Citation : 2022 Latest Caselaw 6419 Cal
Judgement Date : 8 September, 2022
Ct. 05
Item No.07
08.09.2022
(Suvendu)
WPA 20114 of 2022
Techma Engineering Enterprise
Private Limited & Anr.
Vs.
Union of India & Ors.
Mr. Jishnu Chowdhury
Mr. Rudrajit Sarkar
Mr. Assish Chowdhury
Mr. Rabindra Kumar Mitra
Ms. A. Basu
Ms. Puja Tripathy
............for the petitioners
Mr. Ashok Bhaumik
.......for the respondent Nos. 1-3
The affidavit of service is taken on record.
The petitioners complain of a unilateral
change of the tender terms by the Easter Railways
to the detriment of the petitioners. The petitioners
seek a stay of the further process of the said
tender which involves manufacturing and supply
of metal liners to Eastern Railways.
According to learned counsel appearing
for the petitioners, the tender terms incorporated
in the Notice Inviting Tender dated 20.10.2021
was the basis on which the petitioners agreed to
participate in the tender on 25.11.2021. The
Letter of Acceptance of 17.03.2022, however,
changed at least two Clauses of the Special and
General Clauses of the Contract which were a part
of the NIT dated 20.10.2021. Of the two Clauses,
the petitioners are particularly aggrieved by Clause
5(i) which introduces the commencement of
delivery period within three months of issue of the
contract. Counsel submits that the petitioners
may not have participated in the tender had the
petitioners been made aware of the changes which
were inserted later.
Learned counsel appearing for the
respondent Eastern Railways submits that the
petitioners have come to the Court at a belated
stage and the petitioners have failed to supply the
liners despite six months having elapsed from the
issuance of the Letter of Acceptance.
Upon consideration of the documents
placed before the Court on behalf of the parties, it
is apparent that under Clause 5(i), an additional
term was introduced in the Letter of Acceptance
dated 17.03.2022, which was not part of the NIT.
A tender is an invitation to offer, which, in this
case, was made on 20.10.2021 persuading the
petitioners to participate in the tender. The
petitioners' participation may be seen as accepting
an offer which was altered on 17.03.2022 by way
of the Letter of Acceptance in the form of a
counter-offer. The change in the Letter of
Acceptance amounts to a significant alteration
amounting to changing the rules of the game after
the petitioners entered the arena.
Any unilateral change made to the
contractual terms by one of the parties to the
contract mounts to destruction of the contract and
cannot be insisted upon unless the other party
agrees to the alteration. Such unilateral changes
subsequent to acceptance of the offer has a direct
bearing on the binding nature of the contract.
Refer: Suresh Kumar Wadhwa Vs. State of Madhya
Pradesh & Ors., (2017) 16 SCC 757 and Moolji
Jaith & Co. Vs. Seth Kirodimal, AIR 1961 Ker 21.
The judgment in Tej Prakash Pathak & Ors. Vs.
Rajasthan High Court & Ors., (2013) 4 SCC 540,
supports the principle that a change in the rules of
game either midstream or after the game is played
cannot be done.
It also appears from the documents that
other Railways / respondents before the Court
have started issuing purchase orders on the
petitioners based on the altered terms in the Letter
of Acceptance.
The petitioners are hence entitled to relief.
The objection taken on behalf of the
Railways of the petitioners' not supplying the
goods is without basis since the petitioners have
written to the Railways from April to August, 2022
recording their objections to the additions of terms
in the Letter of Acceptance.
This Court is of the considered view that
until the respondents produce their defence by
way of affidavits, the Eastern Railways as well as
the other respondents should be restrained from
proceeding any further with the tender or the
purchase orders issued on the petitioners.
Let affidavit-in-opposition be filed within
one week after reopening of the Court in
November, 2022, as prayed for; Reply within one
week thereafter.
List this matter on 22nd November, 2022.
Urgent photostat certified copy of this
order, if applied for, be given to the parties on
usual undertakings.
(Moushumi Bhattacharya, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!