Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Jaishree Steels Private Limited ... vs West Bengal State Electricity ...
2023 Latest Caselaw 2062 Cal/2

Citation : 2023 Latest Caselaw 2062 Cal/2
Judgement Date : 16 August, 2023

Calcutta High Court
Jaishree Steels Private Limited ... vs West Bengal State Electricity ... on 16 August, 2023
                                                          APO NO. 82 OF 2023
                                                              REPORTABLE

         IN THE HIGH COURT OF JUDICATURE AT CALCUTTA
                   CIVIL APPELLATE JURISDICTION
                            ORIGINAL SIDE



                      RESERVED ON: 28.07.2023
                      DELIVERED ON: 16.08.2023


                               CORAM:

        THE HON'BLE MR. CHIEF JUSTICE T.S. SIVAGNANAM
                                  AND
      THE HON'BLE MR. JUSTICE HIRANMAY BHATTACHARYYA


                        A.P.O. NO. 82 OF 2023
                        (I.A. NO. G.A./01/2023)


         JAISHREE STEELS PRIVATE LIMITED AND ANOTHER
                               VERSUS
    WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY
                        LIMITED AND OTHERS




Appearance:-
Mr. Parathi Sarathi Sengupta, Sr. Adv.
Mr. Ratnanko Banerji, Sr. Adv.
Mr. Ratnesh Kumar Rai, Adv.
Mr. Ankan Rai, Adv.
                                                    ....for the Appellant.




Mr. Abhratosh Majumder, Sr. Adv.
Mr. Suddhasatva Banerjee, Adv.
Mr. Sandip Dasgupta, Adv.
Mr. Aviroop Mitra, Adv.
                                                  .....for the Respondent.



                               Page 1 of 15
                                                                   APO NO. 82 OF 2023
                                                                      REPORTABLE

                                     JUDGMENT

(Judgment of the Court was delivered by T.S. Sivagnanam, CJ.)

1. This intra court appeal at the instance of the writ petitioner is directed

against the judgment and order dated 08.06.2023 in WPO No. 2271 of 2022.

The appellant filed the said writ petition challenging the order dated

12.05.2022 passed by the (CGRO) by which the demand made by the

respondent, West Bengal State Electricity Distribution Company Limited

(herein after referred to as the Distribution Company) by supplementary bill

dated 13.08.2015 was affirmed. By the said demand, the distribution

company demanded delayed payment surcharge (DPS) on the electricity

charges due and payable by the appellant.

2. On 14.06.2016 the appellant entered into an agreement with Durgapur

Projects Limited (DPL) for supply of electricity to its mini steel plant. On

16.07.2014, the revised contract demand was entered into between the first

appellant and DPL. As per the respondent the load having been enhanced

from 7 MVA to 12 MVA, bills are required to be raised with MF 400 instead

of MF 200. On 13.08.2015, DPL informed the appellant that upon

enhancement of load to 12 MVA the bills would be raised with the 400 MVA

as opposed to 200 MVA. On 14.08.2015, the first appellant requested

permission to pay 50% of the said bill and allow 60 installments for payment

of the balance 50%. A letter was addressed by DPL to the first appellant on

17.08.2015 to which the appellant responded on 24.08.2015. DPL vide letter

dated 27.08.2015 directed the appellant to pay the entire outstanding

amount in the supplementary bill in 12 equal installments. According to the

appellant, such payment was without any DPS. By letter dated 02.09.2015,

APO NO. 82 OF 2023 REPORTABLE

DPL had called upon the appellant to pay the first installment and stated

that the appellant would be liable to pay 12 installments of Rs. 19,67, 99,

980/-. Subsequently on 04.09.2015 and on 07.09.2015 the appellant

requested to revise the bill on the ground that there was a computation

error while calculating the electricity due at the concessional rate. On

09.09.2015, DPL sent a reply to the appellant informing that the issue was

pending for approval. As the appellant failed to adhere to the installments

schedule, DPL sent demand letters on five occasions. On 28.05.2016, the

appellant requested for revision of bills raised by DPL mentioning certain

reasons. On 03.03.2017, the first appellant and DPL entered into an

agreement. The appellant would contend that on 13.08.2017 the period of

limitation of two years started from the raising of the supplementary bill on

13.08.2015 came to an end. On 31.12.2018, DPL merged with the

respondent distribution company on 12.03.2019. The respondent

distribution company issued notice under Section 56(1) of the Electricity

Act, 2003 (the Act) threatening disconnection of electricity on account of Rs.

8.81 crores remaining due and payable by the appellant. The appellant by

letter dated 26.03.2019 requested for payment in installment. The

distribution company granted 12 installments to the appellant for clearing

the dues pertaining to the supplementary bill dated 26.03.2019, 27.03.2019

and 10.04.2019. On 04.10.2019, DPS was charged in the billing cycle of the

month of September 2019 and the respondent kept on levying DPS till June,

2021 as and when the appellant defaulted in making the payment of the

dues arising out of the supplementary bill in accordance with the

installments. The appellant had submitted representations on various dates

APO NO. 82 OF 2023 REPORTABLE

with the request for grant of installment and waiver of the DPS demand. The

appellant sent a letter dated 09.06.2021 stating that the entire payment of

Rs. 8,81,64,222/- was made by them. The appellant filed the writ petition

before this Court in WPO No. 260 of 2021 on 06.07.2021. The distribution

company intimated the appellant on 08.07.2021 and the entire DPS claimed

would have to be paid by the appellant to avoid disconnection and since the

amount was not paid by the appellant, the electricity supplied was

disconnected. The writ petition being WPO No. 260 of 2021 was dismissed

by order dated 09.08.2021 holding that the critical question would arise in

calculating and arriving at any conclusion as to whether there has been any

payment of any monthly bill between December 2020 and June 2021 within

the time stipulated. Further it was held that it has to be decided as to

whether late payment charges (DPS) have been included in the claim of the

distribution company either for the period from January 2021 till June 2021

or for the earlier period during which electricity was being supplied by the

erstwhile DPL.

3. The learned writ court opined that the CGRO under the Act is fully and

completely equipped and qualified to undertake the exercise. Being

aggrieved by the said order, the appellant filed an appeal in APOT No. 117 of

2021 and by judgment dated 17.11.2021 the appeal was allowed with a

direction to restore the electricity supply coupled with a direction to the

CGRO to decide the dispute connected to the imposition of DPS qua the

validity and proportionality. The appellant approached the CGRO and made

their submissions both oral and written and after hearing the parties on

several dates, the CGRO by order dated 12.05.2021 held that the DPS

APO NO. 82 OF 2023 REPORTABLE

claimed by the distribution company is justified and granted liberty to take

necessary action in accordance with the Rules and Regulations framed by

the West Bengal State Electricity Regulatory Commission. Being aggrieved

by such order, the appellant filed WPO No. 2271 of 2022 which was

dismissed by judgment dated 08.06.2023 holding that the appellants are

liable to pay Rs. 14,67,16,864/- on account of DPS and in the event if they

do not pay the sum by 31.07.2023, the distribution company would be at

liberty to disconnect the electricity connection of the appellant's factory

premises. Aggrieved by such order, the appellants have preferred this

appeal.

4. We have heard Mr. Partha Sarathi Sengupta, learned Senior Advocate

along with Mr. Ratnanko Banerji, learned Senior Advocate, assisted by Mr.

Ratnesh Kr. Rai, Mr. Ankan Rai, learned advocates for the appellant and Mr.

Abhratosh Majumder learned Senior Advocate assisted by Mr. Suddhasatva

Banerjee, Mr. Chayan Gupta, Mr. Sandip Dasgupta and Mr. Aviroop Mitra,

learned advocates for the respondent.

5. The sheet anchor of the argument of the learned Senior Advocate for the

appellant is by referring to Section 56(2) of the Act. It is contended that in

terms of the Sub Section (2) of Section 56 which commences with a non

obstante clause, the sum due from any consumer under the said section

shall not be recoverable after the period of two years from the date when

such sum became first due unless such sum has been shown continuously

as recoverable as arrears of charges for electricity supplied and the licensee

shall not cut off the supply of the electricity. It is submitted that the period

of limitation commenced from raising of the supplementary bill on

APO NO. 82 OF 2023 REPORTABLE

13.08.2015 and ended on 13.08.2017 and during such period, DPS was

neither levied nor charged and for the first time DPS was levied after the

expiry of four years from the date of issuance of the supplementary bill

dated 13.08.2015. Therefore, it is submitted that the demand is not

sustainable and the respondents are not entitled to invoke Sub Section (2) of

Section 5 by which there is a threat to disconnect electricity supply.

6. It is submitted that crucial words in Sub Section (2) of Section 56 are

"when such sum became due". The date on which it is first due should have

been mentioned in the Bill and in terms of the said Sub Section, bills should

be shown as outstanding. In absence of such compliance, the respondents

are not entitled to invoke Section 56(2) of the Act and if permissible under

law, remedy is available under Sub Section (1) of Section 56. However, the

threat of disconnection is meted out by the respondent by invoking power

under Section 56(2) is wholly without jurisdiction. In support of his

contention, learned Senior Advocate referred to the decision of the Hon'ble

Supreme Court in Assistant Engineer (D1), Ajmer Vidyut Vitran Nigam

Limited and Another Versus Rahamatullah Khan 1, Prem Cottex Versus

Uttar Haryana Bijli Vitran Nigam Limited and Others 2 and K.C. Ninan

Versus Kerala State Electricity Board and Others 3.

7. The learned Senior Advocates had elaborately referred to the various

documents which have been appended to the petition to demonstrate that in

none of the bills which have been raised after 13.08.2015 there is any

mention of any outstanding and the relevant column has been left blank

(2020) 4 SCC 650

(2021) SCC Online SC 870

(2023) SCC Online SC 663

APO NO. 82 OF 2023 REPORTABLE

and for the first time in the bill dated 07.11.2017, the amount was shown as

outstanding and by then, the period of limitation of two years had expired

and therefore Section 56 (2) cannot be invoked.

8. The provision of the West Bengal Electricity Regulatory Commission

(Electricity Supplied Court) Regulations, 2013 was referred to and in

particular Regulation Nos. 3.3.9, 3.4, 3.4.3 and 4.0, the attention of the

court was drawn to the representation given by the appellant dated

27.08.2015 to DPL wherein they sought for payment of the supplementary

bill in equal installments without any delayed payment surcharge. It is

submitted that in terms of the said representation made by the appellant,

DPL had not charged any delayed payment surcharge and only after DPL

had merged with the respondent distribution company for the first time in

the year 2017, power under Section 56(2) was invoked and DPS was

demanded and upon failure to pay DPS there was a threat of disconnection

of electricity.

9. It is submitted that the question of any acknowledgement of liability by

the appellant would not arise as even assuming by certain letters, the

appellant had sought for waiver of DPS, those representations having been

made much after the expiry of the period of limitation of two years, the same

cannot be taken to be acknowledgement of any liability. In this regard,

reliance was placed on the decision of the Hon'ble Supreme Court in Asset

Reconstruction Company (India) Limited Versus Bishal Jaiswal and

Another 4.

(2021) 6 SCC 366

APO NO. 82 OF 2023 REPORTABLE

10. The learned Senior Counsel elaborately referred to the findings

recorded by the CGRO and submitted that the contention which was

canvassed by the appellant before the CGRO were not properly dealt with

and the findings rendered by the CGRO is unsustainable in law. It is

submitted that though substantial portion of the findings rendered by the

learned Single Judge would enure in favour of the appellant, the ultimate

conclusion while dismissing the writ petition was contrary to the findings

recorded earlier more particularly in paragraph 16 of the impugned

judgment and order. With the above submissions, the learned senior

counsel prayed for setting aside the order passed in the writ petition and

allowing the appeal.

11. Mr. Abharatosh Majumder, learned Senior Advocate appearing for the

respondent submitted that in terms of 2013 Regulations, the respondent

distribution company is empowered to charge DPS. As could be seen from

Regulation 3.3.9, the demand for DPS is well within the jurisdiction of the

respondent distribution company. It is submitted that the chargeable event

for levy of DPS is the payment or part payment of the dues and therefore the

appellant cannot contend that the demand made in the year 2017 was

barred by limitation. It is submitted that it is incorrect to state that in the

bills which were raised during 2015 there was no mention about the DPS. In

this regard, learned Senior Advocate has drawn the attention of the court to

the Bill dated 13.06.2015 and submitted that in the bill it is clearly mention

as to what will be the rate of DPS which will be chargeable depending upon

the delay or pro-rated or part thereof. It is submitted that Rs. 9.80 crores

was paid by the appellant to DPL and a sum of Rs. 8.81 crores was due and

APO NO. 82 OF 2023 REPORTABLE

payable to the respondent distribution company upon its merger. The 12

installments given to the appellant commenced from 27.03.2019.

12. On 08.11.2019, the second agreement was entered into and the

appellant had made a part-payment and accordingly DPS was calculated

reckoning the part-payment paid by the appellant. It is further submitted

that the appellant was fully aware of the legal position and that they are due

and liable to pay the DPS and, therefore, sought for waiver of payment of the

DPS by their representations dated 10th February, 2021 and 10th March,

2021. It is submitted that the contention raised by the appellant with regard

to the interpretation of the period of limitation under Section 56(2) of the Act

is an incorrect interpretation as calculation of DPS is a dynamic formula

and is not a static formula and DPS will become liable for payment as and

when the payment is made belatedly. Therefore, the respondents have

accordingly calculated the period of delay and levied DPS on pro-rata basis

taking into consideration the delay in remittance of each of the instalments.

Therefore, it is incorrect to contend that the period of limitation would

commence from the date of the raising of the first supplementary bill on

13.08.2015. Thus, it is contended that the appellant cannot take advantage

of its own wrong and contend that the demand for DPS is beyond the period

of limitation under Section 56(12) of the Act. With the above submission the

learned Senior Advocate prayed for dismissal of the appeal.

13. Power to levy surcharge is traceable to the regulations framed by the

West Bengal Electricity Regulation Commission. Regulation 3.3.9 of the

2013 Regulation states that all categories of consumers committing default

of payment of the bill amount in time and in the stipulated manner shall be

APO NO. 82 OF 2023 REPORTABLE

liable to pay surcharge, penalty etc. at the rates made applicable in the

concerned tariff order or in the Act or in the Regulations along with other

penal actions as per the provisions of the Act and the Regulations. The 2011

Regulation also provides for collection of delayed payment surcharge and in

terms of Regulation 4.1.4. the rates of applicable delay in payment

surcharge arising from non-payment of electricity charges as also other

charges by a consumer shall be 1.2% per month of delay or pro-rated for

part thereof upto 3 months of delay, at 1.5% per month of delay or pro-rated

part thereof for any period beyond 3 months of delay but upto the next 3

months and at 2% per month of delay or pro-rated for part thereof beyond

first 6 months of delay. It further states the delay in payment shall be

accounted from the due date for payment. Thus, delayed payment,

surcharge (DPS) is without prejudice to the provisions of disconnection

under the Act and the Regulations made thereunder. The appellant had

entered into an agreement with DPL and in terms of Clause 12 of the said

agreement and Clause 13 of the agreement would be relevant. Sub-clause

(1) of clause 13 states if the consumer fails/ fail to pay the amount of any

bill under the agreement within the due date of the bill referred to, shall give

the consumer 15 days notice of an intimation to discontinue the supply of

the electricity energy and after the expiry of such period, if payment has not

been received in the meantime, may forthwith disconnect the supply until

full payment for all obligation pending including charge for the work of

disconnection and reconnection has been made. Sub-clause (2) of clause 13

states that for non-payment of any bill within the due date, the consumer

shall pay late payment surcharge at the rate specified in the Schedule II to

APO NO. 82 OF 2023 REPORTABLE

the said agreement. In Schedule II under the column delayed payment

surcharge, it is stated that it shall be as per the tariff order issued by the

West Bengal Electricity Regulatory Commission from time to time. Therefore,

the appellants are precluded and estopped from pleading that no DPC can

be levied and collected from them whenever there is delay in payments of

charges. The question would be as to whether the respondent could have

invoked Sub-section (2) of Section 56 for the purpose of recovery of the DPS

and upon failure to remit the same threatening disconnection. The

contention of the learned Senior Advocate for the appellant is that the period

of limitation for computing the 2 year period as stipulated under Sub-

section (2) of Section 56 is the date on which the supplementary bill dated

13.08.2015 was raised. It is further contended that the bills which were

raised subsequently, there was no indication of any errors payable by the

appellant and for the first time in bill date 07.11.2017 alone the arrears

were shown. Therefore, it is submitted that on and after the date of expiry of

2 years period, computed from 13.08.2015, DPS cannot be recovered by

invoking Section 56(2) of the Act though, it will be open to the respondents

to resort to the procedure under Section 56(1) of the Act in the accordance

with law.

14. Late payment surcharge means the charge on all amounts not paid by

the consumer by the due date prescribed. A surcharge is simply a type of

cost that is applied over and above a standardized cost. Surcharge is an

additional fee an added charge, or an extra tax that gets added to the total

cost of a good or service. Default surcharge is in the nature of a civil penalty

APO NO. 82 OF 2023 REPORTABLE

and this is with a view to encourage business houses to pay the charges/

taxes due on time.

15. On a perusal of the bill dated 13.08.2015 we find that there is clear

mention about the rate of surcharge payable. Even assuming, it was not

explicitly mentioned in the supplementary bill, yet the appellant cannot

escape from the levy charges and liability in the light of the statutory

regulation read with the agreement entered into between the appellant and

the distribution company. Therefore, such argument which is contrary to

the factual position has to be outrightly rejected and accordingly rejected.

Having held thus, if we examine the order passed by the learned Single

Bench, we find that the reasons to be perfectly in order. It has been rightly

held that a combined reading of Regulation 4.1.4 with Section 56 clearly

indicates the approval of the liability to pay DPS arises not from the date

when the bill was first raised for payment of the original principal amount

but from the first instance of non-payment of the concerned charges.

Regulation 4.1.4 states that the licensee may disconnect or cut off supply of

electricity of any defaulting consumer who fails or neglects to pay the

electrify charges and/or other charges due from the consumer as per the

electricity bill and/or demand unless subject to fulfilment of the conditions

of Regulation 4.1.3, 4.1.1 or 4.1.2 whichever is applicable. Thus, the

liability to pay other charges (DPS) would arise as and when a default is

committed. It is not in dispute that the appellant did not adhere to the

payment schedule which was initially granted by DPL and subsequently,

granted by the respondent distribution company by virtue of an agreement

on 08.11.2019. We are not concerned about the dues payable to DPL before

APO NO. 82 OF 2023 REPORTABLE

its merger with the respondent distribution company as it is admitted that

no DPS has been charged in respect of any of the payments which were

made to DPL though belatedly, and the DPL has been calculated taking into

consideration the defaults committed by the appellant from time to time only

with regard to the amount of Rs. 8.81 crores which was due and payable by

the appellant on the date when DPL merged with the respondent

distribution company. The appellants having admitted the default it goes

without saying that the respondent distribution company is entitled to take

into consideration the period of delay and accordingly, levy the DPS as per

the tariff schedule. By way of illustration if the 3rd instalment which was due

and payable was not paid on time and there has been a delay committed by

the appellant for a period of 30 days, then the DPS will become chargeable

for the 30 days period of delay, and this is so because the liability for

payment of DPS is only upon delay in payment. Therefore, learned Senior

Advocate appearing for the respondent distribution company is right in his

contention that the calculation of the DPS is a dynamic formula and is not

static, as DPS is leviable when payment is made belatedly. With regard to

the plea of waiver made by the appellant which was pressed into service by

the respondent during the course of argument in the writ petition, the

learned Writ Court has ruled in favour of the appellant, and in the absence

of any appeal by the respondents distribution company we are not required

to examine the said aspect though we have a slightly different opinion on the

said issue. This is so because of the concept that DPS and calculation

thereof is a dynamic formula then it goes without saying that on every

occasion when there was a delay and DPS become leviable and the

APO NO. 82 OF 2023 REPORTABLE

consumer consciously seeks for waiver of such payment it goes without

saying that at the relevant point of time there was acknowledgement of

liability. However, we do not wish to render any finding on the said issue for

the reason mentioned above. Consequently, there would not be any need to

deal with the decision in Asset Reconstruction Company (India) Limited

Versus Bishal Jaiswal 5.

16. Mr. Sengupta, learned Senior Advocate referred to the decision of the

Hon'ble Supreme Court in Rahamatullah to support the contention that

obligation of a consumer to pay electricity charges arises after the bill is

issued by the licensing company. We need to take note of the facts of the

said case where the issue was an additional demand for consumption of

electricity for the past period and the question arose was whether the

appellant thereunder could have invoked Section 56(2) of the Act.

Considering the said facts and circumstances, the Hon'ble Supreme Court

interpreted Section 56(1) and (2) and held that the obligation of a consumer

to pay would arise when bill is issued by the licensing company quantifying

the charges to be paid and electricity charges would become first due only

after the bill is issued to the consumer, even though the liability to pay may

arise on the consumption of electricity.

17. In our considered view, the decision is clearly distinguishable on facts.

In the case on hand, the demand is with regard to DPS and not for

electricity consumption charges. Admittedly, on the date of merger Rs. 8.81

crores was due and payable towards consumption charges. This was

permitted to be paid in instalments making it clear that DPS will be levied.

(2021) 6 SCC 366

APO NO. 82 OF 2023 REPORTABLE

The appellant did not adhere to the instalment payment committed default,

and admittedly there was delay in payment. Therefore, as and when the

delay occurs, automatically DPS will stand attracted and the appellant

cannot escape from such liability. The decision in case of K.C. Ninan, the

Hon'ble Supreme Court had elaborately considered the implication of

Section 56(2) of the Act on recovery of electricity dues by electric utilities.

However, we find that in the said decision, the aspect regarding levy of DPS

was not the subject matter in controversy and consequently the

interpretation to the period of limitation under Section 56(2) of the Act

should enure in favour of the respondent distribution company having held

that the levy of demand of DPS is a dynamic exercise and not static exercise

and the cause of action continues to arise as and when delay in payment

arises.

18. For all the above reasons, we find no ground to interfere with the

judgment and order passed by the learned Single Bench. Accordingly, the

appeal fails and dismissed. The time stipulated in paragraph 51 of the

impugned order is extended till 30.09.2023. In the event of non-payment,

the respondents are at liberty to proceed in terms of the direction issued in

paragraph 52 of the impugned judgment.

(T.S. SIVAGNANAM, CJ.)

I Agree.

(HIRANMAY BHATTACHARYYA, J.)

(P.A- PRAMITA/SACHIN)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter