Citation : 2024 Latest Caselaw 26362 Bom
Judgement Date : 15 October, 2024
2024:BHC-AS:40842-DB
J-926-ASWP-12039-2019+.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 12039 OF 2019
WITH
INTERIM APPLICATION NO. 3715 OF 2023
IN
WRIT PETITION NO. 12039 OF 2019
1. Hiraman Yashwant Kathe
Age: 60 years, Occ. Agriculturist
2. Shridhar Yashwant Kathe
Age: 58 years, Occ. Agriculturist
3. Bhausaheb Karbhari Gade
Age: 55 years, Occ. Agriculturist
4. Vinayak Sukdeo Kendale
Age: 43 years, Occ. Agriculturist
5. Dagu Sukdeo Kendale
Age: 52 years, Occ. Agriculturist
6. Rajaram Sawliram Borade
Age: 60 years, Occ. Agriculturist
7. Arun Ragho Ichal
Age: 55 years, Occ. Agriculturist
8. Haribhau Waman Ichal
Digitally
signed by
ASHWINI
ASHWINI JANARDAN
JANARDAN VALLAKATI
VALLAKATI Date:
2024.10.15
17:29:23
Page 1 of 25
+0530
October 15, 2024
Ashwini Vallakati
::: Uploaded on - 15/10/2024 ::: Downloaded on - 16/10/2024 00:19:31 :::
J-926-ASWP-12039-2019+.doc
Age: 57 years, Occ. Agriculturist
9. Kishor Dagu Gaikwad
Age: 35 years, Occ. Agriculturist
10. Rajendra Dagu Gaikwad
Age: 55 years, Occ. Agriculturist ...Petitioners/
All R/o. Mauje Akrale, Tal : Dindori, Applicants
District : Nashik
Versus
1. The State of Maharashtra
Through the department of Industry & through
the Department of Environment Protection,
Government of Maharashtra, Mantralay,
Mumbai - 400032
2. Maharashtra Industrial Development
Corporation (MIDC)
A statutory Corporation
through its Regional Officer
Udyog Bhavan, Satpur, Dist : Nashik -7
3. The Land Acquisition, Officer, Nashik
4. The District Collector, Nashik ...Respondents
Mr. S.M. Gorwadkar, Senior Advocate , i/b Sanjay H. Gangal,
Advocates for the Applicants/Petitioner.
Mr. Prashant Chawan, Senior Advocate, a/w Shraddha Chheda, i/b
M/s. Navdeep Vora & Associates, Advocates for Respondent No.2.
Mr. B.V. Samant, Addl.GP, a/w P.M.J. Deshpande, AGP for
Respondent-State.
Page 2 of 25
October 15, 2024
Ashwini Vallakati
::: Uploaded on - 15/10/2024 ::: Downloaded on - 16/10/2024 00:19:31 :::
J-926-ASWP-12039-2019+.doc
CORAM : G. S. KULKARNI &
SOMASEKHAR SUNDARESAN, JJ.
RESERVED ON : SEPTEMBER 26, 2024
PRONOUNCED ON : OCTOBER 15, 2024
JUDGEMENT:
(Per, Somasekhar Sundaresan J.)
1. Rule. With the consent of the parties, taken up for final hearing
and disposal.
2. This Petition, invoking the jurisdiction under Article 226 of the
Constitution of India, challenges a decision by the Maharashtra Industrial
Development Corporation ("MIDC"), Respondent No.2, communicated on
December 8, 2017 and on April 13, 2018 (collectively, " Impugned Order"),
refusing to refer the dispute raised by the Petitioners to the jurisdictional civil
court under Section 34 of the Maharashtra Industrial Development Act, 1961
("the Act").
3. The Petition prays that the Impugned Order be quashed and set
aside. The Petition seeks a direction that the objections of the Petitioners be
referred to the jurisdictional civil court under Section 34 of the Act. Another
prayer seeks the appointment of a Court Commissioner to work out correct
characterisation of the Petitioners' lands. Finally, a prayer seeks a declaration
that the compensation ought to be computed under the Right to Fair
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013 ("2013 Act").
4. With effect from July 3, 2019, the Act was amended to to provide
for linkages with the 2013 Act. Consequently, under Section 33(5), the
principles of computing compensation as provided for in the 2013 Act would
apply to acquisitions under the Act. Likewise, Section 34 has been amended
to provide for references of disputes over compensation to be made to the
"Authority" (as defined in the 2013 Act) instead of references to the "Court"
(as defined in the Land Acquisition Act, 1894). While the prayers and
pleadings in the Petition refer to the civil court, for all purposes of this
judgement, the term "Authority" is used, wherever necessary, in relation to the
forum to which a reference may be made under Section 34 of the Act.
Core Issue:
5. At the heart of the Petition lies the grievance that the classification
of the Petitioners' lands as seasonally-irrigated is wrong and it ought to be
categorised as perennially-irrigated land. It is Petitioners' grievance that such
classification has significantly injured their interests, since under their
agreement with the State, they are being paid an amount of Rs. 52.5 lakhs per
acre (payable for seasonally-irrigated land) as against their entitlement to Rs.
70 lakhs per acre (payable for perennially-irrigated land). The acquisition of
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
the Petitioners' lands were by mutual consent under agreements, which had
provided for a framework of amount payable, the only variation being linked
to the nature of land.
Factual Matrix:
6. The following overview of the factual matrix would be in order:-
a) The Government of Maharashtra, Respondent No.1, issued
a notification on December 6, 2007, declaring an area of
146 Hectares and 35 Ares and another 202 Hectares and
17 Ares in Talegaon Village as an industrial area under the
Act, initiating the statutory process for acquisition;
b) On February 7, 2008, the MIDC authorized the Land
Acquisition Officer, Nashik, Respondent No.3 to
commence the land acquisition proceedings pursuant to
the aforesaid notification;
c) Eventually, on December 17, 2013, agreements were
executed between the Petitioners and the Land Acquisition
Officer under Section 33(2) of the Act, for acquisition of
various parcels of the notified land. The agreements
provided for a framework for computing compensation
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
payable. The amount payable for non-irrigated land was
stated to be Rs.35 Lakhs per acre. For seasonally-irrigated
land and perennially-irrigated land, such amount would be
increased to 1.5 times and 2 times respectively - Rs. 52.50
Lakhs for seasonally-irrigated land; and Rs. 70 Lakhs for
perennially-irrigated land. The terms and conditions
included a stipulation that the landowner would not
initiate any proceedings to air any grievance seeking
enhanced compensation for the land;
d) Different awards were passed on different dates (" Consent
Awards") for various lands owned by the Petitioners under
Section 33(2) of the Act, awarding a total compensation of
Rs.70,92,75,000/-. The Consent Awards record the same
framework for compensation (based on the category the
land would fall under) as set out in the agreements;
e) On November 15, 2014, the Petitioners made a
representation that they should be compensated at the rate
of Rs. 52.50 Lakhs per Acre or Rs. 70 Lakhs per Acre, on
the basis that their land ought not to be classified as non-
irrigated land. Subject to this protest, the Petitioners
accepted payment of Rs.35 Lakhs per acre;
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
f) On November 18, 2015 compensation at the rate of Rs.35
Lakhs per acre was received by the Petitioners;
g) It is seen from the affidavit in reply dated July 13, 2020
("Reply Affidavit"), that on August 11, 2017 the Taluka
Agricultural Officer submitted information that would be
necessary for determination of the categorisation of the
land to the Land Acquisition Officer;
h) The Petitioners made a representation on February 14,
2018 that their representations warranted a reference to
the jurisdictional civil court under Section 34 of the Act;
i) On April 13, 2018 the aforesaid representation was
rejected by way of the Impugned Order. The Impugned
Order recorded that various lands were classified on the
basis of the crop yield data based on crop inspection
entries of a decade prior to the acquisition, and the
compensation as applicable to the respective parcels of
land has been finalised in terms of the framework
contained in the agreements, which also culminated in the
Consent Awards. From the pleadings in the Petition, it
appears that the Petitioners' lands were held to be entitled
to compensation at the rate of Rs. 52.50 lakh per acre, on
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
the premise that it was seasonally-irrigated land, and not
at the rate of Rs. 70 lakh per acre, which is the amount
payable for perennially-irrigated land; and
j) Challenging this decision of April 13, 2018, this Writ
Petition came to be filed over a year later, affirmed on
June 20, 2019.
Contentions of the Parties:
7. We have heard Mr. S.M. Gorwadkar, Learned Senior Counsel on
behalf of the Petitioners, who has determinedly sought to explain that the
Petitioners' stand is simply that mis-classification of the lands has occurred,
which led to the compensation being computed erroneously. Consequently,
he would submit, there is a clear dispute over the compensation, and the
recourse for resolving such a dispute is the reference of such dispute to the
Authority having jurisdiction under Section 34 of the Act.
8. The grounds of attack on the Impugned Order are manifold. One
of the grounds is that the 2013 Act, which has changed the landscape for land
acquisition in India with effect from January 1, 2014, would now govern the
acquisition in question, and that all awards passed under state legislation such
as the Act would be discriminatory and arbitrary. However, Mr. Gorwadkar
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
would fairly state that the core ground of challenge was to the wrongful
categorisation of the lands in question, which has had an injurious effect on
the Petitioners. The agreements and the Consent Awards entail a framework
for computing the compensation, and if the framework is wrongly applied, it
has the effect of erroneous and arbitrary compensation being offered to the
Petitioners, which is amenable to correction by reference to the Authority.
The refusal to refer the dispute to the civil court, Learned Senior Counsel
would submit, ought to be reversed in exercise of the writ jurisdiction of this
Court.
9. According to the pleadings in the Petition, the Petitioners' lands
have been erroneously classified as seasonally-irrigated land giving them
compensation at the rate of Rs.52.50 Lakhs per acre whereas they ought to
have been paid Rs.70 Lakhs per acre on the ground that the lands were
perennially-irrigated. According to Mr. Gorwadkar, the Consent Awards may
appear to be products of conscious agreement, but the agreements in question
only enabled a framework for payment of compensation based on the
categorisation of the land, and did not actually firm up the actual
categorisation of the lands in question. Way back in 2014, the various
landowners had already stated that they would accept the compensation
subject to their grievance that their land should actually be treated as
perennially-irrigated.
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
10. Mr. Gorwardkar would submit that the MIDC has admitted in the
Reply Affidavit that the data based on which categorisation of the land became
possible, was admittedly available only on August 11, 2017. Therefore, the
Petitioners cannot be said to have known prior to 2017 what their final and
actual entitlement would be. . If the final compensation is not in consonance
with the Consent Awards by reason of mis-categorisation, he would submit,
the situation would clearly present a dispute that ought to be referred to the
Authority . He would add that the period of limitation for the Petitioners to
object can be computed only once the categorisation is actually finalised (after
2017 and not at the time of the Consent Awards).
11. In contrast, Mr. Prashant Chawan, Learned Senior Counsel
appearing on behalf of MIDC would submit that there cannot be an
adjudication of an objection to compensation agreed upon by mutual consent
as contained in the Consent Awards. Ms. P.M.J. Deshpande, Addl. G.P. and
Mr. B.V. Samant, Addl. G.P. on behalf of the other Respondents, would submit
that the Petitioners are hopelessly barred by limitation since Section 34 of the
Act provides for a limitation of 60 days from the date of the decision on the
compensation, with no provision for condonation of delay beyond such
period.
12. Any challenge under Section 34 has to be filed within 60 days
from the date of knowledge of the determination of the compensation. They
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
would submit that this facet of the matter is squarely covered by decision of a
Division Bench of this Court in State of Maharashtra and another vs. Keru
Baban Avhad1 (Keru Baban Avhad), which has declared the law that the 60-
day deadline to apply to the Collector seeking referral of the dispute to the
jurisdictional court, cannot be relaxed. Mr. Gorwardkar too would cite Keru
Baban Avhad to undermine the need for a party to have knowledge of the
ingredients of the award.
13. Having heard the Learned Counsel for the parties, who have
meticulously taken through the material on record to canvass their respective
positions, we are of the view that the Petitioners have not made out a case for
our intervention in exercise of our jurisdiction under Article 226 of the
Constitution of India, for a variety of reasons.
Sections 33 and 34 - no Reference in Consent Awards:
14. At the threshold, the following relevant extracts from the
provisions of the Act must be noticed:-
33. Compensation.-(1) Where any land is acquired by the State Government under this Chapter, the State Government shall pay for such acquisition compensation the amount of which shall be determined in accordance with the provisions of this section.
2008 SCC OnLine Bom 379
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
(2) Where the amount of compensation has been determined by agreement between the State Government and the person to be compensated, it shall be determined in accordance with such agreement.
(3) Where no such agreement can be reached, the State Government shall refer the case to the Collector for determination of the amount of compensation to be paid for such acquisition as also the person or persons to whom such compensation shall be paid:
Provided that, no compensation exceeding such amount as the State Government may by general order specify, to be paid for such acquisition shall be determined by the Collector without the previous approval of the State Government or such officer as the State Government may appoint in this behalf.
Provided further that, the State Government while issuing the general order under the preceding proviso shall adhere to the provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (30 of 2013) relating to the determination of amount of compensation in accordance with the First Schedule, and rehabilitation and resettlement specified in the Second and Third Schedules, being beneficial to the affected families.
(3A) Notwithstanding anything contained in sub-section (3), if after the case is referred to the Collector under that sub-section but before he has finally determined the amount of compensation, such amount is determined by agreement between the State Government and the person to be compensated, the compensation shall be determined by the Collector in accordance with such agreement.
(4) Before finally determining the amount of compensation, the Collector shall give an opportunity to every person to be compensated to state his case as to the amount of compensation.
(5) In determining the amount of compensation, the Collector shall be guided by the provisions contained in sections 26 to 30 and other relevant provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (30 of 2013), subject to the modifications that, the reference in section 26 to the date on which notification has been issued under section 11", shall be the reference as "the date of the service of publication of the notice under sub- section (2) of section 32 of this Act in the manner for the time being laid down under this Act", and the reference in section 28 to "the time of the publication of the declaration under section 19" shall be the reference as "the date of the
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
publication of the notice under sub-section (1) of section 32 of this Act in the Official Gazette.
(6) to 12) *****
Section 34. Appeal to Court.
(1) Any person aggrieved by the decision of the Collector determining the amount of compensation may, within sixty days from the date of such decision, in so far as it affects him, by written application to the Collector require that the matter be referred by him for determination of the Court as defined in the Land Acquisition Act, 1894 (I of 1894), in its application to the State of Maharashtra, and when any such application is made the provisions of Part IIT of the said Act shall mutatis mutandis apply to further proceedings in respect thereof.
(2) *****
[Emphasis Supplied]
15. It would be clear from the plain reading of the foregoing that the
determination of compensation is to be done in accordance with Section 33.
Under Section 33(2), where there is an acquisition by agreement, the
determination of compensation has to be done in accordance with the
agreement. It is only when no agreement can be reached, that the jurisdiction
of Section 33(3) is attracted - it provides for determination of the
compensation and identification of the entitlement to the compensation, by
the Collector. Section 33(3A) is noteworthy - if the State and the landowners
reach an agreement before the Collector can determine the compensation,
then the Collector's determination has to conform to the compensation under
the agreement.
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
16. Where the Collector determines the compensation, Section 33(4)
requires him to give those who are to be compensated, an opportunity to be
heard. Section 33(5) is attracted where the Collector is determining the
compensation, requiring him to determine such amount by applying the
principles stipulated in the 2013 Act.
17. Suffice it to say, Section 33(4) and Section 33(5) would only be
attracted where the Collector has to exercise jurisdiction under Section 33(3)
to determine the compensation. The jurisdiction of the Collector comes into
play under Section 33(3), only where no agreement can be reached between
the State Government and the landowner under Section 33(2). Therefore, the
2013 Act would have no role to play at all in the matter at hand, since it is
nobody's case that the State Government and the landowner have not reached
an agreement. Admittedly, the case at hand is one of agreement under
Section 33(2) of the Act having been reached, and the Consent Awards are a
product of such agreement. Therefore, in the matter at hand, the Collector has
no role whatsoever in determination of compensation under Section 33 of the
Act.
18. That would bring us to the scope of Section 34 of the Act. The
subject matter of grievance dealt with in Section 34 is the determination of
compensation by the Collector. Such determination of the compensation by
the Collector can only arise when the provisions of Section 33(3) are attracted.
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
For the jurisdiction of the Collector to determine compensation under Section
33(3) to arise, a precondition is that no agreement can be reached between the
State Government and the landowner. In the instant case, admittedly and
evidently, the very acquisition is under Section 33(2) under which an
agreement has been reached. There may arise differences of opinion among
contracting parties in an agreement, but the forum for resolution of such
disputes cannot be the special reference jurisdiction, which is a creation of
statute under Section 34 of the Act, with explicitly stipulated ingredients to
attract its jurisdiction.
19. For a person to apply to the Collector asking him to refer the
matter to the Authority exercising the reference jurisdiction under Section 34,
he ought to have a grievance about the decision of the Collector "determining
the amount of compensation". In the instant case, it is not the Collector who
has determined the compensation under Section 33(3), applying the
principles laid out in Section 33(5). As seen above, the very scheme of Section
33 gives primacy to consideration arrived at pursuant to an agreement.
20. It is only when the Collector is unilaterally determining the
compensation that he has to give an opportunity of being heard - it would be
trite to say that when the landowners have entered into an agreement of their
own will and accord, their involvement in reaching the mutually agreed
position is inherent. There is no question of a special provision being required
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
to enable a personal hearing - the very agreement is a product of personal
engagement between the parties. In these circumstances, we find merit in the
contention of Mr. Chawan and the Learned Additional Government Pleaders
that in the case at hand, there can be no resort to Section 34 of the Act, when
the compensation has been arrived at as a matter of agreement under Section
33(2) of the Act.
21. Agreements between the State Government and the landowner are
a matter of conscious mutual consent and finalization of a commercial bargain
between the parties who are ad idem on how they understand the bargain in
the agreement. The factors and criteria for determination of compensation in
terms of the 2013 Act governing unilateral determination of compensation
would not at all be relevant, and therefore, there can be no dispute about how
those factors have been applied, for a reference under Section 34 to be made.
22. It is a matter of common sense that a party consciously executing a
contract would apply its mind to it's owns self interest when agreeing to the
terms of the contract, which is what the Petitioners have done. Mr.
Gorwadkar too has rightly stated that the Petitioners' grouse is only really
whether within the framework of the agreement, the right categorisation has
been arrived at, which would lead to the application of the right price among
the three agreed price variants. As seen from the pleadings, the Petitioners
are being compensated at the rate of Rs. 52.50 lakhs per acre, which is the
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
amount agreed as being payable to landowners who have parted with
seasonally-irrigated land. That the Petitioners have a grievance about the
characterisation of their land as seasonally-irrigated land, would at best lead
to a dispute under the agreement, but it cannot lead to a grievance over the
determination of compensation by the Collector under Section 33, for an
application under Section 34 to be permissible.
23. Disputes under the agreement may be amenable to other means of
enforcement in law - for instance, potentially, a civil suit outside the statutory
reference framework of Section 34; or a writ petition on arbitrariness in
categorisation; or such other means as may be available in law. However, for
the reasons articulated above, the compensation not having been determined
by the Collector, no case is made out for directing that a reference be made
under Section 34.
24. While the aforesaid finding should be adequate to dispose of this
Petition for completeness, the arguments of the parties about limitation may
be noticed. In Keru Baban Avhad, a Division Bench of this Court ruled as
follows:-
24. The applications for reference filed by the claimants prima facie appear to be barred by time as they have been filed much beyond the period of 60 days from the date of decision of the Collector and even from the date of disbursement of compensation to them. Since it is not the case pleaded before us that the claimants were present at the time of declaration of the Award, the Court cannot draw any presumption
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
that the claimants were in knowledge of the award and/or its contents on 20th June, 1994 i.e. the date of declaration of award. We have already discussed above that in order to make the remedy fruitful and effective, it is necessary that the claimants should have knowledge of the essential ingredients of the Award. These essentials would be declaration of the award, the details of the land acquired, rate at which compensation is awarded and bare minimum reasons to support those finding. Reference can usefully be made to the judgments of the various Courts, including this Court in the case of Maharashtra Industrial Development Corporation, Nagpur v. Shaikh Khatinabi wd/o Abdul Gaffar Shaikh, 2008 (1) Mh. L.J. 813 as also the Supreme Court in the case of Mahadeo Bajirao Patil v. State of Maharashtra, 2006 (1) Mh. L.J. (SC) 28 : 2005 (7) SCC 440. It has been unambiguously held in those cases that mere declaration of award per se is not a notice to the claimants and the claimants should know or have proper knowledge of the essentials of the Award which will be required for making the remedy of appeal effective and purposeful.
25. In the present case, all these ingredients came to the knowledge of the claimants on 7th July, 1994 when they received compensation in terms of the Award already declared on 20th June, 1994. Once compensation so determined was actually paid to them and received by them, whether with or without prejudice, it would satisfy the basic requirements of knowledge about the declaration of award as it would fairly provide them the required information for taking recourse to their remedy under section 34(1) of the MID Act. The cases in which affidavits have been filed by the claimants to show that they had received payments beyond 7th July, 1994, and in any case 21st July, 1994, certain evidence is required to be led before their claims can be rejected as being barred by time by the Reference Court.
26. The other important aspect of the case is whether the provisions of section 5 of the Limitation Act or any other provisions could be invoked by the Collector or the Reference Court to condone the delay in filing petitions under section 18 of the Act and under section 34(1) of the MID Act. Both these provisions which prescribe for a specific period of limitation do not empower the Collector or the Court to condone the delay in filing a petition for reference. It is thus clear that wherever the petition filed under section 18 of the Act is barred by
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
time, the Collector or the Court has no jurisdiction to condone the delay. Similarly, if a petition is filed under section 34(1) of the MID Act, it must be filed within a period of sixty days from the date of the decision of the Collector and/or at best from a date which could be construed to be the date when the claimants had a fair knowledge about the essential features of the award. But once that date is known and/or determined, in that event, there is no power vested in the Collector or the Court to condone the delay in filing the appeal. In this regard, reference can be made to the judgment of the Supreme Court in the case of Officer on Special Duty (Land Acquisition) v. Shah Manilal Chandulal, 1996 (1) Mh. L.J. (SC) 609 : (1996) 9 SCC 414.
Reference in this regard can also be made to the judgment of the Supreme Court in the case of Mahadeo Bajirao Patil (supra).
28. The period of limitation cannot be extended by the Collector or the Courts and, therefore, reference should essentially be filed within the prescribed period of limitation under section 34(1) of the MID Act.
[Emphasis Supplied]
25. A batch of special leave petitions, inter alia challenging this
judgment came to be dismissed by the Supreme Court by an order dated
January 29, 2015.
26. The Petitioners have cited Keru Baban Avhad for the contents of
paragraph 24 extracted above to state that it is vital for them to have had
knowledge of the ingredients of the compensation - they have even invoked it
in their application to the Collector asking for a reference to be made. The
Consent Awards were made pursuant to the agreements executed in 2013. In
fact, Mr. Gorwadkar fairly states that the receipt of compensation took place
on November 18, 2015. The application to the Collector seeking a reference
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
under Section 34 has been made in February 2018. Since such application
was clearly made years after the receipt of compensation (as against the
limitation period of 60 days), Mr. Gorwadkar submits that it is now an
admitted position that the data for a proper categorisation of the land had
been made available only on August 11, 2017, as is seen from the Reply
Affidavit. Therefore, he would submit, limitation should be counted only from
the stage at which the Petitioners gained knowledge of the categorisation of
their lands, which can only be after August 11, 2017. According to him, the
Petitioners gained knowledge on December 25, 2017 that there had been a
categorisation on December 8, 2017. Therefore, their application on February
14, 2018 was within the limitation period of 60 days from the date of their
knowledge, as stipulated under Section 34 of the Act.
27. The Respondents have cited Keru Baban Avhad to state that the
Consent Awards put the Petitioners on notice of its contents and the 60-day
limitation period commenced then. Since knowledge of determination of the
ingredients of compensation is necessary to challenge it, the question of
limitation is a mixed question of fact and law.
28. Be that as it may, in our opinion, we need not enter upon this issue
at all, since we are firmly of the view that the matter at hand does not at all
lend itself to the jurisdiction of Section 34, for the detailed reasons set out
above. It is only if Section 34 is attracted that one would need to adjudicate
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
upon the computation of the 60-day period. In the facts of the case at hand,
such an exercise is wholly unnecessary.
29. The framework for computing the compensation had already been
agreed between the parties way back in 2013. The parties consciously put
themselves in a position of subjecting their compensation amount to the
categorisation of the land. They even agreed that depending on the
categorisation, they would be entitled to varying pre-agreed rates of
compensation. Even assuming for the sake of argument that the categorisation
was effected only in 2017, in our opinion, on the Petitioners' own showing,
they had not only executed the agreement accepting the compensation
framework, but also bargained for an enhancement in the compensation
depending on the categorisation of their lands. Section 33(2) as well as Section
33(3A) are explicit in their terms, inasmuch as compensation determined by
agreement would be sacrosanct and the Collector would have no role in
determining the compensation where an agreement is involved. Therefore,
since the compensation in question is not determined by the Collector but by
the parties to the agreement, the mixed question of fact and law involved in
determining limitation, is moot.
30. The Petitioners consciously subjected themselves to the procedure
envisaged in the agreements, and bound themselves to compensation as set
out in the agreements. The framework of rates was also accepted by them.
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
Having done that, in our opinion, the jurisdiction of Section 34, which is a
check and balance on unilateral determination of compensation by the
Collector, cannot be invoked. Even if the reference is made to the Authority,
the determination of compensation by that Authority would be by applying the
provisions of the 2013 Act, in order to test the veracity and accuracy of the
Collector's application of the 2013 Act, in determination of compensation .
The Authority would have to work in a vacuum since to begin with, there had
been no action on the part of the Collector to be adjudicated by the Authority,
and moreover, there has been no application of the principles of computing
compensation under the 2013 Act for such computation to be tested by the
Authority. Regardless it is also noted that the Petitioners' request to enhance
compensation had already been rejected multiple times before the Impugned
Order, which rejected the request for making a reference under Section 34.
31. As a result, we have no hesitation in rejecting the prayer for
directing that a reference be made under Section 34, to the Authority.
32. The Land Acquisition Officer, in the Reply Affidavit, has stated
that the categorisation of the lands had been effected on the basis of the crop
inspection entries for the period between 2002-03 to 2013-14. The grounds in
this Petition primarily relate to invoking the jurisdiction of Section 34 of the
Act. There is no material in the Petition to suggest that the interpretation of
the crop data in effecting the categorisation was arbitrary, or that the crop
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
data had been applied arbitrarily or that categorisation of land was without
application of mind to the crop data. Consequently, without any basis to
bring under cloud, the reasonableness of the categorisation on merits, there is
no scope for allowing the prayer for appointment of a Court Commissioner or
the Mamlatdar to undertake the categorization afresh. So also, since the
acquisition in question is pursuant to a framework contained in a mutually
agreed contract, there is no scope for direction computation of compensation
under the 2013 Act.
33. To summarize:-
a) We hold that it would not be possible to make a reference
of a dispute over categorisation of the Petitioners' lands to
the Authority under Section 34 of the Act, since the land
acquisition and the computation of compensation for the
acquisition is by way of agreements executed under
Section 33(2) of the Act;
b) There having been no pleading or any attack on the
reasonableness of the categorisation of the land in the
Petition, with nothing to suggest that the categorisation
was arbitrary, there is no question of issuing a writ to have
the categorisation be effected afresh, whether by a Court
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
Commissioner or the Mamlatdar, or by any other person;
c) No direction for computing compensation, applying the
provisions of the 2013 Act can be issued since the
compensation has been arrived at by agreement under
Section 33(2), which explicitly provides for compensation
being governed by the agreement between the State
Government and the landowner;
d) Section 33(3) and the consequential provisions requiring
the Collector to determine the compensation by applying
the principles under the 2013 Act, can only be applied
when no agreement can be reached over the acquisition
and compensation for it. Even where the Collector
commences such exercise, if such an agreement is reached
between the parties, the Collector's determination of
compensation would need to be in accordance with such
agreement; and
e) Consequently, no relief whatsoever as prayed for, can be
granted to the Petitioners in the facts and circumstances of
the case.
October 15, 2024 Ashwini Vallakati
J-926-ASWP-12039-2019+.doc
34. As a result, Rule is discharged, and the Writ Petition is disposed of
accordingly, without grant of any relief. In view of the disposal of the Writ
Petition, nothing would survive in any application in connection with this Writ
Petition, and the same too would stand disposed of.
[SOMASEKHAR SUNDARESAN, J.] [G. S. KULKARNI, J.]
October 15, 2024 Ashwini Vallakati
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!