Citation : 2022 Latest Caselaw 7 Cal
Judgement Date : 4 January, 2022
January 04, 2022
ARDR
(6)
WPA 10320 of 2021
Samir Ghosal
Vs.
Union of India & Ors.
Mr. Gazi Faruque Hossain,
Mr. Himadri Kumar Mahata,
Ms. Priyanka Mondal,
...for the petitioner.
Mr. Piyush Chaturvedi,
Mr. Uttam Kumar Mandal,
...for the respondent nos. 2 and 3.
Mr. Phiroze Edulji, Ms. Anamika Pandey, Ms. Amrita Pandey, ...for the UOI.
Exception filed by the petitioner against the
report filed on behalf of respondent Power Grid
Corporation of India Limited is taken on record.
The contention of the petitioner is that the plots
of land owned by the petitioner were used by the
answering respondent the Power Grid Corporation of
India Limited for construction of Jirat-Medinipur
transmission line through the property. The
respondent paid an amount of Rs.95,772/- to the
petitioner by way of damage to the crops lying on the
fields/property which were utilised for the project. The
petitioner complains that the said work has
permanently damaged the crops in plot nos. 751 and
1674 and an amount of Rs.9,000/- and Rs.48,000/-
was granted by the respondent to the petitioner for the
damage caused in plot nos. 751 and 1674 respectively.
But no compensation has been granted by the
respondent to the petitioner for permanent damage
caused to the land. The petitioner has referred to the
recommendation for guidelines for payment of
compensation towards damages in regard to the right
of way for transmission lines issued by the Joint
Secretary (Transmission) to the Chief Secretaries/all
the States and Union Territories and other authorities
on 15th October, 2015. The recommendation says that
the compensation towards diminution of land value
should be decided by the States subject to a maximum
of fifteen per cent of the land value as determined
based on Circle rate/Guideline value/Stamp Act rates.
The petitioner prays for compensation in terms of the
said recommendation with regard to the plots of land
used by the respondent.
The respondent the Power Grid Corporation of
India Limited submits that the Corporation acquired
right of user over the petitioner's land in terms of
Section 10(b) of the Indian Telegraph Act, 1885 and
the petitioner has been paid a total sum of
Rs.95,772/- towards damages for the installation work
carried on over the petitioner's land. Learned counsel
for the respondent submits that in the event the
petitioner is aggrieved by the assessment of such
compensation, he is at liberty to approach the
appropriate forum under Section 16(3) of the 1885 Act.
It is not in dispute that the installation work
over the petitioner's land has been completed and the
petitioner has been paid an amount of Rs.95,772/-
towards damages for the same. The recommendation
dated 15th October, 2015, referred to by the petitioner,
indicates that it is only a recommendation issued for
consideration of the States and Union Territories and it
is submitted on behalf of the respondents that the
State of West Bengal has not accepted the said
recommendation. As such, the recommendation has
no statutory force at present.
It is clearly envisaged in Section 10(d) of the Act
of 1885 that in exercise of powers to install telegraph
line or posts over any land, the authority should do as
little damage as possible and pay full compensation to
all persons interested for any damage sustained by
them by reason of such installation. The authority has
paid compensation to the petitioner in terms of the
said provision of law.
The petitioner has heavily relied upon the
recommendation dated 15th October, 2015 in
submitting that besides damages paid to him by the
authority, he is also entitled to compensation at the
rate of fifteen per cent of the market value of the land.
But such recommendation not being accepted by the
State, the respondent has no liability to abide by the
same. In terms of the provisions laid down under
Section 10(d) of the 1885 Act with regard to payment
of compensation for any damage sustained,
compensation has admittedly been paid to the
petitioner by the Power Grid Corporation of India
Limited.
Learned counsel for the respondent has placed
reliance on a judgment in Power Grid Corporation of
India Limited vs. Century Textiles and Industries
Limited and ors. reported in (2017) 5 Supreme
Court Cases 143 passed on December 14, 2016. The
said judgment demonstrates that in view of Section
164 of the Electricity Act, 2003, the Telegraph
Authority/ Power Grid is not under obligation to obtain
prior consent from or issue prior notice upon the
owners of the land and has been empowered to lay
telegraph lines through the land belonging to the
owners on payment of compensation for damages
caused therein on account of such work. However, in
the case in hand, the petitioner has not alleged non-
service of prior notice upon him.
The petitioner is primarily aggrieved with the
compensation paid by the respondent and contends
that the amount has been paid for damages done to
the crops on the land and not for permanent damage
caused to the land itself. I am afraid Section 10(d) of
the 1885 Act does not distinguish between payment of
compensation for the land and damages caused to the
land and the compensation payable in terms of said
provision of law is "for any damage sustained".
Section 16(3) of the 1885 Act is relevant. Section
16(3) says that in case of any dispute arising
concerning sufficiency of the compensation to be paid
under Section 10(d), either party to the dispute can
approach the District Judge within whose jurisdiction
the property is situate, for determination of such
compensation. In view of the same, the petitioner is at
liberty to approach the District Judge within whose
jurisdiction the property is situate, for assessment of
compensation if he is aggrieved by the amount of
compensation paid to him or the determination of such
compensation.
As the respondent has assessed the
compensation in terms of Section 10(d) of the Act of
1885, the remedy of the petitioner lies before the
appropriate forum and this Court, in exercise of extra
ordinary jurisdiction under Article 226 of the
Constitution of India, cannot intervene in such
assessment of compensation, there being alternative,
efficacious remedy available to the petitioner before the
appropriate court.
In view of the above, the writ petition is devoid of
any merit and is liable to be dismissed.
Accordingly, WPA 10320 of 2021 is dismissed.
However, there shall be no order as to costs.
Urgent certified website copy of this order, if
applied for, be furnished to the parties on usual
undertakings.
(Suvra Ghosh, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!