Citation : 2022 Latest Caselaw 7004 Cal
Judgement Date : 27 September, 2022
In the High Court at Calcutta Civil Revisional Jurisdication Appellate Side
Present:-
The Hon'ble Justice Subhasis Dasgupta.
C.O. No. 810 of 2022 Smt. Sarala Mahato & Ors.
Vs.
Smt. Anguri Mahato & Ors.
For the Petitioners : Mr. Chittapriya Ghosh,
Ms. Priyanka Saha,
Ms. Komal Singh.
For the Opposite Parties : Mr. Falguni Bandyopadhyay,
Ms. Riya Ballav.
Heard On : 08.09.2022, 29.07.2022.
Judgment : 27.09.2022.
Subhasis Dasgupta, J:-
Rejection of a prayer for amendment is under challenge in this case.
By order dated 11th March, 2022, Learned Civil Judge (Junior Division),
2nd Court, Purulia in Title Suit No. 72 of 2008 rejected such amendment.
Mr. Chittapriya Ghosh, learned advocate appearing for the
petitioners/plaintiffs submitted that by the proposed amendment, the
incident held on 30.06.2021, relatable to dispossession of
petitioners/plaintiffs from the suit property, for the defendants having
trespassed into the suit land, had been sought to be introduced upon
inviting an amendment, but the same was rejected by the court below.
The alleged story of dispossession of petitioners/plaintiffs from the
suit property is also subject to another claim of recovery of possession in
the pending litigation.
It was thus contended by Mr. Ghosh that it was a subsequent event
that had taken place during the pendency of litigation, and the proposed
amendment ought to have been allowed by the court below.
Reliance was placed by Mr. Ghosh on a decision reported in 2022
SCC OnLine SC 1128 delivered in the case of Life Insurance
Corporation of India Vs. Sanjeev Builders Private Limited and
Another, to enforce the stand of petitioners that the proposed amendment
should have been necessarily allowed for determining the real question of
controversy, as the same would not cause injustice or prejudice to the
other side.
While making elaboration of such issue, Mr. Ghosh submitted that
by the proposed amendment, the petitioners did not seek to withdraw, nor
it had a relatable reference to a time barred claim, and would enable the
court to pin-pointedly consider the dispute and would further aid in
rendering a satisfactory decision.
It was thus emphasized by Mr. Ghosh that delay in applying for
amendment alone, would not be the ground to disallow the same, for the
aspect of delay being arguable one.
Mr. Falguni Bandyopadhyay, learned advocate appearing for the
opposite parties submitted, denying the submission of Mr. Ghosh, that the
story of alleged dispossession had been cooked up, as
defendants/opposite parties were all along in possession of suit property,
on the strength of sale deed, executed in the year 1971, for more than 50
years.
It was thus submitted by the opposite parties that the date of
alleged dispossession, mentioned in the schedule to the plaint for
amendment, is fictitious one, and more so, there had been three previous
amendments already allowed on the prayer of petitioners with costs, for
which the instant amendment, being fourth one, should not have been
allowed in context with the principle, that piecemeal amendment would be
contrary to the sanction of law.
As the proposed amendment was relatable to infraction of Articles
64, 65 of the Limitation Act, and provisions of Specific Relief Act, amount
of court fees, liable to be deposited, before hearing of amendment petition
together with valuation of the suit property, should have been ascertained
first, by calling a report from District Registrar for the purpose.
Further challenge was raised by Mr. Bandyopadhyay that at the
belated stage of the suit, the proposed amendment should not be
considered ignoring the proviso contained in Order 6 Rule 7 of Code of
Civil Procedure.
Reliance was placed by learned advocate for the opposite parties on
a decision reported in 2010 SCC OnLine P&H 1317 delivered in the case
of Khusi Ram Vs. Murli Manohar Thatheran Panchayati Mandir &
Dharamsala to contend that no amendment could be allowed after
commencement of trial, unless the court comes to conclusion that in spite
of due diligence, the parties could not have raised the matter before the
commencement of the trial.
While making elaboration of such decision, Mr. Bandyopadhyay
submitted that the commencement of the trial having been taken place
already, the petitioners seeking amendment had failed to establish that
despite due diligence he could not have invited the proposed amendment
earlier.
Reliance was further placed on a decision reported in AIR 1996
Supreme Court 2358 delivered in the case of Radhika Devi Vs.
Bajrangi Singh & Ors. to contend that when by the proposed
amendment, the petitioners had proposed for recovery of possession, the
effect of the amendment would be to take away a legal right, what
opposite parties had accrued in the meantime with the passage of time, on
the strength of their alleged uninterrupted, continuous possession vide
their sale deed executed in the year 1971 with respect to subject property
under reference.
In reply Mr. Ghosh submitted that though issues in this case had
already been framed on 17th July, 2019, but no witness thereafter had
been examined, followed by tender of evidence-in-chief, under Order 18
Rule 4 C.P.C.
According to Mr. Ghosh, there had been no effective commencement
of trial, as the affidavit-in-chief could not be furnished, as yet.
Rejection of prayer for amendment is virtually on fundamental
ground, for attracting the mischief, mentioned in Order 6 Rule 17 C.P.C.,
for the amendment having being proposed at the belated stage, i.e. after
the commencement of trial.
The schedule of the proposed amendment goes to show that during
the pendency of the litigation, the petitioners claimed to have been
dispossessed on 30th June, 2021, for which the petitioners proceeded to
incorporate a prayer for recovery of possession of the land, already
dispossessed, which is grossly challenged by the opposite parties.
Upon seeing the schedule of proposed amendment, it appears that
amendment if allowed, would not change the nature and character of the
pending suit.
The proposed amendment would, however, facilitate the court below
to unfold the controversy surfaced at the moment, giving appropriate
decision for the purpose.
The story of dispossession, followed by insertion of a prayer for
recovery of possession is always subject to proof, but it has a strong nexus
with the denial of dispossession, disclosed in the written objection of the
opposite parties, filed by against the proposed amendment. The claim of
dispossession of the petitioners, as well as the claim of long continuous
and uninterrupted possession of subject land, since 1971, is a disputed
question of facts and law, which cannot be decided without entering into
trial of this case.
At the same time, the alleged claim of dispossession of petitioners,
followed by claim for recovery of possession, though advanced at a later
stage, since initiation of the suit, the same should not be refused, upon
merely viewing the objection raised by the opposite parties, claiming all
along possession of the suit property, since 1971.
Since, the opposite parties incidentally raised the valuation of suit
plot and consequent payment of court fees, liable to be deposited, the
same may be raised, if necessary, upon filing a separate application for
the purpose, challenging the maintainability of the suit.
Merely upon raising a challenge, disputing with the valuation of the
suit plot together with alleged less payment of court fees, the prayer for
amendment should not be refused.
This is a suit of 2008, in which there has been as many as three (3)
amendments allowed already. Piecemeal amendment is undoubtedly not
encouraging one. But the petitioners having set forth the date, in Para-12
of the proposed amendment, disclosing therein that on 30th June, 2021,
the petitioners had been dispossessed by the opposite parties, which
though challenged to be a fictitious one by the opposite parties, the same
in the absence of evidence being recorded, would be very difficult to attract
the mischief available under Order 6 Rule 17 C.P.C. Merely for the delay
being caused in inviting the proposed amendment, the delay thus caused
should not be critically viewed giving precedence to technicalities, for the
peculiarities of the circumstances involved in this case.
Since an effort has been there to seek piecemeal amendment, the
proposed amendment needs to be considered giving some substantial
amount of costs.
For the discussions made hereinabove, the revisional application
succeeds.
The impugned order is set aside subject to payment of costs of
Rs.25,000/- (Rupees Twenty Five Thousand Only) to be deposited by
petitioners to opposite parties within the second (2nd) week after reopening
of the Puja Vacation of the court below.
It is, however, clarified that after deposition of costs within the
period mentioned hereinabove, the amended copy of the plaint may be
furnished within three (3) days thereafter, upon supplying the same to the
opposite parties/defendants.
Learned court below is directed to accept the amended copy of
plaint. The court below is further directed to fix a suitable date within one
(1) week thereafter, permitting the opposite parties/defendants to furnish
additional written statement, if any, in accordance with law.
This would not, however, prevent the court below to frame any
additional issues, if any, in context with the proposed amended pleadings,
as mentioned hereinabove.
Since, there has been sufficient period of time already lapsed, the
logical conclusion of the suit may be reached expeditiously as possible,
preferably before end of September, 2023.
The revisional application is thus disposed of.
Parties are directed to make communication of this order to the
learned court below.
Urgent photostat certified copy of this order, if applied for, be given
to the parties, upon compliance of all formalities, on priority basis.
(Subhasis Dasgupta, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!