Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Krishna Constructions And Others vs Mr. Subhash Uttam Dalvi And Others
2025 Latest Caselaw 3867 Bom

Citation : 2025 Latest Caselaw 3867 Bom
Judgement Date : 10 June, 2025

Bombay High Court

M/S. Krishna Constructions And Others vs Mr. Subhash Uttam Dalvi And Others on 10 June, 2025

2025:BHC-AS:22796


                                                                          901-AO-744-2024.doc

 rrpillai               IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                      CIVIL APPELLATE JURISDICTION
                                APPEAL FROM ORDER NO. 744 OF 2024

                1.        M/s. Krishna Constructions,
                          A Partnership Firm Registered under
                          the Provisions of Partnership Act,
                          Having Office At : S.No. 28/1,
                          Old Kharadi Mundhwa Road
                          Next To Kran Radar Factory
                          Pune 411014 and also at
                          20, Ghodapdeo Cross Road
                          No. 01, Mumbai-400 010
                          through its Partners

                2.        Mrs. Shikha M. Mistry
                          Age : Adult, Occ : Business

                3.        Mr. Mittal Pranjivan Mistry
                          Age : 48 years, Occ : Business                              ... Appellants

                                               Versus

                1.        Mr. Subhash Uttam Dalvi,
                          Age: 46 Years, Occ: Business,
                          R/at: First Floor, A Wing, Flat No. 103,
                          Spring Dale CHS LTD.,
                          Old Mundhwa Road, Wadgaonsheri,
                          Pune - 411014.

                2.        The Pune Municipal Corporation,
                          Through its Commissioner.


                                                        1/65


                ::: Uploaded on - 10/06/2025                   ::: Downloaded on - 10/06/2025 22:45:49 :::
                                               901-AO-744-2024.doc

3.   The Commissioner,
     Pune Municipal Corporation, Pune.

4.   City Engineer,
     Building Permission and Unauthorized
     Construction, Control Department,
     Office of No. 2(a) to 2(b) above at:
     Pune Municipal Corporation,
     PMC Main Building, Shivajinagar,
     Pune - 411005.

5.   M/s. Sandeep Hardikar & Associates,
     through its authorized signatory
     Sandeep Hardikar [Licensed
     Architect], Age: Adult, Occ:
     Profession/Architect, R/at: Flat No.
     502, Sadhana Apartment,
     Shivajinagar, Pune - 411005.

6.   Mr. Varun Atulkumar Shah,
     Age: 38 Years, Occ: Not Known,

7.   Mrs. Richa Varun Shah,
     Age: 36 Years, Occ: Not Known,
     Both Nos. 6 & 7 R/at : A/602, Shivyog,
     Sambhajinagar, Shiv Vallabh Road,
     Near Sai Baba Temple, Ashok Va
     Dahisar, Mumbai - 400068.

8.   Mrs. Renu Yadav,
     Age: 39 Years, Occ: Not Known,


                                      2/65


            ::: Uploaded on - 10/06/2025            ::: Downloaded on - 10/06/2025 22:45:49 :::
                                                        901-AO-744-2024.doc

9.        Mr. Anil Rajaram Yadav,
          Age : 41 Years, Occ: Not Known,
          Both Nos. 8 & 9 R/at: Flat No. 302,
          Oxy 04 Valley, Phase II, Gade Vasti,
          BJS College, Wagholi,
          Pune - 412207.

10.       Mrs. Laxmi Mukund Mane,
          Age: 40 Years, Occ: Not Known,

11.       Mr. Mukund Gundanna Mane,
          Age: 49 Years, Occ: Not known,
          Both Nos. 10 & 11 R/at:
          Wadgaonsheri,
          Pune - 411014.

12.       Mr. Harshal Uday Kulkarni,
          Age: 40 Years, Occ: Not Known,

13.       Mrs. Amruta Harshal Kulkarni,
          Age: 34 Years, Occ: Not known,
          Both Nos. 12 & 13 R/at: Plot No. 18,
          Gat No. 190/1, Nisarg Colony,
          Pimprala, Jalgaon - 425001.

14.       Mr. Vipul Naveen Thakkar,
          Age: 36 Years, Occ: Not known.

15        Mrs. Shweta Vipul Thakkar,
          Age: 31 Years, Occ: Not known.

16.       Mrs. Lata Naveen Thakkar,
          Age: 57 Years, Occ: Not known.

                                    3/65


::: Uploaded on - 10/06/2025                ::: Downloaded on - 10/06/2025 22:45:50 :::
                                               901-AO-744-2024.doc

      All No. 14, 15 & 16 R/at: Flat No. A-
      903, Goodwill 124, Porwal Road,
      Dhanori,Jakat Naka, Lohegaon,
      Pune - 411047.

17.   R. Pankaj Prakash Patil,
      Age: 38 Years, Occ: Not known.

18.   Mrs. Kalyani Pankaj Patil,
      Age: 35 Years, Occ: Not known,
      Both Nos. 17 & 18 R/at: F-202,
      Santosh Park, Bhoisar Tarapur Road,
      Mark Gate,Tal. Palghar Salvad,
      Tarapor Upper Thane - 401504.

19.   Mrs. Khushboo Sushil Bajaj,
      Age: 38 Years, Occ: Homemaker,

20.   Mr. Sushil Suresh Bajaj,
      Age: 38 Years, Occ: Service,
      Both Nos. 19 & 20, R/at:
      B5 Sai Nandanvan Housing Society,
      Ganesh Nagar, Near Sundarabai
      School, Wadgaonsheri,
      Pune - 411014.

21.   Mr. Kaushik Guha,
      Age : 56 Years, Occ: Not known

22.   Mrs. Priyadarshini Roy,
      Age: 51 years, Occ: Not Known,
      Both Nos. 21 & 22 R/at:


                                       4/65


             ::: Uploaded on - 10/06/2025           ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                         901-AO-744-2024.doc

          Flat No. 5, Building No. 08,
          Konark Nagar, CHS LTD,
          Viman Nagar, Dunkirline,
          Pune- 411014.

23.       Mr. Parmatma Prasad,
          Age: Adult, Occ: Not Known.

24.       Mrs. Pooja Gupta,
          Age: Adult, Occ: Not Known,
          Both Nos. 23 & 24 R/at:
          C-1/1004, Colonade,
          S. No. 25/1A,26/1,
          Kharadi, Pune- 411014.

25.       Mr. Rahul Kumar Singh,
          Age: 35 years, Occ: Not Known.

26.       Mrs. Ruchita Shaligram Bakoliya,
          Age: 33 years, Occ: Not Known,
          Both Nos. 25 & 26 R/at:
          Flat No. 09, Building No. C-2,
          Punyadham Society, Tempo Chowk,
          Wadgaonsheri, Pune- 411014.

27.       Mr. Narendra Bhaskar Lagad         ,
          Age: Adult, Occ: Not Known.

28.       Mrs. Supriya Wamanrao Navale,
          Age: Adult, Occ: Not Known ,
          Both Nos. 27 & 28 R/at:
          Hasnapur Road, Behind Pravara


                                    5/65


::: Uploaded on - 10/06/2025                 ::: Downloaded on - 10/06/2025 22:45:50 :::
                                               901-AO-744-2024.doc

      Bank, At Post. Loni Budruk, Tal.
      Rahata, Loni Budruk,
      Ahmednagar- 413736

29.   Mr. Lakshit Chabda,
      Age: 35 years, Occ: Not Known.

30.   Mrs. Komal Arora,
      Age: 32 years, Occ: Not Known,
      Both Nos. 29 & 30 R/at:
      Flat No. 6, Unique Enclave,
      Sadesatra Nali, Hadapsar,
      Pune- 411028.

31.   Mr. Sujoy Dutta,
      Age: 43 years, Occ: Not known.

32.   Mrs. Saheli Dutta,
      Age: 38 years, Occ: Not known,
      Both Nos. 31 & 32 R/at:
      S. No. 42/2/2A, Plot No. 5B,
      Anand Mangal Society, Ganesh Nagar,
      Jain Temple, Wadgaosheri,
      Pune- 411014.

33.   Mrs. Pooja Agarwal,
      Age: 33 years, Occ: Not known.

34.   Mr. Saurabh Shrivastav,
      Age: 32 years, Occ: Not known,
      Both Nos. 33 & 34 R/at:
      B/1-1106, Tatva Apartment,


                                       6/65


             ::: Uploaded on - 10/06/2025           ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                         901-AO-744-2024.doc

          Old Kharadi- Mundhawa Road,
          Kharadi, Pune- 411014.

35.       Mr. Priya Madhab Mohapatra,
          Age: 35 years, Occ: Not known.

36.       Mrs. Priyanaka Lekan,
          Age: 33 years, Occ: Not known,
          Both Nos. 35 & 36 R/at:
          Trupti Sada, Nimidhi,
          Paradeep gadh, Jagatsinghpur,
          Odisa- 754141.

37.       Mrs. Priya Sagar Jaju,
          Age: 32 years, Occ: Not known.

38.       Mr. Sagar Shamsunder Jaju,
          Age: 33 years, Occ: Not known,
          Both Nos. 37 & 38 R/at:
          A/206, Sidhivinayak Park,
          Ashoka Marg, Ganesh Babanagar,
          Nashik- 411011.

39.       Mr. Kapil Vijay Kulkarni,
          Age: 36 years, Occ Not known.

40.       Mr. Ketan Vijay Kulkarni,
          Age: 38 years, Occ: Not known,
          Both Nos. 39 & 40 R/at:
          Flat No. A3, Radhika Vihar,
          Kesnand Road, Wagholi,
          Pune- 412207.


                                      7/65


::: Uploaded on - 10/06/2025                 ::: Downloaded on - 10/06/2025 22:45:50 :::
                                              901-AO-744-2024.doc

41.   Mrs. Maya Ashish Oza,
      Age: 33 years, Occ: Not known.

42.   Mr. Ashsih Rajaram Oza,
      Age: 35 years, Occ: Not known,
      Both Nos. 41 & 42 R/at:
      A1-201, Runwal Seagal Twonship
      Handewadi Road, Hadapsar,
      Pune- 411028.

43.   Mrs. Shradha Madhur Rathi,
      Age: 36 years, Occ: Service,

44.   Mr. Madhur Babulalji Rathi,
      Age: 37 years, Occ: Service,
      Both Nos. 43 & 44 R/at:
      36, Sarthak, Indramani Housinng
      Society, Near Anand Park Bus Stop,
      Wadgaon Sheri, Pune- 411014

45.   Mr. Amar Vishwas Mane,
      Age: 33 years, Occ: Not known.

46.   Mrs. Snehal Bajirao Shinde
      Age: 31 years, Occ: Not known,
      Both Nos. 45 & 46 R/at:
      S. Nos. 191, Nagpur Chal, Airport
      Road, Post Office, Yerwada, Pune-
      411006

47.   Mr. Amol Dattatray Todkar,
      Age: 37 years, Occ: Not known.


                                      8/65


            ::: Uploaded on - 10/06/2025           ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                          901-AO-744-2024.doc

48.       Mrs. Sangita Sudam Ghavte
          Age: 34 years, Occ: Not known,
          Both Nos. 47 & 48 R/at:
          S. No. 41/5, Jai Housing Society,
          Jai Gas Agency, Wadgaonsheri,
          Dunkerline, Pune- 411014.

49.       Mrs. Jayesh Suhas Shimpi,
          Age: 43 years, Occ: Not known.

50.       Mrs. Ansha Jayesh Smimpi,
          Age: 40 years, Occ: Not known,
          Both Nos. 49 & 50 R/at:
          Flat No. 602, A3, Prasad Nagar
          Society, Sidhivinayak Temple,
          Wadgaonsheri, Pune- 411014.

51.       Mr. Ranjit Sambhaji Pisal,
          Age: 31 Years, Occ: Not known

52.       Mrs. Priyanka Shivaji Shende,
          Age: 31 Years, Occ: Not known,
          Both Nos. 51 & 52 R/at:
          Trivenishwar Temple, Handi Nimgaon,
          Bhalegaon, Ahemdnagar - 414603.

53.       Mrs. Sneha Prasad Dhoot,
          Age: 35 Years, Occ: Doctor,

54.       Mr. Prasad Suresh Dhoot,
          Age: 35 Years, Occ: Service,
          Both Nos. 53 & 54 R/at: A/303, Bora


                                    9/65


::: Uploaded on - 10/06/2025                  ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                901-AO-744-2024.doc

      Ville Society, Kharadi, Pune - 411014.

55.   Mrs. Nayana Paresh Wadodariya
      Age: 56 Years, Occ: Not known,

56.   Mr. Hirishraj Paresh Wadodariya,
      Age: 31 Years, Occ: Not known,
      Both Nos. 55 & 56 R/at: C5, Amrapali,
      Society, Agakhan Palace, Nagar Road,
      Yerwada, Pune - 411006.

57.   Mr. Sandeep Rajendra Satpute,
      Age: 38 Years, Occ: Not known,

58.   Mrs. Bhagyashree Sandeep Satpute,
      Age: 33 Years, Occ: Not known,
      Both Nos. 57 & 58 R/at: Kalparaj,
      Bungalow, Subhash Nagar, Behind
      Sangli Akashwani Kendra, Kolhapur,
      Sangli - 416416.

59.   Mr. Anup Anil Peshwe,
      Age: 41 Years, Occ: Not Known,

60.   Mrs. Nidhi Anup Peshwe,
      Age: 40 Years, Occ: Not Known,
      Both Nos. 59 & 60 R/at: Flat No. 604,
      A Wing, Vishalshrushti Residency,
      Old Mundhwa Road, Wadgaonsheri,
      Pune - 411014.

61.   Mr. Ashok Bhagwanrao Nagargoje
      Age: 55 Years, Occ: Not Known,

                                      10/65


             ::: Uploaded on - 10/06/2025            ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                           901-AO-744-2024.doc

62.       Mrs. Surekha Ashok Nagargoje,
          Age: 45 Years, Occ: Not Known,
          Both Nos. 61 & 62 R/at: Flat No. 3,
          Vishal Corner, S. No. 34/1, Tingre
          Nagar,Pune Sub Office, Indrayani
          Nagar, Pune - 411032.

63.       Mrs. Manisha Raghunath Dabhade
          Age: 47 Years, Occ: Not Known,

64.        Mr. Raghunath Sopan Dabhade,
          Age: 54 Years, Occ: Not Known,
          Both Nos. 63 & 64 R/at: 550,
          Matoshree, Niwas, Baif Road,
          Dabahde Wasti, Wagholi,
          Pune - 412207.

65.       Mr. Akshay Arvind Kayande,
          Age: 31 years, Occ: Not known,
          R/at: Plot No. 71, Yoheshwari Plaza,
          Hanuman Nagar, Nagpur - 440009

66.       Mrs. Smita Sitaram Somwanshi,
          Age: 32 Years, Occ: Not known,

67.       Mr. Ganesh Bhagwan Kakde,
          Age: 34 Years, Occ: Not known,
          Both Nos. 66 & 67 R/at: Building,
          C-305B, Golmohar Paradise Homes,
          Thite Wasti, Behind Zensar IT Park,
          Kharadi, Pune - 411014.


                                  11/65


::: Uploaded on - 10/06/2025                   ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                  901-AO-744-2024.doc

68.   Mrs. Poonam Prakash,
      Age: 58 Years, Occ: Not known,

69.   Mr. Mayank Prakash,
      Age: 28 Years, Occ: Not known,

70.   Mr. Animesh Prakash,
      Age: 33 Years, Occ: Not known,
      All Nos. 68 to 70 R/at: Flat No. 201 A,
      Riverview Apartment, Lane No. 01,
      Wadeshwar Nagar, Sainath Nagar
      Road, Pune - 411014.

71.   Mrs. Prachi Kumar,
      Age: 35 years, Occ: Not Known,
      R/at: Deepak Bungalow, Darshan Mall,
      Shridhar Nagar, Chinchwad,
      Pune - 411033.

72.   Mrs. Ashwini Kailash Lendal,
      Age: 31 Years, Occ: Not known,

73.   Mr. Suhas Shreedhar Veer,
      Age: 35 years, Occ: Not Known,
      Both Nos. 72 & 73 R/at: Plot No. 1,
      Gat No. 139/3,        Chhatrapati Nagar,
      Near Mahadeo Temple, Satra Parisar,
      Aurangabad - 431001.

74.   Mr. Manish Arvind Rashnikar,
      Age: 50 years, Occ: Not Known,

75.   Mrs. Meera Manish Rashnikar,

                                      12/65


             ::: Uploaded on - 10/06/2025              ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                         901-AO-744-2024.doc

          Age: 48 years, Occ: Not Known,
          Both Nos. 74 & 75 R/at: S. No. 51/1,
          House No. 06/847, Renuka Niwas,
          Gharkool Housing Society, Plot No.
          36/2 Behind Stella Marie School,
          Wadgaonsheri, Pune - 411014.

76.       Mrs. Kavita Vijay Shetty
           Age: 43 Years, Occ: Not known

77.       Mr. Vijay Muddanna Shetty
          Age: 54 years, Occ: Not known
          Both Nos. 76 & 77 R/at:
          Flat No. 03, Navdurga Homes,
          S. No. 46/7/8,Bombay Sapphires
          Colony, Plot No. 6, Pune- 411014

78.       Mr. Amit Anant Utekar
          Age: 37 years, Occ: Not known

79.       Mrs. Aparna Amit Utekar
          Age: 36 years, Occ: Not known
          Both Nos. 78 & 79 R/at:
          Room No. 504, 2D Building,
          Phase II, Mohan Tulsi Vihar Complex,
          Hendrapada, Badlapur,
          Thane, 421503

80.        Mr. Himanshu Mishra
          Age: 46 years, Occ: Not known

81.        Mrs. Seema Mishra


                                     13/65


::: Uploaded on - 10/06/2025                 ::: Downloaded on - 10/06/2025 22:45:50 :::
                                               901-AO-744-2024.doc

      Age: 44 years, Occ: Not known
      Both Nos. 80 & 81 R/at:
      Flat No. 06, Wing No. 'A',
      Devkar Residency, S. No. 39/5/2/2
      Near Dutta Temple, Wadgaonsheri,
      Pune- 411014

82.   Mr. Parag Satish Kolhe
      Age: 30 years, Occ: Not known

83.   Mrs. Mamta Satish Kolhe
      Age: 54 years, Occ: Not known
      Both Nos. 82 & 83 R/at:
      Flat No. 504, Building No. C4,
      Lake Town CHS LTD, S. No. 11,
      Katraj, Pune- 411046

84.   Mr. Kishore Shankar Pramanik
      Age: 43 years, Occ: Not known
      R/at: 23B, Kantilal Chal,
      Shreyas Colony,
      Near Arey Road, Next to
      Satyam Park Hall,
      Mumbai, Goregaon East- 400063

85.   Mr. Avinash Ganpat Mahajan
      Age: 33 years, Occ: Not known
      R/at: Ram Temple Area,
      Jalgaon Khurd, Jalgaon - 425002

86.   Mrs. Sapna Gajendra Kedia


                                      14/65


             ::: Uploaded on - 10/06/2025           ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                        901-AO-744-2024.doc

          Age: 31 years, Occ: Not known

87.        Mr. Ankit Suresh Agarwal
          Age: 32 years, Occ: Not known
          Both Nos. 86 & 87 R/at:
          Near Lahanuji Maharaj Temple,
          Krushnarpan Colony, Sai Nagar,
          Amravati- 444607

88.       Mrs. Aparna Arvind Bhairat
          Age: 36 years, Occ: Not known

89.       Mr. Arvind Balaji Bhairat
          Age: 39 years, Occ: Not known
          Both Nos. 88 & 89 R/at:
          301, Vedant Residency,
           Raghvendra Nagar, S. No. 35, Plot
          No. 45, Padmachaya Hsg Soc.,
          Kharadi,Pune- 411014

90.       Mr. Naveenkumar Patro
           Age: 49 years, Occ: Not known

91.        Mrs. Bhavani Lata V
          Age:42 Years, Occ: Not Known
          Both Nos. 90 & 91 R/at:
          27-8-307/33, Survana Plaza,
          Shreenagar Gajuwaka,
          Vishakapatnam,
          Andhra Pradesh- 530026.

92.       Mr. Rahul Ramkumar Rathi,


                                    15/65


::: Uploaded on - 10/06/2025                ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                  901-AO-744-2024.doc

      Age: 36 Years, Occ: Not Known,

93.   Mr. Ramkumar Tolaram Rathi,
      Age: 65 Years, Occ: Not Known,
      Both Nos. 92 & 93 R/at:
      S. No. 232/12, Flat No. 02,
      Anand Avenue Society,
      Sakore Nagar, Viman Nagar,
      Airport Road,Pune- 411014.

94.   Mr. Anil Kumar,
      Age: 38 Years, Occ: Not Known,

95.   Mrs. Nidhi Kumari,
      Age: 37 Years, Occ: Not Known,
      Both Nos. 94 and 95 R/at:
      Flat No. 908, Selene Park, Sasane
      Nagar, Kale Padal Road, Hadapsar
      Pune 411028.

96.   Mr. Pores Bejan Katrak,
      Age: 68 Years, Occ: Not Known,

97.   Mrs. Parveen Pores Katrak,
      Age: 68 Years, Occ: Not Known,
      Both Nos. 96 & 97 R/at:
      Wing 'A', 302-303, Nirlep House,
      GD Ambekar marg,
      Behind Halfkin Institute, Village Parle,
      Parle East, Mumbai 400012.

98.   Mr. Darshan Dinesh Maru,


                                      16/65


             ::: Uploaded on - 10/06/2025              ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                        901-AO-744-2024.doc

          Age: 37 Years, Occ: Not Known,

99.       Mrs. Nilam Darshan Maru,
          Age: 35 Years, Occ: Not Known,
          Both 98 & 99 R/at:
          B-12, Kashinath Bhavan, Old Agra
          Road,Near Ratan Cinema, Narpoli,
          Bhiwandi Vidyashram,
          Bhiwandi Thane 421035.

100.      Mrs. Anushree Das,
          Age: 36 Years, Occ: Not Known,
          R/at: Azad Colony, Bhatt Bazar,
          Purniya, Bihar-854301.

101       Mrs. Madhuri Ashok Shah,
          Age: 58 Years, Occ: Not Known,

102.      Mr. Pratik Kumar Ashok Shah,
          Age: 37 Years, Occ: Not Known,
          Both 101 & 102 R/at:
          B-402, Karan Athena, Sainath Nagar,
          Wadgaonsheri, Near Kumar
          Primavera, Pune 411014.

103       Kiran Kailash Shinde,
          Age: 46 Years, Occ: Not Known,
          R/at: S. No. 59, Rajeshree Colony,
          Road No. 4A, Niramayee Hospital
          Wadgaonsheri, Pune-411014.                          ... Respondents




                                   17/65


::: Uploaded on - 10/06/2025                ::: Downloaded on - 10/06/2025 22:45:50 :::
                                                           901-AO-744-2024.doc

Mr. Surel Shah, Senior Advocate a/w. Mr. Atharva Kamble and Mr.
Ishaan Kapse i/b. Mr. Mrinal Shelar for the Appellants.

Dr. Abhinav Chandrachud (through VC a/w. Mr. Pavan Patil, Mr.
Shubham Saraf, Mr. Darshan Patankar and Mr. Kartavya Ostwal for
Respondent No. 1.

Ms. Manisha Jagtap for Respondent Nos. 2 and 3 - PMC.



                          CORAM: GAURI GODSE, J.
                          RESERVED ON: 2nd MAY 2025
                           PRONOUNCED ON: 10th JUNE 2025
JUDGMENT:

1. This appeal is preferred by defendant nos. 1 to 3 to challenge

the interim order passed in a suit filed by respondent no.1.

Respondent no. 1 is a purchaser of one flat in the building

developed by the appellants. The agreement in favour of the plaintiff

is executed under the provisions of The Maharashtra Ownerships

Flats (Regulation of the Promotion of Construction, Sale,

Management and Transfer) Act, 1963 ("MOFA") by the appellants,

i.e. defendant no. 1 as promoter. The partners of the promoter are

joined as defendant nos. 2 and 3. Defendant no. 4 is the Pune

Municipal Corporation ["corporation"], and defendant nos. 5 and 6

are officers of the corporation. Defendant no. 7 is the Architect of

901-AO-744-2024.doc

the project. Defendant nos. 8 to 105 are the flat purchasers in the

building in question.

2. The suit is filed to seek rectification in terms of the agreement

and specific performance of the rectified agreement, and challenge

the amendment to the sanctioned layout. Various other reliefs are

prayed, including a declaration that the additional floors constructed

as per the amended plan are illegal and thus also challenged the

flat purchase agreements in favour of the flat purchasers of the

additional floors. By the impugned order, the application filed by the

plaintiff seeking the grant of a temporary mandatory injunction and a

temporary prohibitory injunction is decided. The prayer for a

temporary mandatory injunction to hand over possession of the suit

flat is rejected. However, the trial court partly allowed the interim

application and granted a temporary injunction restraining defendant

nos. 1 to 3 (promoters) from carrying out any activity in the said

project with respect to the additional construction and from dealing

with or creating any further third party interest and handing over the

possession to the flat purchasers of the additional floors. The

defendant nos. 4 to 6 are restrained from sanctioning and revising

any plan, issuing any permission, sanction with respect to additional

construction not forming part of the disclosure made to the plaintiff,

901-AO-744-2024.doc

and restrained defendant nos. 8 to 105 from creating any third-party

interest.

3. The appeal was admitted vide order dated 21 st January 2025,

and by way of ad-interim relief, the order of temporary injunction

was stayed. Being aggrieved by the ad-interim relief granted by this

court, the plaintiff filed a Special Leave Petition in the Hon'ble Apex

Court. The Special Leave Petition is allowed, the ad-interim relief

granted by this court is vacated, and this court is directed to hear

and finally decide the appeal. Hence, in view of the directions

issued by the Hon'ble Apex Court, this appeal was heard for final

disposal on 2nd May 2025.

Facts in Brief:

4. By a registered agreement dated 20 th January 2017 entered

into by defendant no.1 as promoter and the plaintiff as flat

purchaser a residential flat No. 502, admeasuring 67.11 square

meters carpet area on the 5 th floor of Wing "A" of the housing

complex known as Lotus Court ("the suit flat") was agreed to be sold

to the plaintiff for a total consideration of Rs.43 lakhs. Out of the

total consideration, an amount of Rs. 5,22,500/- was paid by the

plaintiff as recorded in paragraph 8 of the agreement. The payment

901-AO-744-2024.doc

schedule regarding balance consideration was agreed between the

parties as per the Third Schedule attached to the agreement. Thus,

the balance consideration out of the total consideration of Rs .

44,93,500/- was to be paid slab-wise as indicated in the payment

schedule.

5. The plaintiff filed a suit to challenge the amendment to the

sanctioned layout on the ground that it was altered without the

informed consent of the plaintiff. The plaintiff also prayed for a

declaration that certain clauses in the agreement were violative of

the provisions of MOFA and, therefore, be declared to be duly

rectified to the effect that such clauses do not exist in the

agreement. The plaintiff thus prayed for specific performance of

such a rectified agreement. Various other reliefs were claimed for

declarations that the promoter would not be entitled to carry out

construction and other activities based on the amended plan and

would not be entitled to sell the flats constructed on the additional

floors. The plaintiff also prayed for a decree for possession of his

flat. The plaintiff further prayed for a declaration that the agreements

in favour of the flat purchasers of the additional floors were illegal.

901-AO-744-2024.doc

6. The plaintiff filed an application for a temporary injunction by

seeking various temporary and mandatory injunctions, directing

Defendant Nos. 1 to 3 to hand over the vacant and peaceful

possession of the unit to the Plaintiff, and a temporary prohibitory

injunction restraining Defendant Nos. 1 to 3 from carrying out any

activity, including but not limited to construction/completion activity,

in the said project with respect to the entire additional construction

and from dealing with or creating any further third party interest and

handing over possession under any head (e.g. soft, Interior,

Furniture, Etc.) to the purchasers who purchased their respective

units/flats in the said entire additional construction. A further

injunction was prayed to restrain the Corporation and its officers

from sanctioning and/or revising any plan and/or issuing any

permission/s sanction/s and/or Completion Certificate in part or full

in favour of the Defendant Nos. 1 to 3 with respect to the entire

additional construction The plaintiffs also prayed to restrain

Defendant Nos. 8 to 105 from creating third-party interest on the

basis of their respective agreements.

Submissions on behalf of the Appellants:

7. Learned senior counsel for the appellants submitted as

follows:

901-AO-744-2024.doc

(a)The initial commencement certificate was granted on 30 th

March 2007 for the construction of a total of 68 units. The

commencement certificate was revalidated on 27 th May 2011.

Subsequently, the commencement certificate was received on

13th October 2015 for the construction of 62 units having

Basement, Ground, Upper Parking, Podium, plus seven

floors, with a height of 32.95 metres. By way of an agreement

executed in favour of the plaintiff, he had agreed to have

purchased the suit flat with an initial date for possession as

31st December 2019. On 4th May 2019, the promoter was

permitted to construct 110 units having Basement Ground,

Upper parking, Podium, plus 14 floors with a height of 49.95

meters. On 1st June 2022, a commencement certificate was

issued for the construction of 126 units, having a Basement,

upper parking, a Podium, plus 16 floors, with a height of 55.95

meters.

(b)After filing the suit, the plaintiff called upon the promoter by

letter dated 25th November 2023, seeking possession of the

suit flat. In view of the filing of the suit challenging the various

terms and conditions of the agreement, the promoters replied

to the plaintiff's notice intimating the cancellation of the

901-AO-744-2024.doc

agreement with a refund. The promoter accordingly filed a

Written Statement-cum-Counter Claim and prayed for a

declaration that the agreement in favour of the plaintiff stands

cancelled.

(c) The trial court granted a temporary injunction by holding that

the promoters violated their obligations under MOFA and the

balance of convenience would lie in favour of the plaintiff.

Paragraph 11 of the agreement contained various clauses of

informed consent by the plaintiff. After the entire disclosure

about the project, as contained in paragraphs 2 to 11, the

specific and informed consents on behalf of the plaintiff with

regard to the additional construction were recorded in the

terms and conditions agreed between the promoters and the

plaintiff. Thus, all the relevant clauses in paragraph 11

containing the informed consent of the plaintiff were sought to

be challenged by the plaintiff in the suit. Clauses (c), (f), and

(g) of paragraph 11 contain the informed consent of the

plaintiff.

(d) The plaintiff does not challenge the termination of the

agreement by the promoter in the suit. Hence, the suit for

901-AO-744-2024.doc

specific performance of a terminated agreement would not be

maintainable. The notice dated 20 th February 2023 issued by

the plaintiff is suppressed by him at the time of filing the suit,

hence, in the written statement the promoter specifically

contended that the plaintiff by way of notice dated 20 th

February 2023 sent through Advocate Karan Parmar had

called upon the plaintiff to hand over possession of the suit

flat. The only grievance made by the plaintiff was regarding

the extension of time for completion of the construction. The

plaintiff thus never raised any grievance with regard to the

informed consent for the additional construction. The notice

issued by the plaintiff calling upon the promoters to hand over

possession is completely silent about the challenge raised by

the plaintiff in the suit. The conduct of the plaintiff indicates

that the grounds raised in the suit are by way of an

afterthought, when the plaintiff had already accepted the

additional construction and had called upon the promoters to

hand over possession of the suit flat.

(e)The cause of action pleaded by the plaintiff is of December

2022; however, the suit is filed on 14 th September 2023, after

the construction was completed and third-party rights were

901-AO-744-2024.doc

already created in favour of the flat purchasers of the

additional floors. The sanctioned plan of 27th May 2011

attached to the plaintiff's agreement shows the permissible

tenements as 149 and the proposed tenements as 68. The

consent of all the persons as contemplated under Section 7(1)

(ii) was therefore obtained from the plaintiff as specifically

recorded in paragraph 11 of the plaintiff's agreement. The

clauses in the agreement showing the informed consent of the

plaintiff are challenged for the first time in the suit. Thus, the

prayer for a temporary injunction in the suit is based on the

declaration sought by the plaintiff to challenge the clauses

containing informed consent. Hence, the plaintiff seeking to

challenge the clauses containing informed consent indicates

that he was very well aware of the informed consent as

contemplated under the provisions of MOFA. Thus, the

clauses in paragraph 11 of the agreement containing the

informed consent of the plaintiff are valid and subsisting

unless the plaintiff succeeds in the prayers in the suit seeking

to challenge the clauses. Hence, without considering the

nature of the suit and the peculiar prayers seeking specific

performance of the rectified agreement, which was based on

901-AO-744-2024.doc

the challenge to the clauses of the informed consent, the trial

court has granted a temporary injunction by also completely

ignoring the rights created in favour of the flat purchasers who

are also joined as party defendants.

(f) The occupation certificate upto the 14 th floor has already been

received, and tenements on the 15 th and 16th floors have

already been sold. Out of the total 120 tenements, the

promoter has already sold 110 tenements. Thus, considering

the nature of the dispute raised by the plaintiff, the trial court

was required to consider the three golden rules for the grant

of a temporary injunction, which has resulted in drastic

consequences in the facts of the present case. He submits

that the trial court has completely ignored the three basic

principles of prima facie case, balance of convenience and

irreparable loss.

(g)The sanctioned plan attached to the plaintiff's agreement and

the relevant clauses in the agreement clearly indicate

disclosure of the full potential of the land under development.

All the necessary approvals granted by the competent

authorities upheld the additional construction, hence there is

901-AO-744-2024.doc

no substance in the grievance raised on behalf of the plaintiff

that the additional construction would hamper the structural

integrity of the building. Admittedly, no changes have been

made to the common spaces and amenities as agreed in the

terms and conditions of the plaintiff's agreement.

(h)To support his submissions, learned senior counsel for the

appellants relied upon the legal principles regarding informed

consent as settled in the following decisions:

(a) Jayantilal Investments vs. Madhuvihar Co-op

Housing Society and Others.1

(b) Manratna Developers, Mumbai vs. Megh Ratan

Co-operative Housing Society Ltd, Mumbai and Others. 2

(d) Zircon Venture Co-operative Housing Society Ltd.,

Lohagaon, Pune vs. Zircon Ventures, Pune and Others. 3

(e) Ambalal Sarabhai Enterprise Limited vs. KS

Infraspace LLP Limited and Another.4

(f) Lakeview Developers vs. Eternia Co-operative

Housing Society Ltd.5

1 (2007) 9 SCC 220 2 2009 (2) Mh.L.J. 115 3 2014 (4) Mh. L. J. 481 4 (2020) 5 SCC 410 5 2015 SCC OnLine Bom 3824

901-AO-744-2024.doc

(g) Dosti Corporation, Mumbai vs. Sea Flama Co-

operative Housing Society Ltd. Mumbai and Others 6

(h) Madhuvihar Co-operative Housing Society,

Mumbai and Others vs. Jayantilal Investments, Mumbai

and Others7.

(i) Learned senior counsel for the appellants thus submitted that

the conduct of the plaintiff does not deserve any discretionary

relief as envisaged under Order XXXIX Rule (1) and (2) of the

CPC. He submits that the principle of delay defeats equity

would fairly apply to the facts of the present case. He submits

that in any event, suppression of issuance of notice in January

2023 calling upon the promoters to hand over possession of

the suit flat, without making any grievance about the additional

construction, the plaintiff is not entitled to any discretionary

relief as granted by the trial court.

(j) After the amendment of MOFA by insertion of Section 7A, if

the promoter gets approval from the planning authority for

additional structure or building, the purchaser cannot object to

the additional structure. In the case of Jayantilal Investment, it

6 2016(5) Mh.L.J. 102 7 2011(1) Mh.L.J. 641

901-AO-744-2024.doc

is held that in the absence of consent of flat purchasers, the

promoter cannot raise additional structure without sanction of

the modified plan. In the present case, since additional

structure has come up after the sanction of the local authority,

no express consent was necessary from the flat purchasers.

(k) The plaintiff has miserably failed to prove any prima facie

case, a balance of convenience, or irreparable loss to him. It

is a well-established position of law that before granting a

temporary injunction, the applicant has to satisfy the three

basic principles of a prima facie case, balance of convenience

and irreparable loss. In the facts of the present case and the

conduct of the plaintiff, he is not entitled to the injunction

granted by the trial court. The trial court has erroneously held

that irreparable loss would be caused to the plaintiff. The trial

court has completely ignored that the promoter has invested a

large amount in developing the property to its full potential and

that defendant no. 8 to 105 have invested their hard earned

money for purchasing flats and thus if the defendants are

restricted at this stage by way of temporary injunction granted

by the impugned order, irreparable loss would be caused to

the promoters as well as the flat purchasers and the loss

901-AO-744-2024.doc

cannot be compensated in terms of money. Hence, the

impugned order deserves interference by this court.

Submissions on behalf of the Respondent No.1 (Plaintiff):

8. The submissions made by the learned counsel for the plaintiff

are as follows;

a) The entire complexion of the project has changed in view of

the additional construction in terms of the amended plan. The

promoter does not deny the plaintiff's factual averments in the

written statement. The trial court considered the plaintiff's

specific contention regarding the change in the nature of the

amenities while granting the interim injunction.

b) On the aspect of legal position regarding informed consent,

learned counsel for the plaintiff relied upon paragraphs 14 and

15 of the decision of Jayantilal Investment. Only in the event

of constructing an additional building, informed consent from

the flat purchasers will not be necessary. However, in view of

section 7(1)(ii) of MOFA, the informed consent of flat

purchasers would be necessary in the event any additional

construction is proposed in the same building, which amounts

to a change in the nature of the building. A separate consent

901-AO-744-2024.doc

may not be necessary only when there is a specific disclosure

in the agreement regarding any proposed change or addition

to the building.

c) In the plaintiff's agreement, the disclosure regarding the FSI

potential is 4921.53 sq. meters. However, by way of amended

plans, the same is increased to 11575.14 sq.mtrs. Thus, it is

incumbent upon the promoter to disclose the full development

potential. To support his submissions, learned counsel for the

plaintiff relied upon the legal principles in paragraph 18 of the

decision of Jayantilal Investment.

d) The term 'prior consent' would include disclosure of

everything by the promoter. On the ground of the blank

consents as recorded in the suit agreement, the promoter is

not entitled to carry out changes in the building by adding

floors, which would amount to a change in the complete

complexion of the building. The full and complete disclosure,

even with regard to the phases of the project, is to be made in

the agreement. The additional floors would mean that the

amenities available to the flat purchasers would be required to

be shared with almost double the number of occupants in the

901-AO-744-2024.doc

building, which is unfair to the plaintiff, who was put on notice

that the amenities would be shared by the occupants of only

the ground plus six floors.

e) In the facts of the present case, the clauses in paragraph 11

of the agreement would amount to a blanket consent, which is

contrary to the provisions of MOFA. Hence, the legal

principles settled by this court in the case of Madhuvihar CHS

squarely apply in favour of the plaintiff. The legal principles

settled in the decision of Manratna Developers, relied upon by

the learned senior counsel for the appellants, are

distinguished in the decision of Lakeview Developers.

Considering the legal principles in the decision of Lake View

Developers and Dosti Corporation, the legal principles settled

in the decision of Manratna Developers would not be of any

assistance to the arguments raised on behalf of the promoter.

In the decision of Malad Kokil Co-operative Housing Society

vs. The Modern Construction Co. Ltd .8, this court held that if

the floor space index is utilised by the promoter elsewhere,

then the promoter is required to furnish to the flat purchasers

with all the detailed particulars in respect of such utilisation of

8 (2012) 46 BOM C.R. 476

901-AO-744-2024.doc

the FSI. So far as the residual FSI in the plot or layout is

concerned, it is not consumed by the promoter and will be

available to the promoter only till the registration of the

society. The promoter is therefore not only required to make

disclosure concerning the inherent FSI, but also required to

declare whether the plot in question in future is capable of

being loaded with additional FSI/TDR. This court held that at

the time of execution of the agreement with the flat

purchasers, the promoter is obliged statutorily to place before

the flat purchasers the project scheme for any one building or

multiple buildings. Therefore, in the absence of disclosure of

the project's full potential, the clauses in paragraph 11 of the

plaintiff's agreement would amount to taking a blanket

consent contrary to the legal principles settled by this court in

the case of Madhuvihar CHS.

f) Therefore, in the present case, in the absence of complete

and full disclosure, the promoter would not be entitled to

construct additional floors, which would adversely affect the

rights created in favour of the plaintiff. The obligation as

contemplated under MOFA is to be performed by the

developer. Hence, the termination letter issued after the filing

901-AO-744-2024.doc

of the suit would not be relevant for deciding the prayers for

an interim injunction. The suit was filed on 14 th September

2023, and the promoter issued the termination on 27 th

November 2023. Therefore, it will always be open to the

plaintiff to challenge the illegal termination. Hence, on the

ground of termination not being challenged at this stage, the

plaintiff cannot be denied the relief of a temporary injunction.

g) Learned counsel for the plaintiff, therefore, submits that the

view taken by the trial court is plausible. Hence, in view of the

legal principles settled by the Wander Ltd. vs. Antox India (P)

Ltd9 the plausible view taken by the trial court may not be

interfered with in this appeal only on the ground that a

different view would be possible.

Analysis and conclusions:

9. I have considered the submissions made on behalf of both

parties. I have perused the papers of the appeal. The following

dates and events would be relevant for considering whether the

plaintiff would be entitled to a discretionary relief of temporary

injunction:

9 1990 (Supp) SCC 727

901-AO-744-2024.doc

(a) 20th January 2017: An agreement is executed

under MOFA for purchasing the suit flat based on the

commencement certificate dated 13 th October 2015 for the

construction of 62 out of the permissible units of 126.

(b) 4th May 2019: Commencement Certificate is issued

for constructing 110 units.

(c) 1st June 2022: Commencement Certificate is

issued for constructing 126 units based on the initial

permissible units.

(d) 2017-2020: The plaintiff claims to have visited the

construction site periodically to see the updated

construction.

(e) December 2022: The plaintiff claims to have

visited the construction site for the first time after the

COVID-19 lockdown from March 2020. Plaintiff pleads he

learnt about the construction of higher floors in December

2022.

(f) January 2023: According to the promoter, the

plaintiff issued notice through his Advocate calling upon

901-AO-744-2024.doc

the promoter to handover possession of the suit flat. It is

pertinent to note that the plaintiff made no grievance about

the additional construction in his notice issued through his

Advocate in January 2023. It is further pertinent to note

that the plaintiff has not disclosed the issuance of such

notice in the plaint.

(h) 14th September 2023: The plaintiff filed the present

suit seeking to challenge the relevant clauses in

paragraph 11 of the suit agreement containing informed

consent.

(i) 9th November 2023: The occupation certificate up

to the 14th floor is granted.

(j) 25th November 2023: The plaintiff called upon the

promoter to provide information about the occupation

certificate received and also sought possession of the suit

flat.

(k) 27th November 2023: The promoter intimated the

plaintiff about cancellation of the suit agreement with

refund.

901-AO-744-2024.doc

(l) Admittedly, the suit agreement in favour of the

plaintiff is for a total consideration of Rs. 42 lakhs, and

according to the promoter, the remaining consideration

amount to be paid till date is Rs. 27 lakhs.

(m) 16th July 2024: The trial court decided the interim

application for a temporary injunction and granted various

injunctions restraining the promoter as well as the flat

purchasers of the additional floors.

10. To decide whether the plaintiff is entitled to an interim

injunction, it is necessary to understand the legal position based on

which the plaintiff is seeking an interim injunction. Learned counsel

for the plaintiff has mainly relied upon the decision of this court in

the case of Madhuvihar CHS, to support his submissions that the

construction carried out pursuant to the sanctioned amended plans

without the informed consent of the plaintiff is in breach of the

provisions of MOFA.

11. In view of the unamended Section 7 of MOFA, consent was

attached to the concept of additional structure. Section 7 of MOFA

came to be amended, and for the purpose of removal of doubt,

additional Section 7-A came to be added by the Maharashtra Act 36

901-AO-744-2024.doc

of 1986. The Hon'ble Apex Court in the decision of Jayantilal

Investments, held that by this amendment, the words indicated in

the parenthesis in the unamended Section 7(1)(ii), namely, "or

construct any additional structures" came to be deleted and

consequential amendments were made in Section 7(1)(ii).

Maharashtra Act 36 of 1986 operated retrospectively. The Apex

Court held that reading Section 7 and Section 7-A, it is clear that the

question of taking prior consent of the flat takers does not arise after

the amendment in respect of any construction of additional

structures; however, the right to make any construction of additional

structures/buildings would come into existence only on the approval

of the plan by the competent authority and that the object behind

the said amendment was to give maximum weightage to the

exploitation of development rights which existed in the land. It is

further held that the promoter is also required to declare that no part

of that FSI has been utilised elsewhere, and if it is utilised, the

promoter has to give particulars of such utilisation to the flat takers

and under the proforma agreement, the promoter has to further

declare utilisation of FSI of any other land for the purposes of

developing the land in question which is covered by the agreement.

901-AO-744-2024.doc

12. After discussing Sections 3, 4 and 10 of MOFA, the Hon'ble

Apex Court in the case of Jayantilal Investments held that it was

necessary to balance the rights of the promoter to make alterations

or additions in the structure of the building in accordance with the

layout plan on the one hand vis-a-vis his obligations to form the

society and convey the right, title and interest in the property to that

society. It was further held that at the time of execution of the

agreement with the flat purchasers, the promoter is obliged

statutorily to place before the flat purchasers the entire

project/scheme, be it a one-building scheme or multiple number of

buildings scheme. The Hon'ble Apex Court thus, held that the

condition of true and full disclosure flows from the obligation of the

promoter under MOFA vide Sections 3 and 4 and Form V, which

prescribes the form of agreement and this obligation remains

unfettered because the concept of developability has to be

harmoniously read with the concept of registration of society and

conveyance of title. Thus, it was held that once the entire project is

placed before the flat takers at the time of the agreement, then the

promoter is not required to obtain prior consent of the flat takers as

long as the builder puts up additional construction in accordance

with the layout plan, building rules and Development Control

901-AO-744-2024.doc

Regulations. The Hon'ble Apex Court remitted the matter to the

High Court for reconsideration on merits.

13. Accordingly, this Court decided the matter in the case of

Madhuvihar CHS. In the meantime, the Hon'ble Division Bench of

this Court, by relying upon the legal principles settled by the Hon'ble

Apex Court in the case of Jayantilal Investments, decided the case

of Manratna Developers. The Hon'ble Division Bench held that in

the facts of that case, the parties had agreed that the promoters

would be developing the property in a phased manner, the entire

FSI/TDR was to be used by the Promoter to the exclusion of the flat

purchasers or the Society that they would form, and the disclosure

in regard to TDR was not made in the agreement, as the very

concept of TDR was non-existent in the year 1988. It was thus, held

as under in paragraph 12;

"12. Taking over all view of the matter whats surfaces is that the defendants have constructed only one wing of a building which is very small portion even according to the original sanctioned plan. Rest of the property could not be developed though was intended to be developed in phased manner, as according to the appellants, the premises were not vacated by the tenants. However, after a portion of the plot was vacated by the tenants

901-AO-744-2024.doc

residing in the dilapidated structures, it became feasible for the defendants to develop the property upto its permissible full potential and thus modified plans in accordance with the building bye-laws were submitted to the Corporation. The local authority, on being satisfied that the defendants were not constructing anything in excess of what is permissible according to the potential of the property, sanctioned the modified plan and after approval of the modified plans, the appellant was proceeding to carry out the construction which was objected to by the flat purchasers of erstwhile lower arm of Building "A". The amenities in the form of recreation ground are, in no way, reduced. The consent of the flat purchasers after amendment of section 7 and insertion of section 7A is not necessary if additional structures/buildings are to be raised after obtaining approvals or sanction from the' Municipal Corporation. The balance of convenience lies in favour of the defendants, as restraining them from carrying out the proposed construction which has been sanctioned by the Municipal Corporation, would cause undue hardships and inconvenience and lock the property for years. We are also of the view that the agreements entered into with the flat purchasers clearly postulate the development of the property in phased manner, according to the sanctioned plans or modified plans sanctioned in due course of time. Thus, prima facie, the appellants/defendants appear to have complied with the requirement of true and full disclosure as envisaged by Clauses 3 and 4. There could not have been disclosure in regard to TDR, as the very concept of TDR was not prevailing when the agreement was entered into in the year 1988 and had been

901-AO-744-2024.doc

introduced by the Development Control Rules in the year 1991. Hence, the appellants/defendants can not be blamed on that count."

emphasis applied by me

14. This court in the decision of Madhuvihar CHS, referred to the

findings in Manratna Developers and held that it would not be

applicable to the facts of the case as the plaintiff, who was flat

purchaser in lower arm of building "A", was in occupation of small

portion of the building and the scheme was for development of the

property in a phased manner and not one building scheme; hence,

the Division Bench prima facie found that the amenities in the form

of recreation ground, etc. are nowhere reduced and, as such, in the

facts of the case, as no prima facie case was made out, interfered

with the order of injunction. In the case of Madhuvihar CHS, the

project was never intended to be a project for phased development,

hence this Court held that on the interpretation of section 7(1) of the

MOFA, reference to other judgments except to the judgment of

Ravindra Mutenja vs. Bhavan Corporation 10, would not be

necessary, in view of the law explicitly laid down by the Apex Court

in the judgment of Jayantilal Investments while remanding the

10 2003 (5) Mh. L.J. 23

901-AO-744-2024.doc

matter. The applicability of the judgment in the case of Ravindra

Mutenja was considered, as was directed by the Supreme Court in

the judgment of remand.

15. This Court in the judgment of Madhuvihar CHS, held that the

learned Single Judge in the decision in the case of Ravindra

Mutenja, in unequivocal terms held that once the building shown in

the approved plan submitted in terms of the regulations under an

existing scheme, has been completed and possession handed over,

the builder/owner cannot contend, that because he has not formed

the society and has not conveyed the property under the MOFA, he

is entitled to take advantage of any additional F.S.I. that may

become available because of subsequent events and that once the

building is completed and the purchasers are put in occupation in

terms of plan and the time to form the society or convey the

property in terms of the agreement or the rules framed under MOFA

is over, the permission of such purchasers would be required. The

relevant findings in paragraphs 32 and 33 in the case of Ravindra

Mutneja, were reproduced, which read as under :

"32. The real issue as has been noted earlier is what is the stage up to which the developer/owner can put up additional construction after the building in terms of the registered plan has

901-AO-744-2024.doc

been constructed and occupied. In my opinion, once the buildings shown in the approved plan submitted in terms of the regulations under an existing scheme filed before the authorities under MOFA Act, have been completed and possession handed over, the builder/owner cannot contend, that because he has not formed the society and/or not conveyed the property by sale deed under the Act he is entitled to take advantage of any additional F.S.I. that may become available because of subsequent events. That would be so at the stage the building is under construction or the building is not completed and/or purchasers are not put in occupation provided such building forms part of the development plan and/or layout plan already approved. Subsequent amendment of the layout plan after the building plan is registered under MOFA, without the consent, prima facie, of the flat purchasers would not be permissible. It may be possible to accept that the development plan could be modified as long as the right of the purchasers and the benefits which they are entitled to including recreational and open areas are not effected by the revised development plan. Once the building is completed and the purchasers are put in occupation in terms of plan filed and the time to form the society or convey the property in terms of the agreement or the rules framed under MOFA is over the permission of such purchasers would be required.

33. In the instant case, the building completion certificate for the plaintiff's building, was issued in the year 1997. The

901-AO-744-2024.doc

builder/owner defendant Nos. 1, 3 and 4 had to put up the construction, based upon the permission/license granted. The defendant Nos. 1, 3 and 4 had to construct the building and to convey the title by sale deed in terms of Rule 9. If property had been conveyed, prima facie the remaining FSI or FSI which become subsequently available on the facts of the case, would be to the society to whom the land had to be conveyed. The record shows that the building was approved in December, 2001. It cannot prima facie, be said that defendants Nos. 1, 2, 4 and 5 have any rights under which they are entitled to put up an additional building contrary to section 7A of the Act."

(emphasis applied in the judgment of Madhuvihar CHS)

16. This court, in the decision of Madhuvihar CHS, thus, held in

paragraph 42 as under:

" 42. In the present case, the scheme was floated in the year

1985, showing 7 wings. The building was completed in the

year 1989 and the purchasers who had entered into

agreement with the promoter were put in possession. In this

respect, it would also be relevant to refer to condition No. 4 of

the occupation certificate dated 12th April, 1989 issued by the

Bombay Municipal Corporation, which reads thus :

901-AO-744-2024.doc

"That, the Co-operative Society shall be formed and registered within three months from the dale of issue hereof, or before B.C.C. whichever is earlier."

It is not in dispute, that in furtherance to the statutory obligation enjoined upon the promoter, in view of section 10 of the MOFA and Rule 8 of the Rules, though the promoter had initially taken steps for forming of Co-operative Society, the matter was not taken to logical end. As such, the flat takers were required to move the appropriate authority for registration of the Society. Accordingly, the competent authority granted registration to the plaintiff No. I/Society on 20th January, 1993. It is further to be noted that though the appeal was preferred by the promoter against the said order, the appeal was rejected. It could, thus, be seen that the promoter was under

the statutory obligation in view of section 11 of the MOFA read with Rule 9 of the Rules, to execute conveyance in favour of the Society, within a period of four months. In view of the judgment of the learned Single Judge of this Court, in the case of Ravindra Mutenja (cited supra), once the building shown in the approved plan was completed and possession handed over and the time frame prescribed for registration of the Society and conveying land to the Society is over, the promoter was legally precluded from putting up further construction without consent."

emphasis applied by me

901-AO-744-2024.doc

17. This court, after referring to various other decisions of this

court, decided the question as to whether the consent which is

deemed to be given in the clauses of the agreement would be a

valid consent for the purposes of section 7 of the MOFA. It was held

that it is a consistent view of this Court, that the consent as

contemplated under section 7(1) of the MOFA has to be an

informed consent which is to be obtained upon a full disclosure by

the developer of the entire project and that a blanket consent or

authority obtained by the promoter at the time of entering into

agreement of sale would not be a consent contemplated under the

provisions of the MOFA. In the facts of the case in Madhuvihar

CHS, it was therefore concluded that the promoter was statutorily

obliged to execute conveyance in favour of the Society within a

period of 4 months from 20th January, 1993 i.e. the date of

registration of the Society; therefore the additional structure which

was not forming part of the original layout in the year 1985, could

not have been constructed without consent of the Society.

18. The decision in the case of Lakeview Developers, relied upon

by the learned counsel for the plaintiff, would not be of any

assistance to the plaintiff in view of the different facts of this case.

901-AO-744-2024.doc

After discussing all the legal principles by referring to the various

judgments, including the judgments discussed in the above

paragraphs, this court in the decision of Lakeview Developers, in

view of the facts of that case, held that if the full development

potential of the land is exhausted and the obligation for conveyance

of land in favour of the Society has arisen as per the Act and Rules

and if the developer fails to do so then any further benefit which

would accrue to the developer on account of any additional TDR or

FSI made available, cannot be used by him for the purpose of

construction of additional buildings. Thus, even in the decision of

Lakeview Developers, the stage of construction for utilising the

additional benefits of FSI and the obligation of the promoter to

convey the land to society are considered as important factors.

19. Even the decision of this court in the case of Dosti

Corporation, would not be of any assistance to the plaintiff. This

Court, in the said decision, was dealing with a challenge to the order

of a temporary injunction granted in favour of a society against the

developer restraining from putting up any construction work upon or

over the suit properties till disposal of the suit and further restraining

from using any FSI as available in the suit properties or part thereof

901-AO-744-2024.doc

till disposal of the suit. The relevant facts of the case were that the

development of the suit property commenced on 27 th May, 2004

and continued till 31st March, 2008. During the stage of the

construction on the suit property, various parties entered into

agreement for sale with the defendant No. 1 for purchase of various

flats in the four wings. A complex comprising four wings was

completed, and four separate co-operative housing societies

connected by a common basement podium were registered. A

completion certificate was also issued. Thereafter, the developer

applied for modification of the plan and had applied for construction

of a public parking lot without obtaining consent of the flat

purchasers. In these facts, this court after discussing the well-

established legal principles held that the members of the society

were already put in possession of their respective flats and the

subsequent amendment of the lay out plan could not have been

effected without the consent of the flat purchasers and such

amendment without such consent was not permissible and thus not

binding on the flat purchasers.

20. This court in the decision of Malad Kokil CHS, held that the

very purpose that the entire layout should be presented to the flat

901-AO-744-2024.doc

purchasers and that there should be full disclosure made to him is

with the purpose that he should be aware as to what is the entire

layout of the scheme in which he is going to purchase the property.

It is held that if the original layout shows only the proposed building

of ground + one, the flat taker would purchase the same with the

knowledge that only few more persons are likely to join the Society

and there would not be much effect on the facilities, amenities etc.

provided to the members of the Society; however, if a structure of

ground + one is converted in a towering structure of 28 storeys, the

entire scenario would change and the number of additional

members that would reside on the said plot would increase by

substantial number, thereby putting an additional load on the

infrastructure, amenities, facilities etc. available on the said plot.

This court thus held that if this is permitted, the very purpose of

requiring a developer to make full and complete disclosure would

stand frustrated. This court held that it is a consistent view of this

Court, that the consent as contemplated under Section 7(1) of the

MOFA has to be an informed consent which is to be obtained upon

a full disclosure by the developer of the entire project and that a

blanket consent or authority obtained by the promoter at the time of

entering into agreement of sale would not be a consent

901-AO-744-2024.doc

contemplated under the provisions of the MOFA. It is important to

note that even in this case, the construction was complete, the

society was registered and the suit was filed by the society for a

decree to convey the property and for a declaration that the

concessions/relaxations granted to the developer are bad in law,

malicious etc. and thus prayed for a declaration that

commencement certificate was null and void. In this suit, a

temporary injunction was granted restraining the defendants from

making any construction.

21. In all these decisions, the suit was filed after the construction

was complete and the society of the flat purchasers was formed and

registered. Hence, the issue of informed consent was examined in

the context of full disclosure about the potentiality of the permissible

construction. In the decision of Zircon Venture CHS, this court held

that the sanction of the layouts is evidenced by the certificate issued

by the Architect and therefore, the Promoter/Developer would be

entitled to put up the building as per the layout sanctioned by the

Local Authority. With reference to the contention in respect of the

pressure on the infrastructure on account of the construction of the

building this court held that the said objection cannot be

901-AO-744-2024.doc

countenanced once there is a true and full disclosure of the

complete scheme by the Developer and that it was only when there

is no full disclosure that the said contention would be available to

the flat purchasers. The facts of the scheme of development had

been disclosed and the sanctions envisaged the construction of 12

buildings and therefore, it was held that it was not a case where the

nature of construction has undergone a drastic change, and

therefore the judgment in Malad Kokil CHS would have no

application regarding the contention about the pressure on

infrastructure. It was thus held as under:

"The prior consent of the flat owner would not be required if the

entire project is placed before the flat taker at the time of

agreement and that the builder puts an additional construction in

accordance with the layout plan, building rules and Development

Control Regulations. It is, thus, manifest that if the promoter

wants to make additional construction, which is not a part of the

layout which was placed before flat taker at the time of

agreement, the consent as required under section 7 of the

MOFA, would be necessary."

901-AO-744-2024.doc

22. Thus, considering the well-established legal principles as

discussed above, it is necessary to balance the rights of the

promoter to make alterations or additions in the structure of the

building in accordance with the layout plan on the one hand vis-à-

vis his obligations to form the society and convey the right, title and

interest in the property to that society. At the time of execution of

the agreement with the flat purchasers, the promoter is obliged

statutorily to place before the flat purchasers the entire

project/scheme, be it a one-building scheme or multiple number of

buildings scheme and the condition of true and full disclosure flows

from the obligation of the promoter under MOFA vide Sections 3

and 4 and Form V, which prescribes the form of agreement and this

obligation remains unfettered because the concept of developability

has to be harmoniously read with the concept of registration of

society and conveyance of title. Thus, once the entire project is

placed before the flat takers at the time of the agreement, then the

promoter is not required to obtain prior consent of the flat takers as

long as the builder puts up additional construction in accordance

with the layout plan, building rules and Development Control

Regulations. Thus, the issue of disclosure of the full potential of the

project and developability, and the informed consent of the flat

901-AO-744-2024.doc

purchaser cannot be decided on any straightjacket formula, in as

much as, these issues would depend upon the facts of each case.

The concept of informed consent cannot be stretched beyond the

statutory obligations of the Promoter as contemplated under

Sections 3 and 4 of MOFA and form V, which prescribes the format

of the agreement.

23. In the present case, the flat purchase agreement discloses the

revised layout and revised commencement certificate dated 27 th

May 2011 and 13th October 2015 for the construction of multi-storied

buildings, amenity space, open space and the area under internal

roads. Paragraphs 1 to 5 of the agreement disclose the

specifications of the complex. Paragraph 11 of the agreement

discloses the particulars regarding the explicit consent of the plaintiff

regarding the promoter's entitlement to consume FAR and

Transferable Development Rights, extended construction and

additional floors. The clauses in paragraph 11 also provides for the

developer's right to exploit the full potentiality of development even

if possession of units is handed over and the entitlement of the

promoter to make changes in the elevation and specifications of the

901-AO-744-2024.doc

complex, on a condition that such changes shall not materially affect

the internal plan and location of the unit sold to the plaintiff.

24. It is important to note that the layout of the 2015 annexed to

the plaintiff's agreement discloses the complete area statement,

including permissible tenements of 123 out of which 62 tenements

are shown as proposed. Thus, the clauses providing the plaintiff's

consent in paragraph 11 of the agreement are to be read with

reference to the area statement and the tenement statement in the

approved layout annexed to the agreement. It is further pertinent to

note that the relevant clauses containing the plaintiff's consent,

recorded in paragraph 11 of the agreement, are challenged by the

plaintiff in the suit. The challenge to the amended plans of 2019 on

the ground that it is without the plaintiff's consent is based on the

substantive prayer to challenge the clauses containing the plaintiff's

consent to enable the developer to utilise the full potential of the

land, including extension to the construction and additional floors.

Thus, the plaintiff signed the agreement, with full knowledge about

the scope of the project and he consenting for the promoter to

utilise the full potentiality of the project. However, by filing the suit,

the plaintiff for the first time raised objection to the clauses of the

901-AO-744-2024.doc

agreement containing his consent and sought to withdraw his

consent. Prima facie, the clauses in agreement contain the plaintiff's

informed consent as contemplated under Section 7 of the MOFA,

and the appellants/defendants appear to have complied with the

requirement of true and full disclosure, as contemplated under

Section 3 of MOFA.

25. A perusal of the reasons recorded in the impugned judgment

indicates that the trial court has misinterpreted all the relevant terms

and conditions of the agreement. The trial court has completely

ignored that the substantive prayer in the suit is to challenge the

clauses in paragraph 11 of the suit agreement, which pertain to the

informed consent of the plaintiff for the proposed additional

construction. A perusal of the reasons recorded by the learned trial

Judge does not indicate an appreciation of the disclosure made in

the plaintiff's agreement.

26. The learned trial judge has reproduced the changes made in

the updated and revised plans. However, the learned Judge has

ignored the contents of the agreement and the plan attached to the

agreement, which indicates that the permissible units in the building

in which the plaintiff has purchased the flat are 126 flats. Learned

901-AO-744-2024.doc

Judge has emphasised the commencement certificate and the total

flat area, including amenities, and the open space. However, the

learned Judge has not considered the effect of the specific clauses

in paragraph 11 of the suit agreement, which also disclose the

proposed increase in the floors. Without recording any prima facie

findings on the effect of the specific clauses in paragraph 11 of the

plaintiff's agreement, the learned Judge has held that the consent of

the plaintiff and other flat purchasers was not taken before the

alteration. Learned Judge emphasized the construction of additional

floors; however, completely ignored the effect of the specific clauses

in paragraph 11 of the plaintiff's agreement.

27. Based on the subsequent changes and alterations in the

sanctioned plan, the learned Judge has erroneously concluded that

the promoters have obtained sanction illegally and colluded with the

municipal corporation and its officers. There is absolutely no basis

or foundation for the findings in the impugned judgment for

concluding that there was collusion with the corporation and its

officers. In the absence of any pleadings and prima facie indication

of any collusion, the reasons recorded in the impugned judgment

amount to perverse findings.

901-AO-744-2024.doc

28. Without considering the effect of the clauses in paragraph 11

of the plaintiff's agreement, the learned Judge observed that the suit

raises triable issues. The conclusion recorded by the trial court that

there is a prima facie case made by the plaintiff and that the

balance of convenience lies in his favour, is based on the reason

recorded by the trial court that triable issues are raised in the suit.

Only raising a triable issue would not entitle the plaintiff to any

temporary injunction that has drastic consequences.

29. The learned Judge completely ignored the rights created in

favour of the flat purchasers of the additional floors who were added

as party defendant nos. 8 to 105. The impugned judgment is bereft

of any discussion on the conduct of the plaintiff in not disclosing his

Advocate's letter in January 2023 seeking possession without

raising any grievance about the additional construction and seeking

an injunction at a belated stage despite having knowledge about the

construction of additional floors. The relevant clauses in paragraph

11 of the plaintiff's agreement disclose the future potential

development of the building in which the flat is purchased by the

plaintiff. The learned trial judge has completely ignored the effect

901-AO-744-2024.doc

and drastic consequences of the injunction on the rights created in

favour of the flat purchasers of the additional floors.

30. The learned Judge has not even referred to the total

consideration of the plaintiff's flat and the balance payments yet to

be made by the plaintiff towards the total consideration. Thus, the

impugned order's ultimate effect is granting a drastic injunction in

favour of the plaintiff who has not yet paid the entire consideration

amount. The plaintiff has not pleaded his rights in respect of the

additional TDR or FSI available to the developer. Admittedly, the

stage of formation of a co-operative society and registration of the

society has not yet arisen in the facts of the present case. Hence,

the reasons recorded by the trial Judge in paragraphs 61 and 62

are irrelevant regarding the plaintiff's grievance in the suit.

31. Learned Judge in paragraph 63 of the impugned judgment

further recorded findings on the duties discharged by the architect

and the alleged collusion with the corporation in permitting illegal

construction. Thus, the learned Judge has proceeded on the footing

that the construction carried out by the promoter is an illegal

construction. The reasons regarding collusion between the

promoter, the municipal corporation and the architect are ill-founded

901-AO-744-2024.doc

and imaginary. Thus, the reasons recorded for the grant of an

injunction that has drastic consequences are without any prima

facie findings on the entitlement of the plaintiff to the nature of the

prayers made in the suit. The grant of injunction, even if in aid of

final reliefs, cannot be granted without recording findings on any

prima facie case made by the plaintiff, the balance of convenience

and irreparable loss.

32. Learned Judge held that the irreparable loss and balance of

convenience is in favour of the plaintiff by completely ignoring the

plaintiff's conduct and the execution of the agreements in favour of

the flat purchasers on the upper floors. Nothing is indicated in the

impugned judgment and order about the irreparable loss that would

be caused to the flat purchasers of the additional floors. Thus, the

reasons recorded in the impugned judgment for granting an

injunction with drastic consequences, without satisfying the basic

principles of the grant of a temporary injunction, are therefore

perverse and contrary to the well-settled legal principles. By the

impugned order, the promoter/developer is restrained from carrying

out any activity in the project with respect to the additional floors,

creating any further third-party interest or handing over possession

901-AO-744-2024.doc

to the purchasers of the respective flats of the upper floors. The

impugned judgment and order do not deal with the aspect as to

whether the rights of defendant nos. 8 to 105 need to be protected

for the loss that would be suffered in the event the plaintiff fails in

the suit. The drastic injunction granted by way of the impugned

order without recording any findings on the balance of convenience

and irreparable loss that would be suffered by defendant nos. 8 to

105 would not be sustainable.

33. Prima facie, the clauses in the agreement executed in favour

of the plaintiff, particularly the clauses in paragraph 11, would not

amount to any blanket consent. The challenge to the specific

clauses containing informed consent itself indicates that the plaintiff

was well aware of the informed consent for utilisation of the full

potential of the land under development, including the proposed

additional units as reflected in the sanctioned layout of 2015

attached to the plaintiff's agreement. Admittedly, there is no

alteration in the flat, or there is no alteration or change in the

common amenities to be provided as per the agreement and the

sanctioned layout. Hence, the impugned order granting an

injunction with drastic consequences would not be sustainable.

901-AO-744-2024.doc

34. The plaintiff has not yet challenged the termination of his

agreement. Though it may be open to the plaintiff to amend his

plaint to challenge the termination, it cannot be ignored that at the

stage of deciding the prayer for interim injunction, there is no

challenge to the termination of the agreement. The plaintiff has

prayed for rectification of the clauses in the agreement pertaining to

the disclosure of the project and the plaintiff's consent, which prima

facie amounts to full disclosure and informed consent. The plaintiff

has made a peculiar prayer for specific performance of such

rectified agreement.

35. The learned trial judge ignores the legal principles settled by

the Hon'ble Apex Court in the decision of Ambalal Sarabhai

Enterprises for the grant of the interim injunction. The Hon'ble Apex

court held that the grant of relief in a suit for specific performance is

itself a discretionary remedy, and a plaintiff seeking a temporary

injunction will therefore have to establish a strong prima facie case

on the basis of undisputed facts. It is further held that the conduct of

the plaintiff will also be a very relevant consideration for the purpose

of injunction, and the discretion has to be exercised judiciously and

not arbitrarily. The Hon'ble Apex Court held that the principles in

901-AO-744-2024.doc

Wander Ltd., prescribe a rule of prudence only, and much will

depend upon the facts of each case.

36. In the present case, the learned trial judge has not only

ignored the vital facts but also misappreciated the legal principles;

thus, the trial court has exercised the discretion arbitrarily and the

reasons to grant the injunction are perverse and based on

unreasonable grounds. Therefore, the impugned judgment and

order would require interference by this court. Hence, the decision

in the case of Wander Ltd. would not be of any assistance to the

plaintiff.

37. In the facts of the present case, the legal principles relied

upon by the learned counsel for the plaintiff, referring to the various

judgments discussed above, would not assist the plaintiff's

arguments. For the reasons recorded above, I am satisfied that the

impugned judgment and order granting the injunction is not

sustainable. The appeal is therefore allowed by passing the

following order:

(i) The impugned judgment and order dated 16 th July

2024 passed by the learned 15th Joint Civil Judge

901-AO-744-2024.doc

Pune below Exhibit 5 in Special Civil Suit No. 1869 of

2023 is quashed and set aside.

(ii) The application filed below Exhibit 5 is rejected.

[GAURI GODSE, J.]

Digitally signed by RAJESHWARI RAJESHWARI RAMESH RAMESH PILLAI PILLAI Date:

2025.06.10 07:12:26 +0200

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter