Citation : 2022 Latest Caselaw 3680 Cal
Judgement Date : 29 June, 2022
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.16954 of 2021
Debashish Mitra
Vs.
Union of India and others
For the petitioner : Mr. Ranjan Kali,
Mr. Mitul Chakraborty
For the
respondent nos. 2 to 4 : Mr. Shuvasish Sengupta,
Mr. Soumyajit Mishra
Hearing concluded on : 10.06.2022
Judgment on : 29.06.2022
Sabyasachi Bhattacharyya, J:-
1. The petitioner, being a proprietor of a firm carrying on business under
the name and style of M/s. D. M. Enterprises, emerged successful in a
tender floated by the respondent no.4 on June 9, 2020 and a
provisional acceptance letter was issued to the petitioner on July 21,
2020. On the same date, the petitioner deposited a Performance Bank
Guarantee of Rs.7,13,446/-.
2. The work order was issued in favour of the petitioner on July 31,
2020. An agreement was, accordingly, entered into between the
parties on the same date.
3. Subsequently, the petitioner commenced the work in terms of such
agreement, for maintenance and provisioning of land-line and broad-
band network. However, due to subsequent difficulties faced by the
petitioner, the petitioner gave a letter on August 24, 2020 intimating
the respondent-authorities about the hindrance in the completion of
the job.
4. Due to the natural calamity Amphan, on August 29, 2020 the
petitioner further pointed out a set back to the work by his letter to
the respondents.
5. The petitioner thereafter raised an invoice to the tune of
Rs.5,80,326/-.
6. Subsequently, there was further correspondence between the
petitioner and the respondents regarding the difficulties and
hindrance allegedly faced by the petitioner in completing the job.
7. Letters to such effect dated September 10, 2020, December 8, 2020
and December 3, 2020 were exchanged between the parties.
8. Subsequently, on October 17, 2020, October 31, 2020 and December
17, 2020, the respondent-authorities issued notices to the petitioner,
pointing out the deficiency in performance of the petitioner.
9. Subsequently, vide Notice dated January 12, 20212, the work order of
the petitioner was cancelled by the respondents and the Performance
Guarantee was forfeited.
10. Learned counsel for the petitioner contends that the respondents
violated principles of natural justice and arbitrarily terminated the
contract between the parties, without adhering to the Clauses of the
agreement itself.
11. Being public authorities, the respondents ought to have acted
transparently and without mala fides, it is contended. Learned
counsel for the petitioner places reliance on Clause 3.6(b) of the
Contract, which provides that the contract will be terminated and PBG
(Performance Bank Guarantee) forfeited, upon non-performance and
failure to meet all the SLAs for consecutive three months. Notice shall
be served for non-performance, as per the said Clause, in the first,
second and third months before final termination. It is further
submitted that the respondents in the present case blatantly
contravened such provision for issuance of three notices in each of the
consecutive preceding months before termination.
12. Moreover, the petitioner was not given any right of hearing which,
according to the petitioner, is in gross violation of the principle of audi
alterem partem, which is an essential component of natural justice.
13. Learned counsel appearing for the petitioner further contends that
although there is a provision for arbitration in Clause 20 of the
contract, the Supreme Court as well this Court, in several cases, have
held that an alternative remedy in the form of an arbitration clause is
not an absolute bar in the exercise of power by this Court under
Article 226 of the Constitution of India, if the relevant yardsticks are
met.
14. Learned counsel for the petitioner places reliance on an unreported
judgment dated September 2, 2021 passed by a co-ordinate bench in
WPA 12367 of 2021 between the present parties. A similar violation
was alleged, it is contended, and the learned Single Judge, by
observing that the provision of Clause 3.6(b) was not complied with by
the Authorities, quashed the notices impugned therein.
15. Learned counsel places further reliance on another unreported
judgment of the Supreme Court in Union of India Vs. Tantia
Construction Private Limited, dated April 18, 2011, wherein it was held
that it is well-established that an alternative remedy is not an
absolute bar to the invocation of the writ jurisdiction of the High
Court or the Supreme Court and that without exhausting such
alternative remedy, a writ petition would not be maintainable.
16. Learned counsel for the petitioner next relies on the Supreme Court in
Unitech Limited and others Vs. Telengana State Industrial
Infrastructure Corporation and others, reported at 2021 SCC OnLine
SC 99. In the said judgment, the Supreme Court observed that, while
exercising its jurisdiction under Article 226, the Court is entitled to
enquire into whether the action of the State or its instrumentalities is
arbitrary or unfair and, in consequence, in violation of Article 14. The
jurisdiction under Article 226 was held to be a valuable constitutional
safeguard against an arbitrary exercise of State power or a misuse of
authority. It was further held by the Supreme Court that the presence
of an arbitration clause does oustthe jurisdiction under Article 226 in
all cases though, it still needs to be decided from case to case as to
whether recourse to a public law remedy can justifiably be invoked.
In the said case, it was held that the jurisdiction under Article 226
was rightly invoked by the Single Judge of the Division Bench of the
High Court.
17. Learned counsel appearing for the respondent-authority relies on
Section 14(c) of the Specific Relief Act and submits that the challenge
is to a contract between the parties which determinable in nature. As
such, the present writ petition is not maintainable under said
provision.
18. That apart, the remedy of the petitioner would at best lie in damages,
which precludes the petitioner from seeking, in effect, specific
performance of the contract.
19. Learned counsel for the respondents relies on Radha Krishan
Industries Vs. State of Himachal Pradesh and others, reported at (2021)
6 SCC 771, wherein the exceptions to the rule of alternative remedy
were stipulated to be :
(a) the writ petition has been filed for the enforcement of a
Fundamental Right protected by Part-III of the
Constitution;
(b) there has been a violation of the principles of natural
justice;
(c) the order or proceedings are wholly without jurisdiction; or
(d) the vires of a legislation is challenged.
20. A writ petition, it was held, should not be entertained when an
efficacious alternative remedy is provided by law. When a right is
created by a statute, which itself prescribes the remedy or procedure
for enforcing the right or liability, resort must be had to that
particular statutory remedy before invoking the discretionary remedy
under Article 226 of the Constitution. This rule of exhaustion of
statutory remedies, it was held, is a rule of policy, convenience and
discretion.
21. Learned counsel next places reliance on a Division Bench judgment of
the Delhi High Court delivered in Rajasthan Breweries Limited Vs. The
Stroh Brewery Company, reported in 2000 (55) DRJ (DB) in support of
the proposition that where a technical know-how agreement is
terminated by a party, the contract is determinable by the action of
parties and could not be specifically enforced.
22. Learned counsel for the respondents next cites Kerala State Electricity
Board and another Vs. Kurien E. Kalathil and others reported at (2000)
6 SCC 293 for the proposition that the writ court is not ordinarily the
proper forum for resolution of disputes relating to terms of contract
with a statutory body. A contract, it was held, does not become
statutory simply because it has been awarded by a statutory body for
the construction of a public utility. Contractual or commercial
activities, the Supreme Court held, by a statutory body need not
necessarily raise issues of public law. The principle of exhaustion of
alternative remedies was thus discussed by the Supreme Court in the
context of maintainability of a challenge under Article 226 of the
Constitution. The Supreme Court went on to hold that a statute may
expressly or impliedly confer power on a statutory body to enter into
contracts, in order to enable it to discharge its functions. Dispute
arising out of the terms of such contracts or alleged breaches have to
be settled by the ordinary principles of the law of contract. It was
reiterated that the fact, that a party to the agreement is a statutory or
public body, will not by itself affect the principles to be applied.
23. Learned counsel also relies onJoshi Technologies International INC Vs.
Union of India and others, reported at (2015) 7 SCC 728, in particular
paragraph 70.6 thereof, in support of his propositions.
24. The limited window for interference under Article 226 of the
Constitution of India has been laid down exhaustively by the
judgments cited by the parties, as discussed above. A consideration
of the present contract between the parties is essential to decide
whether such yardsticks are met in the present case.
25. The primary grievance of the petitioner is that Clause 3.6(b) of the
agreement was contravened by the respondents.
26. The said Clause stipulates that the fault parameters, as specified
therein, have to continue forthree consecutive months and notice has
to be served for non-performance in each of the preceding consecutive
three months before final termination of the contract and forfeiture of
the performance guarantee.
27. Clause 20.1 of the contract provides an arbitration clause in respect of
any dispute, difference, question or disagreement arising between the
parties in connection with, construction, meaning, operation, effect
and interpretation of the contract or breach thereof.
28. In the present case, the annexures to the writ petition indicates that
the work order was cancelled vide notice dated January 12, 2021. By
the same notice, the performance guarantee of Rs.7,13,446/- was
forfeited as per Clause 3.6(b) of Section 3 Part-A of the Bid document.
29. Although not produced by the petitioner, the respondent nos. 2, 3 and
4, in their affidavit-in-opposition, have annexed three letters preceding
the termination, each of which complained about the non-
performance and non-compliance of previous letters in respect of the
contract by the petitioner.
30. The allegations made in the said three letters are sufficiently clear to
serve the purpose of notices under Clause 3.6(b) insofar as alleged
violation of contract by the petitioner is concerned, inasmuch as
specific and transparent allegations have been made in that regard.
31. Although on September 21, 2020 the respondent-Authorities issued a
letter asking the petitioner to inform the author of the letter on daily
basis whenever any outdoor fault was restored for the purpose of
verification, the said letter cannot be termed as a letter within the
contemplation of Clause 3.6(b) in respect of non-performance of
contract clauses by the petitioner.
32. However, the subsequent three communications issued by the
respondents in writing clearly indicate and allege the non-performance
of such clause by the petitioner. The respective dates of the said
communications are: October 17, 2020, October 31, 2020 and
December 17, 2020.
33. Going strictly by the letter of Clause 3.6(b), the three notices were not
served in the first, second and third month before termination. The
first letter was dated October 17,2020, whereas the second was issued
on October 31, 2020 and not in November, 2020. The third letter,
however, was duly issued on December 17, 2020.
34. The second letter, thus, does not strictly fulfill the requirement of said
Clause of the agreement.
35. However, it is arguable as to whether the provisions of Clause 3.6(b)
mandate a strict time gap of one month between each of the preceding
letters before termination or whether three notices during the
preceding three-month period would be sufficient for the purpose of
termination within the contemplation ofClause 3.6(b).
36. It is noteworthy that the entire case of the writ petitioner is based on a
technical contravention of the stipulated time-gaps between the
issuance of the three letters preceding termination, which does not
comprise any patent irregularity, arbitrariness or mala fide on the part
of the respondent-Authorities or an effort to favour any third party in
preference over the petitioner.
37. In fact, in public works, a strict standard is to be maintained for
performance, more so, as the nature of the petitioner's work included
maintenance of telecommunication lines and internet connections,
which together comprise the bulwark of the entire virtual
interconnectivity in the state. A disruption in such service would
entail various parts of the state being cut off from each other, causing
several important projects and essential activities to come to a
grinding halt or get delayed.
38. Moreover, the alleged breach committed by the respondents was not of
such a serious nature that it tantamounted to patent violation of any
core provision of the contract and/or any Fundamental Right, for that
matter.
39. Although there was interference in a somewhat similar matterbetween
the parties by a co-ordinate Bench, the occasion for interference there
was clearly recorded to be a gross violation of Clause 3.6(b), as
opposed to the present case.
40. In the said case, no notice was issued at all prior to final termination
whereas, in the present case, three consecutive notice were issued.
Since the language of Clause 3.6(b) was that the notices have to be
served in the "first month, second month and third month" before
final termination, apart from the second notice being one day earlier
than November 1, 2020, the stipulation of the said Clause was
substantially complied with, since the three letters were issued on
October 17, October 31 (one day before November 1, which would
have satisfied the Clause to the letter) and December 17 of the year
2020 respectively.
41. From another perspective, the mandatory three-month time notice
periodcan be construed in such manner that three notices merely
have to be issued for the three preceding months prior to termination,
and need not each have been issued in three distinct months.
42. Inasmuch as the petitioner's proposition, that there should have been
a gap of one month each between the said three notices, the same
cannot be accepted, since the clause-in-question does not provide that
notices had to be issued after a gap of one month each, thrice before
the final termination. The clear stipulation in the clause is that the
notices have to be issued in the first, second and third months before
final termination. Hence, barring the second notice being technically
early by a day, no fault could be found with the respondents in
complying with the provisions of Clause 3.6(b). Hence, it cannot be
said that the petitioner is entitled either to reversal of cancellation of
the termination or damages.
43. In such view of the matter, the writ petition fails. Accordingly,
W.P.A. No.16954 of 2021 is dismissed on contest.
44. There will be no order as to costs.
45. Urgent certified copies of this order shall be supplied to the parties
applying for the same, upon due compliance of all requisite
formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!