Citation : 2021 Latest Caselaw 30 Cal
Judgement Date : 5 January, 2021
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No. 10800 of 2020
United Order and Supply Co-Operative Society Ltd.
Vs.
The State of West Bengal and others
For the petitioner : Mr. Saptangshu Basu,
Mr. Swarup Paul,
Mr. Surya Maity,
Ms. Amrita Maji,
Ms. Mrinalini Majumder
For the respondent-authorities : Mr. Samrat Sen,
Ms. Manali Ali
Hearing concluded on : 22.12.2020
Judgment on : 05.01.2021
Sabyasachi Bhattacharyya, J:-
1. Respondent no. 4 floated a two-tier (technical and financial) re-tender
for supply of cooked diet to indoor patients of Durgapur ESI Hospital
vide ESI/DGP/NIT-04/DIET/20/Re 1/847 on June 25, 2020. The
petitioner participated in the re-tender along with sixteen other
bidders and succeeded in the technical bid. Tender Summary Reports
were uploaded on September 10, 2020, indicating that financial bid
was to be accepted in respect of the petitioner and four other bidders,
while the other bidders had been rejected in the technical bid.
However, vide Memo no. ESIH/DGP/1607 dated November 10, 2020,
all sixteen bidders apart from the petitioner were requested to upload
certain shortfall documents to validate their technical bids. On
November 27, 2020, Memo no. ESIH/DGP/1682 was issued,
requesting the petitioner and four other bidders to attend a selection
process where the successful bidder was to be chosen by draw of lots.
2. Learned senior counsel for the petitioner submits that Rule 47C of the
West Bengal Finance Rules provides for a "two-bid" system for high
value purchase exceeding Rs. 10 lakh or for purchasing plant,
machinery, equipment etc. of complex and technical nature which
indicates that bids shall be invited in two parts, first the technical bid
and then, only in respect of technically acceptable offers, the financial
bid. Taking a cue from such Rule, counsel argues that unless the
technical bid of a bidder is accepted on being eligible, the stage of
financial bid does not arise.
3. Learned senior counsel next places reliance on a Memorandum dated
February 14, 2017, which sets out the revised norms for acceptance of
L1/H1 bid/Single bid when the number of qualified bidders during
second call is less than three. Clause II thereof stipulates the
situations on the basis of which the Tender Inviting Authority shall
take a decision if the number of qualified bidders during tender/re-
tender/re-auction is less than three.
4. Sub-clause 'A' of Clause II governs tenders where the estimate is less
than Rs. 5 lakh. Sub-clause 'B' provides for tenders where the
estimate is equal to or more than Rs. 5 lakh but not more than 1
crore. The "Case I" in both sub-clauses provide, inter alia, that if the
number of qualified bidder is one during re-tender, the Departmental
Head Secretary may accept the tender in consultation with the
financial advisor of the department (in case of 'B' , further on
recommendation of the Departmental Tender Committee).
5. It is argued that, in the present case, the request dated November 10,
2020 to all the sixteen bidders other than the petitioner, to upload
'shortfall documents' to validate their technical bids, is sufficient proof
of the deficiency of all such other bidders in their technical bids.
Thus, the petitioner was the only successful bidder at the technical
bid stage. Drawing analogy from the principle laid down in Rule 47C
of the West Bengal Finance Rules, unless a bidder succeeded at the
technical stage, the bidder would not be eligible for the next stage,
that is, the financial bid. As the petitioner was the only successful
bidder at the technical stage, the revised norms for re-tenders dated
February 14, 2017 apply and the Departmental Head Secretary was to
accept the petitioner's tender and issue work order to the petitioner.
Instead, the other sixteen technically ineligible bidders were permitted
afresh to validate their deficient technical bids and four other bidders
were selected from the said pool of bidders, thereby undertaking a de
novo bid invitation process contrary to the revised norms for re-
tender, which vitiates the process, for which this court ought to set it
aside, according to the petitioner.
6. Learned senior counsel for the petitioner cites Monarch Infrastructure
(P) Ltd. v. Commissioner, Ulhasnagar Municipal Corporation and Others
[ (2000) 5 SCC 287 ] where the Supreme Court endorsed the view of
the Bombay High Court that if a term of a tender was deleted after the
players entered into the arena it was like changing the rules of the
game after it had begun and therefore, if the Government or the
Municipal Corporation was free to alter the conditions, fresh process
of tender was the only alternative permissible.
7. The petitioner next relies on a Division Bench judgment of this court,
reported at 2018 SCC OnLine Cal 5612 [The Berhampore Construction
Syndicate Private Limited and Another v. The State of West Bengal and
Others] where the court, while passing an interim order, dealt with
Rule 216 (3) of the PWD Code, which stipulated that even if, after
taking appropriate steps the response to a Re-Tender is less than
three, the tender may be accepted without reference to the Finance
Department. It was observed by the Division Bench that the relevant
provision only requires a reference of the rate to the Finance
Department for concurrence and not the cancellation of the tender
process.
8. The process of inviting further documents to cover up the technical
deficiencies of the other sixteen bids and subsequent approval of four
out of those for selection with the petitioner by draw of lots is
challenged by the petitioner on the above grounds.
9. Learned senior counsel appearing for the respondents submits at the
outset that the petitioner did not participate in the draw of lots
pursuant to the invitation to do so and work order has already been
issued in respect of the re-tender to the successful bidder, thus
rendering the challenge academic.
10. The impugned notice to furnish shortfall documents, dated November
10, 2020, only called for uploading of documents and cannot be the
subject-matter of challenge in a writ petition. Thus, the dispute raised
in the writ petition is premature and stands infructuous upon
subsequent selection of a successful bidder upon drawing lots and
issuance of work order to the successful bidder.
11. Counsel submits that essential conditions of a notice inviting tender
and norms thereof are to be rigidly construed, but
ancillary/subsidiary conditions can be deviated from, without vitiating
the tender process sufficient for it to be cancelled. The norms dated
February 14, 2017, governing re-tenders, provides merely that, in case
there is a single qualified bidder during re-tender, the Departmental
Head Secretary may accept the tender in consultation with the
financial advisor of the department (in case of 'B' , further on
recommendation of the Departmental Tender Committee). The
expression "may" is directory and the tendering authority is not bound
to accept the tender of the single qualified bidder. The said norm is
only a guideline and is the authority is not bound to follow it
meticulously.
12. Learned senior counsel for the respondents relies on Poddar Steel
Corporation v. Ganesh Engineering Works and Others, reported at AIR
1991 SC 1579, also reported at (1991) 3 SCC 273 where the Supreme
Court, in paragraph no. 6 held that as a matter of general proposition
it cannot be held that an authority inviting tenders is bound to give
effect to every term mentioned in the notice in meticulous detail, and
is not entitled to waive even a technical irregularity of little or no
significance. The requirements in a tender notice can be classified into
two categories - those which lay down the essential conditions of
eligibility and the others which are merely ancillary or subsidiary with
the main object to be achieved by the condition. In the first case, it
was held, the authority issuing the tender may be required to enforce
them rigidly. In other cases it must be open to the authority to deviate
from and not to insist upon the strict literal compliance of the
condition in appropriate cases.
13. Thus, the respondents submit, the further invitation to the other
sixteen bidders, the choice of four successful bidders out of them and
subsequent request to participate in the draw of lots for selection were
part of a perfectly valid process, requiring no interference by court;
more so, since the petitioner chose not to participate in the draw of
lots despite being invited to do so.
14. The case hinges on the question as to how far the revised norms
regarding re-tender, dated February 14, 2017, are binding on the
respondent-authorities insofar as the procedure is concerned, in cases
of re-tender where there is only a single qualified bidder.
15. The principle to be followed was laid down by the Supreme Court in
Poddar Steel Corporation (supra), where essential and
ancillary/subsidiary conditions of eligibility were distinguished. The
first category, it was held, has to be enforced rigidly, while in case of
the second, it is open for the authority to deviate from and not to
insist upon the strict literal compliance in appropriate cases.
16. Even in the second case, the scope of deviation was circumscribed by
the rider "in appropriate cases". In the present instance, no exception
to justify deviation has been made out by the respondent-authorities;
rather, the fresh opportunity to the technically ineligible bidders to fill
in the lacunae in their technical bids would novate the process and
consume more time, which might be detrimental keeping in view the
urgent nature of the work to be awarded, being supply of cooked diet
to indoor patients of Durgapur ESI Hospital.
17. In order to derive the nature of the condition-in-question, whether
essential or ancillary, a comprehensive reading of the revised norms
dated February 14, 2017 is necessary. The expression "norms", in its
general sense, connotes rules or expectations. The first paragraph of
the revised norms (Annexure P3 at page 29 of the writ petition)
mentions that, prior to invitation of tender/auction, the eligibility
criteria and other terms and conditions are required to be prepared
carefully by the tender inviting authority. It was mentioned in the next
paragraph, after the sub-clauses of the first paragraph, that in many
cases the provisions and procedures of reviewing the eligibility criteria
and wide publication of the NIT for tender/second call are not being
properly observed by the tender inviting authority and the
departments; also, in some cases, extending the time for submission
of bids after the expiry of normal time is regarded as equivalent to re-
tender or fresh tender. Under such circumstances, in partial
modification of an earlier department memorandum dated December
2, 2012 and related orders, the following provisions regarding
extension of last date of submission of bids and acceptance of bids
when the numbers of qualified bidders during re-tender is less than
three are to be followed, as per the revised norms.
18. Clause II of the norms, as mentioned thereafter, is captioned : "If the
number of qualified bidders during tender/re-tender/re-Auction is
less than 3". In such event, the Tender Inviting Authority shall take a
decision based on the situations given thereunder.
19. Clause A thereunder provides for estimates less than Rs. 5 lakh. Case
I, falling within such clause, stipulates that if the number of qualified
bidder is one during re-tender, the Departmental Head Secretary may
accept the tender in consultation with the FA of the Department.
20. Case I under Clause B, pertaining to estimates equal to or more than
Rs. 5 lakh but not more than Rs. 1 crore, is similar as Case I under
Clause B, adding that the acceptance would additionally be on
recommendation of the Departmental Tender Committee.
21. The expression "may" in the aforementioned two clauses is highlighted
by the respondents to argue that the condition is ancillary/subsidiary
and not essential.
22. The first report relied on by the petitioner, that is, Monarch
Infrastructure (P) Ltd. (supra), the Supreme Court endorsed the view of
the Bombay High Court that if a term of the tender having been
deleted after the players entered into the arena it is like changing the
rules of the game after it had begun, and, therefore, if the Government
or the Municipal Corporation was free to alter the conditions fresh
process of tender was the only alternative permissible.
23. The said ratio, however, is not relevant for the present case. Here, the
rules of the games have not been changed but sought to be
interpreted to be directory, affording scope for the tendering authority
to deviate therefrom.
24. The Berhampore Construction Syndicate (supra), the second report
cited by the petitioner, does not deal with or lay down any proposition
of law with regard to the mandatory/directory nature of provisions
similar to the provisions of the 2017 norms applicable in the present
case. The Division Bench, in the cited report, considered the third
paragraph of Rule 216 (3) of the PWD Code, which provides for cases
where the response to the re-tender is less than three that such
tender may be accepted without reference to the Finance Department,
provided that the rates do not exceed the estimated or the schedule
rates beyond 3% in case of works estimate and reasonable prevailing
market price for goods and service in other cases; otherwise, such
cases should be referred to the Finance Department for decision. It
was held that the last paragraph of the Rule provides a 3% limit or
cap, but it does not provide for the cancellation of the tender process
in the event the rate exceeds 3%, but only requires a reference of the
rate to the Finance Department for concurrence.
25. Thus, in Rule 216 (3) of the PWD Code tenders may be accepted
without reference to the Finance Department if the response to a re-
tender is less than three. In the event the rates exceed the estimated
or scheduled rates beyond 3%, the cases "should be" referred to the
Finance Department for decision. The above language, in no uncertain
terms, indicates that the existing tenders shall be referred only if the
rate exceeds 3%, implying necessarily that the tenders have to be
accepted if the rates are within 3%.
26. The language of the clauses under consideration in the instant tender,
however, differ in language from Rule 216(3) of the PWD Code. The
2017 norms provide that if the number of qualified bidder is one
during re-tender for estimates under Rs. 5 lakh, the Departmental
Head "may" accept the tender in consultation with other
authority/authorities as stipulated. For estimates equal to/more than
Rs. 5 lakh but not more than Rs. 1 crore, an additional rider is
provided that if the bid is within 2% of the estimate the Departmental
Head/Secretary "may" accept the tender in consultation with the FA of
the Department on recommendation of the Departmental Tender
Committee; if it is beyond 2% of the estimate, there will be a reference
to the Finance Department.
27. A subsequent paragraph of the 2017 norms add that certain
procedures are to be observed in all cases, covering Clauses A, B and
C. As per the said paragraph, in cases where the tender is to be
accepted by the Head of the Administrative Department/Secretary, the
process ultimately culminates in the said Head, after necessary
consultation and recommendation, taking the decision and according
approval at his level. Thus, both Clauses A and B, pertaining to
estimates from less than Rs. 5 lakh up to Rs. 1 crore, are covered by
such culmination of the decision-making process. The parties in the
present case have indicated that the estimate, although not
specifically reflected in the notice inviting tender, is less than Rs. 1
crore, thus falling under either Clause A or Clause B. Hence, despite
the expression "may" used in Clauses A and B, relating to acceptance
by the Departmental Head/Secretary on reference/recommendation,
the process of acceptance ultimately ends with the stipulation in the
last few provisions of the 2017 norms that the Head of the
Administrative Department, upon consultation/recommendation, "will
take the decision and accord approval at his level". A composite
reading of the 2017 norms, thus, reveals that the process of
acceptance of the single bid is mandatory, on the necessary conditions
stipulated therein being satisfied, without further invitation of bids.
The initial expression, "may" has to be read in the context of the last
few paragraphs of the revised norms, 2017, to give a mandatory
meaning to it.
28. The initial paragraphs of the 2017 norms are categorical as to the
necessity of review of the "eligibility criteria". The provisions "are to be
followed", stipulates the third paragraph of the norms. The
predominant purpose of the publication of revised norms on February
14, 2017 was to avoid maladies afflicting the system as regards re-
tender and extensions of time for submission of bids. A holistic
reading of the norms leaves no scope of relegating the stipulations
therein to mere administrative advice, which might be directory in
nature. Rather, the object of the revised norms, as mentioned therein,
was to address defects in re-tender processes and to streamline the
same. If the stipulations in the norm are attributed a directory
interpretation, their very efficacy would be lost and there would be no
compulsion on the tender inviting authorities to review the first tender
conditions or streamline the process. Only a mandatory interpretation
can lend teeth to the 2017 norms to address the systemic drawbacks
pertaining to re-tenders, sought to be remedied by the norms. If the
norms were to be optional/directory, a de novo tender process would
entail, wasting much time and resources and rendering the first
tender process entirely futile. On the contrary, a mandatory
enforcement of the revised norms would streamline the process,
reduce expenses of time and resources and would lend more
transparency to re-tender processes.
29. In the present case, the act of the respondents in inviting the ineligible
technical bidders to validate their lacunae, thereby initiating a fresh
tender process, despite the availability of the petitioner as a single
successful bidder, without any reference as envisaged under
categories A and B under Clause II of the norms, was patently
arbitrary and baseless. No person of ordinary prudence can justify
such action on the part of the authorities. Thus, even in the absence
of express proof of mala fides, the arbitrariness implicit in the
impugned action itself vitiates such action.
30. Although the bidder(s) in whose favour work order(s) has/have been
issued, if any, pursuant to the impugned memoranda have not been
impleaded in the present writ petition, since such persons are the
beneficiaries of the illegal action of the respondents and in view of the
respondents having proceeded with the tender process despite having
notice of the writ petition, the said persons are not parties to the writ
and their non-impleadment does not hinder the disposal of the writ
petition in their absence. Such beneficiaries of the illegal acts of the
respondents will be bound by the consequences thereof.
31. In the circumstances, W.P.A. No.10800 of 2020 is allowed. The
impugned Memo No. ESIC/DGP/1607 dated November 10, 2020 and
Memo No. ESIH/DGP/1682 dated November 27, 2020 are cancelled.
Work order(s) and/or other consequence, if any, issued in pursuance
of such Memoranda stand hereby revoked.
32. There will be no order as to costs.
33. Urgent certified website copies of the order, if applied for, be supplied
to the parties upon compliance of all requisite formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!