Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shree Naman Hotels Pvt. Ltd. vs Mumbai Metropolitan Region ...
2026 Latest Caselaw 3542 Bom

Citation : 2026 Latest Caselaw 3542 Bom
Judgement Date : 8 April, 2026

[Cites 20, Cited by 0]

Bombay High Court

Shree Naman Hotels Pvt. Ltd. vs Mumbai Metropolitan Region ... on 8 April, 2026

2026:BHC-OS:8909-DB
                                                           Shree Naman Hotels-oswp-3209-2017-J-R.doc




                                                                                                  Shephali



                                IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                    ORDINARY ORIGINAL CIVIL JURISDICTION
                                       WRIT PETITION NO. 3209 OF 2017


                     Shree Naman Hotels Pvt. Ltd.,
                     A company registered under the provisions
                     of the Companies Act, 1956, having its
                     registered office at 315, Parekh Market,
                     39, J.S.S. Road, Opera House,
                     Mumbai 400 004.                                                  ...Petitioner

                              ~ versus ~

                     1.     Mumbai Metropolitan Region
                            Development Authority,
                            a Body Corporate having its Head
SHEPHALI
                            Office at MMRDA Office Building,
SANJAY                      Plot Nos. C-14 & C-15, 'E' Block,
MORMARE
                            Bandra Kurla Complex, Bandra (East),
 Digitally signed
 by SHEPHALI                Mumbai 400 051.
 SANJAY
 MORMARE
 Date: 2026.04.09
 15:15:50 +0530
                     2.     The Metropolitan Commissioner,
                            being the Chief Executive Officer of
                            the Mumbai Metropolitan Region
                            Development Authority, having his
                            office at MMRDA Office Building,
                            Plot Nos. C-14 & C-15, 'E' Block,
                            Bandra Kurla Complex, Bandra (East),
                            Mumbai 400 051.                                     ...Respondents

                     A PPEARANCES
                     For the Petitioner              Mr.    Vikram   Nankani,    Senior
                                                     Advocate, with Mr. Vaibhav Krishna
                                                     & Mr. Tahir Pande, i/b Juris
                                                     Consillis.
                     For Respondents-MMRDA           Mr.   Pravin    Samdani,    Senior
                                                     Advocate, with Mr. Nishant Chotani,
                                                     Mr. Nivit Srivastava, Ms. Sneha



                                                   Page 1 of 55


                    ::: Uploaded on - 09/04/2026                    ::: Downloaded on - 09/04/2026 21:35:56 :::
                                              Shree Naman Hotels-oswp-3209-2017-J-R.doc




                                       Patil, Ms. Aditi Sinha, Mr.
                                       Hrishikesh Joshi & Ms. Isha Vyas,
                                       i/b Maniar Srivastava Associates.



                       CORAM     :      SHREE CHANDRASHEKHAR, CJ &
                                        SUMAN SHYAM, J.
           RESERVED ON           :      22nd JANUARY 2026.
        PRONOUNCED ON            :      8th APRIL 2026.

 JUDGMENT (Per Suman Shyam, J):

-

1. Rule, rule is made returnable forthwith.

2. By consent of the parties, the matter is taken up for final

hearing.

3. Assailing the Demand Notice dated 12th September 2017

(Exhibit "P") issued by Respondent No.1-Mumbai Metropolitan

Region Development Authority (hereinafter referred to as

"MMRDA"), whereby, the said Respondent had demanded payment

of additional premium, together with interest, on account of alleged

delay in completion of the construction, the Petitioner has

approached this Court by filing the present Writ Petition inter alia

contending that such demand pertaining to the construction of the

basic built-up area of 18,600 sq. mtrs. in the building known as

"Sofitel Hotel" on Plot Nos. C-57 and C-58 (combined) at Bandra-

Shree Naman Hotels-oswp-3209-2017-J-R.doc

Kurla Complex ("BKC") is contrary to the terms and conditions of

the Lease Deed dated 9th June 2006 and, therefore, is arbitrary,

illegal, discriminatory and also is in violation of the fundamental

rights guaranteed to the Petitioner under Article 14 of the

Constitution of India. The facts and circumstances, giving rise to the

filing of the present Writ Petition, shorn of unnecessary details, are

as hereunder.

4. The Petitioner is a company incorporated under the

provisions of the Companies Act, 1956 having its registered office at

Opera House, Mumbai. It is a subsidiary of "Shree Naman

Developers Ltd".

5. The Respondent No.1, MMRDA is a statutory authority

constituted under the Mumbai Metropolitan Region Development

Authority Act, 1974 (hereinafter referred to as "the MMRDA Act")

and the Respondent No. 2 is the Metropolitan Commissioner of

MMRDA.

6. The Respondent No.1, being the owner of the land, had

floated a Tender on 8th February 2005, for grant of 80-years lease in

respect of Plot Nos. C-57 and C-58 (combined) admeasuring

Shree Naman Hotels-oswp-3209-2017-J-R.doc

approximately 8,092.40 sq. mtrs., situated in 'G' Block of Bandra-

Kurla Complex, for construction of a Star Category Hotel with the

maximum permissible built-up area of 18,600 sq. mtrs. The said

tender was issued in terms of the provisions of the Mumbai

Metropolitan Region Development Authority (Disposal of Land)

Regulations, 1977. Although the bid process was initiated by

Respondent No. 1 on 8th February 2005, yet, the same was kept in

abeyance. Thereafter, fresh bids were invited by the Respondent

No.1 on 18th November 2005 with revised terms including revised

the reserve price.

7. In response to the above tender, the Petitioner's parent

company, viz., Shree Naman Developers Ltd. ("SNDL"), had

submitted its bid on 30th December 2005, offering premium of

Rs.1,10,000/- per sq. mtrs., aggregating to Rs.204,60,00,000/- for

the entire plot. The bid submitted by the SNDL came to be accepted

by Respondent No.1 in its 115 th Meeting held on 3rd February, 2006,

under Resolution No.1072. Accordingly, Letter of Allotment dated

14th February 2006 was issued in favour of SNDL.

8. SNDL, thereafter, paid the entire lease premium of

Rs.204,60,00,000/- (Rupees Two hundred and four crores sixty

Shree Naman Hotels-oswp-3209-2017-J-R.doc

lakhs) to Respondent No.1 pursuant whereto, a Lease Deed dated

9th June 2006 came to be executed by and in between the

Respondent No.1 and SNDL, for granting leasehold rights in respect

of the said plot of land for a period of 80 years for construction of a

Star Category Hotel.

9. Article 2(a) of the Lease Deed dated 9 th June 2006 stipulates

that building plans are to be submitted to the planning authority for

approval. Article 2(d) provides that the lessee shall, within three

months from receipt of approval of the plans, commence

construction and within a period of four years from the date of the

lease, complete and finish the building so as to render it "fit for

occupation". Article 2(e) lays down that in the event of failure to

complete the construction within the stipulated period, the

Metropolitan Commissioner may grant extension of time upon

payment of additional premium at the prescribed rates.

10. Possession of the said plot was handed over to SNDL on 13 th

June 2006. Thereafter, with the permission of Respondent No.1,

granted on 14th July 2006, SNDL had assigned its right, title and

interest under the Lease Deed, in favour of the present Petitioner,

by executing Deed of Assignment dated 1st August 2006.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

11. On 14th September 2006, a notification was issued by the

Ministry of Environment and Forests ("MoEF") requiring

Environmental Impact Assessment ("EIA") clearance for the project.

On 13th December 2006, the Petitioner had applied for permission

from the Respondent No. 1 to commence excavation work pending

EIA clearance from the MoEF. By communication dated 13 th

November 2006, the Respondent No.1 had, however, declined such

permission and informed the Petitioner that excavation permission

could be considered only after the Petitioner obtains the EIA

clearance.

12. The Petitioner accordingly, applied for the EIA clearance on

23rd November 2006 and the same came to be granted on 2 nd March

2007. Pursuant thereto, the Respondent No.1 had granted

excavation permission to the Petitioner on 8th March 2007.

13. In the meantime, the Petitioner had submitted building plans

to Respondent No.1 and applied for Commencement Certificate.

The first Commencement Certificate upto the plinth level was

issued only on 29th October 2007 i.e. after a delay of about 1 year 4

months from the date of execution of the Lease Deed.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

14. According to the Petitioner, considerable time was consumed

in securing statutory approvals including EIA clearance from the

Ministry of Environment and Forest (MoEF), height clearance from

the Ministry of Civil Aviation. The Civil Aviation Ministry had

granted permission for construction only up to a restricted height

vide communication dated 25th March 2008. Thereafter, Intimation

of disapproval and further approvals were processed and ultimately,

Commencement Certificate dated 18th March 2009 was issued by

the Respondent No.1 permitting construction of two basement

levels, ground floor and 12 upper floors.

15. In the meantime, on 31st December, 2008, the Respondent

No.1 had permitted the Petitioner to utilize the area of staircase, lift

and lobbies free of FSI against payment of premium of Rs.6.03

crores, as a result of which, additional built up area of 11849.46 sq.

mtrs. had become available to the Petitioner which resulted in

construction of the 12th and 13th floors. On 16th June, 2010, the

Respondent No. 1 permitted further staircase area of 245 sq. mtrs.

to be treated as free of FSI on payment of Premium. In the above

process, there was substantial and unforeseen delay in

commencement of the construction. The Petitioner could ultimately

Shree Naman Hotels-oswp-3209-2017-J-R.doc

commence construction of the two upper floors only after the

month of July 2010.

16. In view of the above developments, the Respondent No.1

had issued two further Commencement Certificates dated 15 th

October 2009 and 7th July 2010. It is the case of the Petitioner that

while permitting utilization of the additional built-up area, the

Respondent No. 1 had not stipulated any time limit for completing

the construction.

17. It is also the case of the Petitioner that construction of the

entire building, comprising of two basements, ground floor and

thirteen floors was completed on 14th June 2011. Completion of the

construction was, thereafter, certified by the Chief Town and

Country Planning Division of Respondent No. 1 on 17th June 2011.

18. On 18th February, 2011, the Petitioner, through its architect,

had applied for Occupation Certificate. By the communication

dated 3rd October 2011, the Respondent No.1 had informed the

Petitioner that Occupation Certificate would be issued subject to the

condition that "The applicant shall provide 2 suits for 50 nights

each per year and 1 meeting/conference room for atleast 20

Shree Naman Hotels-oswp-3209-2017-J-R.doc

persons to be accommodated on 20 occasions with all necessary

technical equipment for presentations, per year free of any charge,

fee or rent in the Hotel to MMRDA. Food, beverages and other

services will be provided at a discount of 20% excluding taxes and

service charges, if any." Accordingly, the Petitioner was asked to

convey its acceptance of the above condition within 7 days.

19. On 29th September,2011 the Petitioner had once again

requested for issuance of Occupation Certificate for the hotel but

the same was declined. Instead, the Petitioner was asked to give an

undertaking that it will not commence operation of the Hotel until

payment of the additional premium. As such, the Petitioner was

compelled to submit a Notarized undertaking dated 3 rd

October,2011 to such effect.

20. On 11th October 2011, the Respondent No.1 had issued a

conditional Occupation Certificate in respect of the said building.

The Occupation Certificate so issued had also included the

stipulation that the Petitioner shall provide two suits for 50 nights

each per year and one meeting/conference room for atleast 20

persons to be accommodated on 20 occasions, with all necessary

technical support, to the MMRDA, free of charge, fee or rent. It was

Shree Naman Hotels-oswp-3209-2017-J-R.doc

also mentioned that the Petitioner shall not commence operation of

the Hotel until the payment of the additional premium towards

extension of time for completion of construction as per the Lease

Deed and the undertaking dated 03/10/2011 is made.

21. Thereafter, by letter dated 12th October 2011, the Respondent

No.1 had demanded payment of additional premium amounting to

Rs.25,42,74,636/- (Rupees Twenty Five crores Forty Two lakhs

Seventy Four thousand Six hundred and Thirty Six), together with

interest, for the alleged delay in completion of the construction

beyond four years from the date of execution of the Lease Deed i.e.

beyond 9th June, 2010.

22. The Petitioner had submitted representations requesting for

waiver of the demand for payment of additional premium/penalty

but the said request came to be rejected by communication dated

3rd January 2012 issued by the Respondent No.1. As such, in terms

of the undertaking furnished to Respondent No.1, the Petitioner

had paid two installments of Rs.4,39,37,781/-(Rupees Four Crores

Thirty-Nine Lakhs Thirty-Seven Thousand Seven Hundred Eighty-

One only) and Rs.4,54,54,537/- (Rupees Four Crores Fifty Four

Lakhs Fifty Four Thousand Five Hundred and Thirty Seven only)

Shree Naman Hotels-oswp-3209-2017-J-R.doc

respectively, towards the demanded amount of additional

premium/penalty The said amount was, however, paid under

protest.

23. Thereafter, further communications dated 1st September 2014

and 23rd April 2015 came to be issued by Respondent No.1 calling

upon the Petitioner to pay the balance outstanding amount, which

had culminated in the impugned Demand Notice dated 12 th

September 2017, by means of which, the Respondent No.1 had

called upon the Petitioner to pay the entire outstanding dues failing

which, the Respondents would recover the amount as arrears of

Land Revenue and also determine the Lease.

24. It is the further case of the Petitioner that in its 131st Meeting

held on 22nd October 2012, the Respondent No.1 had considered

granting extension of time for completion of construction from four

years to six years in view of the extra time consumed in securing

various statutory approvals from different authorities. In its 138 th

Meeting held on 26th August 2015, the Respondent No.1 had

resolved to amend Clause 2(d) of the standard form of the Lease

Deed so as to provide six years time period for completion of the

construction but made the said amendment applicable only to Lease

Shree Naman Hotels-oswp-3209-2017-J-R.doc

Deeds executed after 26th August 2015. According to the Petitioner,

restricting the benefit of the said amendment only to Lease Deeds

executed after 26th August 2015 was highly arbitrary and

discriminatory.

25. In the aforesaid circumstances, the Petitioner has instituted

the present Writ Petition challenging the Demand Notice dated 12 th

September 2017, as well as the earlier communications dated 12 th

October 2011, 3rd January 2012, 1st September 2014, 23rd April

2015 and 25th June 2015, whereby the Respondent No.1 had

demanded payment of additional premium, together with interest,

on account of alleged delay in completion of the construction.

26. In the reply affidavit filed by the Respondents Nos.1 and 2, it

has been inter- alia contended that the Writ Petition is not

maintainable due to delay and laches on the part of the Petitioner

in approaching this Court that the relief prayed for by the Petitioner

relates to implementation of the terms and conditions of the Lease

Deed dated 9th June 2006 and, therefore, the same cannot be

granted in a Writ Petition; that the Writ Petition having been

instituted beyond the period of three years form the date of the

demand, the same is bared by law of limitation; that the Petitioner

Shree Naman Hotels-oswp-3209-2017-J-R.doc

has an alternative, efficacious remedy in the form of a Civil Suit

and, therefore, the Writ Petition is not maintainable on such count

as well; that the Petitioner, having furnished a Notarized

undertaking to pay the amount of additional premium/penalty and

also agreeing not to commence the operation of the hotel till the

amount is paid, is estopped from challenging the demand, more so,

since part of the amount of additional premium/ penalty has

already been deposited by the Petitioner; that a conjoint reading of

Article 2(a) and 2(d) of the Lease Deed makes it clear that the

construction of the building must be completed within four years

from the date of the Lease Deed. Therefore, the demand made for

additional premium/penalty due to delay in completion of

construction is interim of Article 2(d) of the Lease Deed, which is

on agreed conditions of the Lease Deed. As such, the same cannot

be termed as arbitrary and illegal; that the resolution extending the

period for completion of construction from four years to six years

would apply prospectively and, therefore, the Petitioner would not

be entitled to such benefit. It has, further, been contended that

since most of the other parties have already complied with the

demand of additional premium, hence, there can no justifiable

ground for the Petitioner to dispute the claim; that the appointment

Shree Naman Hotels-oswp-3209-2017-J-R.doc

of one man committee is a matter of "internal management" of the

MMRDA and the report submitted by the committee is only of

persuasive value.

27. In the Rejoinder Affidavit, the Petitioner has reiterated its

stand that the demand for penalty is arbitrary and has denied that

there was any concluded contract to make payment of the penalty.

It has also been contended that in the facts and circumstances of

the case, it was not possible to complete the construction within

four years from the date of execution of the Lease Deed in view of

the additional built-up area allotted to the Petitioner permitting

construction of the 12th and 13th floor and that there was no time

limit for completion of the said construction. As such, the time line

for completion of integrated composite structure of the building by

using the additional built up area would not come within the ambit

of Article 2(d) of the Lease Deed.

28. This Writ Petition was analogously heard along with three

other similar Writ Petitions being Writ Petition No. 864 of 2018,

Writ Petition No. 242 of 2018 and Writ Petition No. 2377 of 2018,

wherein, identical reliefs were prayed for by the Writ Petitioner(s).

Shree Naman Hotels-oswp-3209-2017-J-R.doc

29. Mr. Vikram Nankani, learned Senior Counsel appearing for

the Petitioner has referred to the documents available on record to

submit that the demand for additional premium raised by

Respondent No.1 on account of alleged delay in completion of

construction of the building known as "Sofitel Hotel" on Plot Nos.

C-57 and C-58 at Bandra-Kurla Complex is wholly arbitrary, illegal

and unsustainable in the eyes of law. According to the learned

Senior Counsel, such demand is also contrary to the terms and

conditions of the Lease Deed dated 9th June 2006 and, therefore,

the Respondent No.1 had no authority to levy additional premium

for the alleged delay in completion of the construction.

30. It is further submitted by Mr. Nankani that the delay, if any, in

completion of construction occurred due to circumstances beyond

the control of the Petitioner which included the extra time

consumed in obtaining statutory approvals such as Environmental

Clearance from the Ministry of Environment and Forests , height

clearance from the Civil Aviation authorities as well as other

permissions required for development of the project. According to

the learned senior counsel, the Petitioner could not have

commenced or continued with the construction without obtaining

Shree Naman Hotels-oswp-3209-2017-J-R.doc

such statutory approvals and therefore, the time consumed in

securing such approvals ought to be excluded while computing the

period stipulated under Article2(d) of the Lease Deed for

completing the construction.

31. The learned Senior Counsel has also submitted that the

Respondent No.1 had itself permitted the Petitioner to utilize the

additional built-up area in the same building by excluding certain

areas from the FSI, upon payment of additional premium and by

issuing revised commencement certificates. According to him, once

such additional development was permitted and incorporated in the

building, the project had to be executed as a composite

development plan and therefore, the original time limit

contemplated under Article 2(d) of the Lease Deed could not have

been applied in such a rigid manner for the purpose of levying

additional premium.

32. The learned Senior Counsel has further submitted that the

issues raised in the present Writ Petition are squarely covered by

the decision of this Court in Raghuleela Builders Pvt. Limited and

Anr. vs. Mumbai Metropolitan Region Development Authority &

Shree Naman Hotels-oswp-3209-2017-J-R.doc

Ors.1 wherein, under similar facts and circumstances, this Court has

held that the demand of additional premium/ penalty for alleged

delay in completion of construction was arbitrary and unsustainable

in law. He further submits that the aforesaid judgment has attained

finality in the eyes of law inasmuch as the Special Leave Petition

preferred by the Respondent No.1 against the said judgement also

came to be dismissed by the Hon'ble Supreme Court by order dated

27th July 2020 passed in Special Leave to Appeal (C) No.6411 of

2020. According to the learned Senior Counsel, the principle laid

down in the said decision would apply to the facts of the present

case and therefore, the same would lay down a binding precedent

for this court to follow. As such,submits Mr. Nankani, the

impugned demand of penalty raised by Respondent No.1 deserves

to be set aside and a direction is required to be issued by this Court

to refund the amount of penalty already deposited by the Petitioner

under protest.

33. Responding to the above submissions, Mr. Pravin Samdani,

learned Senior Counsel appearing for Respondents has questioned

the maintainability of the Writ Petition on the grounds that the

1 (2020) (1) ABR 397: 2019 SCC OnLine Bom 4529.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

same involves disputed issues of facts and that, it is hit by delay and

laches in as much as, the relief claimed there-in is also barred by

the law of Limitation. Contending that the demand raised by

Respondent No.1 is in terms of the provisions of the Mumbai

Metropolitan Region Development Authority Act, 1974 and the

Mumbai Metropolitan Region Development Authority (Disposal of

Land) Regulations, 1977 (hereinafter referred to as "Land Disposal

Regulations") Mr. Samdani has argued that the additional premium

has been levied in accordance with the terms of the Lease Deed

executed between the parties, which is in the statutory form

prescribed under the said Regulations. As such, the same cannot be

waived.

34. The learned Senior Counsel for Respondents further submits

that, by filing the present Writ Petition, the Petitioner is in effect

seeking to challenge the contractual stipulations contained in the

Lease Deed without challenging the statutory provisions governing

the same, which is impermissible in law. It is submitted that once

the Petitioner has entered into the Lease Deed with full knowledge

and understanding of the terms and conditions contained therein, it

would be bound by the conditions contained in the Lease Deed.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

Therefore, the Petitioner cannot now resile from its contractual

obligations.

35. The learned Senior Counsel further submits that, under the

terms of the Lease Deed, extension of time for completion of

construction can be granted, only upon payment of additional

premium at the prescribed rates and therefore the demand raised

by Respondent No.1 cannot be said to be arbitrary or illegal. To sum

up his arguments, the learned senior counsel has submitted that it

is not a case of violation of the fundamental rights of the Petitioner

and therefore, it is not entitled to any relief in exercise of

discretionary jurisdiction of this Court under Article 226 of the

Constitution of India. As such, the Writ Petition deserves to be

dismissed.

36. In support of his above arguments, Mr Samdani has relied

upon he following decisions:-

(a) Bank of Baroda, Mumbai & Anr vs. Mumbai Metropolitan Regional Development Authority & Ors.2

(b) Assistant Excise Commissioner & Ors. vs. Issac Peter & Ors.3

2 2010 (3) Mh. L.J. 3 (1994) 4 SCC 104.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

(c) State of UP & Ors. vs. Chaudhari Ran Beer Singh,4

(d) Goetze (India) Ltd. vs. Employees State Insurance Corporation5

(e) Transmission Corporation of Andhra Pradesh Ltd. & Anr. Vs. Sai Renewable Power Pvt. Ltd. & Ors.6

(f) Banda Development Authority, Banda vs. Motilal Agarwal & Ors.7

(g) Punjab Financial Corporation vs. Surya Auto Industires8

(h) Joshi Technologies International IBC vs. U.O.I. & Ors.9

(i) The Godhra Electricity Co. Ltd. & Anr. vs. The State of Gujrat & Anr10

(j) Dhanraj vs. Vikram Singh & Ors.11

(k) Dalip Singh vs. State of U.P & Ors.12

Plea regarding Maintainability of the Writ Petition :-

37. Insofar as the plea of the maintainability of the Writ Petition

is concerned, at the very outset, it deserves to be mentioned herein

that although the maintainability of the Writ Petition has been

questioned inter-alia on the ground that several disputed questions

4 (2008) 5 SCC 550.

5 (2008) 8 SCC 705.

6 (2011) 11 SCC 34.

7 (2011) 5 SCC 394.

8 (2010) 1 SCC 297.

9 (2015) 7 SCC 728.

10 (1975) 1 SCC 199.

11 2023 SCC OnLine SC 724.

12 (2010) 2 SCC 114.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

of facts are involved there-in, yet, after examining the record, we

find that the material assertions made in the Writ Petition are all

based on documents annexed thereto, which are admitted

documents. Moreover, in view of the plea raised by the Petitioner

that the action of the Respondent No. 1 in levying additional

premium/penalty for the delay in completion of construction is

arbitrary and illegal and hence, violative of the fundamental rights

of the Petitioner guaranteed under Article 14 of the Constitution of

India, we are of the view that the issues raised in the Writ Petition

have an element of public law character.

38. In case of Joshi Technologies International IBC vs. U.O.I. &

Ors. (Supra), relied upon by Mr Samdani, the Hon'ble Supreme

Court has observed that there is no absolute bar to the

maintainability of a Writ Petition, even in contractual matters or

where there are disputed questions of fact or even when monitory

claim is raised, provided, the Court is called upon to examine the

issue which has a public law character attached to it. Having regard

to the core controversy involved in this proceeding and considering

the fact that the issues involved in this Writ Petition would call for

determination by this Court based on interpretation of the relevant

Shree Naman Hotels-oswp-3209-2017-J-R.doc

Articles of the Lease Agreement as well as the documents

exchanged by and between the parties so as to ascertain fairness in

the action of the Respondent No 1, we are unable to agree with the

stand of the Respondents that the Writ Petition ought to be

dismissed on the ground that it raises disputed questions of facts.

39. Likewise, from a reading of Section 44 of the MMRDA, Act

1974, we find that the provision for Appeal provided thereunder, is

available for resolving disputes pertaining to recovery of money due

to the authority as arrears of land revenue. Since the challenge

made to the impugned demand notice is on the ground that the

same is contrary to the terms of the Lease Deed, hence, we are of

the opinion that the said controversy cannot be effectively

adjudicated in an Appeal filed under Section 44. Therefore, we

reject the contention of the Respondents that the Petitioner has an

effective and efficacious alternative remedy.

40. We also find that all material facts necessary for dealing with

the controversy have been stated in the Writ Petition. Therefore, the

Writ Petition cannot also be dismissed on account of suppression of

material facts.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

41. In so far as the grounds of delay and laches as well as the

plea of the claim being barred by the Law of Limitations is

concerned, save and except making a bald assertion on such count

the Respondents have failed to mention as to on which date the

cause of action for the petitioner to institute the proceeding had

ceased and on what count.

42. In Banda Development Authority, Banda vs. Motilal Agarwal

& Ors. (Supra), relied upon by Mr Samdani, the Hon'ble Supreme

Court has observed that no limitation has been prescribed for filing

a Writ Petition under Article 226 of the Constitution of India.

However, the High Court will treat the delay in filing the Writ

Petition as unreasonable, if the Writ Petition is filed beyond the

period of limitation prescribed for filing a Civil Suit for similar

cause. From the above, it would be apparent that although

unexplained delay in instituting a Writ Petition could be a valid

ground to decline relief, yet, the law of Limitation would not have

strict application in a Writ Petition.

43. There is no dispute in this case about the fact that the

Respondent No. 1 is an instrumentality of the State and, therefore,

would be an "other authority" within the meaning of Article 12 of

Shree Naman Hotels-oswp-3209-2017-J-R.doc

the Constitution of India. Law is well settled that arbitrariness in

the decision making process of the State or its instrumentality is a

facet of Article 14 of the Constitution of India. In E.P..Royappa v

State of Tamil Nadu,13 it was pointed out that Article 14 would

strike at arbitrariness in State action and ensure fairness and

equality of treatment.

44. The present is not a proceeding simpliciter for enforcing a

money claim but raises significant questions pertaining to the

validity and fairness in the impugned action of the Respondent No

1, which are required to be adjudicated on the touch stone of

Article 14 of the Constitution. As such, we are of the considered

opinion that such pleas cannot be brushed aside merely on the

ground of delay, more so, since such delay has evidently not given

rise to any parallel right of a third party.

45. In view of the fore going discussions, we are of the view that

the Writ Petition is maintainable in law as well as in the facts and

circumstances of the case.

13 (1974) 4 SCC 3.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

46. It would be further pertinent to note herein that in an earlier

decision rendered by a co-ordinate Bench of this Court dated 20 th

November 2019 in Raghuleela Builders Pvt. Limited and Anr. vs.

The Mumbai Metropolitan Regional Development Authority & Ors.

(Supra) wherein, identical issues were involved, this Court had

entertained the Writ Petition. In that case also the Petitioners had

challenged a similar Demand Notice dated 12 th September, 2017

issued by the Respondent No.1 by invoking similar provisions of the

Lease Deed demanding payment of a sum of Rs. 432 Crores as

penalty for the delay in completion of construction of the building.

That was also a case wherein, although the initial built up area was

30550 sq. meters, which was to be consumed by constructing 9

(nine) floors in the building, yet, subsequently, due to the increase

in the FSI, the Respondent No.1 had allotted additional built up

area of 67000 sq. meters to the Petitioner resulting in construction

of 11 additional floors in the same building. Due to the addition of

the built up area, the construction of the building could not be

completed within four years, as stipulated in Article 2(d) of the

original Lease Deed, as a result of which, Demand Notice dated 12 th

September, 2017 was served for recovery of penalty/additional

premium along with interest calculated thereon.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

47. By the Judgment and Order dated 20 th November 2019, in

Raghuleela Builders Pvt. Ltd. & Anr. (Supra), a Division Bench of

this court had set aside the impugned Demand Notice dated 12 th

September 2017 by holding that such a demand was not

maintainable in the eyes of law. That apart, it was also observed

that in view of the change in policy of the MMRDA increasing the

time limit for completion of the building "Fit for occupation", from

four years to six years, the demand for penalty/additional premium

for delay in completion of construction within four years was ex-

facie unreasonable, unjustified and discriminatory.

48. The Special Leave Petition (C) No. 6411 of 2020 preferred by

the Respondent No.1 assailing the Judgment and Order dated 20 th

November 2019 was dismissed by the Hon'ble Supreme Court by

the order dated 27th July 2020 by taking note of the findings

recorded in paragraphs No. 38 and 40 of the Judgment and Order

dated 20th November 2019. However, it was clarified that since the

judgment of the Division Bench of the Bombay High Court was

rendered in the facts of that case, hence, it cannot influence any

other matter in this behalf. With the above observation the Special

Leave Petition was dismissed.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

49. In the order dated 27th July 2020 the Hon'ble Supreme Court,

while dismissing the Special Leave to Appeal (C) No(s) 6411/2020,

had observed as follows:-

"We are not inclined to exercise our jurisdiction under Article 136 of the Constitution of India in the given facts of the case and more so as reflected from paragraphs 38 and 40 of the impugned judgment.

Mr. K. K. Venugopal, learned Attorney General for India expresses some apprehension on account of there being other matters pending.

We clarify that the present matter is in the given facts of the case as stated aforesaid and thus, cannot be said to influence any other matter in this behalf.

The special leave petition is dismissed in terms aforesaid. Pending applications shall also stand disposed of."

50. It appears that the Respondent No. 1 had filed a Review

Petition seeking review of the order dated 27 th July 2020, which

was also dismissed by the Hon'ble Supreme Court vide order dated

29th September 2020 passed in Review Petition (Civil) No. 1764 of

2020 arising out of SLP (C) No. 6411 of 2020.

51. In the order dated 27th July 2020, the Hon'ble Supreme

Court had no doubt observed that the decision in Raghuleela

Builders Pvt. Ltd. & Anr. (Supra) was in the facts of that case.

However, we are of the view that we can take note of the legal

principles, if any, emanating from the said decision. In Raghuleela

Shree Naman Hotels-oswp-3209-2017-J-R.doc

Builders Pvt. Ltd. & Anr this court has entertained a similar Writ

Petition seeking identical reliefs.

52. The the question of maintainability of a Writ Petition is a

mixed question of law and facts. Therefore, such question would

obviously have to be considered having due regard to the peculiar

facts and circumstances of each case. Having regard to the facts and

circumstances of this case and considering the fact that a similar

Writ Petition, raising similar issues in Raghuleela Builders Pvt. Ltd.

& Anr. (Supra) had earlier been entertained by this Court, hence,

for the sake of maintaining uniformity in judicial decision, we are

not inclined to non-suit the Petitioner merely on the plea of

maintainability as raised by the Respondents.

On Merit :-

53. At the very out set it must be noted here-in that as per Article

2(d) of the Lease Deed, the lessee is required to complete the

construction within four years from the date of execution of the

Lease deed. However, Article 2 (c) of the Lease Deed makes it clear

that no work shall commence or be carried out contrary to the

Development Control Regulations and the Building Regulations

Shree Naman Hotels-oswp-3209-2017-J-R.doc

applicable to the plot of land and until the plans, elevations,

sections, specifications and details shall have been approved.

Therefore, in view of Article 2(c), the construction of the building

cannot commence until the receipt of all statutory approvals

including the approval of building plan etc. Article 2(a) of the Lease

Deed mentions that the lessee shall within three months submit

plans etc for approval. However, there is no condition in the Lease

Deed laying down and time line for granting of such approval by

the authority.

54. In a construction of this nature, permission of multiple

statutory authorities including the Municipal Corporation, Fire

department, Environment clearance, height clearance etc. will be

necessary, without which the Commencement Certificate cannot be

issued. Unless the Commencement Certificate is issued by the

Authority, the construction work also cannot commence. These

statutory authorities are not bound by the terms and conditions of

the Lease Agreement. Notwithstanding the same, the Lease

Agreement is completely silent as to who will be responsible in case

of delay in granting approval by these statutory authorities coming

Shree Naman Hotels-oswp-3209-2017-J-R.doc

in the way of early commencement and completion of the

construction.

55. Not only that, the Lease Deed is also silent as to what would

be the effect on the time line of four years for completion of the

construction as laid down in Article (d), in case, there is delay in

granting of statutory approvals. If there is delay in granting

permissions/ approval by the statutory authorities for any reason

whatsoever, leading to delay in commencement of construction,

then in that event, the Lessee will be left with no option to

complete the construction within the stipulated time. Yet, as per

Article 2(d), as interpreted by the Respondent No 1, the lessee

would still be liable to pay penalty for the delay in completing the

construction beyond the period of four years from the date of

execution of the Lease Deed. Viewed from that perspective, Article

2(d) of the lease deed appears to be ex-facie unfair, unreasonable

and hence, unconscionable. However, since the Articles of the Lease

Deed are not under challenge, hence, the said aspect of the matter

need not detain this Court.

56. After hearing the arguments of both the sides and on

examining the materials brought on record, we are of the

Shree Naman Hotels-oswp-3209-2017-J-R.doc

considered opinion that the core controversy involved in this

proceeding would be pertaining to the issue as to whether or not,

the insistence/demand for additional premium/penalty made by

the Respondent No. 1 on the ground of delay in completing the

construction of the building beyond the period of four years from

the date of execution of the Lease Deed was in accordance with law

? To answer the said question, it would be necessary for this Court

to refer to Articles 2(d) and 2(e) of the Lease Deed dated 9 th June

2006, which are reproduced hereinbelow for ready reference:-

"2. The Lessee hereby agrees to observe and perform the following conditions that is to say:

(d) Time limits for commencement and completion of construction work: That the Lessee shall within three months from the receipt of approval of his plans and specifications of building or buildings intended to be erected on the land, commence and within a period of four years from the date of this lease at his own expense and in a substantial and workman-

like manner and with the sound materials and in compliance with the said Development Control Regulations and Building Regulations and all Municipal Rules, bye-laws and Regulations applicable hereto and in strict accordance with the approved plans, elevations, sections, specifications and details, to the satisfactions of the Metropolitan Commissioner and confirming to the building lines marked on the plan hereto annexed, and the Development Control Regulations and Building Regulations, build and completely finish, fit for occupation a building to be used as building with all requisite drains and other proper convenience thereto.

(e) Extension of time stipulated for construction of building or development of land:

Shree Naman Hotels-oswp-3209-2017-J-R.doc

(i) If the Lessee shall not perform and observe the limitations of the time mentioned in clause 2(d) above for construction of the intended building or otherwise development of land leased to him for reasons beyond his control, the Metropolitan Commissioner may permit extension of such time on payment of additional premium at the following rates:

Up to 1 year ______ 25 percent of the premium Between 1 and 2 years ______ 35 percent of the premium Between 2 and 3 years ______ 40 percent of the premium

(ii) If the Metropolitan Commissioner shall refuse to permit such extension of time or shall find the Lessee of having committed breach of any condition or covenant during limitation of time mentioned in clause 2(d) hereinbefore, the Metropolitan Commissioner may forfeit and determine the Lease; provided that in the event of such determination of lease 25 percent of the premium paid by the Lessee to the Lessor shall stand forfeited and the remaining 75 percent of such premium shall be refunded to him; provided further that the power to so determine the Lease shall not be exercised unless and until the Metropolitan Commissioner shall have given to the Lessee or left on some part of the demised premises a notice in writing of his intention to do so and of specific breach of the covenant or condition in respect of which forfeiture is intended and default shall have been made by the Lessee in remedying such breach within three months from the service of a notice on him on the notice being left on the demised premises."

57. As has been noted hereinabove, after the execution of the

Lease Deed on 9th June,2006, physical possession of the plot of land

was handed over by the Respondent No. 1 to SNDL on 13 th June

2006. On 1st August, 2006, SNDL had assigned its rights over the

plot in favour of the Petitioner. On 25 th August,2006, the Petitioner

had applied for height clearance from the Ministry of Civil

Aviation , requesting for increase in the height of the building from

Shree Naman Hotels-oswp-3209-2017-J-R.doc

56.27 mtrs. to 90 mtrs. so as to consume the full FSI. In the

meantime notification dated 14th September,2006 came to be issued

by the Ministry of Environment and Forest laying down that

Environment Impact Assessment (EIA) would be required for such

projects. On 3rd October,2010, the Petitioner had applied for

permission to start excavation but the same was declined on the

ground that Environment Clearance will be necessary. Accordingly,

the Petitioner had applied for EIA which was received on 3 rd

February 2007. Thereafter, the Petitioner had applied for

permission to start excavation and shoring work which was granted

by the Respondent No. 1 on 8th March 2007. Therefore, until 8th

March, 2007, there was no scope for the Petitioner to commence

even the excavation work.

58. It would be significant to note herein that on 20 th March

2007, additional FSI was granted to the Petitioner on payment of

sum of Rs. 1,99,56,035/-. Thereafter, Commencement Certificate

for the work up to the plinth level was issued on 29 th October 2007.

While the aforesaid process was underway, on 18 th November 2008,

the Respondent No. 1 had offered additional built-up area to the

Shree Naman Hotels-oswp-3209-2017-J-R.doc

Petitioner. However, no time limit was laid down for completing the

construction with the additional FSI.

59. On 31st December 2008, the Petitioner paid a sum of Rs.

6,22,34,818/- for 1,849.46 sq. mtrs of additional BUA (lobby/stair

case free of FSI) and on 18 th March 2009, Commencement

Certificate (CC) for two level basement+ground+12 upper floors

was received.

60. From the above facts, it would be evident that although the

Lease Deed was executed on 9 th June 2006 containing the

stipulation in the form of Article 2(d) making it mandatory for the

Lessee to complete the construction of the building within four

years from execution of the Lease Deed, i.e., 9 th June 2006, yet, the

CC for the entire building was issued only on 18 th March 2009, i.e.,

nearly after two years and nine months since the date of execution

of the Lease Deed thereby, leaving a period of barely one year and

three months for the Petitioner to complete the construction. In a

construction of a high rise building of this nature containing 13

floors, it would be wholly inconceivable for any Lessee to

commence and complete the construction of the building within a

period of one year and three months.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

61. In the above context, it would be further pertinent to note

herein that on 1st July 2010, the Petitioner had paid a sum of

Rs.5,96,61,133/- as premium for the additional lobby and passage

area free from FSI. Thereafter, the final CC for two level

basement+ground+13 floors, as per the amended plan, was

received by the Petitioner on 15th October 2009 and 7th July 2010.

62. It is the undisputed position of fact that the Petitioner had

completed the construction of the building upto the 13 th floors on

14th June 2011, which fact has also been duly acknowledged in the

Completion Certificate dated 17th June 2011 issued by the Chief

Town and Country Planning Division of Respondent No. 1.

Notwithstanding the same, the formal request made by the

Petitioner by the letter dated 29th September 2011 for issuance of

Occupation Certificate was not acted upon apparently on the

ground that the Petitioner had failed to pay the proposed penalty

due to the delay in completion of construction of the building.

63. At this stage, it would be significant to note herein that

although the Respondents had demanded additional

premium/penalty due to the alleged delay in completing the

construction of the building within four years from the date of

Shree Naman Hotels-oswp-3209-2017-J-R.doc

execution of the Lease Deed i.e. within 8th June, 2010, yet, until

12th October 2011,no formal demand for payment of the additional

premium/penalty was raised by the Respondent No. 1.

64. In the above context, it would be further pertinent to

mention herein that apparently on being demand by the

Respondent No. 1, on 3rd October 2011, the Petitioner had

submitted a Notarized undertaking to the Respondent No. 1 not to

commence operation of the hotel until the payment of additional

premium is made. Upon receipt of the said undertaking, the Chief

of the Town & Country Planning Division of the Respondent No. 1,

had addressed a letter on 11th October 2011 informing the

Petitioner about the issuance of the Occupation Certificate for two

level basement+ground+13 upper floors for the Five Star category

hotel on land bearing No. C-57 and C-58 (combined) in 'G' Block in

BKC. The Occupation Certificate had, however, clearly mentioned in

Clause-11 that the Applicant, i.e., the Petitioner shall not commence

operation of the hotel until the payment of additional premium

towards extension of time for completion of construction, as per the

provisions of the lease Deed, is made to the MMRDA, as assured by

the communication dated 3rd October, 2011.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

65. As has been noted herein above, the formal request for

payment of additional premium/penalty was made by the

Respondent No. 1 for the first time, by addressing the letter dated

12th October 2011 to the director of Shree Naman Hotels Pvt. Ltd.

The letter dated 12th October 2011 was followed up by the

communications dated 1st September 2014 and 23rd April 2015

thus, renewing the demand for payment of outstanding dues along

with interest, on the additional premium/penalty. Such demand

had culminated in the Notice dated 12 th September 2017,the

contents whereof are reproduced herein below for ready

reference:-

EXHIBIT = 'P' MUMBAI METROPOLITAN REGION DEVELOPMENT AUTHORITY _________________________________________________________ No.LEC/BKC (G)/SNDL(C-57 & 58)/179/2017 Date: 12th September 2017 NOTICE WHEREAS the Mumbai Metropolitan Region Development Authority issued a Show Cause Notice dated 22/08/2014 for non- payment of requisite dues and non-performance of the Lease Deed conditions as stated therein.

WHEREAS you have submitted your say along with explanation vide your letter dated 19/09/2014 & 22/09/2014.

WHEREAS your representation/explanation is examined thoroughly and no merit was found in the submission/ explanation given by you.

AND WHEREAS the explanation submitted vide your letter 19/09/2014 & 22/09/2014 dated with reference to the Show Cause Notice is unsatisfactory and hence was summarily rejected vide our letter dated 23/12/2014.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

WHEREAS you were instructed to pay the outstanding dues as stated in the Notice under reference within a period of 30 days. However, till date you did not pay the requisite dues to MMRDA and thus failed to comply with your obligations.

AND WHEREAS the amount due to the Authority along with the interest due thereon is as shown in the statement annexed hereto as Annexure. An amount due to Authority is un-paid till date & thus you have therefore committed breach of the terms and conditions of the said Deed of Lease and therefore, the Authority has power to recover the said due amount as stated hereinbefore as arrears of land revenue and also resume the said land as per the Article 5 and 6 of the said Deed of Lease.

NOW THEREFORE, in exercise of the powers conferred by Articles 5 and 6 of the said Deed of Lease, I, the Dy. Metropolitan Commissioner for and on behalf of the Metropolitan Commissioner of the Authority hereby call upon you to remedy or cause to be remedied within 30 days from the date of this notice. Please take further notice that in the event of the default to comply with this requisition, the Authority will have the right to determine the Lease and enter upon the premises and proceed further to recover the due amount stated hereinbefore as arrears of land revenue."

Sd/-

(A.R. Wankhade) Dy. Metropolitan Commissioner, M.M.R.D.A. To, The Director, Shree Naman Hotels Pvt. Ltdl, Naman Centre, Plot No. C-31-32, G-Block, Bandra-Kurla Complex, Bandra (East), Mumbai - 400 051.

66. From the facts alluded to hereinabove, it is evident that after

the allotment of the additional built-up area, two additional floors

in the form of 12th and 13th floors, besides other common area

spaces, were added to the built-up area originally sanctioned by the

Respondent No. 1. Such addition in the built-up area did not come

Shree Naman Hotels-oswp-3209-2017-J-R.doc

with any time limit for completing the construction nor was it a

part of the original Lease Deed dated 9th June,2006.

67. It is axiomatic that with the allotment of additional built up

area, there would be fundamental changes in the drawings and

building plan, which would require fresh approval followed by

issuance of Commencement Certificate. Therefore, even as per the

terms of the Lease Agreement, it would not permissible for the

lessee to commence construction of the building without obtaining

such approvals. Under such circumstances, it is apparent that due

to allotment of additional built up area, it would no longer be

feasible for the Lessee to stick to the original time line for

completion of the construction as contemplated by Article 2(d) of

the Lease Deed dated 9 th June 2006. Notwithstanding the same, the

Respondent No.1 had applied pressure on the Petitioner to extract

additional monetary benefits from the Petitioner by relying upon

Article 2(d) on the ground of delay in completing the construction.

68. Be that as it may, it is the case of the Petitioner is that there

was no delay in completing the construction beyond the period of

four years. However, even if it is assumed that there was any delay,

the construction was evidently and admittedly completed on 14 th

Shree Naman Hotels-oswp-3209-2017-J-R.doc

June, 2011 i.e. within the period of six years from the date of

execution of the Lease Deed. Therefore, since the MMRDA has

already taken a policy decision to extend the time period for

completing the construction from four years to six years, as such,

in any view of the matter, no penalty would be payable by the

Petitioner on account of delay in completing the construction.

69. It would be significant to note here-in at the cost of repetition

that as per Article 2(a) of the Lease Deed dated 9 th June 2006, no

work can begin until plans are approved and the requirement of

Development Control Regulations and Building Regulations are

met. As per the Development Regulations, Commencement

Certificate can be issued only after all the statutory approvals

including approval of building plan is obtained. Unless

Commencement Certificate is issued, it would not be permissible to

commence construction.

70. In the present case, the first Commencement Certificate upto

to the plinth level was issued only on 29 th October, 2007 i.e. after a

delay of more than 1 year four month from the date of execution of

the Lease Deed. Thereafter, another Commencement Certificate was

issued on 18th March,2009 i.e. after a delay of more than 2 years

Shree Naman Hotels-oswp-3209-2017-J-R.doc

and 9 months. There is nothing on record to show that the

Petitioner was, in any way, responsible for such delay.

71. In a construction of this nature involving issuance of multiple

Commencement Certificates preceded by changes in design lay out

pursuant to allotment of additional built up area allotted by the

Respondent No 1 itself by realizing adequate premium, it would be

highly unfair for the MMRDA to insist on a time line for completion

of the construction based on a clause in the original Lease Deed

which did not contemplate such subsequent developments.

Therefore, demanding payment of penalty for delay in completion

of the construction, without making adequate adjustment in the

time frame, in our opinion, would be wholly arbitrary, irrational,

unreasonable and hence, liable to be declared so by this court.

72. As has been noted above, there is nothing on record to

suggest that there was any delay in completing the construction

due to the negligence on the part of the Lessee i.e. the Petitioner.

On the contrary, it appears that the construction was delayed due to

the delay in issuance of statutory approvals/ permissions including

environmental clearance. As per the terms and conditions of the

Lease Deed, the construction cannot commence without the

Shree Naman Hotels-oswp-3209-2017-J-R.doc

approval of the building plan and issuance of the Commencement

Certificate, which are beyond the control of the lessee. As such, by a

reasonable and harmonious construction of the Articles of the Lease

Deed, we are of the opinion that, save and except in a case where

there is willful negligence on the part of the lessee, the time line of

four years for completing the construction ought to be computed

from the date of issuance of the Commencement Certificate and not

from any prior date. Since the Commencement Certificate in this

case was issued on 29th October, 2007, hence, we are of the opinion

that even under Article 2(d) of the Lease Deed, the period of four

years would, at best, run from the date of issuance of the first

Commencement Certificate, in which case, the Petitioner would be

entitled to time till 28 th October,2011 for completing the

construction.

73. In present case, the construction was admittedly completed

by the Petitioner on 14th June, 2011. Therefore, having regard to

the facts and circumstances of the case, we are of the view that the

condition precedent for invoking the Article 2(d) of the Lease Deed

was not met in this case. As such, viewed from that angle also, in

our opinion, there was no legal justification for the Respondent

Shree Naman Hotels-oswp-3209-2017-J-R.doc

No.1 to insist on additional premium/penalty from the Petitioner

even under Article 2(d) on account of alleged delay in completing

the construction beyond the period of four years.

74. In so far as the undertaking given by the Petitioner to pay the

additional premium/ penalty is concerned, it must be noted herein

that the Writ Petitioner had not only objected to the demand for

payment of additional premium/penalty for the alleged delay in

completing the construction but had also deposited the amount

under protest, thereby categorically conveying that the deposit was

not made voluntarily or in discharge of its contractual obligation.

Such protest was not only raised contemporaneously but the same

was also in writing and unambiguous in nature, thus, putting the

Respondent No. 1 on clear notice that the Petitioner has not

accepted the decision in principle.

75. It also appears from the materials on record that apparently

due to the pressure mounted by the Respondent No. 1 demanding

payment of additional premium/penalty, the Petitioner was

compelled to deposit the penalty as otherwise the Petitioner would

not only be prevented from obtaining the Occupation Certificate

thus, causing serious economical prejudice to its interest but the

Shree Naman Hotels-oswp-3209-2017-J-R.doc

same would also expose the Petitioner to the risk of termination of

the Lease. Since the Petitioner had evidently made the deposit of

penalty under duress and under compelling circumstances, hence,

the principles of waiver, estoppel and acquiescence would not

operate against it in this case. From the protest raised by the

Petitioner, it was apparent that the Petitioner had reserved its right

to agitate the matter at an appropriate time, thus, keeping the

cause alive. Therefore, we hold that Petitioner would be entitled to

claim refund / seek waiver of additional premium/ penalty on

account of alleged delay, if any, in completing the construction.

76. Section 72 of the Indian Contract Act provides that a person

who receives payment made by the payee under coercion must

repay or return the same.

77. In Fatima Khatoon Chowdrain vs. Mahmoed Jan Chowdhury

(1868) 12 Moo Ind App 65, the Privy Council has held that

payment made not voluntarily but under species of compulsion

would be liable to be returned.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

78. In Valpy vs Manley (1845) 1 CP 594, the Court of England &

Wales has held that money paid under the constraint of threats to

interfere with the legal right is sufficient to make it recoverable.

79. In Ram Kishen Singh vs. Dooli Chand (1881) 8 IA 93 before

the Privy Council, it was held that if a person pays money to save

his property which has been wrongly attached in execution, he is

entitled to recover it.

80. Relying upon the case of Ram Kishen Singh (Supra), the

Privy Council in the case of Kanhaya Lal vs The National Bank of

India Limited14 has held that if a payment is made under protest

and involuntarily, under coercion, the party making such payment

would be entitled to claim refund of the same.

81. In the present case, the Petitioner was forced to give an

undertaking to pay the additional premium under the

circumstances, as noted above, created by the Respondent No. 1.

The arbitrary and high handed action of the Respondent No 1 is

further apparent from the fact that although there was no such

condition in the Lease Deed dated 9 th June,2006, yet, as has been

14 1913 SCC Online PC 4.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

mentioned above, the Respondents had demanded 2 suits for 50

nights and conference facility for 20 persons on 20 occasions free of

charge, fee or rent as a condition for issuing the Occupancy

Certificate to the Petitioner. On a pointed query made by this court

as to under what authority, such demand was made by the

Respondents, the learned Senior Counsel for the Respondents could

not give any convincing reply.

82. In view of the foregoing discussion, we are of the considered

opinion that the demand for payment of the penalty/additional

premium was not maintainable under Article 2(d) of the Lease

Deed. Moreover, such amount was demanded/realized by the

Respondent No. 1 without serving any prior Show Cause Notice

upon the Petitioner thus, acting in clear contravention of the

principle of natural justice. Even a proper Demand Notice was not

served upon the Petitioner before realizing the amount. As such, we

hold that not only the demand for additional premium/ penalty, but

even the retention of any part thereof, as might have been

deposited by the Petitioner under protest, was without the

authority under the law.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

83. In the case of Bank of Baroda, Mumbai & Anr (Supra), relied

upon by Mr Samdani, the primary issue was as to whether the

Respondent No. 1 (MMRDA) was bound to charge premium as per

the provisions of the regulation as applicable during the relevant

period because of the fact that the amendment to the regulations

did not show that it had any retrospective effect. In Assistant Excise

Commissioner & Ors. (Supra), it was held that even in a contract

between the parties which is governed by statutory provisions, the

terms and conditions of the contract would be binding both upon

the Government and the Licensee and neither of them can depart

therefrom. It was also not be open to any officer of the Government

either to modify, amend or alter the terms and conditions. In

Chaudhari Ran Beer Singh (Supra), the Hon'ble Supreme Court has

held that in matters of policy decision, the scope of interference by

the Court is extremely limited. In Goetze (India) Ltd. (Supra), the

Hon'ble Supreme Court has held that when the liability to pay the

interest is statutory, there is no power of waiver of the same; in

Transmission Corporation of Andhra Pradesh Ltd. (Supra), the

Hon'ble Supreme Court has held that when the parties have entered

into the field of contract simpliciter, their rights are controlled by

the contracts executed between them. Therefore, in the absence of

Shree Naman Hotels-oswp-3209-2017-J-R.doc

challenge to the contract, it would not be permissible for the Court

to go behind the contact and permit questioning of the statutory

jurisdiction vested in the regulatory commission. However, as

would be apparent from the facts alluded to herein above, it is

apparent that the issues involved in the Writ petition do not involve

any challenge to a particular Clause/Article in the Lease Deed or to

any statutory provision. On the contrary, the core controversy in

this petition is pertaining to the question of application of the terms

and conditions of the Lease Deed to the facts and circumstances of

this case. Therefore, we are of the opinion that the ratio laid down

in the abovenoted decisions relied upon by Mr Samdani would not

be of any assistance to the Respondents in the facts and

circumstances of the present case.

84. Having held as above, we deem it appropriate to reiterate

herein that the learned Counsel for the Petitioner has argued that

the case of the Writ Petitioner is squarely covered by the decision of

this Court in the case of Raghuleela Builders Pvt. Ltd. & Anr .

(Supra). The said assertion has, however, been strongly resisted by

the Respondent's Counsel by submitting that in view of the

observations made by the Hon'ble Supreme Court in the order

Shree Naman Hotels-oswp-3209-2017-J-R.doc

dated 27th July 2020, no reliance can be placed on the said

judgment for any purpose for deciding the present Writ Petition. On

a careful examination of the Judgment rendered in Raghuleela

Builders Pvt. Ltd. & Anr . (Supra) we also find that the said decision

was rendered in the facts of that case. However, one of the issues

raised in the said proceedings was pertaining to the question as to

whether, the decision of the MMRDA to apply the extension of time

from 4 years to 6 years for completing the construction only to the

post August 2015 was valid in the eyes of law, is also an issue raised

in the present proceeding. While answering the said question, it

was held in Raghuleela Builders Pvt. Ltd. & Anr . (Supra), as

follows:-

"38. The MMRDA constituted a single member committee of retired Judge of the Supreme Court to decide whether the MMRDA should give concession in recovery of premium considering the time required for plot owner to obtain permissions from various authorities for construction of building thereon. It is contended that one member committee has concluded that the charging of premium for extension of time for completing construction in Bandra-Kurla Complex area, specifically in case where additional built up area has been allotted by the MMRDA, was illegal. In its 138th meeting held on 26th August 2015, the MMRDA had acknowledged the difficulties faced by the lessees and that the condition of completion of construction within 4 years of the execution of the lease was adversely affecting the tendering process. The MMRDA had appointed an expert one man committee of retired Supreme Court Judge in that regard. The single member committee has advised that the period of 6 to 7 years be granted for completion of construction.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

39. The lease deed entered into by the MMRDA with the lessees are as per form D, prescribed under the MMRDA (Disposal of Lands) Regulations 1977. Clause 2(a) of the lease deed provides that for building plans to be submitted to country and town planing division for approval within 3 months from the date of lease. Clause 2(c) of the lease deed provides that no work is to be carried out until all plans, elevations, specifications are approved by the concerned authorities. Clause 2(d) provides that within 3 months of the approval of plans, the lessee is to commence construction which is to be completed within four years of the lease. Clause 2(e) provided for extension of time. Clause 2(e) contemplates a situation when the time for completion of construction can be extended, parties to the contract contemplated that certain uncertainties or situations may arise which may require more time for completion of the construction. In view of this, time is not essence of the contract between the parties and rightly so since construction of any building in Bandra Kurla Complex, several permissions are required from the various authorities and not only from the MMRDA who is planning authority for the Bandra Kurla area, namely, (1) The environmental clearance under the Environmental Impact Notification from the Ministry of Environment and Forest. (2) Building height clearance from the Ministry of Civil Aviation because of the close proximity to Airport.

          (3)     Clearance from the high rise committee.
          (4)     Permission from the the MCGM.
          (5)     Permission from the traffic police.

Each of these authorities is required to be approached separately since there is no single window clearance / nodal agency which would co-ordinate with the aforesaid authorities for granting of all necessary permissions. In view of the delay in obtaining permissions which are beyond the control of lessee, no work could be carried out as per clause 2(d) of the lease deed.

40. The MMRDA had issued a letter of allotment dated 20th March 2012 allotting additional 67,000 sq. meters at consideration of 984 crore. Part payment of Rs.196 crore was received on 20th March 2012. The supplementary lease deed was executed for additional built up area of 67,000 sq. meters. The letter of allotment dated 20th March 2012, the acceptance of part payment of consideration for additional built up area allotted, diluted the time period of four years and there was no question of application of condition of occupation certificate for built up area

Shree Naman Hotels-oswp-3209-2017-J-R.doc

within 4 years when additional built up area was allotted for raising additional 11 floors on the same building.

41. The resolution passed by MMRDA for extending the time period for completing construction from 4 years to 6 years only for leases executed after 26th August 2015 also appears to be arbitrary, discriminatory, without basis and justification. The said set of circumstances are prevailing for the construction being carried out under the leases executed prior to 26th August 2015.

Therefore, not extending this benefit of this extension of time from 4 years to 6 years to the prior leases in respect of other plots in the BKC, is completely arbitrary, discriminatory, capricious and violative of Article 14 of the Constitution of India. There is no reasonable basis or justification for this decision. The classification sought to be made between the leases prior and subsequent to 26th August 2015 is not founded on intelligible differentia and neither does this differentia has any logic, rational, nexus to the object sought to be achieved. The MMRDA has sought to treat equals as unequal. The lessees of plots are being discriminated on the basis of their date of execution of their leases. The lessees who are placed in similar circumstances prevailing for construction in Bandra Kurla area are entitled to equal treatment guaranteed under Article 14 of the Constitution of India."

85. It is not in dispute that the Lease Deed involved in

Raghuleela Builders Pvt. Ltd. & Anr . (Supra) was also in Form 'D' of

the Regulations of 1977 wherein the same Articles 2 (d) and (e)

were involved. The Writ Petitioner there-in was also a similarly

situated lessee from whom penalty for delay in completing the

construction beyond the period of 4 years was raised by the

Respondent No 1. The Petitioner in that case had also raised

identical plea as regards the applicability of the time extension

Clause. The Lease Deed in that case was also executed prior to 26 th

August, 2015. If that be so there can be no doubt about the fact

Shree Naman Hotels-oswp-3209-2017-J-R.doc

that the legal principles discussed and the findings & observations

recorded in paragraphs 38 and 41 of Raghuleela Builders, in so far

as applicability of the 6 years time extension clause is concerned,

would be squarely applicable to the facts of the present case.

Therefore, the Respondent No. 1 would be duty-bound to extend

the benefit of extension of time for completion of construction upto

six years to the present Petitioner as well.

86. In the facts and circumstances of this case, we are also of the

opinion that there is no legal justification for the Respondent No. 1

to confine the benefit of the time extension clause only to those

Lease Agreements which were executed after 26 th August 2015 as

such an approach would be highly arbitrary and discriminatory in

nature. Therefore, having regard to the peculiar facts and

circumstances of this case, we do not find any justifiable ground to

take a different view on the aforesaid issue.

87. Law is well settled that for maintaining judicial discipline and

propriety, a decision rendered by a Coordinate Bench on the same

issue must be respected and followed by a Coordinate Bench. In the

case of Mary Pushpam vs. Televi Curusumary & Ors. 15 the Hon'ble

15 (2024) 1 SCR 11.

Shree Naman Hotels-oswp-3209-2017-J-R.doc

Supreme Court has observed that when a decision of a Coordinate

Bench of the same High Court is brought to the notice of the Bench,

it is to be respected and would be binding, subject to the right of

the Bench of such co-equal forum to take a different view and refer

the question to a larger Bench. In other words, any decision of a

Coordinate Bench would be binding on a Bench of equal strength

subject to the condition that if a different view is sought to be

adopted then the matter would have to be referred to a larger

Bench.

88. The above legal principle has taken a firm footing in the

Indian Jurisprudence by a long line of judicial pronouncements. We

do not deem it necessary to burden this judgment by referring to all

those decisions. However, suffice it to mention that unless there are

justifiable grounds to take a different view in the matter warranting

reference to a larger Bench, the previous decision of a coordinate

Bench would be binding on a Bench of equal strength.

89. Consequently, it is held that even as per Article 2(d) of the

Lease Deed dated 9th June 2006, the Writ Petitioner would be

entitled to six years time for completion of the construction with

effect from the date of execution of the Lease Deed, i.e., upto 8 th

Shree Naman Hotels-oswp-3209-2017-J-R.doc

June 2012. Since the construction of the Hotel building was

admittedly completed on 14th June 2011, i.e. within six years

hence, even as per Article 2(d) no penalty would be payable by the

Petitioner on account of delay in completing the construction.

90. For the reasons stated above, we hold that the Demand

Notice dated 12th September 2017, demanding additional

premium/ penalty from the Petitioner, is illegal and without the

authority of law. The same is accordingly set aside.

91. This Writ Petition, therefore, succeeds and the same is hereby

allowed in terms of payer clause (A).

92. It appears from the statement annexed to the Demand Notice

dated 12th September 2017 that the Petitioner has already

deposited a total amount of Rs.8,93,92,318/- together with

interest, as additional premium/penalty due to delay in completion

of the construction. The Respondent No. 1 is, therefore, directed to

verify and refund the entire amount deposited by the Petitioner, as

additional premium/penalty, within a period of 90 (ninety) days

from the date of receipt of the Certified Copy of this order, failing

which, the amount would carry interest at the same rate at which

Shree Naman Hotels-oswp-3209-2017-J-R.doc

interest was payable by the Petitioner under the Lease Agreement

due to delay in paying premium, to be calculated on the above

amount from the date of this order till the date of the refund.

93. With the above observations, the Rule is made absolute.

94. The Writ Petition stands disposed of.

95. Parties to bear their own costs.

(SUMAN SHYAM, J)                                             (CHIEF JUSTICE)








 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter