Citation : 2023 Latest Caselaw 5042 Cal
Judgement Date : 16 August, 2023
IN THE HIGH COURT AT CALCUTTA
Civil Appellate Jurisdiction
(Appellate Side)
MAT 71 of 2018
With
IA No: CAN/1/2018 (Old No: CAN/876/2018)
With
IA No: CAN/2/2018 (Old No: CAN/877/2018)
The State of West Bengal & Ors.
-Versus-
Pranab Kumar Mukherjee
Before: The Hon'ble Justice Arijit Banerjee
&
The Hon'ble Justice Apurba Sinha Ray
For the Appellants/State : Mr. Susovan Sengupta, Adv.
Mr. Subir Pal, Adv.
For the Respondent/writ : Mr. Mihir Kundu, Adv.
petitioner Mr. Subrata Poddar, Adv. Judgment On : 16.08.2023 Arijit Banerjee, J. :-
1. This appeal is directed against a judgment and order dated May 18, 2016,
whereby the writ petition of the respondent no. 1 being W.P. No. 5568(W)
herein was disposed of with similar direction as was given in the judgment
and order dated May 16, 2016, rendered in W.P. 5590(W) of 2016. Such
direction was as follows:-
"This writ petition, therefore, is disposed of by directing the
competent respondent authority to determine the market value of
the land in terms of Section 26 of the Right to Fair Compensation
and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013 and thereafter follow the process of law as
laid down under the new Act of 2013 and ensure compensation is
paid within the statutory time frame stipulated therein to the
petitioners."
2. The undisputed facts of the case are that land of the respondent/ writ
petitioner was requisitioned by the State Government under Section 3 of the
West Bengal (Requisition and Acquisition) Act, 1948, and possession thereof
taken over for construction of Haringhata-Panpur Road in the District of
Nadia, in connection with LA Case no. 52/General/B.R.P/Rehab of 1981-82.
Possession of such land was handed over to the requiring body on August
13, 1982. The land has been utilized for the purpose of constructing the
aforesaid road.
3. For reasons which are not relevant, a fresh L.A. Case No. 3/PWD/2004-
05 was initiated by the competent authority by issuance of notice under
Section 4 of the Land Acquisition Act, 1894. It is not in dispute that no
Award was ever passed in connection with the said land acquisition case.
4. The respondent no. 1 approached the learned Single Judge. The order
under appeal was passed directing the Government to determine and pay
compensation to the writ petitioner in terms of the provisions of the 2013
Act.
5. Being aggrieved, the State Government has come up by way of this
appeal.
6. Appearing for the appellant, learned Advocate submitted that the learned
Single Judge erred in directing the Government to pay compensation
following the provisions of the 2013 Act. Relying on the decision of the
Hon'ble Supreme Court in the case of Haryana State Industrial and
Infrastructure Development Corporation Ltd & Ors. v. Mr. Deepak
Agarwal & Ors. rendered in SLP (C) Nos. 16631 -16632/2018, learned
Advocate submitted that if notice under Section 4 of the LA Act 1894, was
issued prior to the 2013 Act coming into force but no Award was passed
prior to January 1, 2014, when the 2013 Act came into force, the land
acquisition proceedings will continue as per provisions of the LA Act 1894
and only for determination of the compensation amount the provisions of the
2013 Act will be applicable.
7. Learned Advocate then submitted, relying on the Constitution Bench
Judgment of the Hon'ble Supreme Court in the case of Indore Development
Authority v. Manoharlal and Ors. reported at (2020) 8 SCC 129, that
possession of the land of the respondent/ writ petitioner having been taken
over in 1982 and the writ petitioner having approached the Court only in
2016, i.e., after a lapse of 34 years, the writ petition is barred on the
grounds of delay and laches. Learned Advocate submitted that if a claimant
is aware of violation of his rights and does not claim his remedies promptly,
such inaction or conduct tantamounts to a waiver of his right. In such
cases, the lapse of time and delay are very material factors and cannot be
ignored by the Court. He submitted that the writ petition should have been
dismissed on the ground of delay and laches.
8. Learned Advocate for the respondent/writ petitioner submitted that since
no declaration under Section 6 was published within one year from the date
of notification under Section 4 of the LA Act 1894, or at all, in connection
with the L.A. Case initiated in 2004-2005, the acquisition proceedings
lapsed. This has also been admitted by the Government in its MEMO no.
214/1-LA dated February 19, 2015, (Annexure R-5 to the affidavit-in-
opposition of the writ petitioner filed in connection with the stay application
in this appeal). That the acquisition proceedings lapsed was also admitted by
the State Government by filing an affidavit before the learned Single Judge
in W.P. No. 5568 of 2016. No Award was ever published and no
compensation paid to the writ petitioner.
9. Learned Advocate submitted that since the proceedings initiated under
the 1894 Act lapsed, therefore proceedings have to be initiated under the
2013 Act. Alternatively, even if the proceedings did not lapse because of
physical possession of the land having been taken over by the State
Government, since there was no Award as on January 1, 2014,
determination of the compensation amount will have to be in terms of the
provisions of the 2013 Act.
10. Learned Advocate further submitted that since Section 4 notification in
connection with L.A. Case no. 3/PWD/2004 - 2005 was published in the
year 2011, the date of such notification should be treated as the material
date for determination of compensation amount following the provisions of
the 2013 Act.
11. I have given my anxious consideration to the rival contention of the
parties.
12. The undisputed facts of the case have been noted above and I do not
repeat the same. It is not in dispute that in connection with the L.A. Case
initiated in 2004-2005, no Award was ever passed by the competent
authority. It is an admitted fact that as on January 1, 2014, i.e, the date
when the 2013 Act became operational, there was no Award. The short
question is whether or not the notification under Section 4 of the 1894 Act
survived after coming into effect of the 2013 Act?
13. Section 24(1)(a) of the 2013 Act reads as follows:-
"24.(1) (a) where no award under section 11 of the said Land
Acquisition Act has been made, then, all provisions of this Act
relating to the determination of compensation shall apply;"
14. In the case of Indore Development Authority v. Manoharlal and Ors.
(supra), the supreme Court held that where Section 24(1)(a) of the 2013 Act
applies, i.e., where there is no Award on the date of commencement of the
2013 Act, the proceedings initiated under 1894 Act do not lapse. However,
compensation has to be determined under the provisions of the 2013 Act.
15. In Haryana State Industrial and Infrastructure Development
Corporation Ltd & Ors. v. Mr. Deepak Agarwal (supra), a three Judge
Bench of the Hon'ble Supreme Court addressed the question as to whether a
notification issued under Section 4 of the 1894 Act prior to January 1, 2014,
(date of commencement of 2013 Act) "could continue or survive after
01.01.2014 and, as to whether Section 6 notification under the L.A. Act
could be issued after 01.01.2014.
16. The Hon'ble Supreme Court answered the aforesaid questions follows:-
"32. We think that while considering those questions we will have
to bear in mind the purposes and the legislative history of the 2013
Act and also the intention of the legislature in drafting the same in
the manner in which it now exists. We have already dealt with
those aspects. One crucial aspect discernible from Section
24(1)(a) has also to be taken note of in this context. The combined
effect of Section 24(1) and clause (a) thereof is that if land
acquisition proceeding under the L.A. Act was initiated prior to
01.01.2014, the date of coming into force of the 2013 Act, and if it
was not culminated in an award under Section 11 of the L.A. Act,
then all the provisions of the 2013 Act relating to the
determination of compensation should apply to such acquisition
proceedings. Thus, it is obvious that in case of non-passing of an
award in terms of Section 11 of the L.A. Act where the acquisition
proceedings have been initiated prior to 01.01.2014, all provisions
under the 2013 Act relating to the determination of compensation
alone would apply to such acquisition proceedings. In other words,
it would mean that in such circumstances the land acquisition
proceedings should continue, but all the provisions relating to the
determination of compensation under the 2013 Act alone will be
applicable to such proceedings, meaning thereby, the 2013
Act would come into play only at that stage. There can be no doubt
with respect to the position that between the initiation of land
acquisition proceedings by issuance and publication of notice
under Section 4(1) of the L.A. Act and the stage at which
compensation for the acquisition calls for determination, there are
various procedures to be followed to make the acquisition in
accordance with the law. The question is when Section 24(1) of the
2013 Act makes it clear with necessary implication that all
provisions of the 2013 Act relating to the determination of
compensation alone would be applicable to such proceedings
initiated under the L.A. Act but, not culminated in an award, how
the procedures are to be regulated during the intervening period
till the proceedings reach the stage of determination of
compensation. There cannot be any uncertainty on that aspect.
The procedures to be undertaken and the manner in which they
are to be regulated cannot remain uncertain. They are conducted
either in the manner provided under the L.A. Act or in the manner
provided under the 2013 Act. But then, in view of Section 24(1)(a),
the provisions relating to the determination of compensation alone
can be applied to such proceedings or in other words, there is only
a restricted application of the provisions of the 2013 Act in
relation to such proceedings. The inevitable conclusion can only be
that what is applicable to the various procedures to be undertaken
during the period up to the stage of determination of compensation
are those prescribed under the L.A. Act. We have no doubt that
without such a construction, the provisions under Section
24(1)(a) would not work out, in view of the restrictive application of
the 2013 Act. It is in this context that the decision in 'Ambica
Quarry Works' case (supra) assumes relevance. Any construction
of the said provision without taking into the legislative intention,
referred hereinbefore would defeat the legislative intention as also
the very objects of the 2013 Act. Certainly, it would not be in
public interest to allow such proceedings to lapse or allow the
authorities to follow the procedures during such period according
to their sweet will. A uniform procedure has to be followed in
respect of such proceedings. The acquisitions initiated for public
purposes should go on in a fair and transparent manner with a
view to achieve the intent and purport of the 2013 Act and at the
same time, the persons affected shall have definite idea about the
manner in which procedures would be conducted. The Party 'B'
would not be justified in describing such situations of necessity
and the consequential application of provisions which are actually
saved on account of the construction of Section 24 as an attempt
to bring the words expressly employed in Section 24(1)(b) and
absent in Section 24(1)(a), by indirect method to Section 24(1)(a) of
the 2013 Act. The aforesaid conclusions and findings would make
the contentions of Party 'B' that Section 4(1) notification issued
prior to 01.01.2014 could not survive after 01.01.2014 and also
that Section 6 notification under the L.A. Act could not be issued
after 01.01.2014, unsustainable. In fact, all such procedures and
formalities shall be continued till the determination of
compensation by applying all the provisions for determination of
compensation, under the 2013 Act. A contra-construction, in view
of the restrictive application of the provisions to such proceedings
during its continuance, would make the provisions under Section
24(1)(a) of the 2013 Act unworkable."
17. Therefore, the law laid down by the Hon'ble Supreme Court appears to
be that a Section 4 notification under the 1894 Act issued prior to January
1, 2014, would be alive even after that date notwithstanding that as on that
date no Award had been made. Proceedings will continue in terms of the
provisions of the 1894 Act in so far as the procedure is concerned till the
stage of determination of compensation. However, compensation will be
computed applying the provisions of the 2013 Act relating to determination
of compensation.
18. Accordingly, we do not find any infirmity in the judgment and order
assailed before us. The learned Judge has directed the competent authority
to determine the market value of the land in question in terms of Section 26
of the 2013 Act and thereafter follow the process of law as laid down under
that Act. We simply clarify, following the decision in the case of Haryana
State Industrial and Infrastructure Development Corporation Ltd &
Ors. v. Mr. Deepak Agarwal (supra) that proceedings will continue
following the procedure laid down in the 1894 Act excepting that the
provisions in the 2013 Act relating to determination of compensation shall
be applicable for computation of compensation.
19. As regards the point of delay, in Vidya Devi v. The State of Himachal
Pradesh & Ors. reported at (2020) 2 SCC 569=AIR 2020 SC 4709, the
Hon'ble Supreme Court, held, inter alia, as follows:-
"10.1. The Appellant was forcibly expropriated of her property in
1967, when the right to property was a fundamental right
guaranteed by Article 31 in Part III of the Constitution.
Article 31 guaranteed the right to private property, which could
not be deprived without due process of law and upon just and fair
compensation.
10.2 The right to property ceased to be a fundamental right by the
Constitution (Forty Fourth Amendment) Act, 1978, however, it
continued to be a human right in a welfare State, and a
Constitutional right Under Article 300A of the Constitution. Article
300A provides that no person shall be deprived of his property save
by the authority of law. The State cannot dispossess a citizen of his
property except in accordance with the procedure established by
law. The obligation to pay compensation, though not expressly
included in Article 300A, can be inferred in that Article.
To forcibly dispossess a person of his private property,
without following due process of law, would be violative of a human
right, as also the Constitutional right under Article 300A of the
Constitution.
Reliance is placed on the judgment in Hindustan Petroleum
Corporation Ltd. v. Darius Shapur Chennai MANU/SC/0610/2005:
(2005) 7 SCC 627, wherein this Court held that:
6. ... Having regard to the provisions contained in article 300-A
of the Constitution, the State in exercise of its power of
"eminent domain" may interfere with the right of property of a
person by acquiring the same but the same must be for a public
purpose and reasonable compensation therefor must be paid.
In N. Padmamma v. S. Ramakrishna Reddy
MANU/SC/7731/2008 : (2008) 15 SCC 517, this Court held that:
21. If the right of property is a human right as also a
constitutional right, the same cannot be taken away except in
accordance with law. Article 300-A of the Constitution protects
such right. The provisions of the Act seeking to divest such
right, keeping in view the provisions of Article 300-A of the
Constitution of India, must be strictly construed.
In Delhi Airtech Services Pvt. Ltd. and Ors. v. State of U.P. and Ors.
MANU/SC/0956/2011 : (2011) 9 SCC 354, this Court recognized the
right to property as a basic human right in the following words:
30. It is accepted in every jurisprudence and by different
political thinkers that some amount of property right is an
indispensable safeguard against tyranny and economic
oppression of the Government. Jefferson was of the view that
liberty cannot long subsist without the support of property.
"Property must be secured, else liberty cannot subsist" was the
opinion of John Adams. Indeed the view that property itself is
the seed bed which must be conserved if other constitutional
values are to flourish is the consensus among political thinkers
and jurists.
In Jilubhai Nanbhai Khachar v. State of Gujarat
MANU/SC/0033/1995 : (1995) Supp. 1 SCC 596 this Court held as
follows:
48. ... In other words, Article 300-A only limits the powers of
the State that no person shall be deprived of his property save
by authority of law. There has to be no deprivation without any
sanction of law. Deprivation by any other mode is not
acquisition or taking possession under Article 300-A. In other
words, if there is no law, there is no deprivation.
10.3. In this case, the Appellant could not have been forcibly
dispossessed of her property without any legal sanction, and
without following due process of law, and depriving her payment of
just compensation, being a fundamental right on the date of forcible
dispossession in 1967.
...........
10.5 In a democratic polity governed by the Rule of law, the
State could not have deprived a citizen of his property without the
sanction of law. Reliance is placed on the judgment of this Court in
Tukaram Kana Joshi and Ors. v. M.I.D.C. and Ors.
MANU/SC/0933/2012 : (2013) 1 SCC 353 wherein it was held that
the State must comply with the procedure for acquisition, requisition,
or any other permissible statutory mode. The State being a welfare
State governed by the Rule of law cannot arrogate to itself a status
beyond what is provided by the Constitution.
This Court in State of Haryana v. Mukesh Kumar held that
the right to property is now considered to be not only a constitutional
or statutory right, but also a human right. Human rights have been
considered in the realm of individual rights such as right to shelter,
livelihood, health, employment, etc. Human rights have gained a
multi-faceted dimension.
...........
10.7. The contention advanced by the State of delay and laches of
the Appellant in moving the Court is also liable to be rejected. Delay
and laches cannot be raised in a case of a continuing cause of
action, or if the circumstances shock the judicial conscience of the
Court. Condonation of delay is a matter of judicial discretion, which
must be exercised judiciously and reasonably in the facts and
circumstances of a case. It will depend upon the breach of
fundamental rights, and the remedy claimed, and when and how
the delay arose. There is no period of limitation prescribed for the
courts to exercise their constitutional jurisdiction to do substantial
justice.
In a case where the demand for justice is so compelling, a
constitutional Court would exercise its jurisdiction with a view to
promote justice, and not defeat it.
In Tukaram Kana Joshi and Ors. v. M.I.D.C. and Ors.,
MANU/SC/0933/2012 : (2013) 1 SCC 353 this Court while dealing
with a similar fact situation, held as follows:
There are authorities which state that delay and
laches extinguish the right to put forth a claim. Most of these
authorities pertain to service jurisprudence, grant of
compensation for a wrong done to them decades ago, recovery
of statutory dues, claim for educational facilities and other
categories of similar cases, etc. Though, it is true that there are
a few authorities that lay down that delay and laches debar a
citizen from seeking remedy, even if his fundamental right has
been violated, Under Article 32 or 226 of the Constitution, the
case at hand deals with a different scenario altogether.
Functionaries of the State took over possession of the land
belonging to the Appellants without any sanction of law. The
Appellants had asked repeatedly for grant of the benefit of
compensation. The State must either comply with the procedure
laid down for acquisition, or requisition, or any other
permissible statutory mode."
20. It may also be noted that in almost all the cases where the Hon'ble
Supreme Court has refused to entertain a land loser's legal action on the
ground of delay or laches, were cases where the land loser challenged the
acquisition proceedings after undue delay. This is obviously because such
person, having permitted utilization of his land by not challenging the
acquisition promptly, disentitled himself from challenging the legality of the
acquisition proceedings. However, such a person's claim to compensation
cannot be defeated by the State on the ground of delay.
21. In the facts of the present case, the State having deprived the writ
petitioners of their property without following due process of law and
without paying any compensation-which is really an act of expropriation-the
State cannot be permitted to argue that the delay on the part of the writ
petitioners in approaching the Court will cause imposition of greater
financial burden on the State since in the mean time the 2013 Act has come
into operation and holds the field. Had the State acted in accordance with
law, it could have avoided the additional financial burden, if any, that may
be foisted on it by reason of compensation being calculated in terms of the
provisions of the 2013 Act. In this connection one may refer to the decision
of a Coordinate Bench rendered on September 29, 2022 in MAT 464 of
2018 (The State of West Bengal & Ors. v. Dilip Ghosh & Ors.).
22. In view of the aforesaid, we find no merit in the appeal which is
dismissed along with the connected applications. We direct the First Land
Acquisition Collector/ the Competent Authority to complete the process of
determination of the compensation amount, in light of the observations
made in this judgment, within 12 weeks from date and pay the amount to
the respondent/writ petitioner within two weeks thereafter.
23. Urgent certified website copies of this judgment, if applied for, be
supplied to the parties subject to compliance with all the requisite
formalities.
(ARIJIT BANERJEE, J.)
I agree.
(APURBA SINHA RAY, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!