Citation : 2025 Latest Caselaw 6829 Bom
Judgement Date : 14 October, 2025
2025:BHC-AS:44721
KVM
1/4
36 - FAST 22641 OF 2019.doc
Digitally signed
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
by KANCHAN
KANCHAN VINOD
MAYEKAR
VINOD Date:
MAYEKAR 2025.10.14
CIVIL APPELLATE JURISDICTION
20:47:17
+0530
FIRST APPEAL (ST) NO. 22641 OF 2019
ALONGWITH
CIVIL APPLICATION NO. 46 OF 2021
ALONGWITH
CIVIL APPLICATION NO. 47 OF 2021
IN
FIRST APPEAL (ST) NO. 22641 OF 2019
The State of Maharashtra ..... Appellant/
Applicant
VERSUS
Lilabai Madhukar Patil & Ors. ..... Respondents
Mr. A.R.Patil, Addl. G.P. for the State - Applicant.
Mr. Parmar Dixit i/b. Mr.Kaustubh Patil for the Respondents.
CORAM : RAJESH S. PATIL, J.
DATE : 14 OCTOBER, 2025
P.C. :-
CIVIL APPLICATION NO. 46 OF 2021
1) This Civil Application is filed seeking condonation of
delay of 358 days in filing the First Appeal.
2) Heard learned counsel for both sides and I have gone
through the contents of the application.
3) Supreme Court in the judgment of Collector, Land
Acquisition, Anantnag and another Vs. Mst. Katji and Others reported
in 1987 SC 1353, has held that:
KVM
36 - FAST 22641 OF 2019.doc
"Every day's delay must be explained" does not mean that a pedantic approach should be made. Why not every house's delay. Every second's delay ? The doctrine must be applied in a rational common sense pragmatic manner."
4) Supreme Court in the case of S. Ganesharaju (Dead)
through Lrs V. Narasamma (Dead) through Lrs reported in (2013) 11
SCC 341, more specifically, paragraph Nos. 12 and 13, of the said
judgment held that a liberal construction to the cause of delay should
be given. The said paragraphs are reproduced herein below:
12. The expression "sufficient cause" as appearing in Section 5 of the Limitation Act, 1963, has to be given a liberal construction so as to advance substantial justice. Unless the respondents are able to show malafides in not approaching the court within the period of limitation, generally as a normal rule, delay should be condoned. The trend of the courts while dealing with the matter with regard to condonation of delay has tilted more towards condoning delay and directing the parties to contest the matter on merits, meaning thereby that such technicalities have been given go-by.
13. The rules of limitation are not meant to destroy or foreclose the right of parties. They are meant to see that parties do not resort to dilatory tactics but seek their remedy promptly.
5) Bombay High Court in the judgment of Kamalbai
Narasaiyya Shrimal and Another Vs. Ganpat Vithalrao Gavare reported
in 2007 (1) MH. L.J. 807, paragraph Nos.13 and 15 has held:
13. The factual position is manifestly clear on bare perusal of the application for condonation filed by the petitioners before the learned District Judge. The only relevant statement in the application is thus:
"The delay caused in preferring the appeal is of six months. The
KVM
36 - FAST 22641 OF 2019.doc
caused delay is not intentional one. The appellants are poor and helpless persons. If the delay is not condoned appellant may cause irreparable loss which cannot be compensated in terms of money. The suit was for recovery of possession and present appellants are tenants. If the delay is not condoned then appellants will become shelterless."
15. The expression "sufficient cause" cannot be erased from section of the Limitation Act by adopting excessive liberal approach which would defeat the very purpose of section 5 of the Limitation Act. There must be some cause which can be termed as a sufficient one for the purpose of delay condonation. I do not find any such "sufficient cause" stated in the application and as such no interference in the impugned order is called for."
6) According to me, considering the submissions made in the
Civil Application and the law laid down in above judgments, a case is
made out to allow the Civil Application.
7) The Civil Application is allowed in terms of prayer clause
(b) and disposed of accordingly.
FIRST APPEAL (ST) NO. 22641 OF 2019
8) This First Appeal has been filed challenging the Judgment
and Award dated 23 February, 2018 passed by the Civil Judge, Senior
Division, Alibag in Land Acquisition Reference No. 389 of 2016.
9) Acquisition of the land pertains to the notification dated
24 September, 1986 issued under Section 4 of the Land Acquisition
Act. The land pertains to Village Bokadvira, Taluka Uran, District
Raigad for the purpose of 'New Bombay Project'.
KVM
36 - FAST 22641 OF 2019.doc
10) Heard learned counsel for both the sides.
11) Admit. 12) The Appellants to file private paper-book within a period
of six months from today. A copy of the same to be served on other
side.
13) Soft copy of R & P be sent by the trial Court to the High
Court within 4 weeks from today. Original R & P should be preserved
by the trial Court till further orders of this Court. Original R & P to be
sent to the High Court when called for.
CIVIL APPLICATION NO. 47 OF 2021
14) This Civil Application is filed seeking stay to the execution
of the Judgment and Award dated 23 February, 2018 passed by the
Civil Judge, Senior Division, Alibag in Land Acquisition Reference No.
389 of 2016.
15) Learned Additional Government Pleader states that the
amount has already been deposited before the Reference Court.
16) In view of the same, this Civil Application stands allowed
in terms of prayer clause (b).
[RAJESH S. PATIL, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!