Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M3Nergy Sdn. Bhd. (Formerly Known As ... vs Hindustan Petroleum Corp. Ltd. And Anr.
2025 Latest Caselaw 7066 Bom

Citation : 2025 Latest Caselaw 7066 Bom
Judgement Date : 3 November, 2025

Bombay High Court

M3Nergy Sdn. Bhd. (Formerly Known As ... vs Hindustan Petroleum Corp. Ltd. And Anr. on 3 November, 2025

 2025:BHC-OS:19910


                                                                           CARBP.548.2014.docx



                             IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   ORDINARY ORIGINAL CIVIL JURISDICTION
                                     ARBITRATION PETITION NO. 548 OF 2014

                       M3nergy SDN. BHD.                                              ...Petitioner

                             Versus

                       Hindustan Petroleum Corporation Ltd.
                       Prize Petroleum Company Ltd. & Anr                             ...Respondents

                                            WITH
                          COMMERCIAL ARBITRATION PETITION NO. 76 OF 2018

                       M3nergy SDN. BHD.                                              ...Petitioner
                       (Formerly known as Trenergy/
                       M3nergy Berhad)

                             Versus

                       Hindustan Petroleum Corporation Ltd. & Anr                     ...Respondents

                                             WITH
                          COMMERCIAL ARBITRATION PETITION NO. 1101 OF 2018

                       M3nergy SDN. BHD.                                              ...Petitioner
                       (Formerly known as Trenergy/
                       M3nergy Berhad)

                             Versus

                       Hindustan Petroleum Corporation Ltd. & Anr                     ...Respondents


                       Dr. Rishab Gupta a/w Kanika Goenka,Shreya Jain, Swagata
                       Ghosh, Sanjana Kattoor, i/b Shardul Amarchand Mangaldas &
                       Co., for the Petitioner.
          Digitally
          signed by
          ASHWINI
          JANARDAN
                       Mr. Shashwat Singh, i/b Advani Law LLP, for Respondents.
ASHWINI
JANARDAN VALLAKATI
VALLAKATI Date:
          2025.11.03
          15:10:58
          +0530




                                                          Page 1 of 73
                                                        November 3, 2025




                         ::: Uploaded on - 03/11/2025                            ::: Downloaded on - 03/11/2025 21:22:16 :::
                                                                    CARBP.548.2014.docx



                         CORAM:                     SOMASEKHAR SUNDARESAN, J.
                         RESERVED ON                          :    February 5, 2025
                         FURTHER RESERVED ON:                      October 10, 2025
                         PRONOUNCED ON                        : November 3, 2025



JUDGEMENT:

Context and Factual Background:

1. This Petition is filed under Section 34 of the Arbitration and

Conciliation Act, 1996 ("the Act") challenging an arbitral award titled

'partial award' dated January 9, 2014 (" Impugned Award") passed

unanimously by a three-member arbitral tribunal, returning a

fundamental finding that a Joint Executing Agreement (" JEA") that had

been initialled by the parties (but not formally signed and executed) was

validly in existence.

2. The Petitioner, M3nergy Sdn. Bhd. ("M3") questions the very

existence of an arbitration agreement under Section 7 of the Act in the

absence of signatures on the JEA in which the arbitration clause is

contained. The JEA had been initialled as an agreed draft at a meeting

of an "Executing Committee" held between April 16, 2007 and April 18,

2007, attended by the representatives of M3; of Respondent No. 1,

Hindustan Petroleum Corporation Ltd. ("HPCL"); and of Respondent

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

No. 2, Prize Petroleum Company Ltd. (" PPCL"). PPCL at all times

relevant to these proceedings, was itself a joint venture, with HPCL

having a 50% ownership interest.

3. The following factual matrix would be relevant for purposes

of adjudicating this Petition:

a) The Oil and Natural Gas Corporation ("ONGC")

invited tenders for development and exploitation of Offshore

Margin Fields Cluster 7 Project ("Project");

b) M3, HPCL and PPCL executed a Memorandum of

Understanding dated June 29, 2005 (" MOU") to form a

consortium ("Consortium") to bid for the Project. The bid

was filed and coordinated by PPCL;

c) Under the MOU, the parties agreed to define the

principles underlying a JEA that would be executed to

implement the service contract, if the Project were to be

awarded to the Consortium by ONGC. The MOU entailed

participating interest proportions of the parties - M3 at 30%,

HPCL at 60% and PPCL at 10%. M3 and PPCL were meant

to jointly act as "Executing Contractors" for the Project;

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

d) On March 31, 2006, ONGC awarded the Project to

the Consortium. The letter of award is addressed to PPCL on

behalf of the Consortium;

e) A service contract dated September 27, 2006

("Service Contract") was executed between ONGC and the

Consortium. One of the terms of the Service Contract is that

the parties were to execute the JEA within 15 days - this

deadline would fall on October 12, 2006. Such executed JEA

was to be supplied to ONGC within 30 days i.e. by October

27, 2006;

f) Another integral feature of the Service Contract was

that ONGC would interact with only one party as the

Executing Contractor;

g) In the course of negotiating the JEA, M3 raised

concerns about deviations from the MOU in particular in the

matter of the joint Executing Contractors. PPCL countered

this on the premise that the Service Contract having been

executed among the same parties (along with ONGC), the

MOU stood superseded. According to M3, the Service

Contract did not close the issue and that the Service Contract

did not define the term "Executing Contractor";

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

h) Later, M3 expressed its willingness to let PPCL be the

sole Executing Contractor provided the Project was jointly

managed by an Integrated Project Management Team

("IPMT") in terms of a pre-approved schedule and budget,

provided decisions on governance of the Consortium entailed

an affirmative voting percentage of 71%. In other words, if

the IPMT could not decide upon any issue, that issue would

need the positive vote of M3, without which no final decision

could be taken just by the other two parties;

i) The parties met between April 16, 2007 and April 18,

2007 and initialled a draft of the JEA (" 2007 JEA"), which

was a specific agenda item for this meeting. It is M3's case

that the 2007 JEA is not a concluded contract since matters

including accounting procedures and charging of costs of

Executing Committee meetings to the Consortium's account

were still open. At this meeting, the parties agreed to refer

this matter to the Management Committee for a decision.

Meanwhile, the members of the Consortium were advised to

have the initialled document approved at the appropriate

level within their respective organisations " so as to formally

execute the JEA ASAP...";

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

j) On April 23, 2007, the Management Committee of

the Consortium met and the outstanding JEA items were

also discussed and agreed upon. The Manging Committee

resolved that costs of the Executing Committee meetings

would not be charged to the Consortium. It also agreed that

the review and approval matrix concluded by the

Management Committee would automatically get adopted

"upon signing of the JEA";

k) At a meeting of the Management Committee held on

November 22, 2007, it was decided in response to a query

from ONGC (which attended this meeting) that a signed JEA

would be submitted by the parties by January 10, 2008. The

next meeting of the Management Committee was scheduled

for January 28, 2008;

l) Meanwhile, in a meeting of the Executing Committee

held between December 4, 2007 and December 6, 2007, the

accounting procedures were agreed;

m) M3 appears to have continued to held out on the

issue of who the Executing Contractor is - on December 12,

2007, M3 wrote to ONGC asserting that M3 is the Executing

Contractor for the Project. M3 claimed that the JEA would

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

be finalised to reflect this position and will be submitted to

ONGC after all the partners of the Consortium had signed off

on it;

n) On the very next day, HPCL wrote to M3 asserting

that PPCL had already been accepted as the sole Executing

Contractor and this had been agreed in the initialled JEA and

it would be counterproductive to reopen this issue;

o) On December 31, 2007, ONGC called upon the

Consortium to submit the duly executed JEA that would

clarify the issue of the Executing Contractor;

p) On January 10, 2008, the parties jointly wrote to

ONGC seeking extension of time until January 18, 2008 to

submit the executed JEA since certain details were to be

"fine-tuned";

q) PPCL wrote to ONGC on January 18, 2008 that the

parties had agreed on PPCL being the sole Executing

Contractor and had also initialled the JEA containing this

position in April 2007 but M3 had refrained from formally

signing the JEA. PPCL requested that the Management

Committee meet to address the JEA and resolve;

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

r) On January 23, 2008, ONGC rejected this request

and stated that the Management Committee would meet only

after the executed JEA is submitted;

s) On March 4, 2008, M3 executed a different version

of the JEA (one that contained the provisions that it would

agree to) and sent it to the other parties to sign and send it

over to ONGC ("2008 JEA");

t) On April 3, 2008, HPCL wrote to M3 stating that the

roles and responsibilities in M3's 2008 JEA, was

significantly different from the agreed position of the parties;

u) The parties continued to have a stand-off and this

went on right until May 21, 2008, when the ONGC

threatened the parties with terminating the Service Contract

at a meeting of the Management Committee, setting an

ultimate deadline of May 31, 2008. This deadline was

missed;

v) On June 4, 2008, HPCL sought termination of the

Service Contract as against M3 on the ground that it had

failed to submit the executed JEA;

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

w) Through June 2008, ONGC warned that the Service

Contract would get terminated for failure to submit an

executed JEA;

x) On August 1, 2008, M3 wrote to HPCL and PPCL

that it would sign the draft JEA "after discussions with its

management". Through August 2008, M3 held out and the

parties could not arrive at a consensus;

y) On September 4, 2008, ONGC terminated the

Service Contract with the Consortium members

("Termination Notice"); and

z) This led to arbitration proceedings. M3 raised a

jurisdictional objection under Section 16 of the Act on the

premise that there had been no concluded contract in the

form of the JEA, for the arbitration clause contained in it to

be a validly existing arbitration agreement. This led to the

Impugned Award, which is a partial award. Two subsequent

awards of damages and costs were also passed later, and

those are not subject matter of these proceedings.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Impugned Award:

4. The Learned Arbitral Tribunal examined the evidence led by

the parties, the material on record and rendered the following findings:

a) The JEA is validly in existence and binds the parties.

By withholding signature despite agreeing on the content

and even initialling it, M3 has breached the agreed terms of

Article 22.5 of the JEA;

b) HPCL and PPCL had the responsibility of estimating

the oil and gas reserves under Article 5.5 and Article 5.5.1 of

the MOU while M3 was responsible for preparing the initial

development plan ("IDP") for submission to ONGC;

c) M3 kept expressing its unwillingness to agree with

the oil and gas reserves estimation by HPCL and PPCL and

thereby withheld finalising the IDP, which had undergone six

iterations without consensus;

d) The subjects covered by the MOU were superseded

by the Service Contract, which provides that all prior

agreements would be superseded;

e) Article 6.5 of the JEA (agreed and initialled)

stipulated that any difference of opinion among the three

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

parties would be resolved by a 71% vote among the

participating interests - M3 having 30% participating

interest, any critical decision had to be unanimous. Yet, M3

held out on the issue of the Executing Contractor, and had

also withheld the IDP from submission to ONGC;

f) Neither the Service Contract nor the JEA specified

the responsibility for determining the oil and gas reserves.

Article 6.5 of the JEA would come into play;

g) M3 was responsible for preparing the IDP under

Clause 5.4.1.3 of the MOU, which was superseded by Article

36.1 of the Service Contract. Article 13 of the Service Contract

deals with measurement of the oil and gas reserves. The

procedure for metering was to be developed in consultation

with ONGC and approved by the Management Committee.

Therefore, Article 6.5 of the JEA would come into play;

h) Owing to M3 holding up approval for the IDP, it

could not be submitted. Therefore, the Management

Committee and ONGC agreed that M3 would be given an

opportunity to produce its own oil and gas reserve estimates

for the IDP, failing which ONGC would presented with the

estimates prepared by HPCL and PPCL;

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

i) M3 neither prepared its own estimates nor allowed

HPCL and PPCL's estimates to proceed further. Instead, M3

asked ONGC for even more time, which came to be rejected,

with the Service Contract being terminated. Therefore, M3

was liable for the failure to act within stipulated deadlines;

j) The FEED sub-contract was validly granted by PPCL

to Trident (an Australian entity) and M3 did not have any

right to object;

k) PPCL had already been accepted by M3 as the sole

Executing Contractor and M3 had no right to contest this

right granted by the parties to PPCL; and

l) In the result, all the grounds on which ONGC

terminated the Service Contract were grounds attributable

solely to M3's default, which failed to do all things

reasonably necessary to maintain the Service Contract in full

force. Therefore, M3 is liable to compensate HPCL and

PPCL with damages and costs, which would be determined

later by separate awards.

5. A word about a couple of developments would be in order.

The Impugned Award was set aside by a Learned Single Judge on

January 10, 2019 under Section 34 of the Act. However, a Learned

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Division Bench was of the view that a wrong principle of law had been

applied by the Learned Single Judge and the matter was remanded to

the Section 34 Court by a judgement dated October 16, 2019. A special

leave petition by M3 challenging the decision of the Learned Division

Bench was dismissed as withdrawn.

Contentions of Parties:

6. With the consent of the parties, the captioned Petition was

taken up separately. It was agreed by the parties that if this Petition

were to be allowed there would be no need to hear the other two

Petitions, which challenge the award of damages and of costs. On the

other hand, if this Petition is rejected, the other two petitions could

always be considered thereafter. Therefore, by consent of parties, this

Petition was taken up for final hearing and disposal.

7. I have heard at length Mr. Rishab Gupta, Learned Advocate

on behalf of M3 and Mr. Navroz Seervai, Learned Senior Advocate on

behalf of HPCL and PPCL. I have had the benefit of detailed verbal

submissions and written notes on arguments filed by both sides. I have

had the benefit of these written submissions with references to the

record, in examination of the record, indeed bearing in mind the scope

of jurisdiction of this Court under Section 34 of the Act.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

8. Mr. Gupta would contend that while the Learned Division

Bench had set aside the earlier judgement of the Learned Single Judge

and a challenge in the Supreme Court had been withdrawn, the standard

to be applied would still be that this Court should satisfy itself " de novo"

about whether there had been a concluded contract, of course, also

bearing in mind the views expressed by the Learned Arbitral Tribunal.

He would emphasise that the findings of the Learned Arbitral Tribunal

that an agreement had come into being was perverse and patently

illegal.

9. On behalf of M3, Mr. Gupta has tendered and relied upon a

plethora of notes, tables and case law on multiple strands and sub-

strands of each issue he would present in the matter. These include:

                 a)          A 31-page note on written submissions;

                 b)          A List of Dates and Events on the facet of

                             jurisdiction;

                 c)          A note on liability having been fastened on M3 in

                             the Impugned Award;

                 d)          A table on conduct of the parties considered by the

Learned Arbitral Tribunal - the upshot of this

submission is that conduct of parties is no

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

barometer for whether the 2007 JEA was a binding

contract;

e) A table indicating key documents, running into 27

items, with comments on whether they had been

considered or ignored by the Learned Arbitral

Tribunal and the Learned Single Judge in the earlier

round, with a compilation of such documents;

f) A Note on Judgements on when a contract can be

said to be concluded, along with a compilation of

such judgements;

g) A table indicating key dates in negotiation of the

JEA after the JEA was initialled on April 18, 2007 -

the upshot is that there are 23 instances of

negotiations thereby indicating that the JEA

initialled on April 18, 2007 was not a concluded

contract but was merely a draft that was still being

negotiated by all parties;

h) A table of comparison between the 2007 JEA and

the 2008 JEA, to show that there were issues in the

2007 JEA that were not acceptable to M3;

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

i) A flow chart on the grounds under Section 34 of the

Act and the standard of review to be adopted. The

contention is that under Section 34(2)(a)(ii) of the

Act, the standard of review is a de novo review,

which is different from the review under Section

34(2)(b)(ii), which is deferential to the arbitral

award. Under the former provision, the contention

is that the Learned Arbitral Tribunal had no

jurisdiction to consider the matter on merits since

there was no valid or concluded contract. Under the

latter, the contention is that the Impugned Award is

patently illegal since it has been rendered on

assumed jurisdiction under an invalid un-concluded

contract. According to Mr. Gupta, while the findings

of the Learned Arbitral Tribunal must be examined

"carefully and with interest" as held by the Learned

Division Bench, the examination should still also be

a de novo review and not one that is solely

deferential to the Learned Arbitral Tribunal;






                                          November 3, 2025
Ashwini Vallakati





                                                             CARBP.548.2014.docx



                j)        An         academic     paper       from      the       Journal       of

International Arbitration on how to calibrate de

novo judicial review of arbitral jurisdiction;

k) A compilation of 13 judgements on conclusion of

contracts; contracts without authority; execution

being different from initialling; scope of perversity

and patent illegality; scope of Section 34 before the

2015 Amendments to the Act; and

l) Another compilation of case law on scope of review

in a jurisdictional challenge containing nine

judgements.

10. Mr. Seervai on behalf of HPCL and PPCL, would contend that

the Learned Division Bench has already set the standard to be applied in

the course of the review of the Impugned Award. Judicial discipline

would demand that such scope of review under Section 34 has to be

applied, with due deference to the eminently plausible views expressed

by the Learned Arbitral Tribunal.

11. That apart, Mr. Seervai would independently point to how the

JEA had actually been agreed upon by the parties including M3, which

was holding up the formality of signing, with disastrous consequences

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

for the Consortium, for which, the Learned Arbitral Tribunal has rightly

directed that M3 should be brought to account. Formal signatures being

withheld could never undermine the existence of an otherwise

concluded contract that is evident from the record. There was nothing

"essential" in the terms whatever had remained open as of April 18,

2007 and even those were closed out later. Therefore, Mr. Seervai would

contend that the Learned Arbitral Tribunal had returned accurate and

plausible findings. Mr. Seervai too would refer to multiple judgements

on the points canvassed by him, and reduce them to writing in his

written submissions.

12. On October 10, 2025, given the efflux of time since I had first

reserved judgement, I listed the matter afresh to see if the parties had

any objections to judgement still being rendered, and to consider if the

parties were desirous of addressing the Court afresh or with further

submissions. The parties expressed their consent for the Court to

proceed without a further hearing, and indicated that extensive written

submissions recorded by them would obviate the need for making

further verbal submissions.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

ANALYSIS AND FINDINGS:

Scope of Review and the Earlier Round:

13. It is now trite law that the scope of review under Section 34 of

the Act is one of examining if the Learned Arbitral Tribunal has arrived

a plausible view and whether the view expressed by the Learned Arbitral

Tribunal is so perverse that it requires interference by the Section 34

Court. The Supreme Court has repeatedly iterated that Courts must not

lightly interfere with arbitral awards. The scope of review by the Section

34 Court is also well covered in multiple judgements of the Supreme

Court including Dyna Technologies1, Associate Builders2, Ssyangyong3,

Konkan Railway4 and OPG Power5. Even implied reasons that are

discernible, may be inferred by the Section 34 Court, to support the just

and fair outcome arrived at in arbitral awards. To avoid prolixity, I do

not think it necessary to burden this judgement with quotations from

these judgements. Suffice it to say (to extract from just one of the

foregoing), in Dyna Technologies, the Supreme Court held thus:

Dyna Technologies Private Limited v. Crompton Greaves Ltd - (2019) 20 SCC 1

Associate Builders vs. Delhi Development Authority - (2015) 3 SCC 49

Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India - (2019) 15 SCC 131

Konkan Railways v. Chenab Bridge Project Undertaking - 2023 INSC 742

OPG Power vs. Enoxio - (2025) 2 SCC 417

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

"24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as in-

terpreted by various courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibil- ity of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided un- der the law. If the courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom be- hind opting for alternate dispute resolution would stand frustrated.

25. Moreover, umpteen number of judgments of this Court have cat- egorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of con- tract exists. The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardon- able under Section 34 of the Arbitration Act."

[Emphasis Supplied]

14. In the judgement dated January 10, 2019, in the earlier

round, the Learned Single Judge took the view that the jurisdictional

fact to examine if an arbitration agreement is in existence must be

reviewed by the Section 34 Court independently through a prism not

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

necessarily the same as the one used to examine arbitral findings on

merits. The Learned Single Judge indicated that the question of

challenge to a finding in favour of the Arbitral Tribunal having

jurisdiction stands on a footing different from the parameters of Section

34 of the Act. The following extracts are noteworthy: -

"In such challenge, it is for the court to scrutinize the objections to the tribunal's jurisdiction. In that scrutiny, the jurisdictional facts, on the basis of which the tribunal claims to act, are examined by the court for their existence."

"The yardstick applied by the challenge court to the other assessments of the arbitral tribunal, namely, on matters of merit, whether on questions of fact or of law, is not apposite for considering this jurisdictional challenge."

"By coming to an erroneous finding on jurisdictional facts, whether or not its view on such matters be a possible view, it cannot confer upon itself the jurisdiction which it did not possess. In other words, the question of jurisdiction, in the ultimate analysis, is only for the court to decide, though, as part of the principle of party autonomy, the question is, and ought to be, decided in the first instance always by the arbitral forum."

[Emphasis Supplied]

15. With this metric stated, the Court ruled on the purported

existence of an arbitration agreement. In a nutshell, the view taken was

that the arbitration agreement formed part of the JEA, but the JEA itself

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

had not been concluded as an agreement. There had been moving parts

and the parties were negotiating further, even after the JEA was

initialled. Therefore, it was held, the arbitration agreement contained in

it cannot be said to have been agreed upon. The Learned Arbitral

Tribunal's ruling on how the JEA is in existence was not squarely

examined and dealt with. However, the Learned Single Judge

independently came to the view that the JEA not being in existence, the

arbitration agreement contained in it is not in existence.

16. In other words, the standard applied had been that the

plausible view that the JEA had come into existence, could not be visited

on the existence of the arbitration agreement. That the parties were

wrangling over the percentage threshold of affirmative voting; that there

had been no closure on Article 7.3 of the JEA when it was initialled; and

that the arbitration clause was meant to be recast too, all weighed with

the Learned Single Judge, to hold that the Learned Arbitral Tribunal

had no jurisdiction at all.

17. A Learned Division Bench of this Court, exercising

jurisdiction under Section 37 of the Act, found fault with the Section 34

Court re-appreciating evidence to form its own view on execution of the

JEA and substituting the findings of the Learned Arbitral Tribunal. In

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

its judgement dated October 16, 2019, the Section 37 Court held that the

contours of Section 34 were as much applicable to the judicial review of

a decision taken under Section 16. The following extracts from the

Section 37 Court's judgement are noteworthy:-

"The Learned Single Judge has not dealt with the reasoning of the arbitral tribunal on account of the view taken by the learned Single Judge that law enjoined upon him to independently appraise the evidence and not deal with the manner in which the arbitral tribunal has dealt with the evidence."

"....the Court is bound to examine, both carefully and with interest, the reasoning and conclusion of an arbitral tribunal."

[Emphasis Supplied]

18. The principle of law stated by the Learned Single Judge in his

review of the question of jurisdiction and this being the sole issue before

the Section 37 Court, the Learned Division Bench set aside the Learned

Single Judge's judgement and restored the Section 34 proceedings to

the roster of the Section 34 Court for consideration in accordance with

the declared principles governing the Section 34 jurisdiction.

19. With this perspective, it is vital to examine how the Learned

Arbitral Tribunal has considered the existence of the arbitration

agreement between the parties.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Existence of Arbitration Agreement and the JEA:

20. Having examined the record and upon a review of the

Impugned Award, I have no doubt in my mind that the arbitration

agreement was in existence. To my mind, this is a rather straightforward

point notwithstanding the volume of documents and submissions

sought to be pressed into service.

21. Indeed, after the MOU was executed, ONGC awarded the

Project to the Consortium on the strength of the Consortium having

been formed in terms of the MOU. Matters progressed with ONGC even

further, and the Service Contract was executed. Privity of contract to

Service Contract involved the very same parties as the parties to the

MOU, with ONGC now being the counter-party to all of them as one

Consortium. In other words, when the parties spoke to ONGC, they

spoke in one voice. That unified voice represents the agreement

between them on the matters covered by the Service Contract. If such

matters were at a deviation from the provision of the same matters in

the MOU, it would stand to reason that the parties had agreed to move

on from the earlier position under the MOU.

22. I will analyse separately if the Service Contract superseded

the MOU, but at this point, suffice it to say that the parties were well

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

invested in the Project and were taking multiple steps in furtherance of

the award of the Project. One of the requirements stipulated by the

ONGC was that the parties must execute and deliver a JEA and the

parties made significant progress towards executing the JEA as well.

23. I must state that in the formation of commercial contracts, it

can be quite the norm for commercial parties, depending primarily on

the commercial and corporate culture of each party on how to negotiate

for the best bargain, on how much to pursue a desired objective.

Commercial parties push for and extract the best package of give and

take to arrive at a concluded bargain. A bid to reopen negotiations to

agree afresh on elements of concluded contracts depending on a change

of heart, can also be quite the norm, and can form part of the way of life

for parties engaged in long-term contracts such as infrastructure

contracts and hydrocarbon exploration and exploitation.

24. This case appears no different. The parties negotiated hard

and came to an agreed position in the 2007 JEA. Thereafter, M3

continued to hold out on some facets (such as the Executing Contractor,

a point that had been closed out and agreed). The other parties too

reacted to push their respective counter-proposal on bargains already

concluded (such as the affirmative voting threshold already agreed at

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

71% in the 2007 JEA). Each party also expressed openness to move

from its earlier positions, in a bid to commercially accommodate the

competing pulls and pushes from the counterparties. However, the key

issue in the matter at hand is to consider, upon distilling the noise

generated by such negotiations, whether there had been a concluded

bargain among the parties in the 2007 JEA or whether there had been

no bargain at all, with the actual JEA having remained elusive.

25. In my opinion, it is apparent that there was a concluded

bargain in the 2007 JEA. A couple of open issues that could reasonably

not be regarded as essential elements of the bargain too got closed after

the 2007 JEA. Attempts to open up closed topics were indeed made all

around. However, I have no doubt that there had been a concluded

bargain in the form of the 2007 JEA. Attempts to re-open the agreed

position led to retaliation in the form of expressing openness to re-open

but also imposing revisions to terms to effect such a re-opening. In any

event, it is clear to me that there always had been a clear and

unequivocal intent of the parties to refer their disputes to arbitration.

26. Before analysing the contract formation in more detail, it

would be useful to notice some elements of the MOU the parties agreed

upon. The MOU contemplated executing the JEA, which was defined as

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

a framework of agreement governing the execution of the Project by the

'IPMT', which was meant to comprise personnel deputed by the parties

by mutual consent, for implementation of any specified work. The

scope of the MOU was to define principles for the JEA to implement the

Service Contract, if awarded by ONGC.

27. Clause 5 of the MOU provided for 'Performance of Work' and

contained the devolution of responsibility and roles to be played by the

parties. Under Clause 5.2, PPCL was to coordinate activities for

preparation and submission of the bid. PPCL was to engage with ONGC

and provide the well log interpretation and analysis. PPCL was to carry

out economic assessment of the Project from the perspective of the

Consortium. Under Clause 5.4, M3 was to provide various services, one

of which was to prepare the IDP. Clause 6 provided for the role of the

"Executing Contractor" and identified PPCL and M3 jointly as such.

Clause 10 also identified both PPCL and M3 as the Executing

Contractor.

28. Clause 8.2 of the MOU specifically provided that if ONGC

were to request the parties to revise the commercial terms, the parties

will endeavour to agree unanimously on the proposed revision within

the timeframe allowed in the circumstances. In the case of differences

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

between the parties, the most competitive commercial terms were to be

offered by the parties within the available timeframe. Clause 8.3

provided for PPCL being the lead negotiator on behalf of the

Consortium in the acquisition of development rights in the Project from

ONGC. The parties agreed that none of them would withdraw after the

proposal is made to ONGC, and even if the parties agree upon

withdrawal, the withdrawing party would not be relieved of its

obligations incurred until the date of the withdrawal.

29. Under Clause 10, the parties agreed that they would execute

the Project in terms of the Service Contract to be signed with ONGC and

the JEA to be executed among the parties in accordance with the

principles set out in the MOU. The tenure of the MOU was two years

unless terminated earlier. In Clause 14, the parties agreed that the MOU

would terminate if the parties decide to supersede the MOU with any

other agreement between the parties.

30. The MOU contained an arbitration clause - "any dispute

relating to" the MOU would be subjected to arbitration as a means of

resolving the dispute. It provided for a three-member arbitral tribunal.

31. ONGC awarded the Project to the Consortium by a letter

dated March 31, 2006 addressed to PPCL as "leader of consortium

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

consisting of" the parties. ONGC referred to the terms of the

development programme submitted by the parties and called for the

IDP along with estimated capital expenditure and operational

expenditure for the first three years. ONGC called upon the parties to

depute authorised persons to execute the Service Contract. This contract

was executed on September 9, 2006.

32. The Service Contract defined "Contractor" to mean all

companies where the award of the Service Contract is to more than one

company. Clause 7.3 of the Service Contract is unequivocal in its terms

- the functions of the "Contractor" are to be carried out by the

Executing Contractor "on behalf of all constituents of the Contractor "

without this requirement "relieving the constituent(s) of Contractor

from any of its obligations or liability under the Contract ". Clause 7

generally provided for the "Petroleum Operations" (defined to mean

exploration, development production or any combination thereof in a

wide and all-encompassing manner relating to the Project) t0 be carried

out by the Executing Contractor.

33. The JEA was to be executed within 15 days of the Service

Contract, consistent with the terms of the Service Contract. It

necessarily had to provide for the role and responsibilities of the

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Executing Contractor. A decision-making forum, namely the "Executing

Committee" was mandated by the Service Contract to be set out in the

JEA - a committee comprising an agreed number of representatives of

each Consortium member. The functions of the Executing Committee

consistent with discharge of obligations under the Service Contract were

to be set out in the JEA, which was also meant to record that the

Consortium members would be jointly and severally responsible for

discharging the obligations under the Service Contract. The duly

executed JEA was to be filed with ONGC within 30 days or such longer

date as permitted by ONGC. Accounting procedures for purposes of

recognition of income and offering income to tax were annexed to the

Service Contract.

34. Various other operational provisions including requirements

of statutory and regulatory compliances are set out in the Service

Contract and it is not really necessary to allude to them for purposes of

this judgement. The Service Contract too had an arbitration agreement,

but for resolving disputes and differences between the Consortium and

ONGC.

35. Through the MOU and the Service Contract, the parties

having signed on and contracted the entire package of rights and

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

obligations obtaining under these instruments, it was now for them to

comply with the Service Contract by signing the JEA and delivering it to

ONGC. This singular act was subject matter of a breakdown in the

relationship between the parties, and ONGC issued the Termination

Notice. The parties had hit a wall in making their inter se relationship

work, and this led to arbitration.

36. The core question raised in this Petition is whether the

parties had an arbitration agreement.

37. As stated above, de hors the question of whether 2007 JEA is

a concluded contract, the parties already had an arbitration agreement

to resolve all disputes and differences "relating to the MOU".

38. The MOU contemplated PPCL as well as M3 being joint

executing contractors, but clearly ONGC required a sole point of

coordination with responsibility. The MOU had provided that if ONGC

desired anything to change in the commercial terms between the

parties, the parties would need change it within the circumstances. The

parties indeed executed the Service Contract, which clearly recorded

that there shall be a sole Executing Contractor. The Service Contract

contained inter se obligations between the Consortium and ONGC but

when each member of the Consortium who had executed the MOU also

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

executed the Service Contract, it is completely reasonable and plausible

to note that when they executed a subsequent contract on the same

subject, they had moved on from the inter se positions contracted in the

MOU. In any case, it is well declared law that when commercial

transactions end up having to be spread across multiple contracts, there

has to be a harmonious construction across instruments in a manner

that reconciles any perceived conflict among them.

39. In Chattanatha Karayalar6, the Supreme Court declared as

follows: -

3. .......... "The principle is well established that if the transaction is contained in more than one document between the same parties they must be read and interpreted together and they have the same legal effect for all purposes as if they are one document. In Manks v. Whiteley 1912-1 Ch. 735 at p. 754, Moulton, L.J. Stated:

"Where several deeds form part of one transaction and are contemporaneously executed they have the same effect for all purposes such as are relevant to this case as if they were one deed. Each is executed on the faith of all the others being executed also and is intended to speak only as part of the one transaction, and if one is seeking to make equities apply to the parties they must be equities arising out of the transaction as a whole."

[Emphasis Supplied]

S. Chattanatha Karayalar vs. Central Bank of India - (1965) SCC OnLine SC 67

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

40. Seen in this light and from the perspective of the sequence of

events, the movement from M3 and PPCL being joint Executing

Contractors to the need to have a sole Executing Contractor is writ large

in the record by this stage of executing the Service Contract. M3 too had

evidently agreed to the need to have a sole Executing Contractor. The

MOU obligated the parties to readjust the MOU to factor in what ONGC

desired. Therefore, by the time the Service Contract was executed by all

the parties including M3 with commitments being made to ONGC, in

the light of Clause 7.3 of the MOU having contemplated that the parties

would adjust commercial terms to suit ONGC's requirements, the sole

Executing Contractor provided for in the Service Contract and the other

evidence to show M3 agreed to PPCL being the sole Executing

Contractor with the check and balance being the decision-making

matrix agreed to by the parties, giving M3 the veto power, it is a

completely plausible finding that the issue of who should have been the

sole Executing Contractor was no longer in doubt.

Executing Committee Meeting of April 2007:

41. The next facet of the relationship between the parties is to

examine what transpired in the negotiation and conclusion of the JEA.

The parties engaged with one another, brought to bear the commercial

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

pulls and pressures of negotiation, and after multiple drafts of the JEA,

the parties met between April 16, 2007 and April 18, 2007 with a view to

put the final JEA to bed. Whether they had concluded the JEA in that

round is the question that has arisen for consideration because of M3

contending that the JEA had never been finalised at all.

42. Mr. Gupta's table comprising key dates in the negotiation of

the JEA with a view to indicate that there had never arisen consensus ad

idem among the parties, comprises 24 dates, the first of which is the

date of negotiations held between April 16,2007 and April 18, 2007.

43. Prior to this meeting, there had been some back and forth

about a few facets of the JEA. M3 had deleted the provisions in the

draft JEA that provided for a Management Committee. M3 had insisted

about the Executing Contractor being joint between PPCL and M3. The

Management Committee was contemplated to be a higher forum with a

role in policy decisions and comprising higher placed officials. It was

expected to resolve outstanding issues on which the Executing

Committee could not build consensus, by escalating them to the

Management Committee. PPCL wrote to M3 on March 28, 2007

explaining why M3 should not delete the Management Committee and

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

how PPCL alone would be the Executing Contractor after the Service

Contract was executed.

44. M3 replied on the same date i.e. on March 28, 2007

confirming that "M3 can accept that PPCL is nominated as the

Executing Contractor providing that the project is jointly executed via

an IPMT formed by members from all partners and that project is

managed to be approved schedule and budget ". M3 also welcomed the

role for the Management Committee. M3 proposed that the decision-

making process should entail a 71% affirmative vote i.e. partners

holding at least 71% vote would need to support a decision, which would

indicate that unanimity was vital - HPCL along with PPCL holding 70%,

they could not override M3's objections.

45. A plain reading of this letter would also indicate that M3 was

keen to get moving with the JEA. M3 highlighted that the earlier draft

had been circulated on January 7, 2007, and it was discussed on

February 7 and 8, 2007, with a draft turned around on February 12,

2007. PPCL had commented on that draft only on March 28, 2007. M3

complained that quality was being overrun by urgency created by lack of

proper planning.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

46. It is in this background, that the Executing Committee met

on an updated draft of the JEA in the sessions held between April 16,

2007 and April 18, 2007. Before that, all parties had met in Mumbai on

April 10, 2007. At the end of the sessions held in April 16-18, 2007 , the

parties initialled the JEA. Agenda Item (d) for this meeting of the

Executing Committee was titled "JEA Initialing".

47. At this meeting, each party nominated members to the

Executing Committee and to the Management Committee. After a

couple of operational points, the parties recorded that the JEA was

discussed and the "final draft as agreed to among the members was

initialed & taken on record." What was not closed was Article 7.3 of the

JEA relating to charging of costs of the Executing Committee meetings

to the account of the Consortium. The members decided to escalate the

matter to the Management Committee for a decision. The Executing

Contractor (obviously PPCL) advised that meanwhile " members may

have the initialed document approved at the appropriate level within

their organisation so as to formally execute the JEA ASAP upon

decision of the Management Committee on Article 7.3".

48. The minutes also recorded that the parties agreed on the

"Review & Approval Matrix" and "Level of Authorization" and

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

incorporated it in the JEA. The Management Committee, the Executing

Committee, Chairman of Executing Committee, Project Manager and

Project Commercial Manager of the IPMT being authorised parties

based on the prescribed decision-making areas were also agreed on.

49. This meeting has been a significant milestone in the mind of

the Learned Arbitral Tribunal. The agreeing to the draft leaving the

formal execution to later is held by the Learned Arbitral Tribunal as an

agreement having been reached on the JEA. Now only the formal

affixation of signatures was left and M3 withholding that signature has

become the subject matter of the dispute.

50. The execution draft of the JEA initialled by the parties at the

end of this meeting is on record. I have examined the same. It is writ

large that the Executing Contractor nominated by the parties is PPCL

and the JEA was approved consistent with the Service Contract. Article

4 records so in explicit terms. Article 6 provided for the Management

Committee and all decisions were contemplated to be taken

unanimously. The affirmative vote of at least two parties holding

participating interest of at least 71% was agreed to in Article 6.5. This

was a significant protection to M3 to veto any decision since it held a

participating interest of 30% and without its consent, a decision could

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

not be steamrolled by HPCL and PPCL. This would not confer positive

control in the hands of M3 - it could not have had its own view imposed

on HPCL and PPCL, but it gave M3 strong influence over the

Consortium - the others could never ride roughshod over M3 with a

proposal that M3 was unhappy about. It is against this backdrop that

M3's agreement to have PPCL as the sole Executing Contractor cannot

be wished away.

51. Article 7 dealt with the Executing Committee and its powers.

Indeed the parties initialled their agreement to this draft and even

meticulously inserted a handwritten note about Clause 7.3, stating that

it has two variants for consideration by the Management Committee,

which would approve one of the variants. This handwritten note too

was initialled by all parties. Every single page of this 91-page agreement

was initialled by all parties, leaving Clause 7.3 to the Management

Committee. The Arbitration Clause at Article 20 provided for a three-

member arbitral tribunal akin to the arbitration clause in the MOU, with

the only real difference being that the place of arbitration was agreed as

Mumbai instead of Delhi (as per the MOU).

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Management Committee Meeting of April 23, 2007:

52. The Management Committee met on April 23, 2007. Multiple

decisions were taken and recorded in the unanimously confirmed

minutes, which again would inexorably show that the parties moved

forward with the Project. The Management Committee's chair was

meant to rotate among the partners with HPCL nominee being the Chair

for the first year, M3's nominee as Chair in the second year and PPCL

being the Chair for the year after. Nominations to the Executing

Committee and Management Committee were also recorded by the

parties. In paragraph 6, it was recorded that the Management

Committee decided that each partner would bear its own costs for the

Executing Committee's meetings and not charge it to the Consortium's

account. This this, the only open clause i.e. Clause 7.3 of the JEA too

came to a close.

53. The Review and Approval Matrix was also confirmed by the

Management Committee. It was agreed that these would

"automatically get adopted upon signing of the JEA by the MC

members." At this meeting the issue of the Front-End Engineering

Design ("FEED") sub-contract came up. The parties authorised PPCL to

published an invitation of expressions of interest for the same.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

54. The finance professionals of the three partners met at Kuala

Lumpur between December 4, 2007 and December 6, 2007 (M3 is

based in Malaysia). Various decisions on accounting treatment and

approval matrix were taken. In a separate meeting at the same time,

cash calls were discussed and formats for making of cash calls were

agreed.

55. However, the actual appendage of signatures on the initialled

JEA remained pending with M3 postponing the affixation of signatures.

Management Committee Meeting of April 18, 2008:

56. A bare perusal of the Record Notes of the Management

Committee meeting held on April 18, 2008 and the minutes of that

meeting would indicate that HPCL set the context in the deliberations

by agreeing that the JEA not having been finalised until then was a

matter of concern, exposing the Service Contract with ONGC to

jeopardy. M3's lead representative Mr. Madzri Ab Rahman could not

attend until that date owing to flash floods in Kuala Lumpur but he had

been briefed by M3's CEO, the other representative, about the previous

days' deliberations. He indicated his readiness to stay over an extra day,

if required. M3 requested that the agenda items prior to the JEA

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

finalisation be skipped so that the parties could get to clearing the JEA

straight away.

57. The 2007 JEA that had been initialled was tabled and

discussed. Each issue that each party desired to negotiate was

discussed. A careful perusal would show that the parties reached

agreement on almost all open issues - these included HPCL's nominee

being the permanent chairman of the Management Committee (instead

of rotation). HPCL had sought to change the voting percentage

threshold applicable as of then (at 71%) to be reduced to 60% (which

would make HPCL's vote bind all the parties). PPCL, a joint venture of

HPCL had no objection. M3 had objections, and this issue could not be

changed and closed. M3 indicated that it would revert by April 23,

2008.

58. HPCL proposed changes to nominating a Project Manager.

M3 indicated that this is linked to the issue of who is the Executing

Contractor. The two issues were discussed collectively. M3 recognised

the view that HPCL desired to have a more active role in the Project

than envisaged in the run up to the MOU. The parties agreed to discuss

this on the following day and circulate a " finalised matrix" by April 21,

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

59. Specifically, the arbitration clause was discussed. HPCL

indicated that Article 20.2 would need some modification to bring it in

line with the Act. All partners recorded their agreement to this. The

parties had already agreed in the MOU that any dispute relating to the

MOU would be resolved by arbitration. The 2007 JEA, agreed and

initialled also had an arbitration agreement. The re-opening

discussions on the 2007 JEA also got confirmed by all parties as of April

18, 2008. Therefore, to my mind, there was no doubt about the parties

having agreed to resolve their disputes by arbitration. It is trite law that

the arbitration agreement in any agreement always has its own

independent existence. There is no manner of doubt that even if there

were disputes about existence of other contracted provisions, the parties

clearly had recorded their intent to refer disputes to arbitration right

from the time they executed the MOU. Every facet of the JEA is but a

matter relating to the MOU. This continued even when they worked on

the 2007 JEA.

60. Moreover, when ONGC took its eventual decision to issue the

Termination Notice dated September 4, 2008 to terminate the Service

Contract, after giving the Consortium a long rope to get its act together

to submit the executed JEA. At this stage, the Consortium did not

invoke the arbitration clause in the Service Contract to dispute ONGC's

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

termination. The parties did not even dispute with each other about the

Termination Notice by ONGC being unwarranted.

61. On the other provisions of the 2007 JEA on which the parties

held discussions, each of HPCL and M3 had sought some changes - the

other party either agreed to the change requested, or the proposing

party even agreed that the request for change be dropped. Therefore, it

is clear from the record that the Executing Contractor issue was still

being held out by M3 even at this later stage after having consented to

PPCL being the sole Executing Contractor.

62. The parties agreed that after deliberations on the

responsibility matrix scheduled for the next day, with M3's responses

expected by April 23, 2008 with the final changes, the parties would

execute on April 25, 2008 and submit the JEA to ONGC by April 30,

2008.

Management Committee Meeting of May 31, 2008:

63. Despite the Management Committee meeting of April 18,

2008, appending the signatures on the JEA remained elusive although

the parties had confirmed that the initialled 2007 JEA was the final

agreed draft. Proposals to move provisions around were tabled but the

key question is whether these were essential elements of contract

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

without which it could not be stated that an agreement had come into

being.

64. On May 21, 2008, the parties met and representatives of

ONGC met with the Consortium representatives. ONGC candidly asked

if they should part ways or progress further. All the Consortium

members resolved to move forward. It was agreed that the JEA would

be signed by May 31, 2008, failing which it would be presumed that the

Consortium is not interested.

Management Committee Meeting of August 1, 2008:

65. The first agenda item for this meeting held on August 1, 2008

was titled "Sign the JEA and submit to ONGC before they take steps of

Termination". It was squarely agreed by all parties at this meeting and

recorded in the minutes that "the JEA initialled in April 2007 will be the

final document to be executed and submitted to ONGC." M3 agreed to

sign the document on August 5, 2008 " after discussions with their

management".

Concluded JEA in Existence:

66. Having examined each of the aforesaid events and the

material on record, I am of the view that the interpretation by the

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Learned Arbitral Tribunal is at the least, an impeccably plausible view.

It is correct that the JEA was not formally signed, as contended by M3.

The contention itself contains the answer inasmuch as what was missing

was only the formality of appending the signature, which was evidently

being withheld by M3, even while otherwise acting in accordance with

the agreed and initialled 2007 JEA. Indeed the parties jostled for space

attempting to reopen and renegotiate the 2007 JEA but that would not

mean the 2007 JEA did not reflect an agreement among the parties.

The only open issues in the 2007 JEA was the treatment of costs of

holding the Executing Committee meetings. That issue too stood

resolved with the Management Committee deciding on April 23, 2007

that these expenses need not be charged to the Consortium's account.

Therefore, the only open issue of the 2007 JEA i.e. Article 7.3 also stood

resolved.

67. In any case, to my mind, the costs of conducting Executing

Committee meetings cannot be considered to be an essential feature

without which the JEA could have never been agreed upon. This was

evidently adjectival to the larger bargain even in the minds of the

parties, which is why they escalated it to the Management Committee

and the Management Committee also resolved this issue immediately

thereafter. Thereafter, the parties were conducting themselves in

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

accordance with the bargain struck in the 2007 JEA, of course, adopting

stances of renegotiation and countering attempt at renegotiation by the

other parties.

68. As stated by me earlier, even in concluded contracts,

depending on the perceived operational bargaining power, parties to a

contract can hope to extract a renegotiated bargain and hope to get

some movement from the existing positions, but that would not pose an

existential threat undermining an agreed contract. Mr. Gupta's

submissions about "signing" not having taken place are not convincing

when the matter is seen in this light. Indeed, M3 was withholding its

formal signature and that is a plausible view that the Learned Arbitral

Tribunal has legitimately taken. I have carefully examined each of the

24 events listed in the table of dates relied upon by Mr. Gupta to

indicate that negotiations were still underway and that there had been

no contract. As stated elsewhere, to my mind these are only attempts at

re-opening and preventing the re-opening of a bargain that the parties

had already struck.

69. The references to PPCL too having asked for a change in

voting percentage thresholds do not carry M3's case any farther

inasmuch as these are contra bargains and commercial threats thrown

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

at M3, which was attempting to re-open a matter closed by M3 itself

explicitly - the role of the Executing Contractor. In fact, on August 17,

2007, M3 has expressed indignation by indicating that PPCL's proposal

to change the affirmative vote threshold would reopen an agreed

position. Indeed, agreement had been reached among the parties, and

that agreement is found in the 2007 JEA.

70. The issue of Executing Contractor was clearly a closed and

agreed issue that M3 kept indicating was open. In fact, the veto power

that M3 had obtained in the 2007 JEA would indicate clearly that M3's

interests were well bargained for and contracted. Therefore, the

Learned Arbitral Tribunal's view that it was merely attempting to re-

open the issue of Executing Contractor is reasonable and plausible. I

would have taken the same view. In fact, the Service Contract makes it

abundantly clear that ONGC needed to have single point of contact in its

engagement with the Consortium. PPCL led the bid. PPCL coordinated

all the activity with ONGC. The award letter is addressed to PPCL. To

ensure PPCL does not act without consensus of the other parties, the

approval matrix with a 71% vote requirement gave M3 a strong influence

or even a shade of negative control over the policy decisions of the

Consortium. What the Executing Committee could not build consensus

on, would get escalated to the Management Committee, and at the

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Management Committee, the 2007 JEA entailed a 71% positive vote

requirement. Everything stood resolved.

71. Yet, M3 kept leveraging the perceived strength in withholding

affixing its signature on the document, to somehow get a bargain better

than what had been agreed to. This brinkmanship, eventually led to

ONGC terminating the Service Contract. The consequences for breach

of an agreed contract would then follow and that is what the Learned

Arbitral Tribunal has done.

72. In any case, as stated earlier, the arbitration agreement

among the parties was not at all an open issue. The parties had agreed

to Article 20 of the 2007 JEA and that is an arbitration agreement, with

an independent existence. It is an arbitration agreement that was also a

successor to the arbitration agreement in the MOU. It is merely a

further iteration of the undeniable intent to arbitrate already expressed

in the MOU. I see no merit in the contention that there was no

arbitration agreement.

Summary of Conclusions - Existence of JEA:

73. To summarize, on the existence of the arbitration agreement

and the JEA, I emphatically find that the Learned Arbitral Tribunal's

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

view is not just a plausible view, it is an accurate view. It is completely

reasonable to hold that:

a) The parties including M3 always intended to

arbitrate about the disputes and differences between them.

They expressed this first under the MOU. There is no

element of M3's autonomy to arbitrate having been

undermined;

b) The parties moved on to winning the Project on the

strength of the MOU and engaged in finalising the JEA. The

differences between the parties stood resolved by consent

accorded by the parties to the 2007 JEA, which too had an

arbitration clause and indeed, in the 2007 JEA there was no

difference of opinion at all left over the arbitration

agreement. The only area left open was Article 7.3, which was

escalated to the Management Committee meeting scheduled

for a week later, on April 23, 2007, and that too was resolved

at that meeting;

c) It is noteworthy that the Management Committee as

a forum was itself a feature of the 2007 JEA. The MOU had

contemplated only the Executing Committee. M3 had

initially deleted the provision for the Management

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Committee from the draft JEA but saw PPCL's point and was

convinced to agree upon it. This forum forms an integral

essential feature of the agreed and initialled 2007 JEA and

indeed M3 even nominated its representatives to the

Management Committee, and it is this forum that held

multiple meetings to resolve issues among the parties. The

forum was a creature that came into existence only because

of the agreement contained in the 2007 JEA;

d) Despite agreeing and finalising a full bargain on all

substantive issues by April 18, 2007 (and at the latest by

April 23, 2007), leaving only formal execution for later, M3

withheld the formal affixation of signatures. In this phase,

each party did attempt to leverage and bargain further, but to

my mind they were only attempting to get at each other's

attempts to re-negotiate the agreement already reached in

the 2007 JEA. M3 itself rebuffed PPCL's attempt to dilute

the affirmative vote threshold from 71% by replying in

writing on August 17, 2007 that M3 would not renegotiate

the understanding already reached in the " already agreed

and initialled JEA";

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

e) Each of the contents of Paragraph 48 of the

Impugned Award is a perfectly logical and reasoned

conclusion. The Section 34 Court cannot re-appreciate

evidence and search for an alternate and competing view that

is canvassed by M3 as also being plausible;

f) The standard for review by the Section 34 Court has

already been set by the Learned Division Bench acting as the

Section 37 Court. That is the standard I have applied. My

detailed examination and articulation of the record as above,

is not with a view to re-appreciate the evidence but is only an

examination to see if the Learned Arbitral Tribunal's reading

of the record presents any perversity or patent illegality;

g) It is not at all correct to say that the Learned Arbitral

Tribunal has ignored any material evidence or taken into

account any irrelevant evidence. The reading of the post-

April 2007 events would explain that those are evidently

attempts to re-negotiate a concluded contract that was even

being acted upon by the parties including M3. They were

attempts to counter an attempt or to even accommodate the

request to re-negotiate, in the wider interest of moving

forward commercially. Such efforts to resist or

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

accommodate a re-negotiation of a concluded contract

cannot inexorably undermine a binding contract that had

already come into existence with the 2007 JEA;

h) M3 signing the 2008 JEA, its own version of a JEA

that was acceptable to it, could have been a bold and

aggressive attempt to arm-twist HPCL into agreeing to a new

JEA. However, that attempt evidently failed. It would not

follow that the 2007 JEA did not exist. Therefore, the

copious comparison of the terms between the 2007 JEA and

the 2008 JEA are of no avail to take M3's case any higher;

i) The Learned Arbitral Tribunal's reading of the

judgement of the Supreme Court in Trimax7 perfectly

answers the issue of essentiality. The application of Pagnan8

in Trimax and the discussion on it by the Learned Arbitral

Tribunal in the discussion that is responsive to the query

framed at Paragraph 30(a) of the Impugned Award is

impeccable and cannot be faulted at all;

j) The reasons I have already set out above are

responsive to my endorsement of the conclusions of the

Trimax International FZE LTd. Vs. Vedanta Aluminium Ltd. - (2010) 3 SCC 1 @ 30

Pagnan SPA v. Feed Products Ltd. - (1987) 2 Lloyd's Rep 601

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Learned Arbitral Tribunal in response to query it posed in

Paragraph 30(b) of the Impugned Award;

k) The issue raised by M3 that privity to the MOU was

different from the privity to the Service Contract, also does

not further M3's case. The subject matter of the MOU was to

bag the Service Contract. The terms on which the parties

executed the MOU indeed underwent a transformation when

they negotiated and agreed the Service Contract. The MOU

entailed both M3 and PPCL being Executing Contractors

while the Service Contract refers only to one Executing

Contractor. Towards this end, the MOU itself contains the

provision that if ONGC were to require changes the parties

would work towards such changes. When the parties

executed the Service Contract, it stands to reason that they

consciously engaged and arrived at the reference to a sole

Executing Contractor in the Service Contract. That coupled

with M3's own contemporaneous acceptance of PPCL as the

Executing Contractor and indeed the reference to the

presentations by the Executing Contractor in the minutes of

the Management Committee leaves no doubt that this was a

closed issue and re-opening it was a red herring from M3;

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

l) Therefore, in my opinion, nothing perverse can be

found in the reasoning by the Learned Arbitral Tribunal that

the MOU was superseded by the Service Contract. On the

facet of the Executing Contractor, clearly the parties moved

on to a moulded bargain under the Service Contract and this

facet was truly superseded. M3 bargained and received the

safety feature of a pre-agreed budget and the Review and

Approval Matrix and the affirmative voting threshold of 71%

participating interest;

m) That apart, as a matter of evidence, the Learned

Arbitral Tribunal has rightly come to a plausible view that

M3 has confirmed in writing that this issue was accepted by

M3 and put to rest;

n) It is apparent to me that M3's conduct is not of one

who is of the belief that there has been no contract at all. M3

has been well aware that the JEA is an essential requirement

under the Service Contract and its actions are not at all in

conflict with furthering the essential bargain under the 2007

JEA. The disputes and open areas being pressed into service

are distractions holding to distract the line of reasoning and

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

consideration to an impression as if the parties did not have

consensus ad idem; and

o) The Learned Arbitral Tribunal found that under

Indian contract law, a contract need not even be in writing.

It was ONGC's requirement that an executed JEA be

delivered to it. The parties indeed had a contract that was in

writing and even initialled, but to deliver to ONGC, it needed

a formal signature, and that was systematically withheld by

M3 despite having an agreement evidenced by initialling it

and minuting the draft as an agreed position. The aforesaid

reasoning is a sound one and does not call for any

interference as a matter of Indian law. There is nothing

illegal in the aforesaid proposition much less patently illegal.

Therefore, M3's efforts to put too fine a point about the

meaning of the term "execution" does not lend itself to

acceptance for interference under Section 34 of the Act. The

case law relating to development agreements governing

redevelopment of buildings of housing societies cited by Mr.

Gupta on the facet of concluded contracts are totally

distinguishable. A development agreement by law is required

to be registered to be enforceable, and consent to a

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

development agreement involving a housing society

involving multiple constituents, they stand on a very

different footing.

74. Therefore, on the core contention presented in this Petition

under Section 34, namely, that there is no arbitration agreement in

existence, and which contention is based on the premise that the 2007

JEA was not a binding contract, I find nothing wrong with the findings

of the Learned Arbitral Tribunal in terms of Section 34(2)(a)(ii) of the

Act.

75. It would not be out of place to draw reference to the views of

the Supreme Court in Kollipara Sriramulu9 extracted below:

3. We proceed to consider the next question raised in these appeals, namely, whether the oral agreement was ineffective because the parties contemplated the execution of a formal document or because the mode of payment of the purchase money was not actually agreed upon. It was submitted on behalf of the appellant that there was no contract because the sale was conditional upon a regular agreement being executed and no such agreement was executed. We do not accept this argument as correct. It is well established that a mere reference to a future formal contract will not prevent a binding bargain between the parties. The fact that the parties refer to the preparation of an agreement by which the terms agreed upon are to be put in a more formal shape does not prevent the existence of a binding contract. There are, however, cases where the reference to a future

Kollipara Sriramulu v. T. Aswatha Narayana - 1968 SCC OnLine SC 87

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

contract is made in such terms as to show that the parties did not intend to be bound until a formal contract is signed. The question depends upon the intention of the parties and the special circumstances of each particular case. As observed by the Lord Chancellor (Lord Cranworth) in Ridgway v. Wharton [6 HLC 238, 63] , the fact of a subsequent agreement being prepared may be evidence that the previous negotiations did not amount to a concluded agreement, but the mere fact that persons wish to have a formal agreement drawn up does not establish the proposition that they cannot be bound by a previous agreement. In Von Hatzfeldt-

Wildenburg v. Alexander [(1912) 1 CH 284, 288] it was stated by Parker, J. as follows:

"It appears to be well settled by the authorities that if the documents or letters relied on as constituting a contract contemplate the execution of a further contract between the parties, it is a question of construction whether the execution of the further contact is a condition or term of the bargain or whether it is a mere expression of the desire of the parties as to the manner in which the transaction already agreed to will in fact go through. In the former case there is no enforceable contract either because the condition is unfulfilled or because the law does not recognize a contract to enter into a contract. In the latter case there is a binding contract and the reference to the more formal document may be ignored."

4. In other words, there may be a case where the signing of a further formal agreement is made a condition or term of the bargain, and if the formal agreement is not approved and signed there is no concluded contract. In Rossiter v. Miller [3 AC 1124] Lord Cairns said:

"If you find not an unqualified acceptance subject to the condition that an agreement is to be prepared and agreed upon between the parties, and until that condition is fulfilled no contract is to arise then you cannot find a concluded contract."

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

In Currimbhoy and Company Ltd. v. Creet [60 IA 297] the Judicial Committee expressed the view that the principle of the English law which is summarised in the judgment of Parker, J. In Von Hatzfeldt- Wildenburg v. Alexander [(1912) 1 CH 284, 288] was applicable in India. The question in the present appeals is whether the execution of a formal agreement was intended to be a condition of the bargain dated July 6, 1952 or whether it was a mere expression of the desire of the parties for a formal agreement which can be ignored. The evidence adduced on behalf of Respondent 1 does not show that the drawing up of a written agreement was a pre-requisite to the coming into effect of the oral agreement. It is therefore not possible to accept the contention of the appellant that the oral agreement was ineffective in law because there is no execution of any formal written document. As regards the other point, it is true that there is no specific agreement with regard to the mode of payment but this does not necessarily make the agreement ineffective. The mere omission to settle the mode of payment does not affect the completeness of the contract because the vital terms of the contract like the price and area of the land and the time for completion of the sale were all fixed. We accordingly hold that Mr Gokhale is unable to make good his argument on this aspect of the case.

[Emphasis Supplied]

76. Applying this to the facts of the case, it is not even a case of

an oral contract. There is a written instrument in place in the 2007

JEA, that reduced to writing the agreement among the parties, and

initialled by the designated representatives on April 18, 2007 to confirm

that it was an agreed draft. The only provision (Article 7.3 of the 2007

JEA) was also closed out in a week thereafter. The accounting

treatment was subject matter of the Service Contract and in any case

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

loose ends were further tied up by December 2007. Nothing really was

left in the parties' understanding of what they had agreed on. Even the

issue of PPCL being the sole Executing Contractor was resolved with M3

agreeing in writing to it, with the safeguard of its affirmative voting

threshold. When PPCL sought to revisit the affirmative voting threshold

as a reaction to M3's conduct, it was M3 that resisted it stating that the

agreed position could not be revisited. For the aforesaid reasons, I do

find that 2007 JEA was indeed in existence.

77. That apart, the arbitration agreement was indeed in existence

and was truly valid. M3's exercise of its autonomy to arbitrate disputes

with the Consortium partners has been manifestly exercised right from

the execution of the MOU and reiterated under the 2007 JEA that was

agreed and initialled with formal appending of signatures being

withheld.

78. The Impugned Award cannot be set aside under Section

34(2)(a)(ii) either, as canvassed by Mr. Gupta on behalf of M3. I am not

inclined to endorse the standard of de novo review for the Section 34

Court canvassed by Mr. Gupta under Section 34(2)(a)(ii), primarily

because the standard to be applied has been explicitly set in terms of the

remand order of the Learned Division Bench. Yet, looking at the

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

material on record, for the reasons that I have independently expressed,

my views align with the views expressed by the Learned Arbitral

Tribunal. M3 has failed to prove that the arbitration agreement is not in

existence or is not valid under the law to which the parties have

subjected it.

79. On this facet of the matter i.e. the alleged non-existence of

the arbitration agreement, for the very same reasons, even Section 34(2)

(b)(ii) of the Act would not be attracted. As stated above, the doctrine of

essentiality is well articulated in Pagnan and applied in Indian law. Mr.

Gupta would firmly contend that Pagnan itself would indicate that what

is "essential" is for the contracting parties to decide and not for the

Court to impose. He would contend that it is not for the Learned

Arbitral Tribunal or this Court to decide if Article 7.3 was not essential.

Therefore, I believe it is important to extract the following principle

from the summary set out in Pagnan:

(6) It is sometimes said that the parties must agree on the essential terms and that it is only matters of detail which can be left over. This may be misleading, since the word "essential" in that context is ambiguous. If by "essential" one means a term without which the contract cannot be enforced then the statement is true: the law cannot enforce an incomplete contract. If by "essential" one means a term which the parties have agreed to be essential for the formation of a binding contract, then the statement is tautologous. If by "essential"

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

one means only a term which the court regards as important as opposed to a term which the court regards as less important or a matter of detail, the statement is untrue. It is for the parties to decide whether they wish to be bound and, if so, by what terms, whether important or unimportant. It is the parties who are, in the memorable phrase coined by the judge, "the masters of their contractual fate". Of course the more important the term is the less likely it is that the parties will have left it for future decision. But there is no legal obstacle which stands in the way of the parties agreeing to be bound now while deferring important matters to be agreed later. It happens every day when parties enter into so-called "heads of agreement" . Mr Rokison submits that that is a special case, but I do not think it is.

[Emphasis Supplied]

80. Indeed, it is not just for the Court to decide if some element is

inessential. What is clear in the facts of the case is that the parties not

only deferred their final view on Article 7.3, they also agreed on the

variants and only escalated the selection of the variant by the

Management Committee. The Management Committee, in concept, was

inherently also a creature of the 2007 JEA. More importantly, the

Management Committee indeed picked one of the variants and closed it

out. Therefore, what is writ large is that the parties themselves felt

Article 7.3 as being inessential, agreeing to leave it as a loose end only to

be tied by the Management Committee under the escalation mechanism,

which was also part of the very agreement they had arrived at. They

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

worked on that very framework and closed this open issue. Therefore,

the reading of the aforesaid extract from Pagnan in the manner sought

to be canvassed on M3's behalf, does not appeal to me.

81. All that transpired thereafter has been a manifestation of

M3's bold attempts to reopen the agreement, based on its own

perception of its relative strength, which has not found favour with the

Learned Arbitral Tribunal, in its perfectly plausible and reasoned

Impugned Award.

82. For completeness, I must also state that the Learned Arbitral

Tribunal is assailed for not having considered certain documents - in

particular documents prior to April 16, 2007, and a few others

subsequently. I am afraid this too does not turn the needle in M3's

favour inasmuch as (as held in Associate Builders) the Learned Arbitral

Tribunal, as the master of the evidence is the best judge of the quality

and quantity of evidence necessary to draw plausible conclusions. There

is nothing in the documents listed in the table presented on behalf of

M3 as not having been considered by the Learned Arbitral Tribunal, that

would change the analysis set out in this judgement.

83. Likewise, I have also examined the Compilation of Factual

Documents, some of which have admittedly not been part of the record,

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

and I find that the same analysis as above would apply to them too. I

find that most of these documents relied upon by Mr. Gupta to indicate

that the JEA is not yet "finalised" are assertions by M3 and that too well

after April 2007 (December 2007 onwards), by which time, evidently

with the benefit of hindsight, it is apparent that there has been a change

in approach by M3. Contemporaneous with events as they transpired in

2007, M3 itself rebuffed PPCL in August 2007 that there had been an

agreed position on the affirmative vote threshold, which ought not to be

reopened.

Liability Indicated in the Impugned Award:

84. This brings me to the other facet of the Impugned Award,

namely, whether the Learned Arbitral Tribunal's view that it is M3 that

was responsible for the issuance of the Termination Notice, and whether

M3 was liable for damages said to have been suffered by the HPCL and

PPCL, necessitating compensation.

85. Having considered the arbitration agreement to be existent, it

is necessary to examine M3's challenge to this portion of the Impugned

Award. Essentially, the Impugned Award notices that ONGC

terminated the Service Contract because: (i) the parties did not deliver

an executed JEA within the deadline extended from time to time and

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

eventually by the final extended deadline of May 31, 2008; (ii) the

parties were not able to resolve their inter se contractual issues, in

particular on the FEED sub-contract; and (iii) the parties did not deliver

the IDP as required under the Service Contract.

86. The Learned Arbitral Tribunal has found M3 responsible for

each of the foregoing grounds in the Termination Notice. The first

ground has been dealt with in detail above. This segment of the

judgement deals with the Learned Arbitral Tribunal's handling of the

other grounds in ONGC's Termination Notice.

87. On these counts, Mr. Gupta would submit that the scope of

review under Section 34 of the Act ought to be considered through the

prism of the position obtaining prior to the amendments to the Act

effected in 2015. The grounds on which he would contend the

Impugned Award fails in relation to fastening the responsibility and

liability on M3 are said to be breach of natural justice with regard to the

FEED sub-contract; perversity by ignoring vital evidence; and patent

illegality in ignoring contractual provisions.

Non-Submission of IDP:

88. On the non-provision of the IDP, M3 would refer to

provisions in the Service Contract and the MOU to indicate that under

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

the MOU the oil and gas estimation was to be made by HPCL and PPCL

while M3 was responsible for preparing the IDP. M3 claimed that the

submission of the IDP was delayed because HPCL and PPCL failed to

provide the oil and gas estimates necessary for preparing the IDP.

FEED Sub-Contract:

89. According to Mr. Gupta, HPCL and PPCL had conceded that

they had no contractual claim against M3 on the FEED sub-contract

since it did not form subject matter of the Service Contract. Therefore,

it is stated that M3 never had occasion to address the Learned Arbitral

Tribunal on this issue and yet there are findings recorded against M3.

Essentially, what the Learned Arbitral Tribunal has found is that PPCL

indeed had the right to appoint Trident, an Australian third party, as the

FEED sub-contractor and M3 did not have any right to challenge such

appointment.

90. Mr. Gupta would contend that there is an evident violation of

natural justice since the FEED sub-contract was not part of the claim by

HPCL and PPCL and M3 had no occasion to address the Learned

Arbitral Tribunal on this issue. That apart, M3 would hark back to the

MOU, which placed the responsibility for well design and well

engineering on M3 and this fell within the scope of M3's rights,

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

indicating that PPCL had no right to grant a sub-contract on this

subject.

Summary of Conclusions - Liability and Responsibility:

91. Having considered the submission of M3 in this regard, it is

evident that the Learned Arbitral Tribunal examined the evidence on

record including the minutes of meeting of the Management Committee

held on January 10, 2008 at which the sixth version of the IDP was

signed for submission to ONGC. However, it was M3 that was unhappy

with the estimation of oil and gas, and at the meeting of the

Management Committee meeting held on May 21, 2008, M3 had agreed

to take appropriate action of estimating the oil and gas reserves within

four weeks i.e. by June 21, 2008. This was not done and M3, which

simply sought more time from ONGC on June 21, 2008, which was

rejected by ONGC on June 26, 2008.

92. Six versions of the IDP prepared based on oil and gas

estimations made by HPCL and PPCL were not acceptable to M3.

Thereafter, M3 took on itself undertaking this task, and it was agreed

that if M3 failed to do so, the estimations made by HPCL and PPCL

would be the basis for the IDP. When M3 did not perform, it was also

agreed that whatever was already in place would be submitted.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

93. The abiding theme in M3's submissions is that the

estimations made by HPCL and PPCL were "not acceptable" to M3.

ONGC was also examining the conduct of the parties as the party that

had granted the Service Contract to the Consortium. ONGC had, in

parallel, been witness to M3 holding up signatures on the agreed JEA.

94. If the Learned Arbitral Tribunal found that M3 was neither

willing to accept the estimates prepared by HPCL and PPCL nor was it

willing to get its own estimates despite being given a chance to do so, it

is a plausible view that the Learned Arbitral Tribunal is entitled to take

on the basis of the material on record. It appears to me that M3 was

scuttling the Service Contract through these multiple means.

95. It is trite law that the Learned Arbitral Tribunal is the best

judge of the quality and quantity of evidence and so long as its view is a

plausible view, merely because another view can be canvassed, the

Section 34 Court cannot accept a competing view presented as being

plausible. In my considered opinion, after M3 had taken on itself the

task of estimating the oil and gas, with HPCL and PPCL having given

M3 the opportunity to make its own estimates, it is not possible for this

Court to re-appreciate evidence prior to January 2008 and second-guess

the findings of the Learned Arbitral Tribunal.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

96. What is a plausible reading is that for reasons best known to

M3, it's actions on multiple fronts, whether concerted or not, led to the

scuttling of the Service Contract. Withholding the signature on the

agreed 2007 JEA, which was confirmed as agreed again in April 2008,

M3 was also holding up the IDP, which to be fair to the other parties,

went through six iterations with M3 remaining displeased. The seventh

version of IDP filed by HCPL and PPCL without waiting for M3 was also

rejected by ONGC for want of M3's consent.

97. Therefore, the view of the Learned Arbitral Tribunal that

M3's actions had scuttled the Service Contract and therefore it was M3

that was responsible for the termination by ONGC is a perfectly

plausible view that cannot be disturbed lightly.

98. The FEED sub-contract falls in the same bucket. The

Learned Arbitral Tribunal has come to a plausible view, not without any

reference to evidence. Whether HPCL and PPCL made a claim in this

regard and whether any damages are quantified in this regard would be

seen when considering the next arbitral award on damages, but the

Learned Arbitral Tribunal cannot be faulted in returning a plausible

finding that after conceding to PPCL being the Executing Contractor,

and that too in writing, for M3 to still raise objections to the grant of the

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

FEED sub-contract was not acceptable, and therefore had

consequences.

99. The Impugned Award only returns a finding of who is

responsible. The quantification would come later. If HPCL and PPCL

are not pressing for damages on the FEED sub-contract that can be

examined when considering the arbitral award granting damages in the

matter. At this stage, in my opinion, no fault can be found with the

Learned Arbitral Tribunal for its considered, reasonable and plausible

opinion that it was M3 that was scuttling the Service Contract. The

objections to the grant of the FEED sub-contract was held to be

untenable while frustrating the presentation of the IDP was held to be

unreasonable. Since PPCL was agreed to be the sole Executing

Contractor and the FEED sub-contract had been granted by PPCL, this

too is something that Learned Arbitral Tribunal was entitled to plausibly

find.

100. That the governance structure had a need for unanimity

when any matter was escalated to the JEA is evident from the record.

Whether the evidence shows that M3 holding 30% participating interest

was responsible for holding up the unanimity is a matter of finding on

merits, which the Learned Arbitral Tribunal was entitled to find on the

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

basis of the evidence. By examining the evidence, if the Learned

Arbitral Tribunal concluded that the withholding of consent by M3 was

unreasonable, it is a matter of appreciation of evidence that the Learned

Arbitral Tribunal is entitled to engage in, in order to return a plausible

view.

101. Therefore, I am not persuaded that the findings of the

Learned Arbitral Tribunal are perverse in any manner on the ground of

leaving out any material evidence nor is it patently illegal or against

public policy on the ground of taking into account any irrelevant

evidence.

102. It cannot be ignored that Article 22.5 of the 2007 JEA, which

is held to be a binding contract, also enjoins the parties to act

reasonably and do everything reasonably necessary to maintain the

Service Contract in full force. The Learned Arbitral Tribunal has

concluded that M3 failed this standard. All the submissions of Mr.

Gupta would be relevant only if one were to find that the JEA did not at

all exist, which is M3's foundational submission. That being rejected,

the submissions made to get past M3's unreasonable conduct in the

teeth of Article 22.5 of the 2007 JEA are not tenable.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

Final Conclusion:

103. I have already set out a summary of conclusions under each

of the two main heads - (i) existence of the JEA and of the arbitration

agreement contained therein, both independently and as an integral

element of the JEA; and (ii) liability on M3 for being responsible for

what led to ONGC issuing the Termination Notice.

104. The parties have no quarrel with ONGC for wrongful

termination. They appear to be well aware that the receipt of the

Termination Notice was deserved and the Termination Notice was in the

making for a while. The Service Contract too has an arbitration clause

and no proceedings are said to have been initiated against ONGC,

disputing the Termination Notice.

105. The real issue is the inter se disputes between the parties and

of who is responsible for what came to pass. For the reasons articulated

above under each of the two heads outlined in the earlier paragraph, I

am not persuaded to make any intervention into the Impugned Award,

which returns valid, plausible and reasonable findings rendered

unanimously by the three-member Learned Arbitral Tribunal. There is

no perversity at all in the Learned Arbitral Tribunal's conclusions, which

are not of a nature that no reasonable man could have arrived at.

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

106. Therefore, for the aforesaid reasons, the Petition fails and is

hereby dismissed. Interim Applications, if any, would also stand finally

disposed of, accordingly.

Costs:

107. Considering that this is a commercial dispute, costs must

follow the event. However, considering that the matter has languished

for long for no fault of either party, I have restricted costs to a token

sum of Rs. 14 lakhs, which shall be paid by M3 to HPCL and PPCL in the

proportion of 60:10 (the ratio of their participating interests in the

Consortium - Rs. 12 lakhs to HPCL and Rs. 2 lakhs to PPCL) within a

period of one week after the expiry of four weeks from the upload of this

judgement on this Court's website.

An End-Note:

108. This judgement is regrettably long and has also taken

regrettably long in its making. In the interest or brevity and to avoid

prolix reproduction from the whole pile of case law sought to be

presented into service, I have restricted references to them to the bare

minimum, and not indulged in copious extraction from them, bearing in

mind the standard of review applicable under Section 34 of the Act. To

avoid further prolixity and lengthy extraction, I have not extracted from

November 3, 2025 Ashwini Vallakati

CARBP.548.2014.docx

case law cited beyond what I felt is necessary to adjudicate what fell for

review to dispose of this Petition finally.

109. It is also appropriate to record my gratitude to both Mr.

Gupta and Mr. Seervai for having curtailed their verbal submissions

within the reasonable time limits they committed to. There must be a

special mention for Mr. Gupta's ability to compile and present in

writing, extremely well-referenced submissions, to enable the review of

the voluminous material on record, necessary for adjudicating a Petition

of this nature, without extremely time-consuming verbal submissions.

Copious and lengthy written submissions had already formed part of the

record before my predecessors, and Mr. Gupta has assisted me well by

culling out well-referenced written submissions to aid my review of the

record, and disposal of this Petition.

110. All actions required to be taken pursuant to this order shall

be taken upon receipt of a downloaded copy as available on this Court's

website.

[SOMASEKHAR SUNDARESAN, J.]

November 3, 2025 Ashwini Vallakati

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter