Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Debashish Mitra vs Union Of India And Others
2022 Latest Caselaw 3680 Cal

Citation : 2022 Latest Caselaw 3680 Cal
Judgement Date : 29 June, 2022

Calcutta High Court (Appellete Side)
Debashish Mitra vs Union Of India And Others on 29 June, 2022
                     In the High Court at Calcutta
                    Constitutional Writ Jurisdiction
                             Appellate Side

The Hon'ble Justice Sabyasachi Bhattacharyya


                          W.P.A. No.16954 of 2021

                              Debashish Mitra

                                     Vs.

                          Union of India and others


     For the petitioner             :      Mr. Ranjan Kali,
                                           Mr. Mitul Chakraborty

     For the
     respondent nos. 2 to 4         :      Mr. Shuvasish Sengupta,

Mr. Soumyajit Mishra

Hearing concluded on : 10.06.2022

Judgment on : 29.06.2022

Sabyasachi Bhattacharyya, J:-

1. The petitioner, being a proprietor of a firm carrying on business under

the name and style of M/s. D. M. Enterprises, emerged successful in a

tender floated by the respondent no.4 on June 9, 2020 and a

provisional acceptance letter was issued to the petitioner on July 21,

2020. On the same date, the petitioner deposited a Performance Bank

Guarantee of Rs.7,13,446/-.

2. The work order was issued in favour of the petitioner on July 31,

2020. An agreement was, accordingly, entered into between the

parties on the same date.

3. Subsequently, the petitioner commenced the work in terms of such

agreement, for maintenance and provisioning of land-line and broad-

band network. However, due to subsequent difficulties faced by the

petitioner, the petitioner gave a letter on August 24, 2020 intimating

the respondent-authorities about the hindrance in the completion of

the job.

4. Due to the natural calamity Amphan, on August 29, 2020 the

petitioner further pointed out a set back to the work by his letter to

the respondents.

5. The petitioner thereafter raised an invoice to the tune of

Rs.5,80,326/-.

6. Subsequently, there was further correspondence between the

petitioner and the respondents regarding the difficulties and

hindrance allegedly faced by the petitioner in completing the job.

7. Letters to such effect dated September 10, 2020, December 8, 2020

and December 3, 2020 were exchanged between the parties.

8. Subsequently, on October 17, 2020, October 31, 2020 and December

17, 2020, the respondent-authorities issued notices to the petitioner,

pointing out the deficiency in performance of the petitioner.

9. Subsequently, vide Notice dated January 12, 20212, the work order of

the petitioner was cancelled by the respondents and the Performance

Guarantee was forfeited.

10. Learned counsel for the petitioner contends that the respondents

violated principles of natural justice and arbitrarily terminated the

contract between the parties, without adhering to the Clauses of the

agreement itself.

11. Being public authorities, the respondents ought to have acted

transparently and without mala fides, it is contended. Learned

counsel for the petitioner places reliance on Clause 3.6(b) of the

Contract, which provides that the contract will be terminated and PBG

(Performance Bank Guarantee) forfeited, upon non-performance and

failure to meet all the SLAs for consecutive three months. Notice shall

be served for non-performance, as per the said Clause, in the first,

second and third months before final termination. It is further

submitted that the respondents in the present case blatantly

contravened such provision for issuance of three notices in each of the

consecutive preceding months before termination.

12. Moreover, the petitioner was not given any right of hearing which,

according to the petitioner, is in gross violation of the principle of audi

alterem partem, which is an essential component of natural justice.

13. Learned counsel appearing for the petitioner further contends that

although there is a provision for arbitration in Clause 20 of the

contract, the Supreme Court as well this Court, in several cases, have

held that an alternative remedy in the form of an arbitration clause is

not an absolute bar in the exercise of power by this Court under

Article 226 of the Constitution of India, if the relevant yardsticks are

met.

14. Learned counsel for the petitioner places reliance on an unreported

judgment dated September 2, 2021 passed by a co-ordinate bench in

WPA 12367 of 2021 between the present parties. A similar violation

was alleged, it is contended, and the learned Single Judge, by

observing that the provision of Clause 3.6(b) was not complied with by

the Authorities, quashed the notices impugned therein.

15. Learned counsel places further reliance on another unreported

judgment of the Supreme Court in Union of India Vs. Tantia

Construction Private Limited, dated April 18, 2011, wherein it was held

that it is well-established that an alternative remedy is not an

absolute bar to the invocation of the writ jurisdiction of the High

Court or the Supreme Court and that without exhausting such

alternative remedy, a writ petition would not be maintainable.

16. Learned counsel for the petitioner next relies on the Supreme Court in

Unitech Limited and others Vs. Telengana State Industrial

Infrastructure Corporation and others, reported at 2021 SCC OnLine

SC 99. In the said judgment, the Supreme Court observed that, while

exercising its jurisdiction under Article 226, the Court is entitled to

enquire into whether the action of the State or its instrumentalities is

arbitrary or unfair and, in consequence, in violation of Article 14. The

jurisdiction under Article 226 was held to be a valuable constitutional

safeguard against an arbitrary exercise of State power or a misuse of

authority. It was further held by the Supreme Court that the presence

of an arbitration clause does oustthe jurisdiction under Article 226 in

all cases though, it still needs to be decided from case to case as to

whether recourse to a public law remedy can justifiably be invoked.

In the said case, it was held that the jurisdiction under Article 226

was rightly invoked by the Single Judge of the Division Bench of the

High Court.

17. Learned counsel appearing for the respondent-authority relies on

Section 14(c) of the Specific Relief Act and submits that the challenge

is to a contract between the parties which determinable in nature. As

such, the present writ petition is not maintainable under said

provision.

18. That apart, the remedy of the petitioner would at best lie in damages,

which precludes the petitioner from seeking, in effect, specific

performance of the contract.

19. Learned counsel for the respondents relies on Radha Krishan

Industries Vs. State of Himachal Pradesh and others, reported at (2021)

6 SCC 771, wherein the exceptions to the rule of alternative remedy

were stipulated to be :

(a) the writ petition has been filed for the enforcement of a

Fundamental Right protected by Part-III of the

Constitution;

(b) there has been a violation of the principles of natural

justice;

            (c)    the order or proceedings are wholly without jurisdiction; or

            (d)    the vires of a legislation is challenged.

20. A writ petition, it was held, should not be entertained when an

efficacious alternative remedy is provided by law. When a right is

created by a statute, which itself prescribes the remedy or procedure

for enforcing the right or liability, resort must be had to that

particular statutory remedy before invoking the discretionary remedy

under Article 226 of the Constitution. This rule of exhaustion of

statutory remedies, it was held, is a rule of policy, convenience and

discretion.

21. Learned counsel next places reliance on a Division Bench judgment of

the Delhi High Court delivered in Rajasthan Breweries Limited Vs. The

Stroh Brewery Company, reported in 2000 (55) DRJ (DB) in support of

the proposition that where a technical know-how agreement is

terminated by a party, the contract is determinable by the action of

parties and could not be specifically enforced.

22. Learned counsel for the respondents next cites Kerala State Electricity

Board and another Vs. Kurien E. Kalathil and others reported at (2000)

6 SCC 293 for the proposition that the writ court is not ordinarily the

proper forum for resolution of disputes relating to terms of contract

with a statutory body. A contract, it was held, does not become

statutory simply because it has been awarded by a statutory body for

the construction of a public utility. Contractual or commercial

activities, the Supreme Court held, by a statutory body need not

necessarily raise issues of public law. The principle of exhaustion of

alternative remedies was thus discussed by the Supreme Court in the

context of maintainability of a challenge under Article 226 of the

Constitution. The Supreme Court went on to hold that a statute may

expressly or impliedly confer power on a statutory body to enter into

contracts, in order to enable it to discharge its functions. Dispute

arising out of the terms of such contracts or alleged breaches have to

be settled by the ordinary principles of the law of contract. It was

reiterated that the fact, that a party to the agreement is a statutory or

public body, will not by itself affect the principles to be applied.

23. Learned counsel also relies onJoshi Technologies International INC Vs.

Union of India and others, reported at (2015) 7 SCC 728, in particular

paragraph 70.6 thereof, in support of his propositions.

24. The limited window for interference under Article 226 of the

Constitution of India has been laid down exhaustively by the

judgments cited by the parties, as discussed above. A consideration

of the present contract between the parties is essential to decide

whether such yardsticks are met in the present case.

25. The primary grievance of the petitioner is that Clause 3.6(b) of the

agreement was contravened by the respondents.

26. The said Clause stipulates that the fault parameters, as specified

therein, have to continue forthree consecutive months and notice has

to be served for non-performance in each of the preceding consecutive

three months before final termination of the contract and forfeiture of

the performance guarantee.

27. Clause 20.1 of the contract provides an arbitration clause in respect of

any dispute, difference, question or disagreement arising between the

parties in connection with, construction, meaning, operation, effect

and interpretation of the contract or breach thereof.

28. In the present case, the annexures to the writ petition indicates that

the work order was cancelled vide notice dated January 12, 2021. By

the same notice, the performance guarantee of Rs.7,13,446/- was

forfeited as per Clause 3.6(b) of Section 3 Part-A of the Bid document.

29. Although not produced by the petitioner, the respondent nos. 2, 3 and

4, in their affidavit-in-opposition, have annexed three letters preceding

the termination, each of which complained about the non-

performance and non-compliance of previous letters in respect of the

contract by the petitioner.

30. The allegations made in the said three letters are sufficiently clear to

serve the purpose of notices under Clause 3.6(b) insofar as alleged

violation of contract by the petitioner is concerned, inasmuch as

specific and transparent allegations have been made in that regard.

31. Although on September 21, 2020 the respondent-Authorities issued a

letter asking the petitioner to inform the author of the letter on daily

basis whenever any outdoor fault was restored for the purpose of

verification, the said letter cannot be termed as a letter within the

contemplation of Clause 3.6(b) in respect of non-performance of

contract clauses by the petitioner.

32. However, the subsequent three communications issued by the

respondents in writing clearly indicate and allege the non-performance

of such clause by the petitioner. The respective dates of the said

communications are: October 17, 2020, October 31, 2020 and

December 17, 2020.

33. Going strictly by the letter of Clause 3.6(b), the three notices were not

served in the first, second and third month before termination. The

first letter was dated October 17,2020, whereas the second was issued

on October 31, 2020 and not in November, 2020. The third letter,

however, was duly issued on December 17, 2020.

34. The second letter, thus, does not strictly fulfill the requirement of said

Clause of the agreement.

35. However, it is arguable as to whether the provisions of Clause 3.6(b)

mandate a strict time gap of one month between each of the preceding

letters before termination or whether three notices during the

preceding three-month period would be sufficient for the purpose of

termination within the contemplation ofClause 3.6(b).

36. It is noteworthy that the entire case of the writ petitioner is based on a

technical contravention of the stipulated time-gaps between the

issuance of the three letters preceding termination, which does not

comprise any patent irregularity, arbitrariness or mala fide on the part

of the respondent-Authorities or an effort to favour any third party in

preference over the petitioner.

37. In fact, in public works, a strict standard is to be maintained for

performance, more so, as the nature of the petitioner's work included

maintenance of telecommunication lines and internet connections,

which together comprise the bulwark of the entire virtual

interconnectivity in the state. A disruption in such service would

entail various parts of the state being cut off from each other, causing

several important projects and essential activities to come to a

grinding halt or get delayed.

38. Moreover, the alleged breach committed by the respondents was not of

such a serious nature that it tantamounted to patent violation of any

core provision of the contract and/or any Fundamental Right, for that

matter.

39. Although there was interference in a somewhat similar matterbetween

the parties by a co-ordinate Bench, the occasion for interference there

was clearly recorded to be a gross violation of Clause 3.6(b), as

opposed to the present case.

40. In the said case, no notice was issued at all prior to final termination

whereas, in the present case, three consecutive notice were issued.

Since the language of Clause 3.6(b) was that the notices have to be

served in the "first month, second month and third month" before

final termination, apart from the second notice being one day earlier

than November 1, 2020, the stipulation of the said Clause was

substantially complied with, since the three letters were issued on

October 17, October 31 (one day before November 1, which would

have satisfied the Clause to the letter) and December 17 of the year

2020 respectively.

41. From another perspective, the mandatory three-month time notice

periodcan be construed in such manner that three notices merely

have to be issued for the three preceding months prior to termination,

and need not each have been issued in three distinct months.

42. Inasmuch as the petitioner's proposition, that there should have been

a gap of one month each between the said three notices, the same

cannot be accepted, since the clause-in-question does not provide that

notices had to be issued after a gap of one month each, thrice before

the final termination. The clear stipulation in the clause is that the

notices have to be issued in the first, second and third months before

final termination. Hence, barring the second notice being technically

early by a day, no fault could be found with the respondents in

complying with the provisions of Clause 3.6(b). Hence, it cannot be

said that the petitioner is entitled either to reversal of cancellation of

the termination or damages.

43. In such view of the matter, the writ petition fails. Accordingly,

W.P.A. No.16954 of 2021 is dismissed on contest.

44. There will be no order as to costs.

45. Urgent certified copies of this order shall be supplied to the parties

applying for the same, upon due compliance of all requisite

formalities.

( Sabyasachi Bhattacharyya, J. )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter