Citation : 2021 Latest Caselaw 126 Cal/2
Judgement Date : 9 February, 2021
1
A.P. No. 308 of 2020
IN THE HIGH COURT AT CALCUTTA
Ordinary Original Civil Jurisdiction
Original Side
Cuprum Bagrodia Limited
v.
Gainwell Commosales Private Limited
For the petitioner : Mr. Ranjan Bachawat, Sr. Advocate
Mr. Debnath Ghosh, Advocate
For the Respondent : Mr. S.N. Mitra, Sr. Advocate
Mr. Anirban Ray, Advocate Mr. Shounak Mitra, Advocate Mr. Rishav Dutt, Advocate
Hearing concluded on : January 19, 2021 Judgment on : February 9, 2021
DEBANGSU BASAK, J. :-
1. The petitioner has sought interim protection under section 9 of the
Arbitration and Conciliation Act, 1996 by way of the present petition.
2. Learned Senior advocate appearing for the petitioner has submitted
that, the petitioner carries on business of coal mining. The petitioner has
been using the High Wall Mining System for extracting coal. In such
system, a specialised machinery is utilised. The only manufacturer of such
machinery in India is the respondent. The petitioner had placed an order
for delivery of High Wall Miner, model HW 300 on the respondent to be
delivered by August 2018. The petitioner had also placed a separate order
for the Low Seam Cutter Module CM210 on the respondent to be used
together with the High Wall Miner, model HW 300.
3. Learned Senior Advocate appearing for the petitioner has submitted
that, the parties have entered into a contract for supply of High Wall
mining system on May 10, 2019. He has referred to the various terms and
conditions of such contract. He has submitted that, such contract has
stipulated the terms of payment. He has drawn the attention of the court
to the terms of payments as specified in the contract. He has submitted
that, the respondent was supposed to procure vital parts of the machinery
from Caterpillar, the USA manufacturer. He has submitted that, the
petitioner has always been and still is ready and willing to pay for the
machinery. He has referred to the clause of the contract which has dealt
with the title, property and risk. He has referred to Clause 7 of the
contract which has stipulated the delivery date, transportation, insurance,
assembly and testing of the machinery. He has submitted that, under
clause 8 of the contract, the contract cannot be cancelled after execution
of the same.
4. Learned Senior advocate appearing for the petitioner has submitted
that, the contract for supply of the machinery is by its nature non-
terminable. The parties have not terminated the contract. He has
submitted that, the petitioner cannot purchase such machinery from any
other manufacturer in India. The respondent is the only manufacturer.
5. Learned Senior Advocate appearing for the petitioner has referred to
the scope of supply and pricing under the contract. He has submitted
that, the machinery that the respondent had agreed to supply, has a
particular number being GHWM 00186.
6. Learned Senior Advocate appearing for the petitioner has submitted
that, the respondent had part performed the contract. The petitioner had
paid such portion of the total contracted value for the machinery as was
required under the contract to be paid. He has submitted that, the
petitioner inspected the machinery that the respondent was
manufacturing for the petitioner. On such inspection, the petitioner had
found that, the work for the machinery not to be up to the mark. He has
submitted that, the petitioner became aware that the respondent was
trying to enter into the business arena of the petitioner and was trying to
utilise the machinery that was meant for the petitioner, for execution of a
contract that the respondent entered into with the coal companies.
According to him, the respondent had diverted the machinery belonging to
the petitioner for the use of the respondent.
7. Learned Senior Advocate appearing for the petitioner has submitted
that, the respondent has taken different stand at different points of time
with regard to the manufacture and delivery of the machinery. He has
referred to the orders passed from time to time by the court. He has
submitted that the Receiver appointed by the Court could not find the
machinery. He has referred to the Receiver's report. He has submitted
that, the Receiver recorded that, the machinery meant for the petitioner
was not found at the manufacturing area of the respondent. He has drawn
the attention of the Court to the purchase orders for purchasing parts of
the machinery that the respondent placed before the Receiver. He has
submitted that the purchase orders which the respondent claims to have
placed for the purpose of buying different components of the machinery to
be manufactured and supplied to the petitioner, were not for the
machinery of the petitioner. Such orders were for the next machinery that
the petitioner has been assembling at its works. The respondent had
manufactured the machinery having number GHWM 00186. The part of
the machinery that the Receiver has found in his two visits are parts of the
machinery bearing number GHWM 00187.
8. Learned Senior Advocate appearing for the petitioner has submitted
that, the respondent is now manufacturing a machinery with the serial
number 187. The machinery with the serial number 186 belongs to the
petitioner. The respondent had manufactured such machinery bearing
serial No. 186 and is now wrongfully and illegally utilising such machinery
for its own use. The court should take appropriate measures so as to
make the machinery bearing serial number 186 available to the petitioner.
9. The respondent has opposed the application. Learned Senior
Advocate appearing for the respondent has submitted that, the parties had
entered into a contract on May 10, 2019. He has referred to various
provisions of the contract between the parties. He has submitted that, the
contract contains provisions for delay. The contract has provisions for the
time schedule for delivery. He has referred to paragraph 10 of the petition
and submitted that, the petitioner had delayed in making the stage wise
payments. Referring to clause 7.1 of the contract, learned senior advocate
appearing for the respondent has submitted that, in case of delay of
receipt of stage payments, the time for delivery will get extended. He has
referred to an electronic mail dated January 10, 2020 and has submitted
that, the time to make delivery stood extended from February 5, 2020 to
April 30, 2020.
10. Learned senior advocate appearing for the respondent has referred to
the averments made in the petition as well as the correspondence
exchanged between the parties. He has also referred to the affidavits used
by the parties. He has submitted that, there was delay in payment on the
part of the petitioner which caused the delay in delivery. Subsequently,
the petitioner had expressed a desire to procure a different machinery. The
parties had negotiated on such machinery. Ultimately, the petitioner had
gone back to the original specifications. The petitioner had consumed time
in negotiating with the respondent on the kind of machinery that it wants
to purchase. In fact, there has been no delay on the part of the
respondent. The petitioner had wanted changes in the specifications of the
original machine. Ultimately, the parties had agreed to a delivery schedule
and progress of work on September 7, 2020. The petitioner had moved the
court on October 14, 2020. He has submitted that, the delay if any, in
making and delivering the machinery, cannot be attributed to the
respondent.
11. Referring to clause 6 of the contract, learned senior advocate
appearing for the respondent has submitted that, the title to the
machinery has been agreed to pass to the petitioner on delivery. Since the
petitioner has not paid the entire agreed amount and the manufacture of
machine is yet to be completed, the title to the machinery has not passed
to the petitioner. The claim of the petitioner is at best on account of loss
and damages for which no mandatory order of injunction as prayed for
should be passed. He has referred to and relied upon Sections 19 and 21
of the Sale of Goods Act, 1930. In support of his contentions, he has relied
upon 1995 SCC online Bombay 43 (The Commissioner of Sales Tax,
Maharashtra State, Bombay v. M/s. Mazgaon Dock Ltd.) and 1975
Volume 3 SCC 424 (T.V. Sundram Iyengar & Sons v. State of
Madras). According to him, the parties had set the time to make the
delivery at large. He has referred to Section 55 of the Indian Contract Act,
1872 and 1979 Volume 2 SCC 70 (Hind Construction Contractors v.
State of Maharashtra).
12. Learned senior advocate appearing for the respondent has submitted
that, the petitioner is guilty of suppression of facts which are material for
the purpose of adjudication of the disputes between the parties. He has
referred to the averments made by the respondent in the affidavit in
opposition and particularly to paragraph 3 thereof. He has submitted that,
the petitioner is not entitled to any interim protection.
13. The petitioner had entered into a contract with the respondent for
purchase of a High Wall Miner, Model HW 300, Low Seam Cutter Module
CM210 and one High Wall Mining system including a Cutter Module to be
manufactured under licence from Caterpillar, USA along with spare parts
and services. Apparently, the respondent is the sole manufacturer of such
machines under licence from Caterpillar, USA. The parties have entered
into a contract dated May 10, 2019 for such purpose. Such contract has
an arbitration clause. The Court has been informed in the course of
hearing of the petition that the petitioner made a reference of the disputes
and differences to arbitration in terms of the arbitration agreement.
14. By and under the contract dated May 10, 2019, the petitioner had
agreed to pay a sum of Rs. 60,12,93,000/- in staggered manner for the
machinery. A sum of Rs. 6 crores had been agreed to be paid along with
the execution of the contract. A sum of Rs. 6 crores had been agreed to be
paid within 30 days from the date of signing of the contract again receipt
of initial component package and a sum of Rs. 12 crores within 90 days
from first payment against receipt of major components. The payment
clause in the contract dated May 10, 2019 had provided for the balance
payments are to be made in a staggered manner.
15. The dates of payments which the petitioner has disclosed in
paragraph 10 of the petition states that, the first payment had been made
on May 15, 2019 for a sum of Rs. 6 crores. The next payment made by the
petitioner had been on July 26, 2019 for a sum of Rs. 6 crores and the
third payment had been made on January 15, 2020 for the sum of Rs. 12
crores. The schedule of payment as has been disclosed by the petitioner in
its petition demonstrates that the petitioner did not pay in accordance
with the agreed payment schedule under the contract. Whether the
petitioner had been justified in doing so and the ultimate consequences
thereof should best to be decided in arbitration.
16. The contract dated May 10, 2019 had provided that the delivery of
the machinery will be 8 months and 10 days from the date of receipt of 10
per cent advance payment on ex-work basis. The payment terms has also
stipulated that, the receipt of subsequent payments as per the payment
terms are imperative to maintain the delivery schedule. According to the
petitioner, it had made production linked payment to the respondent.
According to the respondent, the petitioner had failed to adhere to the
agreed payment, under the contract dated May 10, 2019.
17. The parties had held joint inspection of the machinery on July 17,
2019 and on November 12, 2019 to ascertain the progress of the
manufacture. By an electronic mail dated November 20, 2019, the
petitioner had called upon the respondent to state the firm delivery
schedule of the machinery. According to the petitioner, the respondent
had to inform the petitioner as to the firm delivery date by November 11,
2019. By an electronic mail dated November 23, 2019, the respondent had
informed the petitioner that the machinery should be ready for ex-work
Asansol by the last week of April, 2020. The respondent had stated in
such e-mail that such date was the firm schedule. The respondent had
called upon the petitioner to release balance payments at the earliest.
18. It appears from the materials made available on record, that, on
January 2, 2020 a meeting had been held between the parties where, the
team of the banker of the petitioner was also present. The respondent had
confirmed that the machinery would be delivered by April 30, 2020 if the
third advance payment of Rs. 12 crores was made on January 15, 2020.
The petitioner had paid the sum of Rs. 12 crores on January 15, 2020 as
has been noted above.
19. According to the petitioner, the respondent had failed to deliver the
machinery within the stipulated date of April 30, 2020. The petitioner had
by the e-mail dated May 8, 2020 asked the respondent for the schedule of
the pre-despatch testing of the machinery to enable the petitioner to send
its representatives for inspection.
20. The country as also the whole world has been suffering from the
ongoing pandemic. The Central Government as well as the State
Government had declared lockdown. By an electronic mail dated May 9,
2020, the respondent had informed the petitioner that in view of the
Covid-19 pandemic, the operations at the factory and plant of the
respondent remained suspended. In response to the electronic mail dated
May 9, 2020, the respondent through its electronic mail dated May 15,
2020 had informed the petitioner that there has been no change in the
lock down notification.
21. According to the petitioner, it had sent reminders on June 16, 2020
and July 31, 2020 with regard to pre-despatch inspection. According to
the petitioner, the respondent has not replied thereto. According to the
respondent, the petitioner had modified its order consequent upon which,
the respondent could not manufacture and deliver the machinery by April
30, 2020. The respondent has also taken the plea of the pandemic and
the declaration of the lockdown for inability of delivery the machinery
within April 30, 2020.
22. The documents disclosed by the parties suggest that, the parties had
agreed to a delivery of the machinery on April 30, 2020 subject to the
petitioner making the payments as agreed in the contract. The documents
in this proceeding as has been disclosed and as annexed to the several
affidavits that they have used suggest that, the petitioner had made three
payments and that those payments were not in accordance with the time
prescribed under the contract. There are correspondence on record
namely, electronic mail dated August 01, 2020, August 15, 2020 and
August 25, 2020 which have suggested that, the parties were negotiating a
different specification of the machinery from what was earlier agreed to.
The parties have relied a minutes of the meeting dated August 10, 2020.
The minutes of the meeting dated August 10, 2020 apart from the other
machinery that the respondent was to supply to the petitioner, has dealt
with the machinery in-question. The minutes has recorded that there
would be cost escalation and that the issues with regard to the cost
escalation and the delivery would be discussed finally on mutually agreed
terms. By the electronic mail dated September 07, 2020, the petitioner
had called upon the respondent to provide the delivery schedule with
month wise progress so that the same can be monitored by the customer
of the petitioner and also the banker of the petitioner. The petitioner had
sent a reminder electronic mail on September 15, 2020.
23. By an electronic mail dated September 15, 2020, the respondent has
placed on record the mutually agreed points, inter alia, to the effect that
the cutter module would be GCM 235 in place of GLM 210. The
respondent has also informed the petitioner that there would be
substantial cost escalation because of the changes and that cost
escalation for changing cutter module GLM 210 to GCM 235 should be
paid by the petitioner.
24. The parties had exchanged further electronic mails. By the
electronic mail dated October 01, 2020 the petitioner has stated that it did
not want any change in the scope of supply. The petitioner had specified
that the equipment should be supplied as per the contract.
25. The contention of the respondent that, the delay in delivery of the
machinery that has been occasioned, is not attributable to the respondent,
prima facie appears to be of some substance. The petitioner did not make
the payments strictly in accordance with the terms of the contract. The
petitioner is yet to pay the entirety of the amount agreed. The parties had
negotiated a modification of the specifications of the machinery.
Ultimately, by the electronic mail dated October 1, 2020, the petitioner
had stated that, it did not want any change in the scope of supply. There
has been a declaration of lockdown during the ongoing pandemic.
Therefore, up to the period of October 1, 2020, prima facie, it appears
that, the respondent cannot be faulted for not having the machinery in a
deliverable state. The parties had been negotiating the specifications till
October 2020. Therefore, it would be a naive to except that the machinery
would be made ready by the respondent immediately after October 1, 2020
given the nature of the machinery. The petitioner had approached Court
on October 14, 2020 when the first order was passed.
26. By interim orders, the Court had appointed a Receiver over the
machinery. According to the petitioner, the respondent had manufactured
the machinery meant for the petitioner and had sent that machinery to a
different place. In fact the respondent had been using such machinery or
at least was contemplating user of such machinery. According to the
respondent, it could not manufacture the machinery as ordered by the
petitioner in view of the pandemic, non payment and negotiations with
regard to specifications contending till October 1, 2020.
27. The Receiver appointed by the Court had visited the workshop of the
respondent twice. The petitioner has not produced any material to
conclusively establish that, the machinery lying at the workshop of the
respondent is not that of the petitioner and that, the respondent had
manufactured another machinery and had taken the same away. It is not
for the Court to fish out evidence for any of the parties. The onus is on the
petitioner to establish by cogent evidence that, the machinery lying on the
floor of the respondent is not that what has been made for the petitioner
under the contract but some other machinery. The respondent has also
failed to establish the whereabouts of the machinery that the petitioner
claims that the respondent had manufactured for the petitioner.
28. There is one more aspect to the matter. Admittedly, the petitioner
has not paid the entire amount for the machinery. Out of sum in excess of
60 crores required to be paid under the contract, the petitioner has paid a
sum of Rs. 20 crores.
29. Section 19 of the Sale of Goods Act, 1930 has stipulated that,
property in the goods passes when the same has been intended to pass by
the parties. In the facts of the present case, Clause 6 of the contract has
specified that, the risk and title to the machinery shall pass to the
petitioner on delivery. Section 21 of the Sale of Goods Act, 1930 has
specified that, where there is a contract for the sale of specific goods and
the seller is bound to do something to the goods for the purpose of putting
them into a deliverable state, the property does not pass until such thing
is done and the buyer has noticed thereof. In the facts of the present case,
the contract has obligated the respondent as the seller to manufacture the
machinery in accordance with the specification of the petitioner as the
buyer and make the machinery at a deliverable state. Admittedly, the
respondent is yet to make the machinery at a deliverable state. Therefore,
prima facie, it appears that, the petitioner not having paid the entirety for
the machinery and the machinery not being in deliverable state, it cannot
be said that, the title to the machinery has passed on to the petitioner.
Therefore, at this stage, the question of passing a mandatory order
directing the respondent to deliver the machinery to the petitioner does
not arise. The machinery, appears on the basis of the materials made
available on record not to be in a deliverable state. The petitioner has
failed to establish that the other machinery with the petitioner is speaking
of, is actually the machinery which is meant for the petitioner.
30. The respondent has referred to and relied upon Section 55 of the
Indian Contract Act, 1872. In the facts and circumstances of the instant
case the issue as to whether, the respondent is entitled to declare a
portion of the contract void or the issue as to whether there was delay by
reason of failure of the petitioner in not adhering to the terms of the
contract or the issue as to what would be the respective rights and
obligations of the parties under the contract by reason of the alleged non
performance by the respondent should best be decided in the arbitration.
31. T.V. Sundram Iyengar & Sons (supra) has considered the issue as
to whether the supply for consideration of bus bodies constructed and
fitted to chassis provided by the customer amounts to sale chargeable to
sales tax or not. It has answered such issue by holding that the supply of
the bus bodies after fitting them to the chassis supplied by the customer
amounts to sale of goods. In M/s. Mazgaon Dock Ltd. (supra), the Court
has considered the issue whether the transaction of building and
supplying a motor launch is a works contract and not a sale. It has
answered such issue by holding that the contract was for sale of the
complete motor launch.
32. The Supreme Court in Hind Construction Contractors (supra) has
held that, whether time is of the essence of the contract, is a question of
intentions of the parties to be gathered from the terms of the contract.
Applying such ratio to the facts of the present case, at this interim stage it
would not be appropriate to garner the intentions of the parties and come
to a definite finding without affording the parties an opportunity to lead
evidence in the arbitration.
33. In view of the discussions above, the application of the petitioner
fails. AP No. 308 of 2020 is dismissed. The Receiver appointed stands
discharged without the requirement to submit accounts.
[DEBANGSU BASAK, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!