Citation : 2021 Latest Caselaw 6553 Cal
Judgement Date : 22 December, 2021
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION
APELLATE SIDE
The Hon'ble JUSTICE SUVRA GHOSH
W.P.A. 8163 of 2016
Ajet Baidya and Others
Vs.
State of West Bengal and Others.
For the Petitioner: Mr. Siddhartha Ruj, Adv.,
For the State: Mr. Lalit Mohan Mahata, Adv.
Mr. Prasanta Behari Mahata, Adv.,
Hearing concluded on: 09.12.2021
Date : 22.12.2021
SUVRA GHOSH, J. :-
1. The prayers of the writ petitioners are as follows:
"a) A declaration be made declaring the Land Acquisition Case being No. L.A.
4/34 of 1999-2000 stood lapse and the respondent authorities be directed
to put petitioners in possession to their respective plot of land forthwith.
b) In the alternative a Writ in the nature of Mandamus do issue commanding
the respondents their men, agents, servants and/or assigns particularly
respondent No. 2 to acquire the petitioner Nos. 1 to 4's parcels of land
measuring each 19 decimals pertaining to Plot/Dag No. 911/1364, 21
decimals of land of the petitioner No. 5 pertaining to Plot/Dag No. 1364 and
10 decimals of land of the predecessor-in-interest of petitioner No. 6
pertaining to Plot/Dag No. 911/1371 lying at Mouza: Gangapur,J.L. No. 35
in the District of South 24 Parganas and to pay the land acquisition
compensation at the present market value of the land in that area in terms
of the present land acquisition act and complete the acquisition proceeding
within 6 (six) weeks from the date of the order to be made herein.
c) A Writ in the nature of Mandamus do issue commanding the respondents
their men, agents, servants and/or assigns particularly respondent No. 2 to
make the payment of compensation to the petitioners within the time
stipulated by this Hon'ble Court."
2. The writ petition was dismissed by an order dated 4th July, 2016 and
appeal against the said order was disposed of by Hon'ble Division Bench
of this Court by an order dated 2nd November, 2017 in M.A.T. 1368 of
2016, granting liberty to the petitioners to pursue the remedy available
under section 18 of the Land Acquisition Act, 1894
3. Review of the said order was sought by the petitioners and by an order
dated 25th September, 2019 in R.V.W. 272 of 2017, the Hon'ble Division
Bench recalled the order dated 2nd November, 2017 in M.A.T. 1368 of 2016
by allowing the review application and remanded the writ petition to this
court for fresh hearing.
4. It is submitted on behalf of the writ petitioners' that petitioners no. 1 to 5
and predecessor-in-interest of petitioner no. 6 acquired right, title and
interest over the plot of land in question by virtue of rayati settlement
deeds executed by the Government of West Bengal in their favour on 25th
April, 1984 and were in possession of the same. On demise of the father of
the sixth petitioner, this petitioner stepped into his shoes along with his
three sisters Kaharjan Bibi, Alekjan Bibi and Malekjan Bibi.
5. It is further contended that part of the petitioners' land was acquired in
Land Acquisition Case No. 4/34 of 1999-2000 for the purpose of
construction of leather complex though possession of the land was taken in
1993. No notice under section 9(3A) of the Land Acquisition (West Bengal
Amendment) Act, 1997 or section 12(2) of the Land Acquisition Act 1894
was served upon the petitioners and no compensation was also paid to
them. As such, the Land Acquisition Case being L.A. 4/34 of 1999-2000
stood lapsed after expiry of the statutory period in terms of section 11A of
the Act of 1894 and the petitioners are entitled to compensation at the
present market value of the land after completion of acquisition
proceedings.
6. A report in the form of an affidavit was submitted by respondent nos. 1, 2 &
3 which demonstrates that Land Acquisition Case being L.A. II/1 of 1993-
94 was initiated for the purpose of establishment of Calcutta Leather
Complex and upon issuance of notice of requisition under section 3(1) of
the West Bengal Land (Requisition and Acquisition) Act, 1948 on 17-11-
1993, possession of the land was taken and made over to the requiring
body on 26-11-1993 but the said proceedings could not be completed in
view of a writ petition filed by one Ziad Ali Molla. Subsequently Land
Acquisition Case No. 4/34 of 1999-2000 was initiated and notice under
section 9(3A) of the Land Acquisition (West Bengal Amendment Act), 1997
was issued on 12-08-1999 and enquiries conducted under the Act.
Objection was raised in respect of the award by some persons as a result of
which the compensation amount with regard to such persons was not paid
and was deposited in the court of the learned Land Acquisition Judge,
Alipore. The petitioners failed to produce documents in respect of their title
and possession in respect of the land and objection was received from the
petitioners after the compensation amount was paid/deposited. The willing
land losers were paid compensation in January, 2001 and compensation
with regard to the other awardees was deposited in court on 10th March,
2006. As such, the writ petition is not maintainable and is liable to be
dismissed.
7. It appears from the letter issued by the Block Land & Land Reforms Officer,
Bhangore - I, South 24 Parganas to the Additional Land Acquisition
Officer, South 24 Parganas on 2nd September, 2013 (annexure R2 to the
report filed by respondent nos. 1, 2 and 3) that the names of the petitioners
were recorded as patta holders in respect of plots in question. It is not in
dispute that possession of the plots was taken in 1993 after initiation of
acquisition proceedings and certificate of possession was issued in favour
of the requiring body on 26th November, 1993 in L.A. Case No. II/1 of 93-
94. A copy of certificate of the possession demonstrates that the plots
occupied by the petitioners were included therein. Admittedly, L.A. Case
No. II/1 of 93-94 could not be completed. Subsequently, L.A. Case No.
4/34 of 1999-2000 was initiated in respect of the same plots.
8. The petitioners claim that no notice was served upon them either under
section 12(2) of the Land Acquisition Act, 1894 or section 9(3A) of the Land
Acquisition (West Bengal Amendment Act), 1997 and consequentially no
compensation was paid to them. The petitioners submitted several
representations before the concerned authority claiming compensation but
such representations fell on deaf ears.
9. It appears that notices under section 12(2) of the Act of 1894 and under
section 9(3A) of the 1997 Amendment Act were issued by the authority in
the year 1999 and 2000 which cover the property of the petitioners but it
cannot be ascertained from the said notices whether they were actually
served upon the petitioners. A notice under section 4 of the West Bengal
Land (Requisition and Acquisition) Act, 1948 in the form of gazette
notification dated 31st March, 1997 with regard to the plots in question
was also issued.
10. The petitioners say that as no award was published despite taking
possession of the land, the acquisition proceedings stood lapsed under
section 11A of the Land Acquisition Act, 1894. But documents reveal that
notice of acquisition as well as notice of award was published by the State
Authorities and compensation has been paid to most of the awardees. The
respondents submit that the petitioners failed to produce any document in
support of their title and possession in respect of the land and raised
objection against the proceedings only after the proceedings was concluded
and compensation was paid/deposited. It is also submitted that
compensation in respect of which dispute arose was deposited in court on
10th March, 2006.
11. Therefore it is crystal clear that L.A. proceedings being 4/34 of 1999-2000
was concluded and compensation disbursed within the statutory period of
time. Admittedly no compensation was granted to the petitioners. In the
premises, the prayer of the petitioners for a declaration that the acquisition
proceeding stood lapsed cannot be acceded to.
12. The petitioners have, in the alternative, prayed for compensation at the
present market value of land in terms of the present Act of 2013.
13. Section 24(1a) of The Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act, 2013 states that in
a proceeding initiated under the Land Acquisition Act, 1894 when no
award under section 11 of the Act has been made, then all provisions of
the 2013 Act relating to the determination of compensation shall apply.
Section 24(2) states that in case of such land acquisition proceedings
initiated under the 1894 Act, when the award under section 11 has been
made five years or more prior to the commencement of this Act but
physical possession of the land has not been taken or the compensation
has not been paid, the said proceedings shall be deemed to have lapsed.
14. In the case in hand, award under section 11 of the 1894 Act was made
within time, possession of the land was taken even prior to that and
compensation was paid/deposited within the statutory period of time.
15. Learned counsel for the respondents has drawn the attention of the court
to the fact that though the petitioners were aware of the acquisition
proceedings all throughout they submitted representations before the
authority only in 2015 and filed the present writ petition in 2016. As the
petitioners chose not to claim any remedy soon thereafter and remained
silent over the matter for more than a decade, the conduct of the
petitioners tantamounts to waiver of their rights and as such, the court
should not deal with the stale demands of the petitioners and the writ
petition should fail on the ground of delay and laches on the part of the
petitioners.
16. It is admitted that possession of the land was taken in 1993 and made over
to the requiring body to the knowledge of the petitioners. Since then the
petitioners remained dormant and submitted representations before the
authority only in 2015 followed by the present writ petition in 2016. The
Hon'ble Supreme Court, in the judgment in Indore Development Authority
v/s. Manoharlal and Others reported in (2020) 8 Supreme Court Cases
129, has observed as follows:- "If a claimant is aware of the violation of his
rights and does not claim his remedies, such inaction or conduct
tantamounts to a waiver of the right. In such cases, the lapse of time and
delay are most material and cannot be ignored by the Court." No
reasonable explanation being given by the petitioners for such inordinate
delay, this court should not go into the stale demands of the petitioners
after lapse of years.
17. In view of the observations made hereinabove, the writ petition being W.P.
8163(W) of 2016 is dismissed.
18. However the petitioners shall be at liberty to pursue their claims before the
appropriate forum in accordance with law.
19. There shall be no order as to costs.
20. Urgent certified website copies of this judgment, if applied for, be supplied
to the parties expeditiously on compliance with the usual formalities.
(Suvra Ghosh, J)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!