Citation : 2026 Latest Caselaw 3523 Bom
Judgement Date : 8 April, 2026
2026:BHC-OS:8696
Judgement-CARBP(L)-473-2025-F.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Digitally
signed by
ORDINARY ORIGINAL CIVIL JURISDICTION
CHAITANYA
CHAITANYA ASHOK
ASHOK JADHAV
JADHAV Date:
2026.04.08
19:34:43
IN ITS COMMERCIAL DIVISION
+0530
COMMERCIAL ARBITRATION PETITION (L) NO. 473 OF 2025
Doha Marine Services W.L.L. ...Petitioner
Versus
Adsun Offshore Diving Contractors Pvt. Ltd. ...Respondent
Mr. Prathamesh Kamat a/w Adv. Kayush Zaiwalla, Adv.
Devesh Dange i/b Adil Patel, for the Petitioner.
Mr. Ashwin Shankar a/w Ramjay Narayan, for the Respondent.
CORAM : SOMASEKHAR SUNDARESAN, J.
RESERVED ON: APRIL 2, 2026
PRONOUNCED ON: APRIL 8, 2026
JUDGEMENT :
Context and Factual Background:
1. This is a Petition filed under Part II of the Arbitration and
Conciliation Act, 1996 ("the Act"), seeking recognition of three Arbitral
Awards in connection with a Charterparty Agreement dated October 7,
2021 ("Agreement"), executed between the Petitioner, Doha Marine
Services W.L.L. ("Owners"), a company incorporated under the laws
of Qatar, and the Respondent, Adsun Offshore Diving Contractors Pvt.
Ltd., an Indian Company ("Charterer").
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
2. The Agreement was executed in connection with the hiring of
MV Topaz Rayyan ("Vessel"). The Charter was for a period of 15 days,
which was amenable to extension from time to time. Disputes and
differences arose between the parties, which led to arbitration being
initiated by the Owners on July 14, 2022. The Learned Sole Arbitrator
came to be appointed on August 15, 2022, to conduct the arbitration in
accordance with the Dispute Resolution Clause in the Agreement.
3. The Owner made a claim for recovery of the hire (charges for
hire of the Vessel) and after one round of submissions, neither party
appears to have had any grievance about the conduct of the arbitration
on a "documents-only basis".
4. The Owners made a claim for sum of USD 439,036.98
towards hire, equipment, material and services and damages; and USD
29,205 for sums invoiced for storage, transport and other charges
relating to the Charterer's equipment, which had been held by the
Owners under lien, on the premise that the hire remained unpaid, along
with interest and costs.
5. The Charterer lodged a counterclaim seeking damages on the
premise that the Owners wrongfully exercised a lien over the equipment
used by the Charterer on the Vessel, including rental payments incurred
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
by the Charterer on such equipment and its replacement value,
amounting to USD 637,000; damages for loss of charter hire in the sum
of USD 661,770; and along with interest and costs.
6. Pursuant to the Agreement, the Vessel is said to have been
delivered for service to the Charterer on October 22, 2021, and the
Charterer placed diving equipment on board the Vessel including setting
up a decompression chamber for the divers. The charter was for a period
of 15 days, and there was an optional standby period of 5 days and two
agreed extensions of seven days each.
7. On November 24, 2021, the Owners purported to suspend
performance under Clause 12 of the Agreement on the ground of non-
payment of hire and exercised a lien over the equipment placed on
board in terms of Clause 19 of the Agreement. There is a dispute
between the parties as to whether the Vessel was re-delivered on
November 25, 2021, as claimed by the Charterer or whether such re-
delivery took place only on December 5, 2021 as claimed by the Owners.
8. The Agreement is governed by the English Law. The Owners
claim that under English Law, the Charterer may only claim a set-off or
make a deduction from the hire payable to the Owners, in respect of
damages claim, when the breach on the part of the Owners as alleged,
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
has deprived the Charterer of the use, or effective use of the Vessel. The
Owners would claim that no other deduction can be made in terms of
the position under English Law, including the Judgements of the
English Courts in the Kostas Melas1 and Boskalis Offshore2.
9. The Owners' contention was that any identifiable issue
entitling the Charterer to withhold payment would need to be notified
promptly in the agreed time period and no deductions can be made
from the sums claimed at a later stage as per Clause 12(e) of the
Agreement. The Charterer was said to have signed the off-hire certificate
("Off-hire Certificate") confirming that the Vessel was off-hire on
December 5, 2021. The Owners deny that there is any basis to withhold
payments of hire on the contention that the certificate in question was
fabricated or was dishonestly procured. They would also claim that even
if the certificate dated December 5, 2021 was not to be relied upon, in
fact, the Vessel was re-delivered to the Owners on that very date.
Therefore, the Owners would claim that the Learned Arbitral Tribunal
should declare that the amount payable towards the hire in the sum of
USD 266,042.64 is due and a partial award in that sum was sought as an
alternative prayer.
1 The Kostas Melas [1981] 1 Lloyd's Rep 18 2 Boskalis Offshore Marine v. Atlantic Marine and Aviation, The Atlantic Tonger, [2019] EWHC 1213 (Comm)
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
10. The various deductions made by the Charterer towards
internet charges, additional crew requests, consumables and catering
were said to be untenable, and that there was no entitlement to claim a
set off or effect any deductions from the hire payable to the Owners.
11. The Charterer contended that the total sum admitted and
payable to the Owners was USD 266,042.64 and that the various
deductions sought to be made were not legitimate and various specific
invoices were either not payable at all or payable only at a future date, or
for that matter were invalid (for example invoices in respect of a lien
exercised over the Charterer's equipment which was assailed as illegal).
12. The most important contention raised by the Charterer,
which also forms the subject matter of the core objection tabled by the
Charterer in this Court, is the manner in which the Learned Arbitral
Tribunal dealt with the Charterer's entitlement under Clause 12(e) of the
Agreement. The law declared in Boskalis Offshore was also
contended to be inapplicable inasmuch as the invoices covered in that
case were issued and payable in arrears rather than being issued and
payable in advance, which is contrary to what is stipulated in the
Agreement. The absence of a due date set out in the invoices in question
was also said to confirm that the invoices were payable in advance,
which resulted in Clause 12(e) becoming inoperable and thereby
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
inapplicable. Therefore, it was contended by the Charterer that the
Charterer's cash flow must be considered by the Learned Arbitral
Tribunal and set off as an equitable remedy, as would be customary,
must be recognized.
13. The Learned Arbitral Tribunal delivered three awards, which
are collectively referred to as the "Subject Awards" - first, a Final
Partial Arbitration Award dated September 19, 2023; second, an Award
of Costs dated April 23, 2024; and third, a Second Award on Costs dated
August 7, 2024.
Contentions of the Parties:
14. The core challenge mounted by Mr. Ashwin Shankar,
Learned Advocate for the Charterer, while tabling objections for the
purposes of Section 48 of the Act, is that the Learned Arbitral Tribunal
has simply not dealt with the contentions of the Charterer in relation to
Clause 12(e) of the Agreement. This is said to result in an infirmity by
way of a violation of the principles of natural justice, rendering the
Subject Awards contrary to the public policy of India within the
meaning of Section 48(2)(b) of the Act. At the threshold, it would be
appropriate to extract Section 48(2)(b) of the Act:
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
48. Conditions for enforcement of foreign awards.--
(1) Enforcement of a foreign award may be refused, at the request of the party against whom it is invoked, only if that party furnishes to the court proof that--
(a) *****
(b) the party against whom the award is invoked was not given proper
notice of the appointment of the arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
(c) to (e) *****
(2) Enforcement of an arbitral award may also be refused if the Court finds that--
(a) *****
(b) the enforcement of the award would be contrary to the public policy of
India.
Explanation 1.-- For the avoidance of any doubt, it is clarified that an
award is in conflict with the public policy of India, only if,--
(i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81; or
(ii) it is in contravention with the fundamental policy of Indian law; or
(iii) it is in conflict with the most basic notions of morality or justice.
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
Explanation 2.-- For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on the merits of the dispute.
[Emphasis Supplied]
15. Mr. Shankar would submit that the Charterer was entitled to
the right of setting off the amounts due to it or demonstrably not
payable by it, from the hire claimed by the Owners. He would submit
that the Owners illegally exercised a lien over equipment that was kept
on board the Vessel. Such equipment was stated to be owned by third
parties, namely Adsun Middle East FZE and Usha Trading and Offshore
LLC. Therefore, the Charterer had to suffer serious damages by
incurring further lease rentals on such equipment, and by the
equipment allegedly having been reduced to scrap value, thereby
resulting in the Charterer incurring replacement costs.
16. The consequential counterclaim mounted by the Charterer
against the Owners in respect of the wrongful exercise of lien is
quantified at approximately USD 1.2 million. It is contended that the
same could not be adjudicated because of the insistence by the Learned
Arbitral Tribunal on a deposit of approximately Rs. 2 crores, which the
Charterer could not furnish, thereby allegedly imposing an
unreasonable condition on the Charterer and depriving it of a fair
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
consideration of the counterclaim, resulting in an imbalance in the
assessment of the amounts awarded.
17. The core contention of Mr. Shankar is that Clause 12(e) of the
Agreement explicitly provides for payment in advance. The covering
sheet of the Agreement, under Box 22 and Box 24, required the hire to
be invoiced in advance with payment being due prior to the
commencement of each seven-day hiring block. Therefore, the
framework for disputing an invoice, paying the undisputed portion and
withholding the disputed portion pending resolution, as envisaged in
Clause 12(e), was unworkable, and therefore business efficacy ought to
have been accorded to Clause 12(e) so as to provide a reasonable and
equitable interpretation of its substance.
18. Therefore, there could never have been any contemporaneous
set-off or deduction. The Learned Arbitral Tribunal has held that the
Charterer did not raise objections within the deadline for raising
objections. However, since under the Agreement, invoices were to be
raised and paid in advance of the hire, there was no question of being
able to raise objections before the payment was due.
19. The key contention by Mr. Shankar is that the Subject
Awards entirely failed to consider the material submissions made by the
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
Charterer on the proper operation of Clause 12(e). Towards this end,
substantive objections were filed by the Charterer vide email dated
August 1, 2023, which were dealt with by the Owners on August 15,
2023. Mr. Shankar would submit that in a documents-only arbitration,
an Arbitral Tribunal has to discharge a higher standard of reasoning,
and it is incumbent upon the Arbitral Tribunal to render reasoned
findings on each material argument advanced in the written
submissions. Any failure to do so would go beyond procedural
irregularity and would constitute a fundamental denial of the
opportunity of being heard.
20. Mr. Shankar would also assail the reliance by the Learned
Arbitral Tribunal on Boskalis Offshore to submit that this was a case
where invoices were issued 14 days in arrears and payment fell due 21
days thereafter. He would submit that the Learned Arbitral Tribunal
had simply concluded that the Charterer had not challenged the invoices
within the due date as stipulated under Clause 12(e), and therefore,
failed to address the Charterer's submission that the invoices contained
no due date and that Clause 12(e) would not apply to hire payments
required to be made in advance. Mr. Shankar would submit that the
Charterer's contention that based on business efficacy and commercial
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
common sense, Clause 12(e) ought to have been interpreted with
equitable adjustment has not been addressed.
21. According to Mr. Shankar, the entire line of argument in
relation to Clause 12(e) has been dismissed by a finding that the
payment mechanism under Clause 12(e) would apply regardless of
whether the charges are payable in advance or arrears (Paragraph No.31
of the Final Partial Award) and no reasoning has been provided for the
finding on why Clause 12(e) must be made applicable despite charges
being payable in advance. Such failure, according to Mr. Shankar,
constitutes a clear breach of principles of natural justice and despite the
line of submissions being quite clear, the Learned Arbitral Tribunal has
not engaged with those submissions on a material issue going to the
root of the dispute, thereby resulting in a violation of the Charterer's
right to effectively present its case.
22. On the aforesaid premise, Mr. Shankar would claim that the
Subject Awards fall foul of Section 48(2)(b) of the Act as being contrary
to the public policy of India. The Subject Awards are said to be
unreasoned inasmuch as they deprive the Charterer of the legitimate
expectation of knowing the reasons for rejection of its material
submissions. The Clause 12(e) point is therefore contended as having
remained unadjudicated. In the result, he would submit that the Subject
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
Awards ought to shock the conscience of the Court, and therefore this
Court must refuse recognition and enforcement of the Subject Awards
under Part II of the Act.
23. Mr. Shankar would submit that there are multiple
Judgements from which the Court must draw inspiration as to how to
test the Subject Awards and these would include Judgements of the
Singapore High Court, namely, PT First Media3, Wan Sern Metal4
and Front Row Investment5 and a judgement of the Supreme Court
of the United Kingdom in Dallah Real Estate6. The contention is
that objections can be raised by the Award Debtor in the enforcement
court, even if the Award has not been challenged in the jurisdiction in
which it was rendered. Mr. Shankar would also rely on Vijay Karia7,
which endorses the finding of the Delhi High Court in Campos
Brothers8.
3 PT First Media TBK (formerly known as PT Broadband Multimedia TBK) v. Astro Nusantara International BV and others and another appeal - [2013] SGCA 57. 4 Wan Sern Metal Industries Pte Ltd v. Hua Tian Engineering Pte Ltd. - [2025] SGCA 5 5 Front Row Investment Holdings (Singapore) Pte Ltd v. Daimler South East Asia Pte Ltd - [2010] SGHC 80.
6 Dallah Real Estate and Tourism Co v. Ministry of Religious Affairs of the Government of Pakistan - [2010] 3 WLR 1472 7 Vijay Karia And Others v. Prysmian Cavi E Sistemi SRL And Others - (2020) 11 SCC 1 8 Campos Brothers Farms v. Matru Bhumi Supply Chain Pvt. Limited and Others - 2019 SCC OnLine Del 8350
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
24. In sharp contrast, Mr. Prathamesh Kamat, Learned Advocate
on behalf of the Owners, would submit that paragraphs 29 to 31 of the
Final Partial Award squarely demonstrate the manner in which Clause
12(e) of the Agreement has been dealt with. Mr. Kamat would submit
that not only has the provision been analysed in detail, but also the
Learned Arbitral Tribunal has stated why, according to it, the
contention of the Charterer that it was entitled to withhold monies in
reliance upon that Clause was not justified. Mr. Kamat would submit
that it would be wholly inappropriate to contend that the Final Partial
Award does not contain reasons, since it has fairly dealt with the
submissions made on behalf of the Charterer. While the Learned
Arbitral Tribunal's reasons may not be to the Charterer's liking, by no
stretch can it be contended that the Final Partial Award fails to deal with
the material submissions of the Charterer.
25. Mr. Kamat would rely upon the Judgements of the Supreme
Court in Shri Lal Mahal9 and Vijay Karia, and also point to how
the Supreme Court has rejected, in Vijay Karia, reliance upon some of
the very same judgements now sought to be pressed into service by the
Charterer in these proceedings.
9 Shri Lal Mahal Limited v. Progetto Grano Spa - (2014) 2 SCC 433
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
Analysis and Findings:
26. Against this backdrop, I have examined the material on
record with the assistance of the Learned Advocates for the parties, and
the case law cited by them to support their respective positions.
27. The Learned Arbitral Tribunal has pointed to Section 47 of
the Arbitration Act, 1996, i.e. the Act applicable in United Kingdom
("English Arbitration Act"), and the declaration of the law in
Kostas Melas to point to the authority of the Learned Arbitral
Tribunal to exercise discretion to make a partial and expedited award
for payment of the hire on the grounds that a certain minimum sum is
due and owing. The Learned Arbitral Tribunal found that the Charterer
may indeed seek to rely on any rights enjoyed by them to make
deductions to resist the making of such an award, and the burden to
establish such right and the justification for making deductions or
claiming a set-off lies on the Charterer.
28. Against this backdrop, the Learned Arbitral Tribunal went on
to examine whether the Charterer had established such an entitlement
and whether based on such entitlement, the right to make deductions or
claim an equitable set-off could have been exercised by them. When
one examines the Final Partial Award, it is apparent that the contention
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
of the Charterer, in particular its reliance upon Clause 12(e), has been
expressly noticed by the Learned Arbitral Tribunal. The proposition that
Clause 12(e) could be read down on equitable and commercial common-
sense principles to permit withholding or an equitable set-off has also
been addressed. This has been specifically dealt with in Paragraphs 30
and 31 of the Final Partial Award.
29. The Learned Arbitral Tribunal squarely held that Clause 12(e)
did not justify withholding of these amounts, since, the clause covered
hire, fuel invoices and disbursements, and the payment mechanism
could be made applicable regardless of whether such amounts were
payable in advance or in arrears. The law declared in Boskalis
Offshore was treated as authority for the proposition that unless
invoices were challenged promptly, they were payable. The Learned
Arbitral Tribunal held that the Charterer could always bring a
counterclaim if it later formed a belief that any sums already paid were
not truly payable. The Learned Arbitral Tribunal held that Clause 12(e)
requires due notice of an intention to withhold payment, and that the
Owners had established an indisputable right to the hire and other
charges invoiced in relation to the use of the Vessel prior to November
25, 2021.
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
30. As a matter of fact, the Learned Arbitral Tribunal assessed
the indisputable hire-related charges, holding that the entitlement to
claim amounts under invoices reflecting disbursements incurred during
the undisputed period of the Charter could be recognised. While some
costs spilled over into the period after the alleged re-delivery of the
Vessel, the date of re-delivery remained in dispute. Therefore,
deductions of until November 25, 2021 were considered and the
Learned Arbitral Tribunal held in Paragraph 33, that the Charterer
failed to establish a right to an equitable set-off. No reasonable grounds
had been made for the deductions claimed by the Charterer in respect of
the Charter until November 25, 2021. This date is vital inasmuch as
even according to the Charterer, the re-delivery took place on November
25, 2021. The Owners claim that the re-delivery took place only on
December 05, 2021 and therefore, the Final Partial Award only relates
to the undisputed period of the Charter i.e. until November 25, 2021.
31. The Learned Arbitral Tribunal found that the accrued Charter
hire and other invoiced charges, such as internet charges, mobilisation
charges, additional crew requests, catering and consumables, could be
awarded by way of a Partial Award, since under Clause 24 of the
Agreement these charges were treated as sums payable in the same
manner as hire. It was also noticed that Clause 46 expressly provided
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
that any additional cost of crew would be invoiced on terms similar to
the charter hire, and therefore such charges were intended to be treated
in the same manner as hire payable for the Vessel.
32. The allegation by the Charterer that the Vessel was off-hire
between November 08, 2021 and November 11, 2021 has been positively
rejected on the premise that the Charterer failed to provide reasonable
grounds to indicate how the Charterer was deprived of or prejudiced in
the effective use of the Vessel for this period in order to give rise to an
equitable set off. A deduction from the hire for such period along with a
deduction towards charges for additional crew was held to be not
justified. A broader right of equitable set off based on claim for
damages including rentals and loss of sub charter hire has also been
examined and rejected on the ground that the Charterer failed to show
how the Charterer has been deprived of the use of the Vessel in order to
claim such a set-off.
33. Indeed, the Learned Arbitral Tribunal has held that the
Charterer did not challenge the invoices within the due date under
Clause 12(e), and therefore it was not entitled to withhold payment. This
is the finding that would come in for sharp criticism by Mr. Shankar,
pointing out that under Box 22, the invoices were to be issued and paid
in advance, and that this finding is perverse inasmuch as it did not
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
address the alleged impossibility of challenging invoices before the due
date when such due date preceded the relevant hire period. However,
the Learned Arbitral Tribunal has indeed found that there was no
prompt objection on such charges too.
34. Having examined the contentions and the findings in the
Final Partial Award, to my mind, the reasons which weighed with the
Learned Arbitral Tribunal can be said to be implicitly discernible,
inasmuch as the Learned Arbitral Tribunal noticed the basis on which
any equitable set-off was being claimed. On evidence, the Learned
Arbitral Tribunal has found that the off-hire contention was not valid in
the absence of showing how the Charterer was deprived of use of the
Vessel.
35. The fact that the parties consciously agreed to payment in
advance would also indicate that the parties had consciously agreed that
there would be no occasion for an equitable set-off at the stage of
making a partial award in respect of indisputable amounts. The Learned
Arbitrator also held that a subsequent contention that a certain portion
was not payable could always be raised by way of a counterclaim.
36. Having examined the manner of analysis by the Learned
Arbitral Tribunal, it is noteworthy that the Charterer did not seek oral
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
hearings and acceded to the documents-only approach of the Learned
Arbitral Tribunal. Evidence ought to have been led by the Charterer,
bearing in mind the need to demonstrate the right to a set off. The
findings by the Learned Arbitral Tribunal for the limited purpose of
making the Final Partial Award was necessarily within the domain of
interpretation and appreciation of evidence and rendering findings
thereon.
37. Indeed, the Learned Arbitral Tribunal has noticed a genuine
dispute as to whether the Vessel was re-delivered on November 25, 2021
or December 05, 2021, and has adjusted for it. I am not satisfied that
the manner of analysis is of the order that would shock the conscience of
this Court. The award has also not been challenged in the United
Kingdom, the jurisdiction where it was made and the laws of which
governed the Agreement. The contentions raised at the stage of
recognition of the Subject Awards therefore need to meet the high bar
set in Section 48 of the Act for denial of their recognition as decrees of
this Court.
38. As a matter of findings based on appreciation of evidence, the
Learned Arbitral Tribunal has held that the Owners of hire certificate
did not establish an indisputable right to claiming hire right until
December 05, 2021. This would depend on proving of facts as to
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
whether the Charterer had indeed signed the off-hire certificate. Such
dispute has in fact been left open by the Learned Arbitral Tribunal for
final determination at a later stage. Therefore, all that the Learned
Arbitral Tribunal ruled upon was its assessment of the indisputable
entitlement of the Owners to the hire and the additional charges, and
the consequent making of a Final Partial Award in respect of such
amounts.
39. The Learned Arbitral Tribunal also examined the Owners'
claim for interest at the rate of 1% per month pursuant to Clause 12(e)
and the Box 25 and in the alternate interest under Section 49 of the
English Arbitration Act. The Learned Arbitral Tribunal has relied on
statutory provisions for the interest rate, and has awarded interest at the
rate of 5% per annum, compounded quarterly, from December 12, 2021
until date of payment and realisation.
40. It is apparent that after this stage, the dispute has not been
pursued in respect of the counterclaim. The Owners have not been
awarded costs as claimed and the Learned Arbitral Tribunal has pruned
the claims in its assessment in adjudication, indeed along with interest
at the same rate.
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
41. The law in relation to the scope of review under Part II of the
Act is well settled in a number of Judgements rendered by the Supreme
Court including Renusagar10, Shri Lal Mahal and Vijay Karia.
The challenge mounted on behalf of the Charterer essentially invokes
the provisions of Section 48(2)(b) i.e. that the Foreign Awards that are
contrary to the public policy of India and for this purpose, what is
claimed is denial of natural justice.
42. In Shri Lal Mahal, a three-Judge Benche of the Supreme
Court specifically held that Section 48 of the Act does not give an
opportunity for a "second look" at a foreign award at the stage of
recognition and enforcement and does not permit a review on merits.
Defects such as the Tribunal having taken into consideration
inadmissible evidence or having ignored or rejected binding and
material evidence by itself need not lead to an award not being
recognised on the ground of public policy. On a close examination of
the matter, in this case, it cannot be said that the Learned Arbitral
Tribunal has ignored any vital evidence or factored in inadmissible
evidence. The Learned Arbitral Tribunal has dealt with the contentions
on Clause 12(e) of the Agreement, which may be unpalatable to the
Charterer, but the threshold for denial of recognition has not been met.
10 Renusagar Power Co. Ltd v. General Electric Co., 1994 Supp (1) SCC 644
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
43. Considering the sole reliance on the contention that the
Charterer was prevented from presenting its case effectively on the
ground of principles of natural justice being violated, the extensive
discussion by the Supreme Court in Vijay Karia, extracted below,
gains significance:
"62. This Court's judgment in Sohan Lal Gupta V. Asha Devi Gupta, lays down the ingredients of a fair hearing as follows: (SCC pp. 504-05, para 23) "23. For constituting a reasonable opportunity, the following conditions are required to be observed:
1. Each party must have notice that the hearing is to take place.
2. Each party must have a reasonable opportunity to be present at the hearing, together with his advisers and witnesses.
3. Each party must have the opportunity to be present throughout the hearing.
4. Each party must have a reasonable opportunity to present evidence and argument in support of his own case.
5. Each party must have a reasonable opportunity to test his opponent's case by cross-examination his witnesses, presenting rebutting evidence and addressing oral argument.
6. The hearing must, unless the contrary is expressly agreed, be the occasion on which the parties present the whole of their evidence and argument."
[Emphasis Supplied]
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
44. The contention of the inability to present one's case, as
noticed by the Delhi High Court in Glencore11, was extracted and
endorsed by the Supreme Court in the following terms :
63. A recent Delhi High Court judgment in Glencore International AG v. Dalmia Cement (Bharat) Ltd. [Glencore International AG v.
Dalmia Cement (Bharat) Ltd., 2017 SCC OnLine Del 8932] puts it thus: (SCC OnLine Del paras 25-26)
"25. The inability to present a case as contemplated under Section 48(1)(b) of the Act [which is in pari materia to Article V(1)(b) of the New York Convention] must be such so as to render the proceedings violative of the due process and principles of natural justice. It is rudimentary that for a fair decision each party must have full and equal opportunity to present their respective cases and this includes due notice of proceedings. In the event a party opposing the enforcement of a foreign award is able to present sufficient proof of such infirmity in the arbitral proceedings, the courts may decline to enforce the foreign award.
26. A clear distinction needs to be drawn between cases where a party is unable to present its case, rendering the arbitral award susceptible to challenge as falling foul of the minimal standards of due process/natural justice and cases where the Arbitral Tribunal does not accept the case sought to be set up by a party. The latter case, obviously, does not give
11 Glencore International AG v. Dalmia Cement (Bharat) Limited - 2017 SCC OnLine Del 8932
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
rise to a ground as mentioned in Section 48(1)(b) of the Act, even if the decision of the Arbitral Tribunal is erroneous."
[Emphasis Supplied]
45. Indeed, the Supreme Court had occasion to examine the
authorities cited in Dallah Real Estate and similar judgements
rendered by the Singapore High Court. The very line of reasoning now
sought to be pressed into service by Mr. Shankar was considered by the
Supreme Court and it was held that the approach under Indian law
would not be identical.
46. In view of the aforesaid position in law, having examined the
contentions advanced by Mr. Shankar and the manner of treatment of
the submissions relating to Clause 12(e) by the Learned Arbitral
Tribunal, in my opinion, the Charterer has not made out a reasonable
case for sustaining the objections under Section 48(2)(b) of the Act.
47. The Learned Arbitral Tribunal proceeded on a documents-
only basis with the consent and acquiescence of the parties, including
the Charterer. The Learned Arbitral Tribunal examined the evidence
that was pressed into service by the Charterers and found that even
upon application of Clause 12(e), any entitlement to withhold payment
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
would require a prompt and substantiated objection within the
stipulated timeline.
48. It cannot be overlooked that the Learned Arbitral Tribunal
was concerned with the indisputable component of the claim while
making a Final Partial Award, and in that context considered the fact
that the parties had consciously agreed that invoices would be issued
and payable in advance. In these circumstances, bearing in mind the law
governing the scope of review and the high threshold required to refuse
recognition of foreign awards, the bar for denying recognition of the
Subject Awards as a decree of this Court has not been met.
49. Implicit is the reconciliation of Clause 12(e) with Box 22 and
Box 25 of the Agreement. The Learned Arbitral Tribunal considered
that the parties intended that amounts raised towards hire prior to
November 25, 2021 would remain indisputable. The counterclaim has
admittedly been left open, and it remains entirely open to the Charterer
to pursue the same if it so chooses.
50. In this backdrop, I am not satisfied that a case has been made
out for denial of according recognition to the Subject Awards under
Section 49 of the Act. I am satisfied that while ordinarily costs should
April 8, 2026 Chaitanya
Judgement-CARBP(L)-473-2025-F.doc
follow the event, considering the costs awarded are reasonably robust,
at this stage, costs need not be awarded.
51. All actions required to be taken pursuant to this order shall
be taken upon receipt of a downloaded copy as available on this Court's
website.
[ SOMASEKHAR SUNDARESAN, J.]
April 8, 2026 Chaitanya
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!