Citation : 2023 Latest Caselaw 2765 Cal
Judgement Date : 20 April, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.7255 of 2023
Hanif Haque
Vs.
The West Bengal State Electricity Distribution
Company Limited and others
For the petitioner : Mr. Falguni Bandyopadhyay,
Ms. Riya Ballav
For the WBSEDCL : Mr. Mihir Kundu
Hearing concluded on : 30.03.2023
Judgment on : 20.04.2023
Sabyasachi Bhattacharyya, J:-
1.
As recorded in the order dated March 30, 2023, a limited question has
arisen for consideration in the present case. The licensee has placed
reliance on an Office Order dated May 5, 2012, which has relied on
Clauses 4.4.1 to 4.4.5 of Regulation 46 of the West Bengal Electricity
Regulatory Commission (WBERC), to ask for an amount of
Rs.2,65,319.65 p from the petitioner for constructing a sub-station
which would be necessary to give electricity connection to the
petitioner.
2. It is seen from Clauses 4.4.1 to 4.4.5 of Regulation 46 that the same
apply to cases where a techno economic study is required to be
undertaken for ascertaining the feasibility to erect or commission a
new sub-station which would be necessary to give electricity
connection to an applicant.
3. The modality of such study has been indicated therein, which is
prefaced by a mandatory requirement to conduct such a study for
such purpose.
4. In the present case, the specific technical stand taken by the
WBSEDCL is that a new sub-station is required to be commissioned to
give the electricity connection to the petitioner.
5. The rest of the provisions under the said segment of clauses follow
automatically, inasmuch as the petitioner is required to pay the
necessary estimated amount for conduct of such study. In the event
such earnest money is paid and remains with the licensee, such a
study would be conducted by the licensee and it would be
communicated to the petitioner whether it is feasible to commission
such sub-station.
6. In the absence of the deposit of such amount, however, the process of
erecting/commission of such sub-station would not be initiated at all.
In the alternative, even if the applicant opts to take back the earnest
money, no such techno economic study would be undertaken and the
earnest money would be refunded.
7. Section 181 of the Electricity Act, 2003 (hereinafter referred to as, "the
2003 Act") empowers the State Commissions to make necessary
Regulations on the subjects covered by the sub-sections of Section
181. Under such provisions, the conditions of license, methods and
principles by which charges for electricity shall be fixed under Section
45(2), the Electricity Supply Code under Section 50, Standards of
Performance of a Licensee under Section 57(1) of the Act and the
terms and conditions for determination of tariff under Section 61 all
are broadly covered. Hence, the WBERC has ample power to
formulate Clauses 4.4.1 and 4.4.5 of Regulation 46. Once framed, the
regulations have the force of law behind them.
8. Office Order No.52 dated May 5, 2012 issued by the licensee company
only reiterates such Regulations and, as such, cannot be said to be de
hors the law. Hence, the limited scope of consideration is whether the
charges levied the petitioner by the licensee in the present case on are
duly sanctioned by law, keeping in balance the right of a consumer to
get electricity supply to his premises under Section 43 of the 2003 Act
and the authority of the licensee in fixing modalities.
9. Section 43(1) of the 2003 Act mandates every distribution licensee, on
an application by the owner or occupier of any premises, to give
supply of electricity to such premises within one month after receipt of
the application after requiring such supply. The first proviso thereto
stipulates that where such supply requires extension of distribution
mains or commissioning of new sub-stations, the licensee shall give
the electricity to such premises immediately after such extension or
commissioning or within such period as may be specified by the
Appropriate Commission.
10. Sub-section (2) of Section 43 provides that it shall be the duty of every
distribution licensee to provide, if required, electric plant or electric
line for giving electric supply to a premises as specified in sub-section
(1).
11. Section 45 of the 2003 Act empowers the licensee to recover charges
for the supply of electricity under Section 43. Thus, Sections 43, 45
and 181 of the 2003 Act, read in conjunction, clearly empower the
licensee to demand as a pre-requisite the payment of amounts as
stipulated by Regulations by the State Commission as a pre-condition
for giving the electricity supply to the applicant.
12. In the present case, the technical assessment made by the licensee
fixed the estimated amount for constructing new sub-station at
Rs.2,65,319.65 p.
13. There is no scope of the petitioner to contest the veracity of such
calculation, in the absence of any rebuttal thereto being produced by
the petitioner.
14. A perusal of the scheme of the 2003 Act, as discussed above, clearly
shows that the licensee acted within its power to claim such amount
from the petitioner, since the right under Section 43(1) of the 2003 Act
is not unfettered but circumscribed by the other provisions of the
2003 Act, including Sections 45 and 181, read with the WBERC
Regulations.
15. In fact, in the present case, keeping in view the economic condition of
the petitioner, the licensee acted graciously enough in agreeing to
waive the cost of Rs.2,00,000/- and to take only Rs.65,000/- from the
petitioner as the necessary cost for constructing the sub-station,
thereby agreeing to bear a portion of such costs.
16. It would be entirely against the law for this Court, sitting in judicial
review under Article 226 of the Constitution of India, to direct the
WBSEDCL to spend further public money by unnecessarily decreasing
the amount payable further, merely to serve the purpose of an
individual. Hence, there is no scope for interference in the present
writ petition. However, in view of the fair offer made by the WBSEDCL
to waive the cost of Rs.2,00,000/- and take only Rs.65,000/- from the
petitioner for constructing new sub-station, it would only be
appropriate if liberty is given to the petitioner to deposit the amount.
17. Accordingly, WPA No.7255 of 2023 is disposed of by granting liberty to
the petitioner to deposit an amount of Rs.65,000/- with the
WBSEDCL within a fortnight from date, upon which the WBSEDCL
shall take expeditious steps for erection/commission of the new sub-
station necessary to give electricity connection to the petitioner and
thereafter shall proceed to give such connection to the petitioner
expeditiously, subject to compliance of all due formalities by the
petitioners.
18. However, it is made clear that the decision in the present case shall
not operate as a precedence and has been passed only due to the fair
approach of the WBSEDCL in waiving Rs.2,00,000/- out of the total
technical costs estimated.
19. There will be no order as to costs.
20. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!