Citation : 2021 Latest Caselaw 317 Cal/2
Judgement Date : 23 March, 2021
IN THE HIGH COURT AT CALCUTTA
Civil Appellate Jurisdiction
(COMMERCIAL DIVISION)
Original Side
Present:- Hon'ble Justice I. P. Mukerji
Hon'ble Justice Md. Nizamuddin.
APO 11 of 2021
AP 405 of 2020
Gannon Dunkerley and Co. Ltd.
Vs.
SREI Equipment Finance Ltd.
For the Appellant : Mr. Mainak Bose,
Ms. Sweta Gandhi Murgai,
Mr. Vinay Saraf, Adv.
For the Respondent : Mr. Swatarup Banerjee,
Mr. Abhijit Sarkar, Mr. Ayan Chakraborty, Mr. Hareram Singh, Adv.
Judgment on : 23.03.2021. I. P. MUKERJI, J.-
Only one point was urged in this appeal: there is no arbitration agreement
between the parties. Hence, the respondent could not have invoked Section
9 of the Arbitration and Conciliation Act, 1996 in this court or anywhere
else seeking the protective measure of appointment of a Receiver over the
equipments in question.
On 7th January, 2021 in a Section 9 application a learned single judge of
this court appointed a Receiver over the assets under Sl. Nos. 3 to 6 of
Annexure IV of the Memorandum of Understanding for settlement dated
30th June, 2020 between the parties with a direction to take their actual
physical possession. It was held by the learned judge that as "lessee" of
equipments the appellant had failed and neglected to pay the agreed
amount of "lease rent" under the said memorandum and that these assets
needed protection.
On 20th January, 2021 the appeal from this order was admitted and
expedited with a modification in the impugned interim order to the effect
that the Receiver could take possession of the assets but would not remove
them from the site. The appellant would not use the equipments in any
manner whatsoever.
Whether or not there was an operative arbitration clause requires an
examination of the transaction between the parties and the execution of
agreements between them.
On 26th June, 2017 an agreement described as the "Master Facility
Agreement" was executed between them. Under this agreement the
respondent was to provide financial assistance to the appellant to purchase
equipments. The loan was to be repaid in instalments. These assets were
charged in favour of the respondent. It appears that as and when the
instalments were paid, the hypothecation in favour of the respondent would
be partly released.
Clause 9.11 of the agreement provided for dispute resolution by arbitration.
The clause is inserted below:
"9.11 Dispute Resolution
Any disputes or differences arising out of or in connection with the
Contract during its subsistence or thereafter between the parties including
any disputes and differences relating to the interpretation of the agreement
or any clause thereof shall be settled by arbitration in accordance with the
provisions of the Arbitration and Conciliation Act, 1996 and rules framed
there under and any amendment, modification, statutory enactment
thereto from time to time and shall be referred to the Arbitration of a sole
Arbitrator appointed by the Company upon intimation to all parties to this
Agreement. The proceedings shall be held at Kolkata. The cost of the
proceedings shall be borne by the parties to this Agreement. The award of
the arbitrator shall be final, conclusive and binding on all the parties."
In or about the end of June, 2020 it so happened that the appellant's dues
climbed up to about Rs.82.43 crores. The parties sat down to settle their
disputes. This ended up with the execution of a document described as "a
Memorandum of Understanding for Settlement" on 30th June, 2020. The
parties settled their outstanding at Rs.72 crores to be paid according to the
Repayment Schedule mentioned in Annexure IV of the Memorandum. The
equipments would continue to remain hypothecated till the entire settled
amount was repaid. However, a part of the assets would be released by the
respondent on timely repayment by the appellant.
Now, this subsequent agreement between the parties did not contain an
arbitration agreement as a clause of that agreement.
The contentions raised by Mr. Mainak Bose, learned Counsel appearing for
the appellant are broadly as follows:-
The agreement of 30th June, 2020 was an entirely new agreement between
the parties in supersession of the Master Facility Agreement of 2017. It did
not, according to learned counsel, contain an arbitration clause. Neither
was the arbitration clause in the original agreement incorporated or
deemed to be incorporated in the memorandum of understanding. He said
that mere reference to the arbitration clause in the memorandum would
not suffice. It had to be made part of the agreement by specific
incorporation which had not been done. Various clauses of the
memorandum, to which I shall refer later were read by learned Counsel in
an attempt to prove this point.
The self same clauses were referred to by Mr. Swatarup Banerjee, learned
counsel for the respondent in his effort to show that the arbitration clause
had been duly incorporated.
Before discussing the submission of learned Counsel for the parties, it is
very necessary to set out certain clauses of the agreement which are very
relevant for the purpose of this appeal:
Whereas:
A) Upon being approached by the Borrower, SEFL and the Borrower had
entered into a Master Facility Agreement dated 26th June, 2017, (herein
after to be referred as "MFA") and pursuant thereto various
Contacts/Tranche Schedule(s) (as more fully and specifically detailed in
Annexure I herein below) were executed from time to time as per the
requisition placed by Borrower to avail financial assistance to purchase
various assets for its business on such terms and conditions as
contained in the said MFA and respective Tranche Schedule(s) thereto.
The said Assets which are detailed in the respective tranches and/or
other relevant documents, are exclusively charged and hypothecated in
favour of SEFL against repayment of the facility under the subject
Tranche Schedule(s) read with MFA.........
DEFINITIONS:-
In addition to the terms defined in the Recitals of this MOU, unless
repugnant to the meaning or context thereof the following words and
terms shall have the meaning set out below:-
i) MOU shall mean this Memorandum of Understanding for Settlement
along with all Recitals, schedules, annexures as appended hereto, as
may be amended and modified in writing and is supplementary to the
Master Facility Agreement (MFA) read with respective Tranches
Schedule(s)...............
4) This MOU shall be valid for period of 6 months from its date of
execution, provided that if the Borrower fails to comply with any of its
obligations under this MOU including payment of Instalments strictly as
per Annexure IV for any reason whatsoever or in any manner
whatsoever, and/or makes any further default as described under
MFA, the following would be the consequences of default in addition to
the consequences of events of default as mentioned in MFA:-
a) SEFL may, notwithstanding anything else stated in this MOU, cancel,
suspend, terminate, withdraw with retrospective effect, all or any of the
relief and/or concessions provided to the Borrowers under this MOU,
b) The Total claim of Rs.82,43 Crores (Rupee Eighty Two crores Forty-
three Lacs Only) excluding the amount paid if any under this MOU
would be forthwith due and payable by the Borrower to SEFL
alongwith interest @18% p.a till full and final realization to the
satisfaction of SEFL.
c) Borrower would immediately and unconditionally surrender all the
assets/securities hypothecated and/or charged to SEFL except those
forming part of the contract, if any, in respect of which the instalment
as mentioned in the Repayment Schedule IV has been paid by the
Borrower.
d) SEFL shall have the right to take possession and/or sell the
hypothecated assets and collateral properties offered against this
settlement as mentioned in Annexure V without any further reference to
Borrower.
6) Parties hereby agree that on occurrence of any default by the
Borrower under this MOU, they will fall back to MFA read with tranche
Schedule(s) and SEFL would be at liberty to execute and enforce all the
rights in terms of the MFA including but not limited to the right to
initiate Arbitration under the respective Arbitration Clause of MFA
besides taking any other action available law against the Borrower to
realize the Total Claim amount to which Borrower would not raise any
objection.
10) The borrower hereby agrees and confirms that this MOU is
supplementary to the MFA earlier executed between the parties and
executed bona fide for the purpose quantifying the claim of SEFL as on
date and for settlement of the disputes between the parties amicably.
Apart from the terms specifically modified herein, all other terms and
conditions of the MFA including Clause pertinent to Governing Law and
Jurisdiction will remain unchanged and binding on the parties and
SEFL has full rights and authorities to refer back to the MFA in case of
my inconsistency of this MOU or default by the Borrower's obligation.
Mr. Bose submitted that the memorandum was a new, complete and valid
agreement without an arbitration clause. It was in complete supersession
of the Master Facility Agreement. The former had been completely novated
and supplemented by the Memorandum creating new rights and liabilities.
By referring to Clause 6, he submitted that it was only a reference to the
Master Facility Agreement in the sense that in the event of any default in
the performance of any condition in the Memorandum by the appellant, the
respondent would be at liberty to "fall back" on the Master Facility
Agreement and enforce rights thereunder. This did not mean or imply that
the arbitration clause in the Master Facility Agreement was incorporated in
the Memorandum. The description of the Memorandum as a
supplementary agreement was proof of the fact that it was a subsequent
agreement.
Learned counsel cited paragraphs 12 and 15 of the Section 9 application.
They are as follows:
12. The petitioner had accordingly accommodated the Respondent
but unfortunately after payment of first two installments due and
outstanding on 30th June, 2020 and 15th July, 2020 in terms of
repayment schedule mentioned in the said MOU dated 30th June,
2020 and after taking NOC with regard to 17 tranches the
respondent have deliberately committed breach with regard to
repayment of the settlement amount due and outstanding from 30th
July, 2020 in connection with remaining tranches as mentioned in
the said repayment schedule executed under the Master Facility
Agreement dated 26th June, 2017 to the petitioner.
15. In the aforesaid circumstances and in view of the failure on the
part of the respondent in making payment of the said outstanding
amount of Rs.76,24,58,000/- the petitioner in accordance with the
terms and conditions of the said MOU by a notice issued by its
Advocate dated 10th October, 2020 immediately called for making
payment of the then outstanding dues of Rs.74,41,30,630/- to your
Petitioner together with further interest thereon until payment at the
agreed rate provided under the said agreement. The respondent also
requested to surrender all the assets/securities, hypothecated
and/or charged including all the collateral properties offered against
this settlement in terms of the default clause of the said MOU. A
copy of the said notice is annexed hereto and marked with the
Annexure 'D'.
He also submitted that the cause of action of the respondent in that
application was based on the alleged breach by the appellant of the terms
and conditions of the memorandum which shows that the memorandum
was treated as a separate agreement.
Mr. Swatarup Banerjee learned Counsel appearing for the respondent
submitted that the existence of the arbitration clause was not questioned
before the learned single Judge. It was raised for the first time on appeal.
He cited Section 7(5) of the Arbitration and Conciliation Act, 1996 which is
as follows:
"7(5) The reference in a contract to a document containing an
arbitration clause constitutes an arbitration agreement if the contract
is in writing and the reference is such as to make that arbitration
clause part of the contract."
He argued that the above clauses of the contract not only referred to the
master facility agreement but had the effect of incorporating the arbitration
clause into the memorandum.
DISCUSSION
First, the law on the subject has to be looked into.
The root case is Union of India vs. Kishorilal Gupta & Bros. reported in
AIR 1959 SC 1362 cited by Mr. Bose. The law was stated by Mr. Justice K.
Subba Rao thus:
"The following principles relevant to the present case emerge from the aforesaid discussion: (1) An arbitration clause is a collateral term of a contract as distinguished from its substantive terms; but nonetheless it is an integral part of it; (2) however comprehensive the terms of an arbitration clause may be, the existence of the contract is a necessary condition for its operation; it perishes with the contract; (3) the contract may be non est in the sense that it never came legally into existence or it was void ab initio; (4) though the contract was validly executed, the parties may put an end to it as if it had never existed and substitute a new contract for it solely governing their rights and liabilities thereunder; (5) in the former case, if the original contract has no legal existence, the arbitration clause also cannot operate, for along with the original contract, it is also void ; in the latter case, as the original contract is extinguished by the substituted one, the arbitration clause of the original contract perishes with it; and (6) between the two falls many categories of disputes in connection with a contract, such as the question of repudiation, frustration, breach etc. In those cases it is the performance of the contract that has come to an end, but the contract is still in existence for certain purposes in respect of disputes arising under it or in connection with it. As the contract subsists for certain purposes, the arbitration clause operates in respect of these purposes."
In Young Achievers vs. IMS Learning Resources Private Limited
reported in (2013) 10 SCC 535 also cited by Mr. Bose, Kishorilal Gupta
was referred to. The facts of that case were somewhat similar to ours in the
sense that the original agreements dated 1st April, 2007 and 1st April, 2010
between the parties were followed by a new agreement dated 1st February,
2011 described as the "Exit Paper". The court held that the subsequent
agreement was in complete supersession of the original agreement and
hence the arbitration clause also were superseded and did not survive.
The facts and decisions in Zenith Drugs & Allied Agencies Pvt. Ltd.
Represented by its Managing Director, Shri Uday Krishna Paul vs.
Nicholas Piramal India Ltd. reported in 2019 SCC OnLine SC 946 were
similar.
The parties entered into the Master Facility Agreement on 26th June, 2017
and the Memorandum of Understanding on 30th June, 2020. They were two
agreements at two different points of times. The Master Facility Agreement
contained an arbitration clause. The Memorandum of Understanding did
not contain such as a clause.
The parties may well enter into two contracts covering the same transaction
at different points of time. Let us assume that in the first agreement there
is an arbitration clause. In the second agreement there is none.
If the second contract supersedes the first contract, the arbitration clause
perishes upon execution of the second agreement.
The second contract may not supersede the first contract. Both may be
separate running contracts between the same parties.
Whether the Memorandum was in supersession of the Master Facility
Agreement by novation or was just in modification thereof? Whether there
were two parallel agreements between the parties with regard to the same
transaction or series of transactions? Whether the second agreement has
incorporated some of the terms and conditions of the first agreement? Is it
a separate agreement but upon happening of a certain contingency the
terms and conditions of the second agreement necessarily became
incorporated into it?
The term which is relevant for our consideration is the arbitration clause in
the Master Facility Agreement.
In my view, the arbitration clause need not be stated to be specifically
incorporated in a subsequent agreement, between the parties. One has to
examine the meaning of the words used by them. If the word are
unambiguous, no further exercise is required. If the language is a little
ambiguous the intention of the parties has to be ascertained as to whether
they intended the arbitration clause to be part of the subsequent
agreement and to be governed by it to resolve their disputes arising from
them or either. The intention of the parties may be express or implied but it
has to be clear from the agreement.
Certain clauses of the Memorandum are very important. In its definition
part it is stated that it would be supplementary to the Master Facility
Agreement (see definition Clause i). In Clause 4 defaults were described as
non-compliance with the requirement of the Memorandum as well as of the
Master Facility Agreement. Clause 6 stated that in case of any default by
the appellant in payment under the document the terms and conditions of
payment under the Master Facility Agreement would revive. More
importantly Clause 6 stated that all the rights under the Master Facility
Agreement could be enforced, with special emphasis on the arbitration
clause. Clause 10 made it plain that "apart from the terms specifically
modified herein, all other terms and conditions of the MFA (Master Facility
Agreement) including Clause pertinent to Governing Law and Jurisdiction
will remain unchanged and binding on the parties".
That the Memorandum of Understanding was described as supplementary
to the Master Facility Agreement goes to show that the latter and the
memorandum would operate concurrently, as one agreement. Only those
parts of the Master Facility Agreement which had been modified by the
Memorandum were made inoperative, temporarily. However, they would
become instantly operative on the breach of specified terms and conditions
in the Memorandum. There is no supersession of the Master Facility
Agreement by the Memorandum. Hence, the court is not called upon to
adjudge whether on supersession of the Master Facility Agreement the
arbitration clause in it was incorporated in the later agreement. Both
agreements operated simultaneously. The later agreement was
supplementary to the original agreement. It is evident from the intention of
the parties that this supplementary agreement was subject to the
arbitration clause as well. The draftsmen of the Memorandum were careful
enough to say that the arbitration clause in the Master Facility Agreement
continued to govern the supplementary agreement also. That is to say it
was deemed to have been incorporated in the Memorandum. No further
specific incorporation of the arbitration clause, in my opinion, was
necessary.
Hence, the Section 9 application before the Hon'ble First Court invoking the
arbitration clause in the Master Facility Agreement and the Memorandum
was maintainable.
This appeal has no merit and is accordingly dismissed. The interim order in
appeal is vacated.
Certified photocopy of this order, if applied for, be supplied to the parties
upon compliance with all requisite formalities.
I agree, (MD. NIZAMUDDIN, J.) (I. P. MUKERJI, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!