Citation : 2021 Latest Caselaw 185 Cal/2
Judgement Date : 23 February, 2021
In The High Court at Calcutta
Constitutional Writ Jurisdiction
Original Side
The Hon'ble Justice Sabyasachi Bhattacharyya
WPO No. 437 of 2019
Sova Solar Limited and another
Vs.
The State of West Bengal and others
For the petitioners : Mr. Anirban Ray,
Mr. Arindam Guha
For the State : Mr. Abhratosh Majumdar, Ld. AAG
Mr. Soumitra Mukhrjee,
Mr. Debasish Ghosh
For the respondent
nos. 2 & 3 : Mr. Talay Masood Sidddiqui Hearing concluded on : 04.02.2021 Judgment on : 23.02.2021 The Court:
1. The petitioners have challenged an order dated March 26, 2019,
passed by the West Bengal Industrial Development Corporation
(WBIDC), being respondent no.2 herein, whereby the petitioners'
request for release of a sum of Rs.2.96 crore under the West Bengal
State Support for Industry Scheme, 2008 (WBSSIS - 2008) was turned
down.
2. The petitioners claimed such sum under three different heads,
namely, Fixed Capital Investment Subsidy, Interest Subsidy and
Electricity Duty.
3. Learned counsel for the petitioners argues that the petitioner no.1 is
entitled to all the incentives as claimed under the said Scheme.
Previously, the petitioners had availed of credit facilities from
respondent no.2, the latter having acted as a Financial Institution as
contemplated in Clause 3.2.1 of the said Scheme. Respondent no.2
subsequently restructured the term loan given to the petitioner no.1
upon such request being made by the petitioners. Ultimately, an One-
Time Settlement (OTS) Scheme was offered for a sum of
Rs.10,98,72,913.25p, with Rs.8,48,00,000/- as principal and
Rs.2,50,72,913.25p as interest. Such scheme was accepted by the
petitioners and respondent no.2 issued a 'No Dues' Certificate on
December 1, 2017, upon payment of the total sum to the petitioners,
certifying that payment obligations of the petitioners had been fulfilled
with regard to the term loan.
4. It is submitted by learned counsel for the petitioners that, as per
Clause 16 of the 2008 Scheme, the only pre-condition of disbursal of
the fixed capital investment subsidy and interest subsidy is the
regular payment of the Value Added Tax under the Value Added Tax
Act, 2003 and the Central Sales Tax Act, 1956 without any default
being committed by the assessee. Clause 16.9 of the Scheme
stipulates that, in the event a unit is exempted from paying VAT/CST,
payment towards the subsidy will be made by the respondent no.2 to
the unit by way of account payee cheque. The petitioners claim to fall
under the exempted category. Annexure P-8 at page 146 of the writ
petition is relied on to show that the petitioner no.1 was exempted
from payment of VAT by a notification dated January 7, 2016. The
entire Scheme, according to the petitioners, does not lay down any
provision for withholding payment of the subsidies if the concerned
industrial unit has paid VAT/CST and interest. The fixed capital
investment subsidy and interest subsidy amounts are, thus, payable
to the petitioners in view of certification of payment of interest by the
concerned Financial Institution, being respondent no.2. That apart,
no penal interest was charged, as evidenced from the affidavit affirmed
by respondent nos. 2 and 3 on December 18, 2020. The OTS Scheme
was, thus, entered into upon due consideration of interest being paid
by the petitioners.
5. However, the respondents withheld the payment of such
incentives/subsidies, compelling the petitioners to move a writ
petition, which culminated in an order dated February 18, 2019 for
considering the claim of the petitioners and passing a reasoned order.
6. However, such direction was followed by the order dated March 26,
2019, rejecting the claim of the petitioners illegally and in a vague
manner, which is impugned in the present writ petition.
7. In the impugned order, it was observed that the principal amount was
not paid and that respondent no.2 had sacrificed the same, leading to
a double benefit in favour of the petitioners. However, respondent
nos. 2 and 3 have admitted in their affidavit dated December 18, 2020
that the entire principal amount was required to be paid under the
OTS. After issuing the No Dues Certificate, the respondents could not
allege that the term loan had not been paid in full by the petitioners.
The pre-condition for payment of the fixed capital investment subsidy
under the Scheme is payment of VAT/CST by the concerned unit. The
petitioners have paid such amount till the petitioner no.1 became
exempted from paying the sum, as acknowledged by the respondents.
Disbursement of such subsidy is not dependent on payment of
interest or certification thereof by respondent nos.2 and 3.
8. In the impugned order, the respondents have also alleged that the
OTS was pursuant to waiver of interest, which is contrary to the
records. In view of the interest paid certificate having been issued by
the Financial Institution (here, respondent no.2) with regard to the
interest incurred by the unit, there was no bar in granting interest
subsidy to the petitioners. It is evident from the documents annexed
to the affidavit dated December, 18, 2020 by respondent nos. 2 and 3
that huge interest of approximately Rupees Seven crore had been paid
by the petitioners.
9. The consideration, that the petitioners have already derived benefit on
account of term loan given by respondent no.2, is beyond the scope of
consideration by respondent no.2 as an agent under the Scheme. If
the term loan had been given by any other commercial bank and not
respondent no.2, the consideration by respondent no.2 for the grant of
subsidy would have been strictly limited to the Scheme and the
interest certificates issued by such Financial Institutions. The
petitioners argue that by coincidence, respondent no.2 itself was the
financial institution for the petitioners in the present case, but the
same reasoning should apply.
10. There is no specific allegation in the affidavit-in-opposition affirmed by
respondent nos. 2 and 3 that the petitioners have not complied with
the Scheme. The quantum of subsidy as claimed in paragraph 40 has
also not been denied or disputed in the opposition. Vide letter dated
February 23, 2018, respondent no.2 accepted that the fixed capital
investment subsidy was admitted and also acknowledged that
respondent no.2 received certificates from the Commissioner,
Commercial Taxes certifying that the unit had not defaulted in the
matter of payment of VAT duties. Issuance of interest paid certificate
by respondent no.2 was also admitted in the opposition. Although the
relevant letter was couched in a manner that the term loan was
settled at a principal amount of Rs.8,48,00,000/-, the figure has been
portrayed erroneously as a reduction in the principal amount.
However, from the supplementary affidavit dated December 18, 2020
filed by respondent no.2, it would be evident that the petitioners had
already paid a principal sum of Rs.1,92,00,000/-. Thus, the principal
as well as interest had been paid pursuant to the OTS Scheme.
Learned Counsel for the petitioners argues that it is de hors the law
for the respondents to defend the impugned order on the basis of
documents and correspondences beyond the consideration of
respondent no.2 while passing the impugned order. It is settled law
that an authority cannot supplement its order by relying on
documents or reasoning not reflected from the order itself.
11. After issuance of a No Dues Certificate, the respondents are estopped
from contending that there was waiver of interest. The allegation that
interests were required to be paid in full to the financial institution as
a pre-condition is also not in terms of the Scheme. Such requirement,
at best, was directory and not mandatory. Clause 9 of the Scheme
clearly indicates that any additional interest paid for delayed payment
would not be acceptable for subsidy purpose. Hence, the 2008
Scheme also contemplates payments of interest beyond the due date.
Respondent no.2, it is argued, admitted that it has received
certification of payment of interest on time and that VAT was paid on
time. Thus, till the time VAT was being paid by the petitioners, they
were entitled to reimbursement of the VAT amount.
12. The No Dues Certificate issued by respondent no.2, it is argued,
indicates that nothing was due and payable by the petitioners with
regard to any term loan or interest. Thus, no claim can be made in
that regard against the petitioners. The contention of the petitioners
deriving double interest in the event of subsidy being given is an
afterthought and an arbitrary action to prevent the payment of
subsidy under the 2008 Scheme. The delay on the part of the
respondent in restructuring financial package and in adhering to the
terms thereof also led to the delay in repayment of the entire amount
to the respondents. The contractual relationship and agreement
between respondent no.2 as a lender and the petitioners as borrowers
is of no consequence in considering entitlement of subsidy under the
2008 Scheme.
13. The OTS did not indicate that its acceptance by the petitioners would
disentitle the petitioners to subsidy under the 2008 Scheme. Since
such a condition is not mentioned in the Offer Letter of the OTS or the
OTS No Dues Certificate, respondent no.2 is estopped from
contending to the contrary. The relevant package provides that
interest would be aligned with the State Bank of India rates, thus
precluding respondent no.2 from claiming interest at a higher rate
than that, leading to a conclusion that there has been a waiver of
Rs.2.5 crore as interest. The restructuring letter at page 181 of the
writ petition shows an agreement that the interest rate would be one
per cent above the SBI base rate. However, the interest calculated for
the purpose of concluding that there was a waiver, was on a much
higher rate.
14. That apart, the petitioners argue, the respondents' action was
arbitrary and an afterthought. The State ought to act in a manner so
as to permit industry and to adhere to its promise to investors. There
is no dispute that the petitioners, as investors, paid huge amounts of
money to respondent no.2. The respondents cannot take advantage of
their own wrong in refusing to pay the dues under the 2008 Scheme.
The State, being the contractual party to such incentive Scheme, has
not disputed the payments in accordance with the terms of the
Scheme. The payment of incentives under the Scheme creates a
contractual liability, as indicated in State of West Bengal & Ors. vs.
Emami Biotech Ltd. & Ors., reported at 2014 SCC OnLine Cal 5978. A
Division Bench of this Court held in the said case that, where there
has been clear admission by the principal, its agent cannot
supplement the stand of the principal.
15. Since the principles of the Code of Civil Procedure are applicable to
the writ jurisdiction of this Court, the provisions of Order VIII Rule 5
of the Code ought to be followed, which stipulate that non-denial by
the respondents of the petitioners' averments tantamount to
admission. Thus, the prayers made in the writ petition ought to be
allowed. Re-sending the matter back to the respondents would serve
no purpose, it is argued, since the respondents have made their stand
clear by not making payment of due subsidies to the petitioners under
the Scheme, by reason of frivolous pleas.
16. Learned counsel for the State-respondent submits in reply that the
petitioners could not repay the loan taken from respondent no.2 as
per schedule and applied for restructuring of the loan. The petitioners
also committed that the subsidy may be adjusted against the
outstanding dues. The petitioners further expressed its willingness to
pledge ten percent of its shares. Thereafter, an OTS was arrived at
between the parties, the terms of which have not been disclosed in the
writ petition.
17. Learned counsel further submits that the accumulated interest on the
date of approval of OTS was Rs.9,22,60,868/-, which was reduced to
Rs.5,57,17,588/- on application of the SBI rate. Consequently, the
principal required to be repaid was Rs.8.48 crore and interest was
determined at Rs.2,50,72,913.25p. Thus, the OTS reduced the
interest liability of the petitioner by Rs.67,187,754.75p. The loan for
capital investment was not repaid within due dates, causing loss to
the coffers of respondent no.2, a wholly-owned undertaking of the
State.
18. Learned counsel for the State-respondent argues that the petitioners
are not entitled to interest subsidy. On a conjoint reading of Clauses
9.2.1 and 9.2.2 of the WBSSIS-2008 Scheme, it is argued that the
certificate from the financial institution is a necessity for claiming
interest subsidy. However, no such certificate was issued in favour of
the petitioner. The petitioner did not make out any case that it paid
instalments on due dates as per terms of the loan.
19. It is argued by the respondents that the petitioners obtained the best
possible bargain through the OTS and cannot claim further equitable
relief of capital investment subsidy, making a further dent in the
public exchequer. The petitioners occasioned financial loss to
respondent no.2 and are not entitled to fixed capital investment
subsidy. It is argued that the capital investment, in the present case,
was inextricably connected with the loan granted by respondent no.2,
since the investment could not have been made without loan being
sanctioned by respondent no.2.
20. Thus, it is argued that the writ petition ought to be dismissed.
21. At the outset, it has to be clarified that respondent no.2 cannot mix
up its dual capacity, as a "Financial Institution" under Clause 3.11 of
the 2008 Scheme and as "Authorized Agent" under Clause 3.4, which
defines the WBIDC as an agent specially authorized by the State
Government for operation of the Scheme.
22. It is to be noted that all the categories of subsidies/incentives claimed
by the petitioners are governed by Clause 16 of the Scheme, which
requires clearance of payment of VAT dues.
23. The claims of the petitioners can be divided into three broad heads -
Interest Subsidy, Fixed Capital Investment Subsidy and Waiver of
Electricity Duty.
24. As far as Interest Subsidy is concerned, Clause 9.2.2 specifically
stipulates that such subsidy will be payable annually, subject to
submission of a statement/certificate by the Financial Institution to
prove that the unit paid the interest in full to the Financial Institution
within the due dates. Clause 9.2.4, relied on by the petitioners, is
irrelevant for the present purpose, since the expression "delayed
payment" used therein pertains to any additional interest which may
be charged on such payment of the principal amount, which will not
come under the purview of Interest Subsidy. No question of additional
interest arises in the present case.
25. Although the petitioners obtained sanction in respect of the three
heads of subsidy from respondent no.2, such sanction was subject to
satisfaction of the norms and guidelines stipulated in the scheme and
extant legal provisions. Thus, mere sanction cannot be construed to
be final, binding the respondent no.2 to grant all the incentives to the
petitioners.
26. As far as Interest Subsidy is concerned, it is evident from the loan
related information issued by respondent no.2 in respect of the
petitioner no.1, annexed at page 167 of the writ petition, that the
petitioner no.1 last paid interest up to August 31, 2011. There is
nothing on record to show that any payment of interest was made by
the petitioners thereafter.
27. The attempt of the petitioners to intertwine the OTS Scheme with the
payment of interest, as contemplated in the 2008 Scheme, cannot be
accepted. Despite the petitioners having cleared all dues in terms of
the OTS between the parties, such clearance does not absolve the
petitioners from the liability under Clause 9.2.2 of the Scheme. Since
the said Clause envisages payment of interest subsidy annually,
subject to submission of statement/certificate by the Financial
Institution to prove that the unit paid the interest in full within the
due dates, the question of such Clause being attracted does not arise
after August 31, 2011 up to which interest was being paid annually by
the petitioners. For the subsequent period, the petitioners were
defaulters in payment of annual interest. Although there was full and
final settlement of all components of dues by the OTS, such
development could not obliterate the past defaults of the petitioners,
to entitle the petitioners to the annual payment of interest
retrospectively, after August 31, 2011.
28. However, as far as Interest Subsidy up to August, 2011 is concerned,
there was no valid ground for the respondents to refuse such subsidy
to the petitioners, in view of the petitioners being eligible on all other
yardsticks stipulated in the 2008 Scheme.
29. As far as Fixed Capital Investment Subsidy (FCIS) is concerned, the
plinth of the arguments advanced by the respondents is that such
subsidy was tied up with the overdue, if any, to the respondent no.2.
30. Clause (i) of the Sanction Letter dated July 31, 2014 issued by
respondent no.2 (Annexure P-6 at page 134A of the writ petition)
stipulates that, at the time of disbursement of the subsidy, overdue
amount to WBIDC, if any, will be adjusted. The said sanction pertains
only to the FCIS and not to the Interest Subsidy or Waiver of
Electricity Duty. However, although the petitioners had been
defaulters prior to the OTS being approved, upon the petitioners
having cleared off all dues in terms of the OTS in full and final
settlement of the claims of respondent no.2 in the latter's capacity as
a Financial Institution, there was no overdue amount to respondent
no.2 at the time of disbursement of the subsidy. As such, Clause (i) of
the sanction dated July 31, 2014 is rendered academic and cannot be
a bar to release such subsidy in favour of the petitioners.
31. Hence, in view of the petitioners having cleared the other hurdles in
terms of the 2008 Scheme, including the payment of VAT, they were
entitled to FCIS in full at the juncture of disbursement of the subsidy.
32. As far as Waiver of Electricity Duty is concerned, the same is governed
by Clause 9.3 of the 2008 Scheme, which contemplates that an
eligible unit for the approved project will be entitled to Waiver of
Electricity Duty on the electricity consumed for its production activity
for a period of five years from the date of commencement of the
commercial production, subject only to the unit having obtained all
kinds of statutory clearance.
33. In the impugned order of refusal of subsidy dated March 26, 2019,
there is no mention of any default on the part of the petitioners in
respect of the statutory clearance of dues, nor any dispute regarding
the quantum of electricity consumed for the production activity of
petitioner no.1, as envisaged in Clause 9.3 of the Scheme.
34. The impugned order cites primarily the principle of double benefit for
refusal of the subsidies to the petitioners. Such ground is de hors the
2008 Scheme itself, which clearly distinguishes between the identities
of respondent no.2 (WBIDC), in its dual capacities as Authorized
Agent of the State Government and as a Financial Institution, defined
respectively in Clauses 3.4 and 3.11 of the Scheme. Thus, it does not
lie in the mouth of respondent no.2 to plead double benefit as a
ground of refusal of subsidy, since, upon full and final settlement of
all claims between the petitioners and respondent no.2 (acting as a
Financial Institution), there could not arise any question of overdue or
previous waiver of interest by the respondent no.2. In the event the
Financial Institution granting loan of the petitioners was some other
entity than respondent no.2, such argument would be meaningless. In
view of segregation of the two capacities of respondent no.2 in the
2008 Scheme itself, the same logic applies to respondent no.2, in its
capacity of a Financial Institution, as well. Thus, double benefit or
waiver of interest could not be a ground for refusal of subsidy by
respondent no.2 in its capacity as an Authorized Agent of the State
Government for operation of the Scheme. Such grounds are alien to
the Scheme itself.
35. In view of the above discussions, WPO No.437 of 2019 is disposed of
by holding that the petitioners are entitled to Interest subsidy under
the WBSSIS-2008 up to August 31, 2011, to Fixed Capital Investment
Subsidy in full, as claimed by the petitioners, and to total Waiver of
Electricity Duty, as stipulated in Clause 9.3 of the WBSSIS-2008.
36. The respondents shall disburse the amounts due to the petitioners by
way of such subsidies at the earliest, latest by 30 days from date.
37. There will be no order as to costs.
38. Urgent certified copies of this order shall be supplied to the parties
applying for the same, upon due compliance of all requisite
formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!