Monday, 01, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Om Sri Maa Shakti I Namah vs Marve Co-Operative Housing Society Ltd
2026 Latest Caselaw 4630 Bom

Citation : 2026 Latest Caselaw 4630 Bom
Judgement Date : 5 May, 2026

[Cites 8, Cited by 0]

Bombay High Court

Om Sri Maa Shakti I Namah vs Marve Co-Operative Housing Society Ltd on 5 May, 2026

  2026:BHC-OS:11518

                                                                     901-CARBP-126-2023.docx

         rrpillai            IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   ORDINARY ORIGINAL CIVIL JURISDICTION
                         COMMERCIAL ARBITRATION PETITION NO. 126 OF 2023

                        M/s. Om Sri Maa Shakti I Namah
                        A Partnership firm duly registered
                        under the provisions of
                        Indian Partnership Act, 1932
                        and having its principal place of
                        Business at Shop No. 8, Saloni Apts.
                        TPS 56th Road, Borivali (West), Mumbai 400 092
                        Represented by its Authorised
                        Representative Mr. Prashant K. Doshi         ...     Petitioner
                               Versus
                        Marve Co-operative Housing Society Ltd.
                        A society registered under the Maharashtra
                        Co-operative Societies Act, 1960
                        and having its office at Marve Road,
                        Malad (W), Mumbai-400 064                    ...     Respondent


                        Mr. Bhavin Gada, Mr. Ameet Mehta, Mr. Nirav Marjadi, Ms.
                        Srushti Mehta, Mr. Kushal Harnesha i/b. Solicis Lex for the
                        Petitioner.
                        Mr. Gauraj Shah a/w. Mr. V. A. Joshi, Mr. Vir Patel i/b. Chitnis
                        Vaithy and Co.for the Respondent.
                                                        CORAM : GAURI GODSE, J.
                                                 RESERVED ON: 22nd DECEMBER 2025
                                                 PRONOUNCED ON: 5th MAY 2026

           Digitally
           signed by
           RAJESHWARI
RAJESHWARI RAMESH                                            1/23
RAMESH     PILLAI
PILLAI     Date:
           2026.05.05
           16:10:38
           +0530

                         ::: Uploaded on - 05/05/2026                 ::: Downloaded on - 06/05/2026 15:34:32 :::
                                                  901-CARBP-126-2023.docx


JUDGMENT:

1. This petition is filed under Section 34 of the Arbitration

and Conciliation Act, 1996 ("Arbitration Act"), for setting aside

the Arbitral Award dated 11th July 2022, passed by the Sole

Arbitrator, dismissing the petitioner's claim for specific

performance, challenging the termination of the development

agreement, and partly allowing the counterclaim of the

respondent. The claimant is directed to pay to the respondent

the amount received from the members for the additional

area.

Facts In Brief Pleaded By The Claimant:

2. The respondent society negotiated with the petitioner

and entered into a Development Agreement, under which all

members were to be provided with 7% of the area over and

above the area occupied by them in the old building. The

members also insisted on the upfront payment of the entire

corpus fund to the society, amounting to Rs. 24 Lakhs, which

has been duly paid. Thereafter, the respondent, by following

due process of law, duly appointed the petitioner by passing a

901-CARBP-126-2023.docx

unanimous resolution, to redevelop the building of the

respondent.

3. The building of the said society was constructed

sometime in the year 1973. There are 21 members who have

22 flats (one member has two flats with one share certificate)

in the old building, on ground plus four upper floors, without a

lift. On average, each flat had 380 sq. ft. of carpet area. The

petitioner, in pursuance of said Development Agreement,

initiated various steps by offering rent to the members of the

respondent and, upon obtaining various approvals from

MCGM, started construction on the said property. Until the

stoppage of work, the petitioner had incurred a sum of

approximately Rs. 18,00,00,000/- towards the redevelopment

process and had reached the construction of the ground + five

upper floors.

4. As per the Development Agreement, the area assigned

for redevelopment was about 1239.3 square metres, but upon

conducting enquiry, the petitioner came to know that the area

of the plot as per the MCGM record was 1309.3 square

metres, but out of this area, certain area had been

901-CARBP-126-2023.docx

surrendered for construction of road on two occasions,

thereby leaving behind a net area of 892.30 square meters

which was available for the purpose of redevelopment. On 1st

March 2013, IOD was issued, and the petitioner made an

application for a commencement certificate on 28 th December

2011. On 7th June 2013, a commencement certificate was

issued. On 19th November 2013, a commencement certificate

up to 5 floors was issued. On 12th February 2015, the property

card was issued by the concerned authority of MCGM

showing the respondent's name. On 1st August 2015, the

respondent's advocates issued a termination letter terminating

the Development Agreement and invoking the arbitration

clause.

5. On 23rd September 2015, a reply was issued to the

respondent's termination notice. The petitioner had explained

the steps it had taken after obtaining vacant possession of the

subject property, such as obtaining a property card and area

rectification, to secure further CC for the redevelopment of the

subject property. Further, the petitioner followed up with

departments for area correction/boundary correction of the

901-CARBP-126-2023.docx

subject property, to claim the road setback area and hand

over the same to MCGM, to carry out subdivision of land and

get appropriate orders thereon, and to carry out rectification of

the conveyance deed of the subject property. On 17 th October

2015, the advocate for the claimant, in a rejoinder letter to the

petitioner's reply, raised false and incorrect contentions.

6. On 7th December 2015, PAAA was executed between

the petitioner, the respondent and a member of the

respondent. On 12th July 2016, an order by this Court in the

respondent's Section 9 petition was passed, whereby by

consent, the parties decided that the rent deposited by the

petitioner with the court be handed over to the respondent,

and the petitioner undertook to furnish a Bank Guarantee for a

sum of Rs.75,00,000/- and pay arrears of property tax within a

period of four weeks.

7. The respondent undertook to withdraw its letter to the

MCGM if the petitioner complied with its undertaking. The

petitioner was granted liberty not to hand over possession of

the flats to the members of the respondent until its claim

regarding the payment required to be made by the members

901-CARBP-126-2023.docx

for the additional area was decided. Respondent's Section 9

petition was disposed of. On 30th August 2016, the respondent

issued a termination notice to the petitioner for allegedly

defaulting on its obligations under the development

agreement and the undertakings given to this Court. On 14 th

September 2016, reply to the second Termination Notice by

the advocate for the petitioner was issued to the respondent.

The petitioner contended that it had, by its letter dated 12 th

July 2016, requested the respondent to extend the time period

for complying with the order dated 12 th July 2016, and that the

respondent had agreed to include the suggestion in the

respondent's meeting to be held on 18 th August 2016.

However, without considering the request, the respondent had

purportedly terminated the agreement.

8. On 20th June 2017, the petitioner, by letter, forwarded

copies of the pay orders for the Bank Guarantee, rent, and

property taxes to the respondent. On 3 rd December 2017, the

members of the respondent executed a consent letter in

favour of the petitioner, allowing the petitioner to carry out the

redevelopment.

901-CARBP-126-2023.docx

9. The petitioner filed the statement of claim challenging

the termination of the agreement and sought specific

performance. The respondent filed a statement of defence

and a counterclaim. On 13th November 2019, a demand draft

of Rs. 2,70,00,000/- was issued by the petitioner in favour of

the respondent, and on 22nd November 2019, consent terms

were executed between the petitioner and the respondent.

The terms are signed by the members of the respondent, by a

representative of the respondent and by the advocates of the

respective parties. On 22nd November 2019, minutes of a

meeting was recorded that the matter was reserved for the

passing of an order by the Arbitral Tribunal. On 27 th December

2019, the parties exchanged a draft of the consent terms. On

3rd March 2020, the respondent's advocate sent an email to

the Tribunal requesting an award.

10. The respondent took a complete resiled after having

agreed to most of the terms between the parties and, in fact,

signing a consent term to that effect. On 3 rd March 2020, the

petitioner's advocate sent an email to the Tribunal and the

respondent, expressing shock and surprise at the

901-CARBP-126-2023.docx

respondent's conduct. It was stated that the respondent has

not received any communication since the parties signed the

consent terms. A request was made to the Tribunal to

convene a meeting to understand and seek the reason why

the consent terms between the parties were unilaterally

rejected. On 9th March 2020, minutes of the meeting were

recorded, whereby the Tribunal noted that the parties were

trying to settle the disputes. It is further noted that the

mandate had expired. Parties undertook to file an appropriate

application seeking an extension. On 9th March 2020, the

minutes of the consent terms meeting were exchanged

between the petitioner and the respondent. On 29 th June

2020, an email by the advocate of the petitioner to the

advocate of the respondent, forwarding the minutes of

settlement arrived between the parties, and requesting to

finalise the same.

11. On 8th July 2020, an email by an advocate of the

respondent to an advocate of the petitioner wrongly alleged

that no settlement talks had purportedly transpired between

the parties as recorded on 9 th March 2020. Further, the

901-CARBP-126-2023.docx

respondent made demands that were over and above the

terms agreed between the parties. On 2 nd October 2020, this

Court extended the mandate until 28th February 2021 to

complete the arbitral proceedings. On 26 th February 2021, the

petitioner filed written submissions before the Tribunal. On

26th April 2021, the respondent filed written submissions

before the Tribunal. On 26th April 2021, this Court extended

the mandate of the Hon'ble Tribunal by three months to pass

an award. On 26th July 2021, the extended mandate of the

Tribunal. On 11th July 2022, the impugned award was passed

by the Arbitral Tribunal.

Defence of The Respondent:

12. The claimant breached the terms and conditions of the

contract. Under clause 18 of the development agreement, if

the benefit of any enhanced FSI became available after

issuance of the full IOD, the same was to be shared between

the parties in equal proportion. The benefit of fungible FSI that

had become available after issuance of the IOD was neither

discussed nor disclosed to the respondent. The claimant

failed to provide the 7% additional carpet area under clause

901-CARBP-126-2023.docx

26 of the agreement. The claimant also failed to disclose the

total number of car parking spaces in the approved plan as

required under clause 31 of the agreement. The claimant

failed to make payment of the municipal assessment taxes as

agreed in clause 43 of the agreement, and also failed to

obtain the requisite insurance policy as per clause 48 of the

agreement. Under clause 59 of the agreement, the claimant

was required to furnish an irrevocable bank guarantee of Rs.

1,25,00.000/-. However, only a bank guarantee of Rs. 75

lakhs was furnished, which lapsed on 23rd January 2015.

13. According to the respondent, the petitioner did not

comply with the obligations under the agreement, failed to

obtain the plans' approval, and did not pay the monthly

compensation. In breach of the agreed terms, the claimant

created a third-party interest without handing over the 22 flats

to the members. Hence, the termination of the agreement was

valid. In the absence of compliance with the terms and

conditions of the agreement and failure to plead and prove the

readiness and willingness to perform its part of the contract,

the claimant was not entitled to specific performance of the

901-CARBP-126-2023.docx

contract as prayed.

Submissions On Behalf Of The Petitioner (Claimant):

14. The claimant had always shown readiness and

willingness to comply with the terms and conditions of the

contract. Pursuant to the order passed by this court, the

claimant had also deposited a pay order in this Court. The

claimant had also issued a letter on 20th June 2017 to the

society for submitting further pay orders. Hence, the claimant

was always ready and willing to provide all the security as per

the terms and conditions of the contract, and also comply with

all the obligations on the part of the claimant.

15. As per clauses 37 and 39 of the agreement, if any

member wishes to purchase additional area over and above

the area provided free of cost, then the member was required

to pay such extra consideration amount, and the member's

right to the additional area would be concluded only upon full

payment. Hence, there was no substance in the grievance

made on behalf of the respondent that an additional area was

not provided. A period of 24 months, including a grace period

901-CARBP-126-2023.docx

of six months, was agreed upon from the date of

commencement of the certificate to complete the construction.

It was also agreed that if there was any difference or any

dispute between the petitioner and the society, the same

would be settled by mutual discussion, and if not settled, the

parties would go to arbitration. Hence, the respondent's

conduct in terminating the agreement shows a complete

disregard for the terms and conditions of the contract.

16. By the counterclaim, the society sought to recover the

amount paid by members for the purchase of additional area

under the contract. Hence, the society would not be entitled to

claim any amount from the petitioner on behalf of the

members. The learned Arbitrator failed to consider the

questions of law and facts involved in the dispute. The learned

arbitrator passed the award in a hurry after a very long time,

following the conclusion of the arguments. Hence, the award

would be liable to be set aside on the ground that it was

passed after a very long lapse of time after the conclusion of

the arguments.

17. The learned arbitrator failed to take into consideration

901-CARBP-126-2023.docx

the relevant terms and conditions of the contract. Hence,

failure on the part of the learned Arbitrator to decide in

accordance with the terms of the contract governing the

parties would attract the patent illegality ground as the

oversight would amount to gross contravention of section

28(3) of the Arbitration Act. He therefore submitted that the

impugned award is liable to be set aside under Section 34 of

the Arbitration Act. To support his submissions, learned

counsel for the petitioner relied upon the decisions of the

Apex Court in State of Chhattisgarh and Another vs. Sal

Udyog Pvt. Ltd.1 and State of Maharashtra vs. Hindustan

Construction Company Ltd.2

Submissions On Behalf Of The Respondent:

18. The claimant breached various terms and conditions of

the contract. The learned Arbitrator has considered all the

terms and conditions of the contract and the claimant's failure

to comply with its obligations. Failure to provide flats to the

members before creating third-party rights is also considered

an important factor in refusing the discretionary relief of

(2022) 2 SCC 275

(2010) 4 SCC 518

901-CARBP-126-2023.docx

specific performance. A perusal of the award would indicate

that the law arbitrator has considered all the terms and

conditions of the contract.

19. The learned Arbitrator held that the question of any

delay in the execution of the project on account of time spent

updating or rectifying the property card would not arise. All the

defences raised by the petitioner are dealt with in the

impugned award. The petitioner's contention that the project

was delayed on account of changes in the Development

Control Regulations, demonetization, introduction of the GST

Act, defending the proceedings initiated by third-party flat

purchasers and one of the building contractors is discarded in

the impugned award with reasons.

20. The learned Arbitrator held that the claimant failed to

comply with the undertakings as recorded in the consent

orders dated 16th June 2016 and 12th July 2016. Hence, the

respondent rightly terminated the Agreement. The respondent

issued the termination notice dated 29th August 2016 on

account of the petitioner's failure to honour the undertakings

given to this Court to furnish security and to pay taxes. The

901-CARBP-126-2023.docx

petitioner took no action for more than a year against the

termination of the agreement and the power of attorney. The

petitioner's attempts are to harass the respondent society and

to block the respondent society from appointing a new

developer to complete their redevelopment.

21. The respondent's counterclaim for the return of the

amount accepted by the petitioner from the members for the

additional area is based on clause 37 of the agreement. The

petitioner accepted the amount from the members for the

additional area under the agreement. Hence, the respondent's

counterclaim for return of the said amount in view of

termination of the agreement is well within the scope of the

terms and conditions of the agreement. There is no substance

in the additional grounds raised by the petitioner that,

because the development agreement was not executed

independently with the members, the counterclaim cannot be

allowed. There is also no substance in the additional ground

of challenge that the award is made after a long lapse of time

from the date of extension of the mandate. The award is made

well within the extended mandate period. All the arguments of

901-CARBP-126-2023.docx

the petitioner and the entire evidence on record are clearly

dealt with by the learned Arbitrator. Hence, there is no

substance in the additional grounds raised by the petitioner.

22. The petitioner has no financial capacity, readiness, or

willingness to perform his part of the contract. The petitioner

failed to perform the obligations under the development

agreement and has breached every single undertaking given

to this court and the indulgence granted by the society and its

members. The grounds raised in this petition are an attempt to

reargue the case by re-appreciating the evidence, which is not

permissible under section 34 of the Arbitration Act. It is an

established legal principle that the interference of a court

under Section 34 is limited and permissible only when the

arbitral award is arbitrary, perverse or suffers from patent

illegality, which goes to the root of the matter or when the

conscience of the court is shocked. In the present case, no

such ground is made out, warranting any interference under

Section 34 of the Arbitration Act. The respondent has taken

over the physical position of the property and is at an

advanced stage of its development by appointing a new

901-CARBP-126-2023.docx

developer. The petitioner's conduct of consistently breaching

its obligations and the undertaking given to this court also

precludes the petitioner from any relief in this petition.

Analysis and Conclusions:

23. I have carefully perused the findings recorded by the

learned Arbitrator while considering the submissions of the

parties. I have also perused the pleadings and the evidence.

The terms of the contract and all subsequent stages are

discussed in detail by the learned Arbitrator. The terms of the

contract reveal the petitioner's obligations. The petitioner's

argument that steps were taken to complete all the

procedures required for area correction and the incorporation

of the respondent's name on the property card are part of the

obligations recorded in the agreement. The petitioner, on

sanction of the plans, had to enter into a permanent alternate

accommodation agreement with the members of the

respondent. The members of the respondent had to vacate

their respective flats only after the petitioner obtained IOD. If

members of the respondent wish to purchase additional area,

then the consideration was provided in the agreement. The

901-CARBP-126-2023.docx

timelines to complete construction were also provided. The

petitioner could offer possession to third-party purchasers only

after offering possession to the members. Therefore, in view

of the terms and conditions agreed between the parties and

the subsequent conduct of the petitioner in not performing all

the obligations and not adhering to the timelines are dealt with

by the learned Arbitrator. The petitioner's grounds to

challenge the termination of the agreement are also dealt with

by the learned Arbitrator. Considering the petitioner's conduct

as seen from the evidence on record, the learned Arbitrator

has discarded all the grounds raised for challenging the

termination of the contract. Failure on the part of the petitioner

to prove readiness and willingness, and the capacity to

complete the project, is also considered an important factor in

refusing relief of specific performance.

24. The learned Arbitrator has recorded findings on the

breaches committed by the petitioner by referring to the

relevant clauses 18, 26, 31, 43, 48, 59 and 62 of the

agreement. There appears to be no dispute that the petitioner

also failed to comply with the obligation to furnish the bank

901-CARBP-126-2023.docx

guarantee as security, as agreed in the terms and conditions

of the agreement. The breach committed by the petitioner of

the undertaking given to this court is also part of the record.

The explanations and justifications given by the petitioner

regarding the provision of security in view of the mutually

agreed terms are rejected by the learned arbitrator for want of

any satisfactory evidence. Therefore, all the grounds raised

on behalf of the petitioner as recorded in the above

paragraphs are only about reviewing the evidence.

25. I have perused the terms and conditions of the

agreement and the counterclaim. Learned counsel for the

respondent is right in pointing out that the counterclaim is well

within the scope of the terms and conditions of the contract,

and in particular, clause 37 of the agreement. There is no

dispute that the amount accepted by the petitioner from the

members pertains to the additional area under the

development agreement. Therefore, the counterclaim is well

within the scope of the terms and conditions of the

development agreement. The respondent is entitled to seek

return of the amount on behalf of its members on the ground

901-CARBP-126-2023.docx

of termination of the development agreement. There is also no

merit in the additional ground of challenge that the award is

liable to be set aside, as it is made after a long lapse of time

from the date of extension of the mandate. The award is made

well within the extended mandate period. Nothing is shown as

to how the award is vitiated on the said ground. I have already

recorded reasons to hold that the award is made on well-

considered reasons after appreciating the pleadings and

evidence on record. It is not a ground raised by the petitioner

that any particular evidence or any submission was not

considered by the learned Arbitrator. Hence, there is no merit

in the additional grounds raised by the petitioner. The award

cannot be set aside on the additional grounds raised by the

petitioner.

26. The grievance made that the terms were amicably

settled and the respondent resiled without any intimation or

reason has no meaning. There is nothing on record to indicate

that any terms of amicable settlement were finalised and

accepted on record by the learned Arbitrator. Therefore, such

a grievance cannot be considered for the first time in a

901-CARBP-126-2023.docx

Section 34 petition. It is also not a valid ground to set aside

the award.

27. The learned Arbitrator has, in detail, dealt with the terms

and conditions of the agreement, after appreciating the

evidence, interpreted all the terms of the contract, and

concluded that the petitioner failed to comply with the

obligations and that the respondent is justified in terminating

the contract. The reasonable conclusion reached by the

learned Arbitrator is a plausible view. It is a well-established

legal principle that reappreciating the findings of the arbitral

tribunal and taking an entirely different view is not permissible

in a petition under Section 34, thereby virtually acting as a

court of appeal. There cannot be a reappreciation of evidence,

and the award cannot be set aside only on the ground that, on

merits, another view is possible. It is also a settled view that

perversity would include patent illegality if the finding is based

on no evidence at all, or an award that ignores vital evidence,

or a finding based on documents taken behind the back of the

parties. In the present case, the learned Arbitrator has

considered the entire evidence. Thus, the view taken by the

901-CARBP-126-2023.docx

learned Arbitrator is based on a consideration of the entire

evidence on record and an interpretation of the terms of the

contract. Hence, the decisions of the Apex Court relied upon

by the learned counsel for the petitioner are of no assistance

to the petitioner in the facts of the present case.

28. The law on the scope of interference in the Section 34

petition is no longer res integra. In multiple decisions of the

Apex Court, it is held that the Section 34 Court must not lightly

interfere with arbitral awards in a casual and cavalier

manner, unless a conclusion can be drawn that the award

suffers from perversity and patent illegality that goes to the

root of the matter. The Apex Court has held in various

decisions that the mandate under Section 34 is to respect the

finality of the arbitral award and the party autonomy to get

their dispute adjudicated by an alternative forum as provided

under the law.

29. In the present case, there is no ground to set aside the

award under the limited scope of Section 34 of the Arbitration

Act. Hence, no interference is called for in the impugned

Award.

901-CARBP-126-2023.docx

30. For the reasons recorded above, the petition is

dismissed.

[GAURI GODSE, J.]

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter