Citation : 2025 Latest Caselaw 6729 Bom
Judgement Date : 10 October, 2025
KVM
1/4
36 - FAST 724 OF 2020.doc
Digitally signed
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
by KANCHAN
KANCHAN VINOD
VINOD MAYEKAR
MAYEKAR Date:
2025.10.14
CIVIL APPELLATE JURISDICTION
16:19:01 +0530
FIRST APPEAL (ST) NO. 724 OF 2020
ALONGWITH
INTERIM APPLICATION NO. 403 OF 2020
ALONGWITH
INTERIM APPLICATION NO. 404 OF 2020
IN
FIRST APPEAL (ST) NO. 724 OF 2020
Executive Engineer,
Nandur Madhyameshwar Project,
Division Nashik ..... Appellant/
Applicant
VERSUS
Dagdu Tukaram Shirsat & Ors. ..... Respondents
Mr. Mahesh Pawar i/b. Ms.Chaitrali A. Deshmukh for the Applicant.
Mr. Sarfaraj Shaikh i/b. Mr.Sachin Gite for the Respondent No.3.
Mr. A. R. Patil, Additional G.P. for the State - Respondent No.4.
CORAM : RAJESH S. PATIL, J.
DATE : 10 OCTOBER, 2025
P.C. :-
INTERIM APPLICATION NO. 403 OF 2020
1) This Interim Application is filed seeking condonation of
delay of 2 years and 49 days in filing the First Appeal.
2) Heard learned counsel for both sides and I have gone
KVM
36 - FAST 724 OF 2020.doc
through the contents of the application.
3) Supreme Court in the judgment of Collector, Land
Acquisition, Anantnag and another Vs. Mst. Katji and Others reported
in 1987 SC 1353, has held that:
"Every day's delay must be explained" does not mean that a pedantic approach should be made. Why not every house's delay. Every second's delay ? The doctrine must be applied in a rational common sense pragmatic manner."
4) Supreme Court in the case of S. Ganesharaju (Dead)
through Lrs V. Narasamma (Dead) through Lrs reported in (2013) 11
SCC 341, more specifically, paragraph Nos. 12 and 13, of the said
judgment held that a liberal construction to the cause of delay should
be given. The said paragraphs are reproduced herein below:
12. The expression "sufficient cause" as appearing in Section 5 of the Limitation Act, 1963, has to be given a liberal construction so as to advance substantial justice. Unless the respondents are able to show malafides in not approaching the court within the period of limitation, generally as a normal rule, delay should be condoned. The trend of the courts while dealing with the matter with regard to condonation of delay has tilted more towards condoning delay and directing the parties to contest the matter on merits, meaning thereby that such technicalities have been given go-by.
13. The rules of limitation are not meant to destroy or foreclose the right of parties. They are meant to see that parties do not resort to dilatory tactics but seek their remedy promptly.
5) Bombay High Court in the judgment of Kamalbai
KVM
36 - FAST 724 OF 2020.doc
Narasaiyya Shrimal and Another Vs. Ganpat Vithalrao Gavare reported
in 2007 (1) MH. L.J. 807, paragraph Nos.13 and 15 has held:
13. The factual position is manifestly clear on bare perusal of the application for condonation filed by the petitioners before the learned District Judge. The only relevant statement in the application is thus:
"The delay caused in preferring the appeal is of six months. The caused delay is not intentional one. The appellants are poor and helpless persons. If the delay is not condoned appellant may cause irreparable loss which cannot be compensated in terms of money. The suit was for recovery of possession and present appellants are tenants. If the delay is not condoned then appellants will become shelterless."
15. The expression "sufficient cause" cannot be erased from section of the Limitation Act by adopting excessive liberal approach which would defeat the very purpose of section 5 of the Limitation Act. There must be some cause which can be termed as a sufficient one for the purpose of delay condonation. I do not find any such "sufficient cause" stated in the application and as such no interference in the impugned order is called for."
6) According to me, considering the submissions made in the
Interim Application and the law laid down in above judgments, a case
is made out to allow the Interim Application.
7) The Interim Application is allowed in terms of prayer
clause (b) and disposed of accordingly.
FIRST APPEAL (ST) NO. 724 OF 2020
8) This First Appeal has been filed challenging the Judgment
KVM
36 - FAST 724 OF 2020.doc
and Award dated 22 August, 2017 passed by the Civil Judge, Senior
Division, Nashik in Land Acquisition Reference No. 105 of 2010.
9) Acquisition of the land pertains to the notification dated
29 December, 2005 issued under Section 4 of the Land Acquisition
Act. The land pertains to Village Kavnai, Taluka Igatpuri, District
Nashik for the purpose of 'Mukne Dam's Additional Height
Submersible Area'.
10) Heard learned counsel for both the sides.
11) Admit. 12) The Appellants to file private paper-book within a period
of six months from today. A copy of the same to be served on other
side.
13) Soft copy of R & P be sent by the trial Court to the High
Court within 4 weeks from today. Original R & P should be preserved
by the trial Court till further orders of this Court. Original R & P to be
sent to the High Court when called for.
INTERIM APPLICATION NO. 404 OF 2020
14) Stand over to 28 November, 2025.
[RAJESH S. PATIL, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!