The
notification dated 22nd of August, 2013 also takes
note of State highways expansion project except
those in hilly terrain and ecologically sensitive areas
exempted from purview of Environment Impact
Assessment Notification, 2006. Learned counsel for
the State has also relied upon the judgment of the
Hon'ble Supreme Court in the matter of National
Highways Authority of India vs. Pandarinathan
Govindarajulu and Another reported in (2021) 6
SCC 693 wherein the notification dated 22nd of
August, 2013 has been noted with approval.
Hence, we are of the opinion that due procedure
has been followed by the State authorities and
necessary permissions have been obtained for the
purpose of felling the trees in question. It is worth
noting that the felling of trees is for the public
purpose of widening of the road which cannot be
carried out otherwise.
Learned counsel for the petitioner has placed
reliance upon the judgment of the Hon'ble Supreme
Court in the matter of State of West Bengal and
Others vs. Mani Bhushan Kumar reported in
(2011) 10 SCC 147 but the said judgment relates to
the issue of concurrence in terms Section 88 of the
Motor Vehicles Act, 1988 in case of inter-state
permit. The present case stands on a different
footing and even otherwise, no irregularity in respect
of the concurrence by any competent authority has
been found in the matter.
So far as the compliance of Section 9 of the
State Act of 2006 is concerned, the record reflects
that the same has duly been complied with.
Thus, in the aforesaid circumstances, we do not
find any flaw in the permissions which have been
obtained by the respondent authorities for the
purpose of felling of trees.
The next issue is about compensatory
plantation of trees which is also an important and
relevant issue in this case. The original record
reflects that before the competent authority, a
declaration was submitted by the Assistant Engineer
that against the cutting of 840 number of trees, the
five times of trees, i.e., 840 x 5 = 4200 trees will be
planted on both sides of the Tarakeswar-Chawkdighi
road within the length of 13,000 mts. and within
18,000 sq.mts. and that the plantation will be done
on or before 22nd of January, 2022.
Learned counsel for the State has submitted
that compensatory plantation in terms of the said
declaration could not be done because the work has
not progressed. He has sought leave to file before
this Court an undertaking of the competent
authority disclosing the fresh cut-off date before
which the work of compensatory plantation will be
completed.
Hence, we adjourn the present petition for the
limited purpose of filing the above undertaking on
the next date of hearing.
List on 30th of January, 2023.
[Prakash Shrivastava, C.J.]
[Rajarshi Bharadwaj, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!