Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vishnu Darshan Row Houses Cooperative ... vs The Competent Authority And District ...
2026 Latest Caselaw 3201 Bom

Citation : 2026 Latest Caselaw 3201 Bom
Judgement Date : 30 March, 2026

[Cites 0, Cited by 0]

Bombay High Court

Vishnu Darshan Row Houses Cooperative ... vs The Competent Authority And District ... on 30 March, 2026

Author: Amit Borkar
Bench: Amit Borkar
 2026:BHC-AS:15086
                                                                                   6-wp-11689-2015.doc


                       Shabnoor
                                  IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                          CIVIL APPELLATE JURISDICTION

                                             WRIT PETITION NO.11689 OF 2015

         Digitally
         signed by
                       Vishnu Darshan Row Houses
         SHABNOOR
SHABNOOR AYUB
AYUB     PATHAN
                       Cooperative Housing Society
PATHAN   Date:
         2026.03.30
         16:14:42
                       Through Its Secretary Vijay Anikhindi         ... Petitioner
         +0530
                                   V/s.
                       The Competent Authority &
                       District Deputy Registrar of the
                       Cooperative Societies & Ors.                  ... Respondents

                       Ms. Arundhati Walawalkar a/w Ms. Sakshi Agarwal i/b
                       Mr. Bipin J. Joshi, for the Petitioner.
                       Ms. Ashwini A. Purav, AGP, for the State - Respondent
                       No.1.


                                                      CORAM    : AMIT BORKAR, J.
                                                      DATED    : MARCH 30, 2026
                       P.C.:

                       1.      Rule. Rule is made returnable forthwith.

2. By the present Petition, the petitioner has assailed the judgment and order dated 14 July 2015 passed by the Competent Authority, whereby the application preferred by the petitioner under Section 11 of the Maharashtra Ownership Flats Act 1963 seeking grant of unilateral deemed conveyance in respect of the entire property bearing Survey No. 69, Hissa No. 2/2, situated at Mauje Belavli, Badlapur (East), Taluka Ambernath, District Thane, admeasuring 22,500 sq. mtrs., came to be rejected. The challenge is founded on the ground that the Competent Authority failed to

6-wp-11689-2015.doc

properly appreciate the statutory scheme of Section 11, which is intended to protect flat purchasers from inaction of the promoter, and instead adopted an unduly technical approach, thereby defeating the object of the legislation.

3. The facts giving rise to the present Petition disclose that a Development Agreement dated 4 November 2004 was executed between the landowners and Respondent No. 2, thereby conferring development rights upon the said respondent. Pursuant thereto, Respondent No. 2 obtained IOD and Commencement Certificate on 8 December 2004 for construction of row houses. It further emerges that between 2004 and 2009, various purchasers, who are now members of the Petitioner Society, entered into separate agreements for sale in accordance with Section 4 of MOFA. These agreements created enforceable rights in favour of the purchasers not only in respect of their individual units, but also in the common property forming part of the project, thereby casting a corresponding statutory obligation upon the promoter.

4. Despite due service of notice, the respondents have failed to appear before this Court and contest the Petition.

5. The record further indicates that Occupation Certificates were issued in phases on 7 April 2006, 11 December 2007, and finally on 1 April 2009 for the remaining row houses. This clearly establishes that the project was completed in a phased manner and stood fully completed by 1 April 2009. The Petitioner Society came to be registered on 3 January 2014. Thereafter, a legal notice dated 30 June 2014 was issued calling upon Respondent Nos. 2 to

6-wp-11689-2015.doc

18 to execute conveyance in favour of the Society. The issuance of such notice demonstrates due compliance with the statutory requirement and reflects that the promoter was afforded an opportunity to discharge his obligation, which he failed to do.

6. It further appears that on 22 September 2014, the Petitioner submitted an application for deemed conveyance along with requisite documents and thereafter furnished hard copies as required. Notices of hearing were issued by the Competent Authority from time to time. Despite service of notice, the respondents failed to appear before the Authority and contest the proceedings. In such circumstances, the petitioner placed on record written submissions and an indemnity bond. The matter was thereafter reserved for orders; however, by order dated 14 July 2015, the Competent Authority rejected the application. The rejection, in absence of any rebuttal from the respondents, indicates non-consideration of uncontroverted material placed by the petitioner.

7. Learned Advocate for the petitioner has invited attention to the agreements executed under Section 4 of MOFA, including the agreement dated 15 December 2006, to demonstrate that each purchaser was granted an independent and identifiable right in respect of his respective row house. It is further submitted that the entire project comprises 76 row bungalows constructed on the said plot admeasuring 22,500 sq. mtrs., as reflected in the sanctioned plan. This submission is significant, as it establishes that the project is a single composite development and not a fragmented or severable undertaking.

6-wp-11689-2015.doc

8. It is further submitted, on the basis of the Architect's Certificate, that the permissible FSI for the said plot at the relevant time was 0.85. The total constructed built-up area of the 76 row houses is stated to be 7,953.84 sq. mtrs., whereas the permissible built-up area is 9,193.68 sq. mtrs. This material demonstrates that the development was within permissible limits and that no excess construction is alleged. The Authority, however, failed to consider this material in its proper perspective, thereby rendering its conclusion unsustainable.

9. The Competent Authority rejected the application primarily on the ground of discrepancy in the area mentioned in the Architect's Certificate. Such a ground, in the considered view of this Court, is wholly insufficient to deny substantive relief under Section 11 of MOFA, particularly when the discrepancy, if any, is not shown to affect the identity or extent of the property sought to be conveyed.

10. It is not in dispute that the construction commenced around 2006-2007 and stood completed on 1 April 2009 upon issuance of the Completion and Occupation Certificate by the Municipal Corporation. This admitted position reinforces the fact that the promoter's obligation to execute conveyance had arisen long prior to the filing of the application, and continued non-compliance on his part justifies invocation of the remedy of deemed conveyance.

11. On perusal of the agreements executed under Section 4 of MOFA, particularly Schedule 'A' annexed thereto, it clearly emerges that the entire property forming the subject matter of the project

6-wp-11689-2015.doc

admeasures 22,500 sq. mtrs. Clauses (38)(a) and (40) of the agreements specifically cast an obligation upon the promoter to form a co-operative society and to convey the property in its entirety. These contractual stipulations are in consonance with the statutory mandate and leave no ambiguity regarding the extent of land to be conveyed.

12. In view of the aforesaid facts, and having regard to the agreements executed under Section 4 of MOFA, the sanctioned plans, and the Architect's Certificate, this Court is satisfied that the petitioner has established its entitlement to unilateral deemed conveyance in respect of the entire property admeasuring 22,500 sq. mtrs. The impugned order, having been passed without proper appreciation of material on record and on an untenable ground, cannot be sustained and is liable to be set aside.

13. Accordingly, Rule is made absolute in terms of prayer clause

(a).

14. The writ petition stands disposed of in aforesaid terms.

15. There shall be no order as to costs.

(AMIT BORKAR, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter