Citation : 2023 Latest Caselaw 5106 Cal
Judgement Date : 17 August, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
WPA No. 7644 of 2023
Himshila Ferro Alloys Pvt. Ltd. and another
Vs.
Damodar Valley Corporationand others
For the petitioners : Mr. Subir Sanyal,
Mr. Siddhartha Banerjee,
Mr. Debasish Karmakar,
Mr. Arya Nandi,
Mr. Parikshit Lakhotia
For the DVC : Mr. Joydip Kar,
Mr. Prasun Mukherjee,
Mr. Deepak Agarwal
Hearing concluded on : 09.08.2023
Judgment on : 17.08.2023
Sabyasachi Bhattacharyya, J:-
1. The conspectus of the challenge is very short. The petitioner no.1-
Company, of which the petitioner no.2 is a director, was a consumer
of electricity from the respondent no.1-Damodar Valley Corporation
(DVC). However, due to non-payment of electricity charges, the
connection of the petitioner no.1 was severed. Subsequently, the
petitioners sought restoration of the connection upon payment of the
dues.
2. The DVC raised a bill, inter alia, stipulating a particular amount
payable as security deposit. The present challenge has been thrown
by the petitioners only against the quantum and basis of calculation
of the security deposit.
3. As a brief aside, a challenge, being WPA No.169 of 2023, was preferred
in connection with the alleged previous dues, which came up for an
interlocutory order before a co-ordinate Bench. Certain directions of
payment were passed therein. However, those issues are not gone
into now since the parties do not agitate those herein.
4. Learned counsel for the petitioner argues that there is disparity in the
amount of security charges claimed by the DVC at different points of
time. Whereas, when the petitioner no.1 was enjoying electricity
previously, with a contract demand of 0.9 MVA, the security deposit
charged by the DVC was Rs.23,49,000/-. However, although the
contract demand at present is 0.5 MVA, which is about half the
previous contract demand, the security deposit charged is about
double, to the tune of Rs.43,23,000/-. Ex facie, such claim is
exorbitant, it is argued.
5. Learned counsel for the petitioner next contends that the DVC is
taking a contradictory stand, once insisting that the connection to be
given to the petitioners would be a reconnection, thereby implying that
the old connection is subsisting, and, in other places, while assessing
security deposit, proceeding on the premise that it will be a new
connection.
6. Apart from such contradiction, the petitioners also argue that the DVC
ought to give credit to and adjust the security deposit still lying with
the DVC in connection with the previous deposits made by the
petitioners.
7. Lastly, learned counsel for the petitioners submits that the load factor
of 0.65, taken by the DVC as the basis of calculation of the security
deposit is without any reasonable basis whatsoever. Such whimsical
assessment by the DVC has unnecessarily raised the security deposit,
it is argued.
8. Learned senior counsel appearing for the DVC submits that there has
been no contradiction in the stand of the DVC. Whereas the petitioner
was a consumer previously, the said jural relationship between the
petitioner and the DVC was snapped after 180 days from the
disconnection of electricity, in terms of the relevant clause of the
agreement between the parties as well as the extant WBERC
Regulations.
9. It is argued that there are different variables for calculating the
security deposit. The load factor is roughly equivalent to the contract
demand divided by the gross energy. It is submitted that the gross
energy consumed by the petitioner on previous occasions varied from
time to time, which led to the calculation of security deposit on such
occasions.
10. It is further argued that there have been two tariff revisions since the
previous calculations, which also contributed to the increase of the
security deposit. Learned senior counsel places reliance on the copies
of such tariff revision orders, which have been annexed to the
affidavit-in-opposition of the DVC.
11. Learned senior counsel reiterates that the contract between the
parties ended after 180 days from disconnection and the fresh
connection is to be treated as a new connection.
12. Thus, the basis of calculation of the security deposit, including the
load factor, is the demand of the petitioner. It is, in any event, subject
to adjustment after twelve months, based on the actual consumption
by the consumer, as per the relevant clause in the agreement between
the parties and the prevailing Regulations of the WBERC. It is
submitted that the previous balance of security deposit amount has
already been adjusted, as reflected in the communication by the DVC
dated January 4, 2023.
13. Upon hearing learned counsel for the parties, it is clearly revealed
from the communication of the DVC dated January 4, 2023, that the
DVC calculated the security deposit to be paid by the petitioner on the
contract demand of 0.5 MVA to be Rs.43,23,000/-.
14. In the same breath, the DVC has clarified that the security deposit
available after invocation of bank guarantee of Rs.23.49 lakh was
Rs.8,56,442/. After adjusting necessary payables, the said remaining
balance has been deducted from the total amount of security deposit
of Rs.43,23,000/-, arriving at the figure of Rs.34,66.558/- which is
the amount claimed by the DVC from the petitioner at present.
15. Insofar as the alleged contradiction in stands of the DVC is concerned,
the said argument cannot be accepted. The expression "reconnection"
is used, wherever it is, obviously since the petitioner had been
enjoying electricity from the DVC in the recent past, and need not per
se connote that the previous contract is subsisting.
16. Clause 23 of the Power Supply Agreement between the parties
stipulates that if the power supply to any consumer remains
disconnected continuously for a period of 180 days, where the
disconnection has been effected in compliance with any of the
provisions of the Electricity Act, 2003 and clauses of the agreement,
the agreement with the consumer shall be deemed to have been
terminated with consequential effect on expiry of the said period of
180 days.
17. Apart from that, Clause 4.6.1 of Regulation 55 of the WBERC, the
„Electricity Supply Code‟, also contains the same stipulation. Since,
admittedly, 180 days have passed after the previous disconnection, for
all practical purposes, the agreement between the parties has
terminated by operation of the said provision and the connection now
sought by the petitioner would be a new connection for all practical
purposes.
18. Clause 16 of the agreement between the parties provides for the
charging of security deposit. In case of a new applicant, the estimated
consumption based on its declared load shall be treated as an
advance for the consumer, which shall be appropriately adjusted with
the amount of security deposit that would eventually be determined
on the basis of its first 12 months‟ consumption when the latter time-
period is over. The provision as to existing consumers is not required
to be looked into, since the present application is to be treated is one
for new connection, as discussed above.
19. Hence, in any event, the challenge preferred in the present writ
petition is premature, since the assessment made is merely on the
basis of an estimate, arrived at on the basis of the declared load of the
petitioner, and shall be appropriately adjusted, by being treated to be
an advance, after the first 12 months‟ consumption.
20. The petitioners also allege disproportionate variation between load
factor and security deposit as opposed to previous periods when the
earlier contract was subsisting. However, the said argument is not
tenable. The bill dated April 2, 2020, annexed by the petitioners to
the writ petition, shows the load factor to be 4.93 and the gross energy
consumed, in KWH, is 20,320, whereas in the bill dated May 2, 2020,
that is, for the very next month, the load factor percentage is 0.36
whereas the gross energy in KWH is only 510. Again, in the bill dated
July 1, 2020, the load factor percentage is 3.49 and the gross energy
is 11,960. Thus, a perusal of the previous bills shows that the load
factor varied hugely over a period of only a few months, being tied up
with the gross energy consumed by the petitioner no. 1 during the
said period vis-à-vis the contract demand, although the contract
demand remained 0.9 MVA all along. Hence, the load factor is not the
only determinant of security deposit. At this juncture, when a new
connection is to be given, only a reasonable estimate can be made by
the licensee, which has precisely been done by the DVC.
21. In fact, if an average of the load factor for the said period is taken, it
would much exceed 0.65, which has been estimated as load factor in
the present case by the DVC.
22. Thus, the average load factor of 0.65, calculated by the DVC as the
basis of arriving at the figure of security deposit, cannot be faulted in
any manner whatsoever.
23. The challenge of the petitioner to the break-up of calculation for the
security deposit revolves primarily around the average load factor.
Insofar as the other factors are concerned, no specific challenge has
been thrown. Hence, those are not gone into.
24. Hence, on a comprehensive perusal of the materials on record and the
relevant law and the provisions of the contract between the parties,
the calculation of the DVC in respect of the security deposit payable
by the petitioner for the connection-in-question, to the tune of
Rs.43,23,000/-, is not exorbitant or arbitrary.
25. Moreover, the DVC has given due credit to the current amount lying
with it. After adjusting current dues and invocation of bank
guarantee of Rs.23.49 lakh, the remaining amount has been deducted
from the security deposit calculated, after which, the claim of DVC is
to the tune of Rs.34,66,558/-, which is fully justified.
26. Hence, there is no necessity to interfere with the impugned
assessment of security deposit in any manner whatsoever.
27. Accordingly, WPA No.7644 of 2023 is dismissed on contest without,
however, any order as to costs.
28. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!