Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gautam Ghosh vs The State Of West Bengal & Ors
2022 Latest Caselaw 8501 Cal

Citation : 2022 Latest Caselaw 8501 Cal
Judgement Date : 20 December, 2022

Calcutta High Court (Appellete Side)
Gautam Ghosh vs The State Of West Bengal & Ors on 20 December, 2022
                                     1


                    IN THE HIGH COURT AT CALCUTTA
                     CIVIL APPELLATE JURISDICTION
                            APPELLATE SIDE
                            F.M.A. 1197 of 2022
                                   With
                          I.A. No. CAN 1 of 2022
                               Gautam Ghosh
                                    VS
                      The State of West Bengal & ORS.
                                    And
                            F.M.A. 1189 of 2022
                                   With
                          I.A. No. CAN 1 of 2022
                               Gautam Ghosh
                                    VS
                      The State of West Bengal & ORS.

BERORE: THE HON'BLE JUSTICE ARIJIT BANERJEE
                     AND
       THE HON'BLE JUSTICE APURBA SINHA RAY

For the appellant         : Mr. Arijit Bardhan, Adv.
                            Mr. Gopal Chandra Banerjee, Adv.
                            Mr. Amit Ranjan Pati, Adv.
                            Mr. Sunayan Ghosh, Adv.

For the 24 Parganas       : Mr. Tapash Kumar Mandal. Adv.
(South) Zilla Parishad

For the State             : Mr. Lalit Mohan Mahata, Adv.
                            Mr. Rudranil De, Adv.

Heard On                  : 6.12.2022 & 12.12.2022

CAV On                    : 12.12.2022

Judgment On               : 20.12.2022


Arijit Banerjee, J.

1. These two appeals and the connected applications have been taken up

together for hearing and disposal as common questions of fact and law are

involved in the two appeals.

2. The issue involved in both the appeals is the validity/legality of

termination of a works contract awarded to the appellant by the South 24

Parganas Zilla Parishad and forfeiture of earnest money deposit and security

deposit. Two works contracts were terminated by orders, both dated

February 16, 2022, issued by the District Engineer of the Zilla Parishad.

Two writ petitions were filed by the appellant challenging the two orders of

termination of contract. The two appeals were disposed of by similar orders,

both dated July 20, 2022. Being aggrieved by the said two orders, these two

appeals have been filed by the writ petitioner.

3. For the sake of convenience we will refer to the records of one of the

writ petitions being W.P.A 8071 of 2022.

4. A Work Order was issued by the Zilla Parishad through the District

Engineer in favour of the appellant for upgradation of road from Golar More

to Chakda under Magrahat-I Panchayat Samity under RIDF - XVII on June

7, 2012. The terms of the work order required the appellant to start the work

immediately and complete the same within 12 months.

5. Clause 2 of the conditions of contract required the appellant, in the

event he failed to comply with any of the conditions, to pay compensation as

indicated in the said clause, subject to a maximum of 10 per cent of the

tender amount. Clause 3 of the conditions of contract empowered the Zilla

Parishad to terminate the contract in the event the appellant was in breach of

the conditions of contract and also to get any unfinished work done through

some other contractor at the risk and cost of the appellant.

6. The appellant fail to complete the work within the stipulated period of

12 months. A show cause notice was issued to him on December 22, 2017.

He replied to such notice. Time to complete the work was extended by the

Zilla Parishad.

7. The appellant failed to complete the work even within the extended

time period. On his request, time was again extended for completion of the

work. Again the appellant was unable to complete the work within the

further extended time period.

8. Another show cause notice was issued to him on October 4, 2021. He

answered such notice. Further extension of time was granted to him to

complete the work. However, again the appellant failed to complete the

work within the extended time period.

9. Finally by a communication dated February 16, 2022, issued by the

District Engineer, the contract was terminated, the security deposit and

earnest money deposit were forfeited and the appellant was debarred for a

period of 2 years from participating in any tender process floated by the said

Zilla Parishad. This communication was challenged by the appellant before

the learned Single Judge.

10. Before the learned Single Judge, the appellant urged the following

points:-

(i) The District Engineer of the Zilla Parishad is not the competent

authority to terminate the contract.

(ii) Time was never the essence of the contract since several

extensions were granted by the Zilla Parishad.

(iii) There is no provision in the contract to blacklist the appellant

and debar him from participating in other procurement processes

undertaken by the Zilla Parishad.

11. The Zilla Parishad urged the following points before the learned

Single Judge:-

(i) The subject work was required to be completed within 12

months from the date of issuance of the work order. Even after ten

years the writ petitioner was unable to complete the work. Several

extensions were granted to the writ petitioner in the interest of the

project. However, his performance was miserable. Ultimately the

Zilla Parishad had no option but to terminate the contract.

(ii) The Zilla Parishad has engaged a separate contractor for

completing the work that has been left unfinished by the writ

petitioner.

(iii) Clause 3 of the conditions of contract clearly indicates that the

District Engineer is the competent authority to terminate the

contract.

12. It was, however, conceded on behalf of the Zilla Parishad that the

contract did not have any clause authorizing or empowering the Zilla

Parishad to blacklist a contractor for any period of time. On the basis of such

concession, the learned Single Judge set aside the decision of the District

Engineer to debar the writ petitioner from participating in procurement

processes under the said zilla Parishad for a period of 2 years. The learned

Judge however did not interfere with the decision of the District Engineer to

terminate the contract and forfeit the security deposit and earnest money

deposit. Being aggrieved the writ petitioner is before us by way of this

appeal.

13. Appearing for the appellant, Mr. Arijit Bardhan, learned Counsel,

submitted that the termination of the contract was bad in law. Although,

initially there was a clause in the contract making time essence of the

contract, after having granted several extensions to the appellant, the Zilla

Parishad could not have relied on such clause for terminating the contract.

Time ceased to be essence of the contract. It was unreasonable on the part of

the Zilla Parishad to terminate the Contract.

14. Learned Advocate also argued that the Zilla Parishad could not have

taken all kinds of coercive steps after terminating the contract. It has not

only forfeited the security deposit and the earnest money deposit. It has

withheld the dues of the appellant. It is getting the balance of the work done

through another contractor at the risk and cost of the appellant.

15. Learned Counsel did not urge the point of lack of authority of the

District Engineer to terminate the contract. Indeed, there is no substance in

such point. The conditions of contract clearly authorize the District Engineer

to issue termination letter in circumstances which, in our view, existed in

this case.

16. We are of the considered view that in the facts and circumstances of

this case, it was not unreasonable or arbitrary on the part of the Zilla

Parishad to terminate the contract. The Zilla Parishad allowed the appellant

almost ten years to complete the work which the appellant was required to

do within one year. The Zilla Parishad showed indulgence of the highest

degree to the appellant for reasons which are not clear to us. Even then, the

appellant could not complete the work. In our view, the contract should have

been terminated much earlier as it was a public project and it is of utmost

importance that such projects are completed within a reasonable time period

which would be reflected in the contract.

17. As regards forfeiture of the earnest money deposit and security

deposit, the terms of the contract clearly authorized the Zilla Parishad to do

so upon the failure of the appellant to perform in terms of the contract. It was

an administrative decision of the Zilla Parishad which we do not find to be

unreasonable in the factual matrix of the case. The learned Single Judge

rightly refused to interfere with such forfeiture.

18. The Zilla Parishad is also entitled, under the terms of the contract, to

have the unfinished portion of the work completed by engaging some other

contractor at the cost of the appellant. The whole idea is that if the Zilla

Parishaad has suffered monetary loss by reason of breach of contract

committed by the appellant, the same is recoverable by the Zilla Parishad

from the dues of the appellant. Of course the Zilla Parishad cannot make a

windfall profit by blocking or not paying the entirety of the legitimate dues,

if any, of the appellant, if such dues exceed the amount that the Zilla

Parishad is entitled to recover from the appellant in terms of the conditions

of contract.

19. The learned Judge has granted liberty to the appellant to approach the

appropriate authority for disbursement of the monies which according to him

are payable to him in terms of the contract. This will necessarily involve an

accounting exercise. In the event the appellant makes any representation in

the above regard before the appropriate authority, the same shall be disposed

of by the authority in accordance with law and the terms of the subject

contract, by a reasoned order, within 3 months from the date of receipt of

such representation after granting adequate opportunity of hearing to the

appellant or his authorized representative. The decision so taken shall be

communicated to the appellant within a week from the date of the decision.

Needless to say, if the authority finds after settlement of accounts, that

monies are due to the appellant, such dues will be paid within a month from

the date of the decision.

20. We see no apparent infirmity in the order under appeal. The order

does not warrant any interference. F.M.A. 1197 of 2022With I.A. No. CAN

1 of 2022 and F.M.A. 1189 of 2022 with I.A. No. CAN 1 of 2022 are

accordingly disposed of with, however, no order as to costs.

21. Urgent certified website copies of this judgment, if applied for, be

supplied to the parties subject to compliance with all the requisite

formalities.

I agree.

(Apurba Sinha Ray, J.)                              (Arijit Banerjee, J.)
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter