Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ajet Baidya And Others vs State Of West Bengal And Others
2021 Latest Caselaw 6553 Cal

Citation : 2021 Latest Caselaw 6553 Cal
Judgement Date : 22 December, 2021

Calcutta High Court (Appellete Side)
Ajet Baidya And Others vs State Of West Bengal And Others on 22 December, 2021
                      IN THE HIGH COURT AT CALCUTTA
                     CONSTITUTIONAL WRIT JURISDICTION
                               APELLATE SIDE

  The Hon'ble JUSTICE SUVRA GHOSH

                                W.P.A. 8163 of 2016

                              Ajet Baidya and Others
                                        Vs.
                         State of West Bengal and Others.



  For the Petitioner:                     Mr. Siddhartha Ruj, Adv.,

  For the State:                          Mr. Lalit Mohan Mahata, Adv.
                                          Mr. Prasanta Behari Mahata, Adv.,

  Hearing concluded on: 09.12.2021

  Date      : 22.12.2021



SUVRA GHOSH, J. :-

1. The prayers of the writ petitioners are as follows:


 "a) A declaration be made declaring the Land Acquisition Case being No. L.A.

     4/34 of 1999-2000 stood lapse and the respondent authorities be directed

to put petitioners in possession to their respective plot of land forthwith.

b) In the alternative a Writ in the nature of Mandamus do issue commanding

the respondents their men, agents, servants and/or assigns particularly

respondent No. 2 to acquire the petitioner Nos. 1 to 4's parcels of land

measuring each 19 decimals pertaining to Plot/Dag No. 911/1364, 21

decimals of land of the petitioner No. 5 pertaining to Plot/Dag No. 1364 and

10 decimals of land of the predecessor-in-interest of petitioner No. 6

pertaining to Plot/Dag No. 911/1371 lying at Mouza: Gangapur,J.L. No. 35

in the District of South 24 Parganas and to pay the land acquisition

compensation at the present market value of the land in that area in terms

of the present land acquisition act and complete the acquisition proceeding

within 6 (six) weeks from the date of the order to be made herein.

c) A Writ in the nature of Mandamus do issue commanding the respondents

their men, agents, servants and/or assigns particularly respondent No. 2 to

make the payment of compensation to the petitioners within the time

stipulated by this Hon'ble Court."

2. The writ petition was dismissed by an order dated 4th July, 2016 and

appeal against the said order was disposed of by Hon'ble Division Bench

of this Court by an order dated 2nd November, 2017 in M.A.T. 1368 of

2016, granting liberty to the petitioners to pursue the remedy available

under section 18 of the Land Acquisition Act, 1894

3. Review of the said order was sought by the petitioners and by an order

dated 25th September, 2019 in R.V.W. 272 of 2017, the Hon'ble Division

Bench recalled the order dated 2nd November, 2017 in M.A.T. 1368 of 2016

by allowing the review application and remanded the writ petition to this

court for fresh hearing.

4. It is submitted on behalf of the writ petitioners' that petitioners no. 1 to 5

and predecessor-in-interest of petitioner no. 6 acquired right, title and

interest over the plot of land in question by virtue of rayati settlement

deeds executed by the Government of West Bengal in their favour on 25th

April, 1984 and were in possession of the same. On demise of the father of

the sixth petitioner, this petitioner stepped into his shoes along with his

three sisters Kaharjan Bibi, Alekjan Bibi and Malekjan Bibi.

5. It is further contended that part of the petitioners' land was acquired in

Land Acquisition Case No. 4/34 of 1999-2000 for the purpose of

construction of leather complex though possession of the land was taken in

1993. No notice under section 9(3A) of the Land Acquisition (West Bengal

Amendment) Act, 1997 or section 12(2) of the Land Acquisition Act 1894

was served upon the petitioners and no compensation was also paid to

them. As such, the Land Acquisition Case being L.A. 4/34 of 1999-2000

stood lapsed after expiry of the statutory period in terms of section 11A of

the Act of 1894 and the petitioners are entitled to compensation at the

present market value of the land after completion of acquisition

proceedings.

6. A report in the form of an affidavit was submitted by respondent nos. 1, 2 &

3 which demonstrates that Land Acquisition Case being L.A. II/1 of 1993-

94 was initiated for the purpose of establishment of Calcutta Leather

Complex and upon issuance of notice of requisition under section 3(1) of

the West Bengal Land (Requisition and Acquisition) Act, 1948 on 17-11-

1993, possession of the land was taken and made over to the requiring

body on 26-11-1993 but the said proceedings could not be completed in

view of a writ petition filed by one Ziad Ali Molla. Subsequently Land

Acquisition Case No. 4/34 of 1999-2000 was initiated and notice under

section 9(3A) of the Land Acquisition (West Bengal Amendment Act), 1997

was issued on 12-08-1999 and enquiries conducted under the Act.

Objection was raised in respect of the award by some persons as a result of

which the compensation amount with regard to such persons was not paid

and was deposited in the court of the learned Land Acquisition Judge,

Alipore. The petitioners failed to produce documents in respect of their title

and possession in respect of the land and objection was received from the

petitioners after the compensation amount was paid/deposited. The willing

land losers were paid compensation in January, 2001 and compensation

with regard to the other awardees was deposited in court on 10th March,

2006. As such, the writ petition is not maintainable and is liable to be

dismissed.

7. It appears from the letter issued by the Block Land & Land Reforms Officer,

Bhangore - I, South 24 Parganas to the Additional Land Acquisition

Officer, South 24 Parganas on 2nd September, 2013 (annexure R2 to the

report filed by respondent nos. 1, 2 and 3) that the names of the petitioners

were recorded as patta holders in respect of plots in question. It is not in

dispute that possession of the plots was taken in 1993 after initiation of

acquisition proceedings and certificate of possession was issued in favour

of the requiring body on 26th November, 1993 in L.A. Case No. II/1 of 93-

94. A copy of certificate of the possession demonstrates that the plots

occupied by the petitioners were included therein. Admittedly, L.A. Case

No. II/1 of 93-94 could not be completed. Subsequently, L.A. Case No.

4/34 of 1999-2000 was initiated in respect of the same plots.

8. The petitioners claim that no notice was served upon them either under

section 12(2) of the Land Acquisition Act, 1894 or section 9(3A) of the Land

Acquisition (West Bengal Amendment Act), 1997 and consequentially no

compensation was paid to them. The petitioners submitted several

representations before the concerned authority claiming compensation but

such representations fell on deaf ears.

9. It appears that notices under section 12(2) of the Act of 1894 and under

section 9(3A) of the 1997 Amendment Act were issued by the authority in

the year 1999 and 2000 which cover the property of the petitioners but it

cannot be ascertained from the said notices whether they were actually

served upon the petitioners. A notice under section 4 of the West Bengal

Land (Requisition and Acquisition) Act, 1948 in the form of gazette

notification dated 31st March, 1997 with regard to the plots in question

was also issued.

10. The petitioners say that as no award was published despite taking

possession of the land, the acquisition proceedings stood lapsed under

section 11A of the Land Acquisition Act, 1894. But documents reveal that

notice of acquisition as well as notice of award was published by the State

Authorities and compensation has been paid to most of the awardees. The

respondents submit that the petitioners failed to produce any document in

support of their title and possession in respect of the land and raised

objection against the proceedings only after the proceedings was concluded

and compensation was paid/deposited. It is also submitted that

compensation in respect of which dispute arose was deposited in court on

10th March, 2006.

11. Therefore it is crystal clear that L.A. proceedings being 4/34 of 1999-2000

was concluded and compensation disbursed within the statutory period of

time. Admittedly no compensation was granted to the petitioners. In the

premises, the prayer of the petitioners for a declaration that the acquisition

proceeding stood lapsed cannot be acceded to.

12. The petitioners have, in the alternative, prayed for compensation at the

present market value of land in terms of the present Act of 2013.

13. Section 24(1a) of The Right to Fair Compensation and Transparency in

Land Acquisition, Rehabilitation and Resettlement Act, 2013 states that in

a proceeding initiated under the Land Acquisition Act, 1894 when no

award under section 11 of the Act has been made, then all provisions of

the 2013 Act relating to the determination of compensation shall apply.

Section 24(2) states that in case of such land acquisition proceedings

initiated under the 1894 Act, when the award under section 11 has been

made five years or more prior to the commencement of this Act but

physical possession of the land has not been taken or the compensation

has not been paid, the said proceedings shall be deemed to have lapsed.

14. In the case in hand, award under section 11 of the 1894 Act was made

within time, possession of the land was taken even prior to that and

compensation was paid/deposited within the statutory period of time.

15. Learned counsel for the respondents has drawn the attention of the court

to the fact that though the petitioners were aware of the acquisition

proceedings all throughout they submitted representations before the

authority only in 2015 and filed the present writ petition in 2016. As the

petitioners chose not to claim any remedy soon thereafter and remained

silent over the matter for more than a decade, the conduct of the

petitioners tantamounts to waiver of their rights and as such, the court

should not deal with the stale demands of the petitioners and the writ

petition should fail on the ground of delay and laches on the part of the

petitioners.

16. It is admitted that possession of the land was taken in 1993 and made over

to the requiring body to the knowledge of the petitioners. Since then the

petitioners remained dormant and submitted representations before the

authority only in 2015 followed by the present writ petition in 2016. The

Hon'ble Supreme Court, in the judgment in Indore Development Authority

v/s. Manoharlal and Others reported in (2020) 8 Supreme Court Cases

129, has observed as follows:- "If a claimant is aware of the violation of his

rights and does not claim his remedies, such inaction or conduct

tantamounts to a waiver of the right. In such cases, the lapse of time and

delay are most material and cannot be ignored by the Court." No

reasonable explanation being given by the petitioners for such inordinate

delay, this court should not go into the stale demands of the petitioners

after lapse of years.

17. In view of the observations made hereinabove, the writ petition being W.P.

8163(W) of 2016 is dismissed.

18. However the petitioners shall be at liberty to pursue their claims before the

appropriate forum in accordance with law.

19. There shall be no order as to costs.

20. Urgent certified website copies of this judgment, if applied for, be supplied

to the parties expeditiously on compliance with the usual formalities.

(Suvra Ghosh, J)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter