Wednesday, 06, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mumbai Metro One Private Limited vs Hindustan Construction Company
2025 Latest Caselaw 9048 Bom

Citation : 2025 Latest Caselaw 9048 Bom
Judgement Date : 18 December, 2025

[Cites 25, Cited by 0]

Bombay High Court

Mumbai Metro One Private Limited vs Hindustan Construction Company on 18 December, 2025

Author: Abhay Ahuja
Bench: Abhay Ahuja
  2025:BHC-OS:25300


                                                                                             13.IA-1969-2025.doc


                                             IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                                 ORDINARY ORIGINAL CIVIL JURISDICTION
           Digitally signed
           by KANCHAN                                 IN ITS COMMERCIAL DIVISION
KANCHAN PRASHANT
PRASHANT DHURI
DHURI    Date:
         2025.12.18
           20:02:37 +0530
                                                 INTERIM APPLICATION NO. 1969 OF 2025
                                                                  IN
                                                COMMERCIAL SUMMARY SUIT NO. 3 OF 2025

                               Mumbai Metro One Private Limited              ... Applicant

                               In the matter between:
                               Hindustan Construction Company                ...Plaintiff
                                      Versus
                               Mumbai Metro One Private Limited              ...Defendant


                               Mr. Karl Tamboly a/w Mr. Tushad Kakatiya a/w Mr. Paresh Patkar, Mr.
                               Kartik Hede, Mr. Ayaan Zariwalla and Ms. Bhakti Chandan i/b Mulla
                               and Mulla & CBC, Advocate for the Applicant/Defendant.

                               Mr. Shanay Shah a/w Ms. Viloma Shah a/w Mr. Ativ Patel & Mr.
                               Harshad Vyas i/b. AVP Partners, Advocate for the Respondent/Plaintiff.

                                                                  CORAM      :       ABHAY AHUJA, J.
                                                         RESERVED ON         :      10th OCTOBER 2025
                                                         PRONOUNCED ON       :      18th DECEMBER 2025
                               ORDER. :-

1. This Interim Application has been filed by the Defendant seeking

to refer the suit to Arbitration under Section 8 of the Arbitration and

Conciliation Act, 1996 and accordingly dispose of Commercial

Summary Suit No. 3 of 2025.

2. The background facts leading to the filing of this application has

been stated in the Application as under:

13.IA-1969-2025.doc

2.1 The Applicant is a private limited company and statedly is

operator/concessionaire of Mumbai Metro Line - 1 project, operating

between Versova, Andheri and Ghatkopar in Mumbai. The Respondent

is a company operating inter alia in the infrastructure and construction

sector.

2.2 The Applicant appointed the Respondent as a contractor to

execute various works in respect of the Mumbai Metro Line - 1 project

(between Versova - Andheri - Ghatkopar). Thereafter parties entered

into a contract agreement dated 16th August 2010 (the "Contract")

which set out the terms and conditions between the parties. The Clause

19.7 of the said contract provided for reference to arbitration. The said

clause is reproduced as under:

19. CLAIMS, DISPUTES, CONCILIATION AND ARBITRATION 19.1 ...

......

19.7 If the efforts to resolve all or any of the disputes, differences or controversy through negotiation fail, then such disputes or differences, whatsoever arising between the Parties, arising out of or relating to construction, measuring, operation or effect of the Contract or the breach thereof shall be referred to arbitration in accordance with the following provisions:

13.IA-1969-2025.doc

(a) Matters to be arbitrated upon shall be referred to a sole arbitrator if the total value of the claim is upto Rupees ten (10) million and to a panel of three (3) arbitrators if total value of claims is more than Rs.10 million. The sole arbitrator shall be appointed mutually by the Parties and in case the Parties fail to agree on the sole arbitrator, then the sole arbitrator shall be appointed in accordance with the provisions of the Arbitration and Conciliation Act, 1996. In the arbitration panel each Party shall nominate one (1) arbitrator each and the third arbitrator shall be chosen by the two (2) arbitrators nominated by the Parties.

The arbitrator(s) shall be appointed within a period of thirty (30) days from the date of receipt of written notice/demand of appointment of arbitrator from either Party.

(b) The arbitration proceedings shall be held in Mumbai. The language of proceedings, documents and communication shall be English.

(c) The award of the sole arbitrator or the award by majority of three arbitrators as the case may be shall be binding on all Parties."

2.3 It is submitted that during the course of the works, disputes arose

regarding certain performance bank guarantees furnished by the

Respondent under the Contract. In view of the aforesaid arbitration

clause, the Respondent preferred an application under Section 9 of the

Arbitration and Conciliation Act, 1996 (the "Arbitration Act") whereby

inter alia release of performance bank guarantees was sought.

13.IA-1969-2025.doc

2.4 During the pendency of the said application the parties entered

into a Settlement Agreement dated 28th March 2024 ( the "Settlement

Agreement") whereby the Applicant agreed to return the performance

bank guarantees furnished by the Respondent and pay a sum of

Rs.9,00,00,000 (Rupees Nine Crores Only) to the Respondent towards

full and final settlement of the disputes between the parties.

2.5 It is submitted that the Applicant returned the performance bank

guarantees to the Respondent as well as issued the final taking-over

certificates. The Application under Section 9 of the Act was disposed of

as infructuous with liberty to the Plaintiff to adopt appropriate

proceedings to recover the amount of Rs. 9 Crores in terms of the

Settlement Agreement.

2.6 It is submitted that the Applicant was in financial difficulty due

to which the amount of Rs. 9 Crores under the Settlement Agreement

remained unpaid. In view of the same, the Respondent on 1 st March

2025 filed the Commercial Summary Suit on the basis of the Settlement

Agreement towards the settlement of its outstanding dues.

13.IA-1969-2025.doc

2.7 It is submitted on behalf of the Applicant that the Settlement

Agreement was executed in furtherance of the Contract, and in view of

obligations arising there under, as well as Work Orders bearing

numbers 23534303, 23523192 and 2523272. Accordingly, any disputes

arising under the Settlement Agreement would also be required to be

settled by way of Arbitration.

3. The Respondent/Plaintiff objects to the grant of any reliefs in the

Application on the ground that Settlement Agreement has superseded

the Contract and that being so, the Contract no longer exists. It is

further stated that there is no arbitration clause in the Settlement

Agreement and on this ground alone, this Application ought to be

dismissed.

4. Further it is submitted that Article 2 of the Settlement Agreement

provides the governing law and a jurisdiction clause which expressly

omits the arbitration clause and only provides for courts at Mumbai to

have jurisdiction over the subject matter thereof.

5. In rejoinder, the Applicant has submitted that the Settlement

Agreement, in the absence of express written intent, could not have

13.IA-1969-2025.doc

superseded the Contract, and the arbitration clause contained therein

applies to the disputes arising out of the Settlement Agreement as well.

It is further stated that the arbitration clauses contained in a contract

are separate and autonomous, and survive even after the termination of

the main contract.

6. Mr. Karl Tamboly, Learned Counsel appearing for the Applicant

has submitted that the reference under Section 8 would be necessitated

in view of the Arbitration Clause contained in the contract agreement

dated 16th August 2010.

7. Mr. Tamboly, has submitted that the recitals of the Settlement

Agreement more particularly Recital E make it expressly clear that it

arises in furtherance of the Contract and the Work Orders, and is

therefore intrinsically linked to the same. The said recital contained in

the Settlement Agreement is usefully reproduced as under:

"E. Further the Employer and the Contractor have jointly reconciled the total amounts that are due and payable to the Contractor under the Contract and WO and the Parties have agreed that the total amount, due and payable to the Contractor by the Employer under the Contract and WO, towards, full and final settlement, is Rs.9,00,00,000/- (Rupees Nine Crores Only) ("Settlement Amount"), as per the details given in Annexure-1."

13.IA-1969-2025.doc

8. Next, Mr. Tamboly had drawn this Court's attention to the

Contract Agreement dated 16th August 2010, Clause 1 of the Agreement

which states the following documents constitute the Contract (a) Work

Order dated July, 2010 (b) Contract Agreement dated August, 2010, (c)

Schedules to the Contract Agreement dated August 2010, (d)

Conditions of Contract signed on August 2010, (e) Schedules to the

Conditions of Contract dated August 2010, (f) Employer's

Requirements - Drawings, (g) Employer's Requirements - Technical

Specifications (including Appendices) signed on August, 2010; (h)

Employer's Requirements - General Specifications (including

Appendices) signed on August 2010; (i) Other Tender Documents; and

(j) Tender.

9. Learned Counsel would submit that the Clause 1.1.18 and Clause

1.1.19 which defines "Contract" and the "Contract Agreement" which is

reproduced as under:-

"1.1.18 "Contract" means the agreement between the Employer and the Contractor for the Execution of the Works, including the Work Order, the Contract Agreement, the Conditions of Contract, the Schedules, the Employer's Requirements, the Tender, Other Tender Documents and such further documents which are listed in the Contract Agreement and includes any amendment thereto made in accordance with the

13.IA-1969-2025.doc

provisions hereof.

1.1.19 "Contract Agreement" means the agreement entered into by the Parties along with the Pricing Document and scope of Works and includes any amendment thereto made in accordance with the provisions hereof."

10. Mr. Tamboly has also taken this Court through the Clause 19 to

the Contract which provides for Claims, Disputes and Arbitration,

clause 19.1 which sets out the procedure for claims and particularly

clause 19.1(f) which is reproduced as under :

"19.1 (f) Notwithstanding anything contained in the Contract, the Employer shall not be liable for any claim for any matter, arising out of or in connection with the Contract or the Execution of the Works, unless the Contractor shall have given a notice to the Employer in respect thereof, in writing, within sixty (60) days from the date of issuance of the Final Taking Over Certificate. It is clarified for the avoidance of doubt for any such claim under this Clause 19.1(f), the Contractor shall still be required to comply with the procedure set out under Clause 19.1(a) to 19.1(e)."

11. Mr. Tamboly has submitted that Settlement Agreement was

executed in furtherance of the Contract and Work Orders, and as the

Contract contains a provision for the settlement of disputes through

arbitration, in Clause 19.7 thereof accordingly this dispute arising

under the Settlement Agreement would also be required to be settled

13.IA-1969-2025.doc

by way of arbitration. Learned Counsel would submit that the

arbitration agreement contained in Clause 19.7 is wide enough to cover

the dispute raised by the Respondent which arises out of the original

contract.

12. Mr. Tamboly has submitted that the Settlement Agreement does

not operate to supersede and / or override the Contract, the principle

that an arbitration agreement is separate and severable from the main

contract is now settled law, and is statutorily recognized under Section

16(1) of the Arbitration Act. It is only in cases where the main contract

is alleged to be void, illegal, or executed under fraudulent

circumstances, that the arbitration agreement also ceases to hold force.

Mr. Tamboly has relied upon the decision of the Hon'ble Supreme Court

in Interplay between Arbitration Agreements under Arbitration and

Conciliation Act, 1996 and Stamp Act, 1899 In re, 1 in support of his

contention.

13. It is submitted therefore that the reliefs as sought for in this

Application be granted.

14. On the other hand, Mr. Shanay Shah, Learned Counsel for the

Respondent has opposed the Application and would submit that this

(2024) 6 SCC 1

13.IA-1969-2025.doc

application is nothing but merely an attempt to derail the entire

proceedings. Mr. Shah would submit that it is an admitted fact that the

Defendant has failed and neglected to pay the admitted amount of Rs.

9 Crores as the execution of the Settlement Agreement is not disputed.

That there is an explicit admission of liability and this application

proceeds on an erroneous basis.

15. Mr. Shah, has submitted that a bare perusal of the Settlement

Agreement will make it evident that the Contract has been

superseded/novated/abrogated by the Settlement Agreement. Mr. Shah

would submit that the same is evident from Article 5(i) and Article 5(ii)

of the Settlement Agreement which is reproduced as under:

"ARTICLE 5 MISCELLANEOUS The Employer and the Contractor agree that the obligations as listed in Article 1 hereto are the full and final obligations to be performed by either/both of the Parties.

This Settlement Agreement supersedes any/all consideration, contemporaneous negotiations, understanding and agreement, whether written or oral, agreed upon by the Parties."

16. Mr. Shah has submitted that therefore in light of the Article 5 (i)

and (ii) the arbitration agreement contained in the Contract can have

no nexus to the Settlement Agreement.

13.IA-1969-2025.doc

17. Mr. Shah has also submitted that the Article 2 of the Settlement

Agreement sets out the governing law and jurisdiction wherein it is

categorically mentioned that this Settlement Agreement shall be

governed and construed in accordance with the laws of India and

courts of Mumbai will have exclusive jurisdiction. That as the

Settlement Agreement is silent on arbitration and as there is novation

of contract and the previous contract does not survive the claim for

non-payment of outstanding dues under the Settlement Agreement is

not arbitrable.

18. Mr. Shah would draw this Court's attention to the Order dated

24th September 2024 passed in the Commercial Arbitration Petition (L)

No. 34225 of 2023 and submit that the order records the categorical

admission of the Applicant/ Defendant that it is in fact liable to pay the

outstanding amount of Rs. 9 Crores and provided liberty to the Plaintiff

to adopt appropriate proceedings to recover the admitted amount of

Rs. 9 Crores. Mr Shah, would submit that if at all the arbitration clause

contained in the Contract also applied to the Settlement Agreement,

the observations made in the Order dated 24 th September 2024 would

never have been made.

13.IA-1969-2025.doc

19. Mr. Shah would submit that after the Section 9 Petition was

disposed of, the Plaintiff addressed a legal notice calling upon the

Defendant to pay a sum of Rs. 9 Crores along with interest at the rate

of 18% a within a period of 14 days. Mr. Shah would draw attention of

this Court to the response of the Applicant/Defendant dated 3 rd January

2025 wherein the Applicant/Defendant has categorically admitted its

obligations under the Settlement Agreement and requested for a few

months time from the Respondent/Plaintiff. Mr. Shah would submit

that even in this response the Applicant/Defendant has admitted its

liability.

20. Mr. Shah would place reliance on the decision of the Delhi High

Court in the case of Larsen and Toubro Limited v. Ireo Victory Valley

Private Limited2 submitting that the facts of this case are identical to

the present application wherein the Court was dealing with a similar

question of the survival of the arbitration clause in a contract after the

contract is superseded by the execution of Settlement Agreement and

submitted that if a mutual settlement supersedes the original contract,

the original arbitration clause would not survive. Mr. Shah would

submit that therefore in light of this decision this Court ought not to

refer the dispute to arbitration.

2024 SCC OnLine Del 2882

13.IA-1969-2025.doc

21. Mr. Shah has submitted that the findings of the Hon'ble Supreme

Court in Interplay between Arbitration Agreements under Arbitration

and Conciliation Act, 1996 and Stamp Act, 1899 In re(supra) do not

disturb the settled position of law namely that if the parties put an end

to a validly executed contract, the arbitration clause of the original

contract also perishes with it and has relied on the decision of this

Court in the case of BKS Galaxy Realtors LLP v. Sharp Properties and

Others.3

22. Mr. Shah has submitted that a reference under Section 8 of the

Arbitration Act as sought by the Applicant can only be made only if the

matter in an action is also subject matter of Arbitration Agreement, and

therefore this Court is required to ascertain whether the action in

present Suit is also subject matter of Arbitration and has relied on the

decision of this Court in the case of Capri Global Capital Limited v.

M/s. Divya Enterprise and Others4 in support. Mr. Shah has further

submitted that the Hon'ble Supreme Court in the decision of Zenith

Drugs & Allied Agencies Pvt Ltd. v. Nicholas Piramal India Limited 5 has

laid down the following conditions to be satisfied for referring the

2024 SCC OnLine Bom 3514

2025: BHC-OS:18363

(2020) 17 SCC 419

13.IA-1969-2025.doc

parties to arbitration under Section 8 of the Act:-

(i) there is an arbitration agreement

(ii) a party to the agreement brings an action in the court against the other party;

(iii) subject matter of the action is the same as the subject matter of the arbitration agreement

(iv) the opposite party applies to the judicial authority for referring the parties to arbitration before it submits his first statement on the substance of the dispute.

23. Mr. Shah has submitted that the present summary suit as clearly

stated in paragraphs 69, 70 and the prayers in the Plaint has been filed

under Order XXXVII of the Code of Civil Procedure, 1908 ("CPC") on

the basis of the Settlement Agreement and the subsequent default of

the Defendant to repay the admitted amounts in terms of the

Settlement Agreement and therefore the dispute between the parties is

not an arbitrable dispute as the Settlement Agreement having an

independent governing law and jurisdiction clause which expressly

omits the arbitration clause and only provides for Courts at Mumbai to

have jurisdiction over the subject matter.

24. In rejoinder, Mr. Tamboly would contend that the

Respondent/Plaintiff themselves moved the Arbitration Court after the

13.IA-1969-2025.doc

Settlement Agreement and the Petition under Section 9 was only

disposed of as infructuous as the reliefs claimed under the Section 9

were satisfied and nothing survived. Therefore, it would be incorrect on

the part of the Respondent/Plaintiff that in view of the order passed in

the Section 9 Petition, the arbitration clause does not survive.

25. Mr. Tamboly, has further relied on the decision of this Court in

Shree Siddhivinayak Classic Construction Pvt Ltd & Anr v. IIFL Finance

Limited & Anr.6 where in an Application under Section 11, wherein the

disputes and differences between the parties relating to a Settlement

Agreement, the existence of an arbitration agreement itself was in

doubt owing to a subsequent settlement having been reached between

the parties, the Court in this decision referred the dispute to

Arbitration. Mr. Tamboly would submit that in light of this decision this

Court ought to refer this dispute to Arbitration.

26. Mr. Tamboly has submitted that even in cases where a settlement

agreement was purported to supersede a prior contract courts have

rightly distinguished that it was only in cases where the main contract

was expressly superseded, rescinded, or overridden by a subsequent

contract, that the arbitration clause contained in main agreement

2025 BHC-OS : 12113

13.IA-1969-2025.doc

would also cease to have force and has relied on the following

decisions:-

(i) Gold Prism Realty Pvt Ltd v. M/s. Paradigm Ambit Buildcon7

(ii) Sirajuddin Kasim and Another v Paramount Investments Limited 8

27. Learned Counsel has submitted that the decision of the Delhi

High Court in the case of Larsen and Toubro Limited v. Ireo Victory

Valley Private Limited (supra) is based on the judgments of the Hon'ble

Supreme Court in the case of Union of India v. Kishorilal Gupta & Bros 9

and Damodar Valley Corporation K.K.Kar10 and that the Hon'ble

Supreme Court in paragraphs 115 and 116 of the decision in Interplay

between Arbitration Agreements under Arbitration and Conciliation

Act, 1996 and Stamp Act, 1899 (Supra) noted that the separability

doctrine has undergone a significant evolution, spurred in part by the

enactment of the Arbitration and Conciliation Act, 1996 and the

inclusion of Section 16 therein. Mr. Tamboly has submitted that

therefore these developments have rendered the decisions of the

Hon'ble Supreme Court in Union of India v. Kishorilal Gupta & Bros

(supra) and Damodar Valley Corporation v K.K.Kar (supra) redundant.

2019:BHC-OS:11039

(2010) 8 SCC 557

1959 SCC OnLine SC 6

(1974) 1 SCC 141

13.IA-1969-2025.doc

28. Mr. Tamboly has submitted that the findings of this Court in BKS

Galaxy Realtors LLP v. Sharp Properties and Others (supra) would have

to be read in the context in which they were rendered. That in that

case, the Court concluded that the arbitration clause could not be said

to have survived upon the Sale Deed being executed, since upon such

execution, the prior Agreement for Sale would indisputably come to an

end, however, in the present case the question of whether the

Settlement Agreement has completely superseded the Contract is a

question which is at large and that following the dictum of the Hon'ble

Supreme Court in Interplay between Arbitration Agreements under

Arbitration and Conciliation Act, 1996 and Stamp Act, 1899 (Supra)

this dispute between the parties about whether the subsequent

agreement does or does not supersede the prior agreement must also

be referred to the arbitral tribunal, as in any event, Section 16 of the

Arbitration Act makes it clear that the arbitral tribunal is competent to

rule on its own jurisdiction, and any objection thereto can be raised

before the Arbitral Tribunal once constituted.

29. I have heard the Learned Counsel at length and considered the

rival contentions. The hearing of this Application was concluded on 10 th

October 2025 and the order was reserved.

13.IA-1969-2025.doc

30. As noted above the Interim Application is filed under Section 8 of

the Arbitration and Conciliation Act seeking to refer the disputes to

Arbitration.

31. Under Section 8 of the Arbitration Act, an action brought before

the Court in a matter which is the subject of an Arbitration Agreement

needs to be referred to arbitration. Section 8 of the Arbitration Act is

reproduced for reference:-

"8. Power to refer parties to arbitration where there is an arbitration agreement.--

[(1)A judicial authority, before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party to the arbitration agreement or any person claiming through or under him, so applies not later than the date of submitting his first statement on the substance of the dispute, then, notwithstanding any judgment, decree or order of the Supreme Court or any Court, refer the parties to arbitration unless it finds that prima facie no valid arbitration agreement exists.] (2) The application referred to in sub-section (1) shall not be entertained unless it is accompanied by the original arbitration agreement or a duly certified copy thereof:

[Provided that where the original arbitration agreement or a certified copy thereof is not available with the party applying for reference to arbitration under sub-section (1),

13.IA-1969-2025.doc

and the said agreement or certified copy is retained by the other party to that agreement, then, the party so applying shall file such application along with a copy of the arbitration agreement and a petition praying the Court to call upon the other party to produce the original arbitration agreement or its duly certified copy before that Court.] (3) Notwithstanding that an application has been made under sub-section (1) and that the issue is pending before the judicial authority, an arbitration may be commenced or continued and an arbitral award made.

32. Thus an application under Section 8 of the Arbitration act can be

made only if the subject matter of the suit is also the same as the

subject-matter of arbitration and only those disputes which are

specifically agreed to be resolved through arbitration can be the

subject-matter of arbitration; and upon satisfaction of the same, the

Court can refer the parties to arbitration.

33. The Hon'ble Supreme Court in the decision of Zenith Drugs and

Allied Agencies Private Ltd v. Nicholas Piramal India Ltd (Supra) has

laid the following conditions which have to satisfied under Section 8

for referring the parties to arbitration:

(i) there is an arbitration agreement;

(ii) a party to the agreement brings an action in the court against

13.IA-1969-2025.doc

the other party;

(iii) subject-matter of the action is the same as the subject matter of the arbitration agreement;

(iv) the opposite party applies to the judicial authority for referring the parties to arbitration before it submits his first statement on the substance of the dispute.

34. Therefore a reference under Section 8 of the Arbitration Act can

be made only if the matter in an action is also subject of an Arbitration

Agreement. Therefore, this Court is required to ascertain whether the

action in the present Suit is also the subject matter of Arbitration.

35. The Summary Suit has been filed for a sum of Rs.9,00,00,000/-

being the principal amount along with Rs.1,35,44,384/- as interest at

the rate of 18% per annum from 27 th April 2024 till filing of the suit.

The said amount is claimed under the Settlement Agreement and

admittedly there is no arbitration clause in the Settlement Agreement.

Mr. Tamboly has sought to trace the arbitration clause to the Contract

which was entered into for carrying out civil works by the Plaintiff for

the Defendant in 2010. Owing to disputes between the parties the

Plaintiff had instituted a Petition under Section 9 of the Arbitration Act

against the Defendant and the disputes between the parties were

settled in terms of the Settlement Agreement.

13.IA-1969-2025.doc

36. In Zenith Drugs & Allied Agencies Pvt Ltd. v. Nicholas Piramal

India Limited (supra) the Hon'ble Supreme Court has relying on the

decision of the Hon'ble Supreme Court in the case of Yogi Agarwal v.

Inspiration Clothes & U11 observed that filing application under Section

8 of the Act should relate to the arbitration agreement or to be

applicable to the dispute. Paragraph 15 of the decision is usefully

quoted as under:-

"15. Observing that filing application under Section 8 of the Act should relate to the arbitration agreement or to be applicable to the dispute, in Yogi Agarwal v. Inspiration Clothes & U, it was held as under:

"9. When a defendant invokes Section 8 of the Act by alleging existence of an arbitration agreement, he should establish that such arbitration agreement related to, or is applicable to, the suit transaction/contract. The parties may enter into different contracts at different points of time or may enter into a series of unrelated transactions. It is possible that in regard to some, they may provide for arbitration. Obviously, the existence of an arbitration agreement with reference to some other transaction/contract to which the plaintiff was or is a party, unconnected with the transactions or contracts to which a suit relates, cannot be considered as existence of an "arbitration agreement" in regard to the suit transactions/contracts."

(2009) 1 SCC 372

13.IA-1969-2025.doc

37. In Larsen and Toubro Limited v. Ireo Victory Valley Private

Limited (supra) the Delhi High Court had the occasion to consider a

very similar fact situation as the present case wherein the Delhi High

Court held that if a mutual settlement supersedes the original contract,

the original arbitration clause would not survive. Paragraphs 32 and 33

are relevant and are usefully quoted as under:-

"32. In B.L Kashyap and Sons Ltd v. Mist Avenue Private Ltd ., 2023:DHC:3996, the Court laid down the principles as to cases in which the arbitration clause can be invoked from the original contract. The said principles are as under:

"23. For the purposes of the present case, the following principles emerge from these authorities: a. An arbitration clause contained in an agreement which is void ab initio cannot be enforced as the contract itself never legally came into existence.

b. A validly executed contract can also be extinguished by a subsequent agreement between the parties. c. If the original contract remains in existence, for the purposes of disputes in connection with issues of repudiation, frustration, breach, etc., the arbitration clause contained therein continues to operate for those purposes. d. Where the new contract constitutes a wholesale novation of the original contract, the arbitration clause would also stand extinguished by virtue of the new agreement.

24. An application of these principles requires an

13.IA-1969-2025.doc

interpretation of the subsequent agreement between the parties-in this case, the MOU-to determine whether the arbitration clause in the original agreement remains enforceable."

33. The above stated judgment holds that in cases where there is a subsequent Settlement Agreement, a valid contract can be extinguished. The Settlement Agreement in the present case is the subsequent agreement, whose interpretation would show that the arbitration clause in the original agreement would not be enforceable as this is a full and final settlement with respect to the contract and will be treated as a foreclosed document. The text of the Settlement Agreement is clear to the effect that this is a final settlement and MOU, with respect to the disputes and claims that arose between the parties in consideration to the contract and that there are no pending claims, neither any future claims were permitted to be raised."

38. In the case of BKS Galaxy Realtors LLP v. Sharp Properties and

Others (supra) this Court while dealing with an appeal against an order

rejecting the Application under Section 8 of the Arbitration Act held

that as there is only a general reference of the prior agreement in the

subsequent Memorandum of Understanding between the parties there

is absence of any specific reference to the arbitration agreement in the

subsequent agreement and therefore there is no incorporation of the

13.IA-1969-2025.doc

arbitration agreement by reference in the Memorandum of

Understanding.

39. Thus in cases where the parties therein enter into a subsequent

agreement to a contract settling the disputes between the parties the

Court has to examine whether the subsequent agreement supersedes

the Original Contract and whether the arbitration clause contained in

the Original Contract survives and is incorporated in the Settlement

Agreement.

40. The Settlement Agreement as can be seen is between the

Defendant and the Plaintiff. The recitals and in particular recital 'E'

clearly indicates that the outstanding amount of Rs.17,99,80,506/- has

been reconciled jointly by the parties and the parties have agreed that

the total amount, due and payable to the contractor, viz. the Plaintiff by

the employer, viz. the Defendant under the contract and the work

order, towards full and final settlement is Rs.9 Crores. In recital 'F', it

has been recorded that other than the amount stated in recital 'E'

above, the parties unequivocally state and declare that there are no

monies which are balance, outstanding and unpaid from the Defendant

to the Plaintiff. The said recitals are usefully quoted as under :

13.IA-1969-2025.doc

A. The Employer is Concessionaire for a period of 35 years to build, own, operate and transfer, Mumbai Metro Line - 1 in the city of Mumbai.

B. The Employer has engaged the Contractor for construction, installation, testing and commissioning of civil works, by entering into a Contract Agreement ("Contract") dated 16th August 2010.

C. Under the said Contract, Employer issued following Work Orders ("WO") bearing Nos.23534303, 23523192 and 23523272 to Contractor to perform the Works as specified under the terms of the Contract.

D. Further Contractor raised several invoices, out of which, invoices amounting to Rs.17,99,80,506/- (Rupees Seventeen Crores Ninety-Nine Lakhs Eighty Thousand Five Hundred and Six Only), are payable to Contractor towards outstanding invoices.

E. Further the Employer and the Contractor have jointly reconciled the total amounts that are due and payable to the Contractor under the Contract and WO and the parties have agreed that the total amount, due and payable to the Contractor by the Employer under the Contract and WO, towards full and final settlement, is Rs.9,00,00,000/- (Rupees Nine Crores Only) ("Settlement Amount"), as per the details given in Annexure-1. F. Other than the amount stated in Para E above (that is payable by the Employer to the Contractor as per Annexure-1), the parties unequivocally state and declare that there are no monies which are balance, outstanding and unpaid from the Employer to the Contractor.

41. The Settlement Agreement supports by recording that in

consideration of the mutual agreements, covenants, representations

and warranties set forth in the contract/work order, and for other good

13.IA-1969-2025.doc

and valuable consideration, the receipt and sufficiency of which is

acknowledged by the parties, the parties have agreed as contained in

Articles 1 to 5 of the said Agreement.

42. In Article 1, the terms of settlement have been set out in clause

(iii) thereof, the Plaintiff has agreed that all the disputes raised under

the contract/work order shall be withdrawn/not proceeded in

consideration of the settlement. Accordingly, on 24 th September 2024,

after recording the submissions on behalf of the parties and in

particular on behalf of the Defendant that the Petition stood worked

out, the Petition was disposed of as infructuous with liberty to the

Plaintiff who was the Petitioner therein to adopt the appropriate

proceedings to recover the admitted amount of Rs.9 Crores in terms of

the Settlement Agreement. Moreover Article 2 of the Settlement

Agreement sets out the governing law and jurisdiction wherein it is

categorically mentioned that this Settlement Agreement shall be

governed and construed in accordance with the laws of India and

courts of Mumbai will have exclusive jurisdiction. However the said

clause does not include an alternate dispute resolution mechanism.

43. The perusal of the clauses and the language of the Settlement

Agreement leave no manner of doubt that the Settlement Agreement

13.IA-1969-2025.doc

clearly modified and superseded the Contract. I agree with Mr. Shah,

that it is evident from reading of the Article 5(i) and Article 5(ii) of the

Settlement Agreement that the Contract has no nexus with the

Settlement Agreement. The Settlement Agreement has intentionally

departed from the dispute redressal mechanism provided under the

Contract by adding a governing law and jurisdiction clause without

adding an alternate dispute resolution mechanism and thus expressly

excluding the arbitration agreement contained in the Contract. There is

also no specific reference to the arbitration clause of the Contract in the

Settlement Agreement, and therefore in the light of the above facts, the

arbitration clause of the Contract does not get incorporated or become

applicable or govern the rights of the parties when the parties have

settled their differences and compromised the matter and entered into

a Settlement Agreement which is a different agreement. Therefore the

arbitration clause in the prior Contract cannot be read into the terms of

the Settlement Agreement unless expressly mentioned in the

Settlement Agreement.

44. The Settlement Agreement has overriden the Contract and the

claims therein and the Parties agreed to a full and final settlement

amount of Rs. 9 Crores. The Settlement Agreement makes it

13.IA-1969-2025.doc

abundantly clear that it is a full and final settlement irrespective of

whatever claims were raised under the Contract and Work Order.

Therefore if all the claims are dealt with and settled no issues under the

Contract are left to be adjudicated upon in arbitration.

45. The Applicant has in fact acted upon the Settlement Agreement

and in terms of the Settlement Agreement, the Applicant handed over

the performance bank guarantees and the final take over certificate to

the Respondent. The Applicant has thus recognized that Settlement

Agreement is binding between the parties but has failed to repay the

settlement amounts within the stipulated timeline

46. Even in response dated 3rd January 2025 to the letter sent by the

Plaintiff on 10th December 2024 the Applicant has stated that with an

intent to resolve the matter amicably and to not precipitate the issues,

they entered into a Settlement Agreement with the Respondent on 28 th

March 2024 and forthwith returned the Bank Guarantees. The

Applicant has also recognized that the Settlement Agreement paved the

way for resolving the Section 9 Petition filed by the Respondent herein.

In paragraph 14 of the said letter the Applicant has categorically stated

13.IA-1969-2025.doc

that it is committed to liquidate its obligations and is keen to honor the

Settlement Agreement but has been delayed in its ability in making

such payment.

47. There are no claims raised by the Respondent/Plaintiff which

arise out of the Contract at all as the full and final settlement amount

in the Settlement Agreement was agreed to irrespective of the claims

under the Contract and WO. Therefore the only claim is in respect of

non-payment of the amount due under the Settlement Agreement

which the Applicant/Defendant has acknowledged and not refuted.

48. In the present case, the Settlement Agreement makes a reference

to the Contract but does not incorporate the Contract or the arbitration

agreement in the Settlement Agreement and in fact as per Article 5 (ii)

of the Settlement Agreement, the Settlement Agreement superseded

any/all consideration, contemporaneous negotiations, understanding

and agreement, whether written or oral, agreed upon by the Parties.

Further, there is a governing law and jurisdiction clause in the

Settlement Agreement but no reference to alternate dispute resolution

mechanism.

13.IA-1969-2025.doc

49. The judgments which have been relied upon by the Applicant/

Respondent in support of its contention that the issue of whether the

Settlement Agreement supersedes the Contract is also an arbitrable dis-

pute and the same ought to be referred to arbitration are not applicable

in the present case. The facts of the aforesaid decisions are clearly dis-

tinguishable from the facts of the present case.

50. In the case of Shree Siddhivinayak Classic Construction Pvt. Ltd.

and Anr. V IIFL Finance Limited and Anr. (supra) an application was

made under Section 11 of the Arbitration Act and in that case there was

an arbitration agreement between the Applicant and the Respondent,

that agreement was assigned by the Respondent to a third party, the Re-

spondent continued to collect amounts under the Loan Agreement even

after the assignment agreement was entered into, and the relationship

between the Applicant and the third party was governed by the assign-

ment agreement for some time before a new settlement was reached

between them. These facts are clearly distinguishable from the facts of

the present case where there was a new settlement agreement entered

into between the parties which specifically contained a governing law

and jurisdiction clause but did not include an arbitration clause.

13.IA-1969-2025.doc

51. Similarly the case of Gold Prism Realty Pvt. Ltd. v M/s. Paradigm

Ambit Buildcon (supra) is also distinguishable on facts as that was also

a matter under Section 11 of the Arbitration Act and the settlement in

this case did not contain any mention of a governing law and jurisdic-

tion clause unlike the present case.

52. The case of Sirajuddin Kasim and another v. Paramount Invest-

ments Limited (supra) is also distinguishable on facts as in that case

one of the Petitioners was not a party to the settlement agreement and

hence his rights were not superseded by the settlement agreement.

53. Further, the aforesaid decisions are in applications under Section

11 of the Arbitration Act and as is settled law, the nature and scope of

issues arising for consideration in an application under Section 11 of

the Arbitration Act for appointment of the Arbitrator are far narrower

than those arising in an application under Section 8 of the Arbitration

Act seeking reference of the parties to a suit to arbitration. While

considering an application under Section 11 of the Arbitration Act, the

Chief Justice or his designate would not embark upon an examination

of the issue of 'arbitrability' or appropriateness of adjudication by a

private forum, once he finds that there was an arbitration agreement

13.IA-1969-2025.doc

between or among the parties, and would leave the issue of

arbitrability for the decision of the arbitral tribunal. If the arbitrator

wrongly holds that the dispute is arbitrable, the aggrieved party will

have to challenge the award by filing an application under Section 34

of the Arbitration Act, relying upon Sub-Section 2(b) (i) of that section.

But where the issue of 'arbitrability' arises in the context of an

application under Section 8 of the Act in a pending suit, all aspects of

arbitrability have to be decided by the Court seized of the suit and

cannot be left to the decision of the Arbitrator. This view of the Hon'ble

Supreme Court in the decision of Booz Allen and Hamilton Inc. Versus

SBI Home Finance Limited and Others 12 has also been followed by this

Court in the case of Capri Global Capital Limited v. M/s. Divya

Enterprise (Partnership Firm) and Others (supra).

54. It is also pertinent to refer to decision of the Hon'ble Supreme

Court in Interplay between Arbitration Agreements under Arbitration

and Conciliation Act, 1996 and Stamp Act, 1899 (Supra) relied upon by

the Applicant which itself in paragraph 164 holds that the provisions of

Section 8 and Section 11 of the Arbitration Act cannot be read as laying

down a similar standard. The paragraph 164 is usefully quoted as under:-

2011) 5 SCC 532

13.IA-1969-2025.doc

"164. The 2015 Amendment Act has laid down different parameters for judicial review under Section 8 and Section 11.

Where Section 8 requires the Referral Court to look into the prima facie existence of a valid arbitration agreement, Section 11 confines the Court's jurisdiction to the examination of the existence of an arbitration agreement. Although the object and purpose being both Sections 8 and 11 is to compel parties to abide by their contractual understanding, the scope of power of the Referral Courts under the said provisions is intended to be different. The same is also evident from the fact that Section 37 of the Arbitration Act allows an appeal from the order of an Arbitral Tribunal refusing to refer the parties to arbitration under Section 8, but not from Section 11. Thus, the 2015 Amendment Act has legislatively overruled the dictum of Patel Engg, where it was held that Section 8 and Section 11 are complementary in nature. Accordingly, the two provisions cannot be read as laying down a similar standard."

55. Therefore for the reasons discussed above, the reliance on the

decisions in the cases of Shree Siddhivinayak Classic Construction Pvt

Ltd & Anr v. IIFL Finance Limited & Anr (supra), Gold Prism Realty Pvt

Ltd v. M/s. Paradigm Ambit Buildcon (supra) and Sirajuddin Kasim and

Another v Paramount Investments Limited (supra) is misplaced and

does not advance the case of the Applicant.

13.IA-1969-2025.doc

56. The Applicant has also sought to canvas that the decisions of the

Hon'ble Supreme Court in Union of India v. Kishorilal Gupta & Bros

(supra) and Damodar Valley Corporation v K.K.Kar (supra) on which

the Delhi High Court has relied upon in Larsen and Toubro Limited v.

Ireo Victory Valley Private Limited (supra) are rendered redundant in

view of what has been held by the Hon'ble Supreme Court in Interplay

between Arbitration Agreements under Arbitration and Conciliation

Act, 1996 and Stamp Act, 1899 (Supra). In the decision of BKS Galaxy

Realtors LLP v. Sharp Properties and Others this Court has held that the

findings of the Hon'ble Supreme Court in Interplay between Arbitration

Agreements under Arbitration and Conciliation Act, 1996 and Stamp

Act, 1899 (Supra) do not disturb the finding in Union of India v

Kishorilal Gupta & Bros (supra), namely that if the parties put an end

to a validly executed contract, the arbitration clause of the original

contract also perishes with it. Applying the aforementioned decisions

to the facts of the present case, it is clear that the parties have entered

into a Settlement Agreement superseding any previous agreement

between the parties and specifically incorporating a governing law and

jurisdiction clause without incorporating an alternate dispute resolution

clause and hence the Contract and the arbitration clause contained in it

13.IA-1969-2025.doc

are no longer applicable and it is the Settlement Agreement that

prevails between the parties.

57. Section 16(1) (b) of the Arbitration Act provides that a decision

by the arbitral tribunal that the contract is null and void shall not entail

ipso jure the invalidity of the arbitration clause. But this does not in any

way suggest that when the parties consciously enter into a subsequent

agreement that finally determines their rights, the arbitration clause

embedded in the prior contract survived independently of that contract.

58. Even otherwise the judgments relied upon by the Applicant do

not advance the case of the Applicant in as much as the construction of

a judgment should be made in light of the factual matrix involved

therein and the clauses of the agreement therein. In the facts of the

present case, in view of the Settlement Agreement executed between

the parties superseding and novating the Contract containing a

Governing Law and Jurisdiction clause but not including an arbitration

clause, thereby rendering the arbitration clause contained in the earlier

Contract inapplicable and incapable of being invoked.

59. The Settlement Agreement is a separate agreement between the

parties which does not contain any arbitration clause. The Settlement

13.IA-1969-2025.doc

agreement having superseded the Contract and as it does not make a

specific reference to arbitration despite containing a specific governing

law and jurisdiction clause, no case is made out under Section 8 of the

Arbitration Act.

60. Ergo the dispute involved in the Suit cannot be referred to

Arbitration. The Interim Application accordingly stands dismissed.

(ABHAY AHUJA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter