Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Pant Nagar Ashwamegh Co-Operative ... vs Kavya Construction Company(Formerly ...
2025 Latest Caselaw 7833 Bom

Citation : 2025 Latest Caselaw 7833 Bom
Judgement Date : 21 November, 2025

Bombay High Court

Pant Nagar Ashwamegh Co-Operative ... vs Kavya Construction Company(Formerly ... on 21 November, 2025

2025:BHC-OS:21759


                                                                                       CARBP-224-2024.doc



      PURTI
             Digitally
             signed by
             PURTI
             PRASAD
                                    IN THE HIGH COURT OF JUDICATURE AT BOMBAY
      PRASAD PARAB
      PARAB Date:
             2025.11.21
             12:40:27
             +0530                     ORDINARY ORIGINAL CIVIL JURISDICTION
                             COMMERCIAL ARBITRATION PETITION NO. 224 OF 2024

                           Pant Nagar Ashwamegh Co-operative
                           Housing Society Limited                                    Petitioner
                                    Versus
                           Kavya Construction Company
                           (formerly known as Akruti Constructions
                           Company)                                                   Respondent


                           Mr. Ranjeev Carvalho a/w Mr. Rishab Murali and Ms.Sakshi
                           Agarwal i/b Mr. Bipin Joshi for the Petitioner.
                           Mr. Chetan Kapadia, Senior Advocate a/w Ms. Kausar Banatwala
                           and Ms. Sneha Mahawar i/b Mr. Tushar Goradia for the
                           Respondent.

                      CORAM:                                   SOMASEKHAR SUNDARESAN, J.
                      RESERVED ON:                             MARCH 6, 2025
                      FURTHER RESERVED ON:                     OCTOBER 15, 2025
                      PRONOUNCED ON:                           NOVEMBER 21, 2025

                      JUDGEMENT :

Context and Factual Background:

1. This Petition is filed under Section 9 of the Arbitration and

Conciliation Act, 1996 ("the Act") essentially seeking, pending execution

of an Arbitral Award dated August 2, 2021 ("Arbitral Award" ), payment

of a sum of Rs.1.68 Crores of which Rs.1.43 Crores is towards arrears in

rent and brokerage along with interest @ 18% per annum; and a

November 21, 2025 Purti Parab

CARBP-224-2024.doc

direction that the original documentation surrounding the subject

redevelopment be handed over to the Petitioner.

2. The Petitioner, Pant Nagar Ashwamegh Co.operative Housing

Society Limited ("Society" ) is a Housing Society which had appointed

the Respondent, Kavya Construction Company a partnership firm

("Developer") for redevelopment of its premises by executing a

Development Agreement dated January 17, 2007. The Society

comprises 30 members and occupants and is entitled to land

admeasuring 6600 sq. ft bearing Survey No. 236-A corresponding to

CTS No. 5681 (Part) namely Building No. 16 at Pant Nagar, Ghatkopar

("Property").

3. The Development Agreement was accompanied by a Power of

Attorney of the same date, i.e., January 17, 2017. The Intimation of

Disapproval ("IOD") for the project had been received on September 1,

2010. A few months thereafter, the parties executed a first Supplemental

Agreement on April 4, 2011. A second Supplemental Agreement

followed on December 6, 2013. All the aforesaid documents are

collectively referred to as "Development Documentation".

4. The second Supplemental Agreement cancelled the first

Supplemental Agreement and it was agreed that each member of the

November 21, 2025 Purti Parab

CARBP-224-2024.doc

Society would get certain entitlements set out in more detail therein

including Permanent Alternate Accommodation with a new building

comprising a ground floor, stilt and 16 upper floors being created by the

redevelopment. The members of the Society were entitled to transit

rent of Rs.17,000/- per month with an escalation of 10% every 11

months. So also brokerage in the sum of Rs.17,000/- per month

escalated by 10% every 11 months was contracted. Each member was

entitled to a corpus sum of Rs.3,50,000/- of which Rs.2,65,000/- was

payable at the time of vacation and balance of Rs.85,000/- was payable

against handing over of the possession of the redeveloped premises. In

the event of certain enhanced FSI being available, a further sum towards

corpus were also contracted. The new building was meant to be

constructed and handed over within a period of 24 months with a grace

period of six months from the issuance of the Commencement

Certificate. The Developer was to provide a bank guarantee of Rs. 2

Crores which was meant to be released in stages. Certain enhanced

payments were also to be made by way of further rent and compensation

in the event of the deadline with an aggregate period of 30 months for

the delivery of the new flats being missed by the Developer.

5. The members of the Society vacated their premises and the

building was demolished in June 2014. The Commencement Certificate

November 21, 2025 Purti Parab

CARBP-224-2024.doc

was however issued only by June 24, 2016. The deadline of 30 months

would therefore be computed from June 24, 2016.

6. Various breaches were alleged against the Developer. The

Society filed a Arbitration Petition (L) No.1495 of 2019 under Section 9

of the Act ("First Section 9 Petition"). The parties arrived at Consent

Terms dated February 18, 2020 ("Consent Terms"). The arrears were

to be cleared by the Developer with further compensation while the

deadline for completion was reset to March 2022. The Supplemental

Agreements were meant to be registered and building plans were meant

to be amended with two wings one for the rehabilitation component and

the other for free sale component.

7. Further breaches of the Consent Terms took place leading to

filing of Arbitration Petition (L) No.1949 of 2021 under Section 9 of the

Act ("Second Section 9 Petition") and Contempt Petition (L) No. 1590

of 2021 for breach of the Consent Terms. An order dated February 9,

2021 ("Section 9 Order" ) was passed under the Second Section 9

Petition, disposing it of by converting it into an Application under

Section 17 of the Act and recording that all contentions would be left

open to the Arbitrator with the amounts accepted by the Society until

then being treated as without-prejudice acceptance of payments. A

November 21, 2025 Purti Parab

CARBP-224-2024.doc

schedule of payments until 2023 was recorded and agreed by the

parties.

8. The Learned Arbitral Tribunal treated the Section 9 Order as

an Order under Section 17 of the Act and kept the Section 17 Application

pending to monitor compliance. The Developer was directed to file

affidavit of disclosure with an update of the status of various approvals,

permissions, timelines etc. One such disclosure led to the discovery that

the property had been encumbered in favour of a non-banking finance

company, ECL Finance Limited ("ECL").

9. Eventually, the Learned Arbitral Tribunal passed the Arbitral

Award on August 2, 2021. The Award essentially was a direction to

comply with the Consent Terms dated February 18, 2020, with a full

disclosure of the status of the project being directed. That apart, deficit

stamp duty on the Supplemental Agreements and registration was

directed. The other documentation such as Permanent Alternate

Accommodation were also to be executed and registered and the arbitral

proceedings came to be disposed of. The Society's counter claim was

also disposed of as withdrawn.

10. Essentially, this would substantially constitute second round

of consent terms and the Arbitral Award is a Consent Award between

November 21, 2025 Purti Parab

CARBP-224-2024.doc

the parties. Thereafter, the disputes again arose between the parties

with the Consent Award not being complied with. This led to the

Society passing a resolution at a Special General Body Meeting

terminating the Development Documentation on September 18, 2021.

On October 2, 2021, the Society issued a notice communicating the

termination of the Development Documentation ( "Termination

Notice"). Thereafter, the captioned Petition was filed on March 31,

2022.

11. On September 1, 2023 a Learned Single Judge of this Court

passed an order recording the undertaking by the Developer to pay a

sum of Rs.1.40 Crores without prejudice to the rights and contentions of

the parties, only to demonstrate bona fides of the Developer. On

October 9, 2023, the Society confirmed receipt of the said sum of

Rs.1.40 Crores. On November 22, 2023 the Maha RERA issued a

Registration Certificate for the project valid until December 21, 2024

subject to renewal.

12. On August 6, 2024 the Municipal Corporation of Greater

Mumbai, ("MCGM") issued a warrant of attachment on the Property on

account of outstanding property taxes being in arrears. By December 3,

November 21, 2025 Purti Parab

CARBP-224-2024.doc

2024 the MCGM issued further demand notice threatening to sell the

Property by auction in the event of a default.

13. Pursuant to an order dated February 25, 2025 an affidavit

cum indemnity dated March 3, 2025 was filed by the Developer

undertaking that the project would be completed and the flats will be

handed over by March 2027. The Developer also assured that out of

borrowings from ECL, only an amount of Rs.21.50 Crores related to the

project and the Court was assured that such dispute would be settled

within a period of four months and that the Society would be

indemnified from any claim made by ECL on the property and that

rehabilitation component of the building would be handed over to the

members of the Society. The Developer also assured that the

compensation due to the members of the Society as well as Municipal

dues would be paid within specific deadlines.

14. On June 18, 2025 Beacon Trusteeship Limited ( "Beacon")

claiming to be a debenture trustee acting on behalf of ECL issued a

possession notice purporting to take symbolic possession of the

Property purportedly in exercise with clause under Section 13(4) of the

Securitisation and Reconstruction of Financial Assets and Enforcement

of Security Interest Act, 2002 ("the SARFAESI Act"). The claim against

November 21, 2025 Purti Parab

CARBP-224-2024.doc

the Developer and its related parties was in the sum of Rs.429.04

Crores. Securitisation Application No.404 of 2025 challenging a notice

of symbolic possession and other measures under the SARFAESI Act

have been filed by the Society before the Debt Recovery Tribunal, and is

pending.

Contentions of the Parties:

15. The core grievance by the Society is that the Developer has not

completed the construction of the project in terms of the bar chart

submitted to the Learned Arbitral Tribunal in the run up to the Arbitral

Award. So also, there is allegedly non-compliance with the directions to

provide full disclosure as well, leaving the Society in the dark. Neither

have arrears been paid in full nor have the Permanent Alternate

Accommodation Agreement and the Supplemental Agreement been

registered. Additional FSI of 0.5 had been availed of, which also leads to

an entitlement of the Society to be paid a further sum of Rs.55 Lakhs.

16. The Developer's contention is that the Petition under Section

9 of the Act is not the avenue available in law to the Society since the

Arbitration Award has already been passed. The Developer would

contend that the Arbitral Award ought to be executed instead of filing an

Application under Section 9 of the Act. It is further contended that

November 21, 2025 Purti Parab

CARBP-224-2024.doc

having accepted a sum of Rs.1.40 Crores in the course of hearing of this

Petition, the Society has given a go-by to its Termination Notice and in

fact has taken further steps in line with the Arbitral Award to further

redevelop the property, rather than moving away from the Arbitral

Award to terminate it. Construction of six floors is said to have been

completed, with nine floors remaining and total payment of Rs.25.78

Crores is said to have been made towards the project. The disclosures

are defended as having been valid in compliance with the Arbitral

Award and indeed it is claimed that it was the Society that refused to

furnish the No Objection Certificate to MHADA even while expecting

the Developer to pay premium to MHADA.

17. The Developer contends that he is ready and willing to make

payment to MHADA subject to the Society confirming the withdrawal of

the Termination Notice. It is further contended that the Developer is in

the midst of arriving at a settlement with ECL and the Petitioner's

concerns in relation to enforcement of security interest by ECL would

stand addressed and indemnified by the Developer.

Analysis and Findings:

18. I have heard Learned Advocates for the parties Mr. Ranjeev

Carvalho, Learned Advocate on behalf of the Society and Mr. Chetan

November 21, 2025 Purti Parab

CARBP-224-2024.doc

Kapadia, Learned Advocate on behalf of the Developer at length. With

the assistance of Learned Advocates, I have examined the material on

record. Initially, the matter had been heard and reserved on March 6,

2025. Thereafter, considering the further time having passed by, the

matter was listed afresh on October 15, 2025 to get an update of any

subsequent development in the matter and to factor in the same.

19. At the threshold, it must be noted that this Petition is filed for

protective measures to secure the Arbitral Award, i.e. after the award

was passed, which essentially would need to entail that the stance of the

Society would need to be in furtherance of the Arbitral Award.

However, the post-award Section 9 Petition unequivocally records facts

and contentions that move in a diametrically opposite direction. While

the Arbitral Award entails completion of the redevelopment by the

Developer within specific deadlines, the intention to terminate the

Agreement would flow in the opposite direction.

20. Therefore, the Termination Notice truly cannot be in aid of the

execution of the Arbitral Award, which is the prayer made by the

Society. It is another matter if the termination were to be treated as a

separate and new event, with a Section 9 Petition being filed without

any linkage to the execution of the Arbitral Award. This directional

November 21, 2025 Purti Parab

CARBP-224-2024.doc

dichotomy in the position of the Petition is what needs to be dealt with

while considering the appropriate manner of disposal of this Petition.

What is noteworthy is that, in the course of hearing of this very Petition,

there has been a further movement towards the redevelopment rather

than termination.

21. The Petitioner would contend that an Application under

Section 9 may indeed be filed after an Arbitral Award and would cite

multiple judgments in support of this proposition. While one cannot

with the proposition, it cannot be forgotten that the Arbitral Award

entails completion of the redevelopment within the same relationship

whereas the Termination Notice entails parting of ways and the

cessation of the relationship. It is in this light, that the reliefs as sought

in terms of return of the Development Documentation and non-

interference in the project would not only run counter to the Arbitral

Award but also would present facts relating to a fresh cause of action

being pursued by the Society.

22. After this Petition was filed, the Developer has indeed paid a

sum of Rs.1.40 Crores to the Society, which has indeed been accepted by

the Society. Indeed such acceptance is without prejudice to the

Petitioner's rights and contentions. Whether such payment and

November 21, 2025 Purti Parab

CARBP-224-2024.doc

acceptance is an action that recognizes that the Termination Notice is

given a go-by cannot be conclusively and finally ruled upon in a Section

9 Petition, but prima facie it would suggest that the direction is contrary

to the direction of the Termination Notice issued after the Arbitral

Award, while it is securing the Arbitral Award that would form the

subject matter of a post-award Section 9 Petition.

23. Therefore, de hors this Petition, if the Society were to initiate

fresh arbitration proceedings in view of the disputes and differences

between the parties, recourse to Section 9 of the Act would be differently

available. Indeed, receipt of Rs.1.40 Crores after this Petition was filed

may suggest a prima facie view of the intent to terminate having been

diluted, but equally, it can be stated that such receipt is without

prejudice to its rights and contentions which would indeed mean that

the Society is not estopped and precluded from terminating the

Development Documentation. After all, the redevelopment was

originally envisaged in 2007 and eventually commenced in June 2016

and is yet to be completed in 2025. It would be totally open to the

Society to give a redevelopment agreement a go-by and assert a fresh

bundle of enforcement rights by reason of the cause of action to issue

the Termination Notice now being available to the Society. However,

November 21, 2025 Purti Parab

CARBP-224-2024.doc

that is not the framework in which the current Section 9 Petition has

been filed. This cannot be wished away.

24. Therefore, whatever is stated in this judgment is also without

prejudice to the rights that may be available in law to the Society to take

such fresh action as may be available to it in law, whether under Section

9 or otherwise.

25. It is equally seen that the Developer has not made payment of

the outstanding property taxes, which could jeopardize the interests of

the Society. So also, the security interest said to have been created over

the Society's property, with the indebtedness secured running into

several hundred crores, undermines the interest of the Society and that

too when the overall indebtedness is said to be much wider and larger

outside the ambit of the monies borrowed and deployed in the project

for redeveloping the Society's building. Therefore, the Section 9 Court

cannot be blind to the situation at hand, particularly in view of the

jurisdiction being an equitable jurisdiction.

26. In these circumstances, the question that arises is how the

Section 9 Court, regardless of the dichotomy between seeking protection

of the rights flowing under the Arbitral Award and the attempt to

terminate the relationship, can best balance the competing interests of

November 21, 2025 Purti Parab

CARBP-224-2024.doc

the parties. Rather than taking a narrow technical view that the Section

9 Petition in the manner drafted cannot be considered at all, it is

considered appropriate to issue directions to the Developer, adopting

the Developer's own stand that the payment and receipt of Rs.1.40

Crores is an indication of moving forward with the redevelopment

rather than proceeding with the termination.

27. By merely stating so, the Developer cannot be said to be

absolved from the need to take specific measures under directions of

this Court to secure the interests of the Society. Therefore, bearing the

aforesaid stance of the Developer in mind, and indeed the position of

the Society that it had approached this Court to secure the fruits of the

Arbitral Award, it is felt necessary to issue specific directions to the

Developer so that the interests of the Society can be protected and the

competing interests of the parties can be balanced and adjusted.

Directions and Order:

28. With the aforesaid analysis in mind the following order is

passed:

(a) The Developer is directed to clear all dues payable in

respect of the property taxes payable to MCGM in respect of

November 21, 2025 Purti Parab

CARBP-224-2024.doc

the Society's property within a period of four weeks from this

order;

(b) The proposed schedule of computation contained in

the affidavit of the Developer tendered by the Learned Senior

Advocate on behalf of the Developer shall be adhered to, and

the amounts payable to the Society shall be cleared in the

following manner:

(i) The outstanding compensation payable as of

December 31, 2024, then computed in the sum of

Rs.3,07,19,160/- shall be paid in three equal

instalments between the date of this Order and

January 31, 2026, in the terms set out below;

(ii) It is noteworthy that in the affidavit dated

March 3, 2025, the entire amount had been promised

to be cleared by the Developer by August 16, 2025.

The Developer was expecting execution of fresh

Consent Terms for this commitment to commence.

However, without the need for signing fresh consent

terms, it is directed that such amount shall be cleared

by extended deadline granted hereby. Should the

November 21, 2025 Purti Parab

CARBP-224-2024.doc

Society write to the Developer indicating that it

intends to pursue the redevelopment and not effect

the termination (such indication may be made by a

written notice to be issued by Advocates on record for

the Society to Advocates on record to the Developer),

the aforesaid direction to pay this entire amount in

three equal instalments shall be complied with;

(iii) Should the Society indicate in writing to the

Developer that it is not interested in continuing with

the redevelopment (the Society shall be entitled to

confirm that it stands by the Termination Notice) the

parties shall effect adjustment of the sum of Rs.1.40

Crores towards the dues owed by the Developer to the

Society in respect of the period preceding the

Termination Notice. The amounts due and owed

from the Developer to the Society and its members

would stand adjusted against the said sum of Rs.1.40

Crores. Should there be any residual amount, the

same would be held by the Society subject to

adjustment in any new arbitration proceedings that

may be initiated and conducted including a claim for

November 21, 2025 Purti Parab

CARBP-224-2024.doc

damages, for the disputes going forward. Should

there be a shortfall in the amount owed by the

Developer to the Society, the Society shall be at liberty

to pursue the same including by way of a fresh

Section 9 Petition to secure its interests after an

unequivocal stance on the Termination Notice; and

(iv) Should the Society opt for continuing with the

redevelopment, all amounts payable after December

31, 2024 until December 31, 2025 shall be paid by the

Developer to the Society (over and above the three

equated instalments referred to above) no later than

January 31, 2026. In such event, the monthly

compensation starting from January 1, 2026 shall be

paid before 15th day of each and every calendar month

without any delay, and any delay shall attract interest

in the first instance at 18% per annum, subject to such

orders as an Arbitral Tribunal may deem fit after

hearing the parties;

November 21, 2025 Purti Parab

CARBP-224-2024.doc

(c) The No Objection Certificate to be secured from

MHADA shall also be secured no later than December 31,

2025;

(d) Should the Society agree to continue with the

redevelopment, the bar chart set out in Exhibit 1 to the

affidavit dated March 3, 2025 shall be acted upon and further

steps to be taken by the Developer in respect of the

redevelopment shall be implemented, with the only

adjustment that the commencement of such activity would be

from January 1, 2026 whereas the commencement of the

activity indicated in the bar chart is from April 2025; and

(e) Nothing contained in this judgement shall preclude

the Society from making a claim for continued payment of

transit rent and compensation even after the date of the

Termination Notice until free and vacant possession of the

Society's property is handed back to the Society either in the

form of redeveloped premises or without the premises being

redeveloped as it stands.

29. With the aforesaid directions, the Petition is finally disposed

of.

November 21, 2025 Purti Parab

CARBP-224-2024.doc

30. It is noteworthy that the Arbitral Award itself was a consent

award and not a product of adjudication of issues. Needless to reiterate,

it would be completely open to the Society to take a decision that it does

not desire to act further on the Arbitral Award by entrusting the

redevelopment to the Developer, and initiate arbitration proceedings.

In such event it shall be completely open to the Society to file fresh

arbitration proceedings including proceedings under Section 9 of the

Act to protect its interests pending such newly initiated arbitration.

31. With the aforesaid directions, the caption Section 9 Petition is

finally disposed of.

32. All actions required to be taken pursuant to this order shall be

taken upon receipt of a downloaded copy as available on this Court's

website.

[SOMASEKHAR SUNDARESAN, J.]

November 21, 2025 Purti Parab

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter