Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Shagun Exports, Mumbai Thr. Vice ... vs Shri. Kavinder Kumar Jogindernath ...
2025 Latest Caselaw 6801 Bom

Citation : 2025 Latest Caselaw 6801 Bom
Judgement Date : 14 October, 2025

Bombay High Court

M/S Shagun Exports, Mumbai Thr. Vice ... vs Shri. Kavinder Kumar Jogindernath ... on 14 October, 2025

2025:BHC-NAG:10867



                                                 1                     9-mca-295-25.odt

                  IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                            NAGPUR BENCH : NAGPUR

                       Misc. Civil Application (ARBN) No. 295 of 2025
          M/s Shagun Exports, Mumbai through its Vice President and authorized
                        representative Shri Sharukh Kesri Master
                                         Versus
                  Shri Kavinder Kumar Jogindernath Talwar and others

         Office Notes, Office Memoranda of              Court's or Judge's Order
         Coram, appearances, Court's Orders
         or directions and Registrar's order

                     Shri Shadan Khan Advocate h/f Shri Masood Shareef, Advocate
                     for the applicant.
                     Ms. Anvita Pande, Advocate for the respondent nos. 1 to 3.

                                      CORAM : NIVEDITA P. MEHTA, J.

Reserved on : 25th SEPTEMBER, 2025.

Pronounced on : 14th OCTOBER, 2025.

The applicant has preferred the present application under

Section 11 of the Arbitration and Conciliation Act, 1996

(hereinafter referred to as "the Act of 1996") for appointment of

Arbitrator. The applicant has invoked clause no. 30 of the

Supplementary Agreement dated 29.04.1997 entered into

between Smt. Amritbala Wd/o Late Shri Jogindernath Talwar

and M/s Shagun Exports and clause no.29 of the Agreement of

SKNair 2 9-mca-295-25.odt

Development and Sale dated 31.12.1994 entered into between

Smt. Amritbala Wd/o Late Shri Jogindernath Talwar and M/s

Satyam Exports, a proposed Company (later on M/s Shagun

Exports since the said proposed Company could not be

incorporated). The subject matter of the application is

reproduced below :

(a) Apartment No.A-001 on the Ground Floor of the building

known and styled as "Shubham Apartments" covering a built up

area of about 1213 square feet; and

(b) Row House No.-B-002 consisting of Ground Floor, First

Floor and Top or Terrace of the building known and styled as

"Shubham Apartments" together with restricted area of 169.00

Sq. Mtrs. comprising of the restricted area of the earlier retained

Apartment (i.e. 95.00 Sq. Mt.).

2. Pursuant to the said Agreement of Development M/s

Shagun Exports prepared a plan of a multi-storey building

known and styled as "Shubham Apartments". The respondent

no.1's mother had entered into an agreement dated 29.04.1997

SKNair 3 9-mca-295-25.odt

with the applicant captioned as "Supplementary Agreement"

whereby it was agreed that applicant shall sell to her the entire

RCC Superstructure comprising Row House No. B-001

consisting of ground floor, first floor and top or terrace of the

building admeasure 1363 Sq. Ft together with restricted area of

169.00 Sq. Mtrs. It was specifically agreed that the entire cost of

construction was to be paid by the respondents' late mother

which was fixed for a total consideration amount of

Rs.8,00,000/-.

3. The respondents' mother had entered into an Agreement

of Development & Sale on 31.12.1994 in relation to entire land

bearing Nazul Plot No-5, Sheet No-34-C, admeasuring 19500

sq.ft. and in which it was agreed that the respondents' mother

shall be entitled for owning one Apartment on ground floor

covering a super built area of about 1213 sq. ft. in the proposed

Multi-storied Building No-A which was to be constructed by the

developer at its own costs. After completion of the same, the

delivery of possession was given in favor of respondents' late

SKNair 4 9-mca-295-25.odt

mother and accordingly a possession letter was duly signed by

both parties.

4. It is the contention of the learned counsel for the applicant

that in consequence of the agreement of sale which was executed

between the applicant and the mother of the respondent, the

apartment was duly handed over to the mother of the

respondent vide possession letter dated 22.05.1997. However, as

per the "Supplementary Agreement" dated 29.04.1997, it was

agreed that the applicant shall sell to the respondent no.1's

mother the entire RCC superstructure comprising Row Hose

No.-B-001 consisting of Ground Floor, First Floor and Top or

terrace of the building admeasuring 1363 Sq. Ft together with

restrict area of 169.00 Sq. mtrs. It was necessary on the part of

respondent No.1's late mother to make necessary payments

towards the cost of construction of the which was fixed for a

total consideration amount of Rs. 8,00,000/-. However, the said

payment was not made and therefore till date the possession of

the row house has not been handed over. The respondents'

SKNair 5 9-mca-295-25.odt

mother passed away on 22.03.2007. During her life time, she

had failed to pay the balance amount of Rs.6,00,000/- along

with necessary interest.

5. The learned counsel for the applicant further contends

that in May, 2021 the respondents had illegally and without any

legal right or authority started work of constructing a water tank

on the terrace of the said Row House. On coming to know

about the same, applicant had visited the said row house and was

shocked to note that the lock of the applicant stood replaced

with a new lock on the door; which had been illegally done by

the respondents. In February 2021, the applicant had last visited

the said building, placed his lock on the entry door, and

maintained exclusive possession throughout the period. Due to

these illegal activities, the applicant issued a notice to the

respondents alleging therein that, (1) the removal of the

applicant's lock amounts to criminal offense and (2) the

demolition of a portion of the ground floor wall, and

subsequent construction amounted to trespass and illegal

SKNair 6 9-mca-295-25.odt

construction, as the respondents had allegedly unlawfully

entered the row house. This legal notice was duly replied to by

the respondents.

6. The learned counsel for the applicant further pointed out

that there is a specific clause i.e., clause 30 of the supplementary

agreement dated 29.04.1997 and clause 29 of the development

and sale agreement dated 31.12.1994 which specifies that if any

dispute arises between the parties, the same shall be referred to

the panel of Arbitrators to be appointed by each of the party and

in view of the said agreement clause, the applicant has preferred

the present application for appointment of the arbitrator.

7. The applicant submits that he has also issued a notice to

that effect on 20.08.2024 which has been duly received by the

respondents on 21.08.2024. However the respondents have

failed to comply with the said notice.

8. Learned counsel for the applicant has placed reliance on

the judgments of the Hon'ble Apex Court in Uttarakhand Purv

SKNair 7 9-mca-295-25.odt

Sainik Kalyan Nigam Limited v. Northern Coal Field Limited,

reported in (2020) 2 SCC 455, and Interplay between

Arbitration Agreements under the Arbitration and Conciliation

Act, 1996 and the Indian Stamp Act, 1899 , reported in 2023

SCC OnLine SC 1666, to contend that, in view of the mandate

of Section 16 of the Arbitration and Conciliation Act, 1996,

judicial intervention at the pre-reference stage is limited. It is

submitted that the issue of limitation is a jurisdictional question

that falls within the domain of the arbitral tribunal and,

therefore, ought to be decided by the arbitrator under Section

16, rather than by the High Court at the pre-reference stage.

9. Per contra, the learned counsel for the respondents

submits that present application is ex-facie barred by limitation

and is not maintainable. It is her further contention that as per

Section 11 of the Act of 1996, the period for referring a dispute

to arbitration or for seeking appointment of an arbitrator is three

years from the date on which the cause of action arises.

According to her, the cause of action arose on 26.03.1998 when

SKNair 8 9-mca-295-25.odt

late Smt. Amritbala Talwar took possession of the incomplete

row house bearing No.B-002. As per the clause 3 of the

supplementary agreement wherein it is specifically mentioned

that it is agreed between the parties the developer will strictly

deliver the possession of the said row house duly completed and

finished by 25.03.1998. In case failure to do so by the

Developer it was agreed that the owner will be entitled to take

possession of the row house no. B-002 on 26.03.1998 and

accordingly possession was taken by the respondent no.1's

mother. The late mother of the respondent no.1, completed the

remaining construction of the row house at her own expenses.

Moreover, the respondents continue to remain in possession till

date and the applicant has never raised any objection to the

possession of the respondents.

10. Learned counsel for the respondents further contends that

the applicant even after issuing the legal notice dated

07.06.2021 failed to take any further steps for nearly three years

thereafter. Inaction to complete the row house on part of the

SKNair 9 9-mca-295-25.odt

applicant clearly reflects lack of diligence and renders the present

application not only belated but also illegal and unsustainable.

She further submits that almost 27 years have passed from the

date of execution of the agreement to sale and development and

also supplementary agreement and therefore the application

under Section 11 of the Arbitration and Conciliation Act is

devoid of merits and should be dismissed.

11. Upon considering the pleadings, submissions of both

parties, and the documents on record, the core issue that arises

for adjudication is whether the present application under Section

11 of the Act of 1996, is maintainable in light of the

respondent's objection that the claim is ex facie barred by

limitation.

12. The Act of 1996, while facilitating party autonomy and

minimal judicial interference, does not itself prescribe a

limitation period for invocation of arbitration. However, it is

now well settled through judicial pronouncements that the

SKNair 10 9-mca-295-25.odt

general provisions of the Limitation Act, 1963, govern the

commencement of arbitration proceedings. Article 137 of the

Limitation Act prescribes a three-year limitation for applications

where no specific period is provided, which includes an

application under Section 11 of the Arbitration Act for the

appointment of an arbitrator. This period begins to run from the

date when the cause of action first arises.

13. In the present matter, the Supplementary Agreement

dated 29.04.1997 clearly stipulated in Clause 3 that possession

of the Row House No. B-002 was to be delivered on or before

25.03.1998, and in the event of failure to do so by the developer,

the purchaser late Smt. Amritbala (respondent no.1' mother)

would be entitled to take possession on an "as is where is" basis

from 26.03.1998. The respondents have consistently maintained

that possession was accordingly taken on 26.03.1998, that the

structure was completed by them at their own cost, and that they

have remained in peaceful, continuous possession ever since.

This assertion is not effectively denied by the applicant, nor is

SKNair 11 9-mca-295-25.odt

any credible evidence placed on record to show that possession

was retained by the applicant until the alleged incident in 2021.

14. The applicant's case rests on the contention that cause of

action arose in May 2021, when he discovered alleged

unauthorized entry by the respondents, and thus the arbitration

clause could be validly invoked in 2024. However, this

argument lacks legal substance and factual credibility. First, the

agreement itself fixes a date for performance and possession,

making the date of accrual of cause of action as 26.03.1998,

when according to the applicant, the respondents failed to make

the remaining payment and allegedly took unauthorized

possession. Secondly, the long period of inaction from 1998

until 2021 spanning over two decades is neither explained nor

justified by the applicant. Even assuming the cause of action

revived in 2021, there is a delay of over three years before the

arbitration clause was invoked in August 2024, again without

any explanation or action in the intervening period.

SKNair 12 9-mca-295-25.odt

15. The applicant's plea that discussions for settlement were

ongoing cannot be accepted at face value in absence of any

correspondence or documentary proof. On the contrary, the

reply to the legal notice issued in 2021 reveals that the

relationship between the parties was adversarial, not conciliatory.

The claim of ongoing settlement talks appears to be an

afterthought, aimed merely at explaining the long inaction. It is

further relevant to note that no civil suit, police complaint, or

any form of legal proceeding was initiated by the applicant at

any time prior to 2024, despite alleging trespass, illegal

possession, and non-payment of substantial consideration.

16. It is important here to address the judgments relied upon

by the applicant:

In Uttarakhand Purv Sainik Kalyan Nigam Ltd. v.

Northern Coal Field Ltd., (2020) 2 SCC 455, the Hon'ble

Supreme Court held that issues relating to limitation and

arbitrability are primarily within the domain of the arbitral

tribunal under Section 16 of the Act. However, the Court also

SKNair 13 9-mca-295-25.odt

clarified that where the issue of limitation is not ex facie

apparent, it should be left to the arbitrator. The aforesaid ruling

does not help the applicant in the present case because the delay

is apparent on the face of the record the cause of action (whether

based on non-payment or possession) clearly arose in 1998, and

the arbitration was invoked only in 2024, well beyond the three-

year limitation period. Hence, this is not a case where limitation

is debatable; rather, it is ex facie and demonstrably barred.

The applicant's reliance on N.N. Global Mercantile Pvt.

Ltd. v. Indo Unique Flame Ltd., 2023 SCC OnLine SC 1666, to

argue that pre-reference scrutiny by the courts must be minimal,

and issues such as validity, limitation, and arbitrability should be

left to the arbitral tribunal, is misplaced. The Hon'ble Apex

Court in this case as dealing with the interplay between

arbitration clauses and stamping requirements not limitation per

se.

17. It is no more res-integra that at the stage of section 11

proceedings the court does not conduct a detailed examination.

SKNair 14 9-mca-295-25.odt

However, when there is no reasonable doubt that arbitration

cannot proceed viz., when the claim is barred by limitation,

should it refuse reference. In this context Vidya Drolia v. Durga

Trading Corporation, (2021) 2 SCC 1, which is the leading

authority on Section 11 post-N.N. Global, makes it abundantly

clear that courts can refuse reference if the claim is ex facie

barred by limitation. Specifically, in Vidya Drolia (supra), the

Supreme Court held in paragraph in 147.11, 148 and 154.4:

"147.11 The interpretation appropriately balances the allocation of the decision-making authority between the court at the referral stage and the arbitrators' primary jurisdiction to decide disputes on merits. The court as the judicial forum of the first instance can exercise prima facie test jurisdiction to screen and knockdown ex facie meritless, frivolous and dishonest litigation. Limited jurisdiction of the courts ensures expeditious, alacritous and efficient disposal when required at the referral stage.

148. Section 43(1) of the Arbitration Act states that the Limitation Act, 1963 shall apply to arbitrations as it applies to court proceedings. Sub-section (2) states that for the purposes of the Arbitration Act and Limitation Act, arbitration shall be deemed to have commenced on the date referred to in Section

21. Limitation law is procedural and normally disputes, being factual, would be for the arbitrator to decide guided by the facts found and the law applicable. The court at the referral stage can interfere only when it is manifest that the claims are ex facie time barred and dead, or there is no subsisting dispute.....

154.4 Rarely as a demurrer the court may interfere at the Section 8 or 11 stage when it is manifestly and ex facie certain

SKNair

15 9-mca-295-25.odt

that the arbitration agreement is nonexistent, invalid or the disputes are non-arbitrable, though the nature and facet of non- arbitrability would, to some extent, determine the level and nature of judicial scrutiny. The restricted and limited review is to check and protect parties from being forced to arbitrate when the matter is demonstrably 'non-arbitrable' and to cut off the deadwood...."

Applying this principle to the present case, the cause of

action admittedly accrued in 1998, and the delay of over two

and a half decades is not only inordinate but also unexplained.

The claim, therefore, amounts to "deadwood", and the Court

would be abdicating its responsibility if it were to mechanically

refer such a stale claim to arbitration. Thus, hopelessly time

barred claims can be treated as "deadwood". In the case in hand

there is "no vestige of doubt" that the claim of applicant is

deadwood.

18. Furthermore, in National Insurance Co. Ltd. v. Boghara

Polyfab Pvt. Ltd., (2009) 1 SCC 267, the Hon'ble Apex Court

emphasized that limitation is part of substantive law and

governs arbitration proceedings just as it governs civil litigation.

SKNair 16 9-mca-295-25.odt

The Court held that if the claims are demonstrably barred by

limitation, they may be rejected at the threshold.

19. In Arif Azim Company Ltd v. Aptech Ltd., (2024) 5 SCC

313, the Hon'ble Supreme Court had observed that Section

11(6) would be covered by Article 137 of the Limitation Act,

1963 which prescribes a limitation period of 3 years from the

date when the right to apply accrues. Furthermore, limitation is

an admissibility issue, yet it is the duty of the Courts to prima

facie examine and reject non-arbitrable or dead claims, so as to

protect the other party from being drawn into a time-consuming

and costly arbitration process.

20. Finally, the conduct of the applicant further reinforces the

absence of diligence. Despite being aware of the alleged default

in payment and unauthorized possession since 1998, no civil,

criminal, or arbitral proceedings were initiated for over two

decades. Even after alleging illegal acts in 2021, the applicant

took no steps until August 2024. There is no document

evidencing acknowledgment of liability or a fresh promise to SKNair 17 9-mca-295-25.odt

pay under Section 18 of the Limitation Act that could extend

the limitation period.

21. Thus, the plea of ongoing settlement discussions,

advanced without any supporting material and in the light of

outright vehement denial of the same by respondents, is wholly

unconvincing and insufficient to revive a long-dead claim.

22. In the present case, the claim sought to be referred to

arbitration pertains to events that occurred in or before 1998.

No acknowledgment of liability or promise to pay, as

contemplated under Section 18 of the Limitation Act, is

demonstrated. The application has been filed in 2024 over 26

years after the cause of action allegedly arose without any

intervening steps that could extend or renew the limitation

period. The cause of action sought to be pleaded vis-a-vis the

incidence of 2021 does not inspire confidence as no steps

available in law were taken by the applicant. As such, the

invocation of arbitration clause is hopelessly delayed.

SKNair 18 9-mca-295-25.odt

23. Therefore, in light of the settled legal position, the facts on

record, and the unexplained and inordinate delay of over two

decades, it is manifest that the claims are ex-facie barred by

limitation. The arbitration clause cannot be invoked at such a

belated stage, especially when the applicant has failed to act with

reasonable diligence. This court, exercising jurisdiction under

Section 11 of the Act o f 1996, cannot turn a Nelson's eye to

such glaring latches and stale claims. Arbitration, though a

private dispute resolution mechanism, is not an exception to the

law of limitation, and equity cannot be extended to a party who

has slept over its rights for more than two decades.

24. Accordingly, the application under Section 11 of the Act

of 1996, is dismissed as being barred by limitation. No order as

to costs.

(NIVEDITA P. MEHTA, J.)

Signed by: Mr. S.K. NAIR SKNair Designation: PS To Honourable Judge Date: 14/10/2025 18:29:58

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter