Citation : 2023 Latest Caselaw 1202 Cal
Judgement Date : 15 February, 2023
IN THE HIGH COURT AT CALCUTTA
Civil Appellate Jurisdiction
APPELLATE SIDE
Present:
The Hon'ble Justice Tapabrata Chakraborty
&
The Hon'ble Justice Partha Sarathi Chatterjee
FA 131 of 2017
Shyamal Kumar Roy
versus
Sushil Kumar Agarwal
For the Appellant : Mr. Tapash Kumar Bhattacharya,
Mr. Aviroop Bhattacharya,
Mr. Bishnu Prosad Singha Roy.
For the Respondent : Mr. Shuvanil Sen Gupta,
Mr. Debdut Mukherjee.
Hearing is concluded on : 31st January, 2023.
Judgment On : 15th February, 2023.
Partha Sarathi Chatterjee, J.
Preface :
1. The present appeal preferred at the instance of defendant/appellant
is directed against the judgment and decree dated 15th June, 2016 passed
by the learned Civil Judge (Senior Division), Second Court at Barasat, 24
parganas (North) in Title Suit no. 04 of 1999 whereby the suit for specific
performance of contract and permanent injunction instituted by the
developer against the owner was decreed.
Plaintiff/Respondent's Case :
2. Facts epitomized in the plaint presented by the
plaintiff/respondent/developer (in short, developer), in brief, are as follows :
i. That on 16.1.1995, owner of the premises No. P-173, Block B,
P.S. - Lake Town, Kolkata-89 (hereinafter referred to as the suit
property) entered into a development-agreement with the
developer for construction of a four storied building thereon and
parties to the agreement covenanted that within four months
from the date of execution thereof, owner shall get plan
sanctioned from South Dum Dum Municipality at his own costs
and hand over the sanctioned plan to the developer and in case,
within a period of four months from that date or any other
extended time for another two months, the plans are not
sanctioned due to any reason whatsoever, the developer shall be
at liberty to demolish the entire building and to submit new
building plan and in that event the owner shall get 40% of the
constructed area and the developer shall get balance 60% of
constructed area;
ii. It was expressly agreed and/or understood that with effect from
the date of execution of agreement and at all times during
subsistence of the agreement, the developer shall have full and
free and unfettered access into and out of the said premises;
iii. Developer shall pay Rs.7 (seven) lakhs to the owner as monetary
consideration, out of which Rs.3,31,000/- was to be paid on
the date of execution, Rs.51,000/- at time of handing over the
sanctioned plan and rest Rs.3,18,000/- would be paid
simultaneously with the delivery of possession by the developer
to his nominee/nominees and/or purchaser, as the case may
be, without payment of the said sum to the owner;
iv. Developer covenanted that construction shall be completed and
he shall make the same tenantable and shall hand over
possession within 12 months from the date of obtaining and
delivering sanctioned plan and vacating and delivering
possession of the premises;
v. It was agreed by and between the parties that owner shall get
ground floor with one car parking space and the first floor as his
allocation whereas developer's allocation would be second and
third floor of the building;
vi. It was claimed therein that plaintiff-developer paid
Rs.3,31,000/- on the date of execution of agreement and then,
from time to time he paid Rs.4,50,000/- to the owner till date;
vii. That the defendant being the owner submitted modified plan on
repetitive occasions and submitted plan for getting sanctioned
five times i.e. on 13.2.1995, 5.3.1995, 29.3.95, 11.4.95 and
22.5.95 before the competent authority and lastly, on
22.9.1995, sanctioned plan was handed over to the plaintiff
and possession of the premises was handed over after Diwali of
that year. In the result, there had been a delay of more than two
months;
viii. That the developer started construction diligently and in the
month of January, 1996 he completed construction of ground
and first floor of the building and even handed over possession
to the owner;
ix. That taking possession of ground and first floor, i.e. his own
allocation, owner started creating disturbance in the way to
early completion of the rest construction i.e. developer's
allocation. The owner off and on put padlock on the storeroom
and denied access of the plaintiff and his workers to the suit
premises. Lastly on 24.10.96, the developer was prevented from
entering the premises and from storing building materials and
hence, developer was constrained to lodge one diary with local
P.S. which was registered as GDE no. 1007 of 1996 dated
24.10.96;
x. That in the meantime, by giving one letter dated 3.10.1996,
owner asked the developer to start construction within seven
days from the date of receipt thereof and to complete
construction within three months;
xi. The developer responded to that letter by his letter dated
14.10.1996 wherein he mentioned that due to non-cooperation
on the part of the owner, the rest part of the construction could
not be completed and one instance was cited that on 11th
October, 1996 the owner refused to hand over key of the go-
down and prevented the developer from storing the building
materials and the owner also did not allow the electricians to do
their job. By the letter dated 14.10.1996 cooperation from the
owner was solicited but in vain;
xii. That then by one letter dated 18.10.1996, suddenly, the owner
terminated the contract;
xiii. That on 4.11.1996, developer lodged one complaint with the
local P.S. and on 8.11.1996, developer gave a notice to the
owner asking him to allow him to make construction and the
owner replied to that notice dated 8.11.1996 by giving two
letters dated 11.11.96 and 14.11.96. The developer gave a
further notice on 3.12.1996 to which the owner responded on
12.12.1996;
xiv. That in 1997, developer filed a suit vide. Title Suit no. 14 of
1997 for declaration and injunction and on 17.3.97, his
application for interim injunction was turned down and hence,
order dated 17.3.1997 was assailed in Misc. appeal no. 66 of
1997 and by an order dated 29.11.97, order passed by the
learned trial court on 17.3.1997 was set aside and by passing
an order of injunction, respondent therein being the owner was
restrained from creating any obstruction and interference in the
development and construction work in the suit premises and
owner was also restrained from alienating the suit property to
third party in violation of the terms of the agreement till the
disposal of the suit;
xv. That the owner impugned the order dated 29.11.97 before the
Hon'ble High Court at Calcutta in C.O. no. 3270 of 1997 which
was allowed by an order dated 25.9.98 and order dated
29.11.1997 was set aside;
xvi. That on 4.1.99, Title Suit no. 14 of 1997 was withdrawn with
liberty to file afresh on the self-same cause of action and on
8.1.99, the suit vide. Title Suit no.04 of 1999 was filed.
Defendant/Appellant's Case :
3. Defendant/appellant/owner (in short, owner) resisted the suit by
filing written statement wherein denying all the averments made in the
plaint, it was specifically contended as follows :
i. That the terms and conditions of the agreement dated
16.1.1995 are not binding upon the defendant since the same
had been cancelled;
ii. That the plaintiff had never requested the defendant to allow
him to complete the remaining work of construction;
iii. That on 22.9.1995, plaintiff received the sanctioned plan
without any objection and plaintiff was to complete the
construction within 12 months from the date being 22.9.1995
i.e. within 21.9.1996 but he failed and neglected to complete the
construction within the time stipulated in the agreement;
iv. On 14.2.1996, plaintiff stopped construction work and finally
left the site on 16.5.1996 and he took away all the building
materials from the site;
v. That on 03.10.96, the defendant by giving a letter requested the
plaintiff to start construction work and then, lastly by one letter
dated 18.10.96, defendant cancelled the agreement;
vi. That the plaintiff paid only Rs.4,15,000/- on diverse dates out
of Rs.7,00,000/-;
vii. That suit for specific performance of contract cannot lie in like
case since compensation would be the adequate remedy for
breach of such contract;
viii. That the allegation contained in the notice of the plaintiff dated
14.10.96 had no legs to stand in view of the conduct and
performance of the plaintiff and it was claimed that defendant
completed finishing work of 1st floor;
ix. That the suit is barred by limitation and is hit by the provisions
of Order 2 Rule 2 of the CPC;
x. That in the agreement, there was an arbitration clause (clause -
26) and hence, the suit is not maintainable.
Case - record :
4. Record postulates that in corroboration of the fact depicted in the
plaint, plaintiff adduced oral testimonies of four witnesses including himself,
who were examined as PW-1 to 4 and plaintiff tendered some documents
which were admitted in evidence and marked as Ext.1 to 22. On the other
hand, to lent support to the contents of written statement, defendant
produced oral accounts of three witnesses including himself, who were
examined as DW-1 to DW-3 and documents produced by the defendant were
marked as Ext.-A to O.
5. As has been stated earlier, learned court below decreed the suit and
directed the defendant to give free access to the plaintiff into the suit
property so that plaintiff can complete rest portion of the construction and
defendant was restrained from creating any obstruction to the plaintiff in
completion of the construction.
Grounds of appeal :
6. Aggrieved thereby, the present appeal has been preferred
contending, inter alia, that the learned court below failed to consider that it
was not the plaintiff but the defendant who was ready and willing to
perform his part of the contract and plaintiff was under obligation to
complete entire construction and deliver possession of owner's allocation
within 12 months from the date of receipt of sanctioned plan and delivery of
possession of the site and plaintiff only tried to store building materials in
the premises on 24.12.1996 i.e. long after one year from the date of
agreement and learned court below did not consider that suit was barred by
limitation as well as by the provisions of Section 8 of Arbitration and
Conciliation Act, 1996 and such point was raised in written statement and
learned court committed mistake in passing the decree.
Submission of Appellant :
7. Mr. Bhattacharya, learned advocate appearing for the appellant i.e.
the owner argued the matter at length. Crux of his argument is that suit is
barred by the provisions of Section 8 of the Arbitration & Conciliation Act,
1996 (hereinafter referred to as the Act of 1996) and suit was barred by
limitation and it would be preposterous to say that since the court granted
leave to file a fresh suit, court condoned the delay. He asserted that delay in
filing any suit cannot be condoned. He submitted that question of limitation
is a question of jurisdiction also and since, suit was barred by limitation, the
learned court below lost its jurisdiction to entertain the suit.
8. He vociferously submitted that suit for specific performance of
contract instituted by developer is barred in view of Section 14(3)(c) of the
Specific Relief Act.
9. He added that the suit was barred under Order 2 Rule 2 CPC. He
asserted that in the given case, plaintiff failed to complete the construction
within 12 months and time was the essence of the contract and hence, the
agreement was rightly cancelled and he stated that plaintiff cannot get any
relief in such framing of suit. He prayed for setting aside of judgment and
decree.
10. In support of his contention, he placed reliance upon the
judgments delivered in the cases of Urvashi Aggarwal (since deceased) thr.
Lrs & Anr. -vs- kushagr Ansal (successor-in-interest of Erstwhile Def. no. 1
Mrs. Suraj Kumari) And Ors. reported in AIR 2019 SC 1280, K. S.
Vidyanadam & Ors. -vs- Vairavan reported in (1997) 3 SCC 1, Sushil Kumar
Agarwal -vs- Kalidas Sadhu reported in 2009(2) CHN 650, K. Kallaiah -vs-
Ningegowda reported in AIR 1982 Kar 93, Coffee Board -vs- Ramesh Exports
Private Ltd. reported in (2014)6 SCC 424, Lachhman Singh (dceased) thr. Lrs.
& Ors. -vs- Hazara Singh (deceased) thr. Lrs. & Ors. reported in (2008) 5 SCC
444.
Submission of respondent :
11. Per contra, Mr. Senguta, learned advocate representing the
respondent strenuously contended that the appellant did not file any
application under Section 8 of the1996 Act before submission of his written
statement and hence, it shall be deemed that appellant had waived such
arbitration clause and in support of such contention, he relied upon a
judgment of Lindsay International Pvt. Ltd. & Ors. -vs- Laxmi Niwas Mittal &
Ors. reported in AIR 2021 Cal 24.
12. He further argued that Article 54 of the Limitation Act lays down
that for specific performance of contract, the period of limitation is three
years from the date fixed for performance and where no such date is fixed,
the date from which the plaintiff had notice that performance was refused.
He submitted that by using the words 'from the date fixed for performance',
legislature wanted to mean that such date would be a specific date like 31st
March etc. and here no date was so fixed and hence, period of limitation
begins to run from the date of refusal i.e. from the date of termination of
contract i.e. from 18.10.1996 and the second suit was filed on 8.1.1999
which is well within the period of limitation. In support of such contention,
he placed reliance upon the judgment of Madina Begum & Anr. -vs- Shiv
murti Prasad Pandey & Anr. reported in (2016) 15 SCC 322 and T. L
Muddkrishana & Anr. -vs- Lalitha Ramchandra Rao (Smt.) reported in (1997)
2 SCC 611.
13. He added that Order 2 Rule 2 of the CPC applies where plaintiff
being entitled to any relief omits to claim such relief or omits to include any
claim in previous suit, he shall not be able to make such claim or pray for
such relief in subsequent suit but here, first suit was withdrawn and taking
liberty from the court, second suit was filed and hence, there is no
applicability of Order 2 Rule 2 CPC.
14. He arduously argued that the present agreement is not a building
contract simpliciter. Here, interest of the developer was created by the
owner in respect of constructed area and hence, such suit is not barred by
Section 14(3)(c) of Act of 1963 and in support of such contention, he placed
reliance upon the judgment of Full Bench decision of this court rendered in
cases of Ashok Kumar Jaiswal -vs- Ashim Kumar Kar, reported in AIR 2014
Cal 92 and the judgment delivered in the case of Sushil Kr. Agarwal -vs-
Meenakshi Sadhu reported in (2019)1 CHN (SC) 6.
15. He submitted whether time is essence of contract or not shall be
question of intention of parties to be gathered from the terms of the contract
and from the conduct of the parties. He added that there was a delay of
almost 9 months in handing over sanctioned plan and in delivery of
possession of site but the plaintiff did not raise any objection and he has
waived the right accrued on such delay and even, defendant himself
extended time by giving letter dated 3.10.96. In view thereof, time was not
essence of contract. In support of such contention he relied upon a
judgment of Hind Construction Contractors By Its Sole Proprietor Bhikam
Chand Mulchand Jain (Dead) By Lrs. -vs- State of Maharashtra reported in
(1979) 2 SCC 70.
16. He invited the attention of the court to the conduct of the
defendant being the owner by saying that owner had accepted Rs.4.5 lakhs
out of 7 (seven) lakhs and he took delivery of his allocation i.e. ground floor,
1st floor and one car parking space within the time stipulated and from his
evidence, it would be apparent that after taking possession of the
constructed area, he started creating obstruction to the developer in
completion of construction of part of developer's allocation and raised the
plea that construction has not been completed within the time stipulated
and the owner has grabbed the entire suit property.
17. He asserted that the learned court below has rightly exercised its
equitable jurisdiction and decreed the suit keeping no scope to interfere with
the same. He prays for dismissal of the appeal.
Observation of the Court :
18. Upon scrutiny of the pleadings and arguments advanced by the
parties, it transpires that we are entrusted with the job to answer the
following queries :
1. Whether suit is barred in view of the arbitration clause embodied
in the agreement ?
2. Whether the subsequent suit is barred in view of the provisions of
Order 2 Rule 2 of CPC ?
3. Whether the suit is barred by limitation ?
4. Whether the suit is barred in view of Section 14(3)(c) of Specific
Relief Act, 1963 ?
5. Whether in the given facts and circumstances, the learned court
below has erred in decreeing the suit ?
Answer to Query no. 1.
19. Admittedly, in clause 26 of the agreement dated 16.1.1995, there
was an arbitration clause which is extracted below :
'All the disputes and difference in any manners relating to and/or
arising out of the provisions herein contained shall be referred to the
Arbitration of such person as be nominated by the parties hereto by
mutual consent and the award of such arbitrator may be final and
binding on the parties hereto. Such Arbitration shall otherwise be in
accordance with the Indian Arbitration Act, 1940 as modified from time
to time.'
20. Undisputedly, both under Section 34 of Act of 1940 or under
Section 8 of Act of 1996, party or parties to the agreement has and/or have
to apply for reference not later than the date of submitting his/their first
statement on the substance of the dispute before the court.
21. Owner being the defendant did not make any such application
before filing his written statement in the learned court below although in
written statement such plea was taken.
22. There are repetitive judgments on the score that there is difference
between the expressions being 'first statement on the substance of the
dispute' and 'written statement' and legislative intent is that such
application is to be applied at the earliest. If a party to an agreement having
arbitration clause does not make such application seeking reference to
arbitration, it shall be deemed that he has subjected himself to jurisdiction
of the court and waived his right to get the disputes arbitrated. [See the
judgment delivered in the case of Lindsay Int'l Pvt. Ltd.& Ors.(supra)].
23. In the case at hand, no such application has been made by the
owner seeking reference to arbitration and hence, it shall be deemed that
owner has waived such right.
Answer to Query no. 2.
24. To answer this query it would be useful to revisit the provisions of
Order 2 Rule 2 CPC which read thus :
'Order 2 Rule 2 CPC : Suit to include the whole claim.- (1) Every suit
shall include the whole of the claim which the plaintiff is entitled to make in
respect of the cause of action; but a plaintiff may relinquish any portion of his
claim in order to bring the suit within the jurisdiction of any court.
(2) Relinquishment of part of claim.- Where a plaintiff omits to sue in
respect of, or intentionally relinquishes, any portion of his claim, he shall not
afterwards sue in respect of the portion so omitted or relinquished.
(3) Omission to sue for one of several reliefs- A person entitled to more
than one relief in respect of the same cause of action may sue for all or any of
such reliefs; but if he omits, except with the leave of the Court, to sue for all
such reliefs, he shall not afterwards sue for any relief so omitted.'
25. Order 2 Rule 2, like the principle of res judicata, is based on
salutary principle that all disputes must be settled once and for all and no
person should be vexed twice. If a plaintiff is entitled to several reliefs
against the defendant in respect of same cause of action, he cannot spilt up
those reliefs and he is not permitted to make any claim in subsequent suit if
he omits to claim the same in earlier suit.
26. The provisions of Order 2 Rule 2 CPC bar the plaintiff to get the
remedy and hence, such provision is to be construed strictly. In the case at
hand, suit was withdrawn under Order 23 Rule 1(3) with liberty to institute
a fresh suit in respect of self-same cause of action and in respect of same
claim. Since first suit was withdrawn with liberty to file afresh on the self
same cause of action, bar under Order 2 Rule 2 CPC will not apply and in
this regard, it would be useful to refer to the judgment of three judges'
bench passed in case of Gurinderpal -vs- Jagmittar Singh reported in (2004)
11 SCC 219 where initially, suit for permanent injunction was withdrawn
taking leave under Order 23 Rule 1(3) and then second suit was filed
seeking specific performance with alternative prayer for refund of
consideration of money. The Hon'ble Apex Court held that suit was not
barred under Order 2 Rule 2 CPC.
Answer to query no. 3
27. Placing reliance upon the judgment of T.L. Muddukrishana & Anr
(supra), Mr. Bhattacharya submitted that when the date is fixed for
performance, time begins to run from that date and for that purpose
whether time was the essence or not would be of no relevance.
28. Mr. Bhattacharya's assertion is that in the given case, time to
complete the construction was 21.9.1996 and although, the first suit was
filed in 1997, the same was not for specific performance of contract and
then taking leave from the court, in 1999, second suit being suit for specific
performance of contract was filed on 8.1.1999, which is barred by limitation
and court while granting leave cannot condone the delay in filing the suit.
29. Under Article 54 of the Limitation Act, 1963 a suit for specific
performance of contract is to be filed within a period of three years from the
date fixed for the performance of the contract or if no such date is fixed, the
date from which the plaintiff has notice that performance is refused.
30. In case of Madina Begum & Anr. (supra), it was ruled that the
expression 'Date fixed' for specific performance of contract in Article 54
means specific date in calendar and where no date is fixed, then 2nd part of
Article 54 will apply. In this case, period for performance was fixed 'within
the period of six months'. It was held that since no specified date in the
calendar had been fixed, 2nd part of the Article would be applicable.
31. So, in the case at hand, time begins to run from 18.10.1996 i.e.
from the date of repudiation of the contract by the owner and second suit
was filed on 8.1.1999. So, we have no qualm to hold that the learned court
below did not err in holding the suit was not barred by limitation. Even if
for the sake of argument, it is assumed that time begins to run from
22.9.1996 (date, according to owner, is fixed for completion of construction),
then also the suit was filed within the period of limitation. Hence, query no.
3 is answered in favour of the respondent herein.
Answer to query no. 4.
32. The query as to whether suit for specific performance of contract
can be maintained at the behest of the builder against the owner is no more
res integra. In case of Sushil Kr. Agarwal -vs- Meenakshi Sadhu (supra),
considering the Special Bench Judgment of High Court at Calcutta (AIR
2014 Cal 92) and other related judgments, the Hon'ble Supreme Court
endorsed the view of the High Court at Calcutta that in case where one
interest in the constructed area has been created in favour of the developer
in the development agreement, suit for specific performance of contract by
the builder and/or developer against the owner can be maintained.
33. In the given case, in the subject agreement, it was covenanted that
upon completion of agreement, owner shall get ground floor and 1st floor and
one car parking space whereas the developer shall get 2nd and 3rd floor. So,
it is apparent that in the agreement, a share and/or interest was created in
favour of the developer. Hence, it is not a building contract simpliciter. So,
we are of the view that the learned court has rightly held that suit is not
barred in view Section 14(3)(c) of Act of 1963.
Answer to query no. 5 :
34. Undoubtedly, jurisdiction to refuse or grant relief in suit for
specific performance of contract is discretionary and court is not bound to
grant relief merely because it is lawful to do so. It is to be noted that such
discretion has to be exercised judiciously and not arbitrarily or capriciously.
It is well settled proposition of law that conduct of the parties plays
important role in the matter of exercise of discretionary jurisdiction by a
Court of law and intention of the parties can be gathered from the conduct
of the parties. Person coming to court with pair of dirty hands cannot claim
equity from the court and court shall exercise such discretion considering
totality of facts and circumstances.
35. In the given case, parties entered into an agreement on 16.1.1995
and it was agreed that within four months, owner shall hand over the
sanctioned plan and deliver the possession of site to the developer and such
time can be extended for two months and parties covenanted that if plans
are not sanctioned due to any reason whatsoever, the developer shall be at
liberty to demolish the entire building and to submit new building plan and
in that event the owner shall get 40% of the constructed area and the
developer shall get balance 60% of constructed area.
36. In the given case, owner modified the plan on repeated occasions
and ultimately, he got the plan sanctioned on 22.9.1995 and
plaintiff/developer claimed that possession of site was delivered after Diwali
and owner rebuffed such claim but could not mention any date on which
possession thereof was given. So, it is apparent that although there was
delay in handing the sanctioned plan and in delivery of possession of site,
developer did not take advantage of default clause.
37. Mere fixation of time for performance in the contract will not lead
the court to hold that time was the essence of contract. Answer to the query
as to whether time was the essence of contract shall be gathered from the
conduct of the parties and in the case at hand, from such conduct of the
both the parties to the contract, it seems that although in the contract, it
was agreed that within 12 months from the date of delivery of sanctioned
plan and possession of site construction was to be completed but the parties
did not treat that time would be the essence of contract.
38. In the given case, owner has taken more 4(four) lakhs from the
plaintiff/developer but he did not disclose such facts in written statement.
Owner has taken possession of the portion of his allocation within the time
stipulated in the contract. Then, suddenly on 3.10.1996, he gave letter
giving 7 days' time to the developer to commence construction and on
14.10.1996 by giving reply, developer stated that due to non-cooperation
and obstruction from the end of the owner, he could not complete
construction within the stipulated time and then on 18.10.1996 i.e. within
fifteen days from the date of issuance of the letter dated 3.10.96, he
unilaterally terminated the contract.
39. Owner himself in his deposition admitted that he covenanted to
give free access to the site to the developer for completion of construction
but developer made allegation that owner did not give free access to the site
to him. The developer's employees were also not allowed to store building
materials in the go-down. In his deposition, the owner stated he gave vacant
possession of entire premises to the plaintiff and then said he only gave
vacant possession of only 2 rooms on the first floor to the developer.
40. Although the owner terminated the contract yet he did not feel it
necessary to refund the money to the developer. He has been enjoying the
portion of his allocation and has been running business therein. It thus
appears that on one hand the owner on various pretext obstructed the
developer from completing the remaining part of construction and on the
other hand raised a plea that he had suffered pecuniary loss and thereafter
abruptly terminated the contract with a mala fide attitude only to grab the
entire property.
Conclusion :
41. So, basing upon the observations made hereinabove, we are of the
considered view that the learned court below has rightly held that suit is not
barred either in view of Article 54 of limitation or in view of any provision of
Arbitration Act, 1940 or Order 2 Rule 2 of the CPC or in view of Section
14(3)(c) of Specific Relief Act, 1963 and on consideration of entire conduct of
the owner and taking the totality of facts and circumstances into account,
we have no hesitation to hold that the learned court below did not err in
exercising its equitable discretion in favour of the plaintiff and we do not
find any infirmity, irregularity and impropriety in the approach and decision
of the learned court below.
Order :
42. Consequently, the appeal be and the same is dismissed, however,
without any order as to the costs. The judgment and decree impugned
herein are affirmed.
43. The parties would be at liberty to take back the amount, if any
deposited in the court.
44. Let a decree be drawn up accordingly.
45. Let a copy of the judgment and LCR, if called for be sent down to
the learned court below forthwith.
46. Urgent Photostat copy of this judgment, if applied for, shall be
granted to the parties as expeditiously as possible, upon compliance of all
formalities.
(Partha Sarathi Chatterjee, J.) (Tapabrata Chakraborty, J.)
Later
After delivery of judgment, the learned advocate representing the
appellant prays for stay of operation of the judgment.
Such prayer is considered and rejected.
(Partha Sarathi Chatterjee, J.) (Tapabrata Chakraborty, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!