Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Manik Chandru Deokar vs State Of Maharashtra Through ...
2023 Latest Caselaw 11104 Bom

Citation : 2023 Latest Caselaw 11104 Bom
Judgement Date : 30 October, 2023

Bombay High Court
Manik Chandru Deokar vs State Of Maharashtra Through ... on 30 October, 2023
Bench: G. S. Kulkarni, Jitendra Shantilal Jain
2023:BHC-AS:32491-DB
                 Tauseef                                                     22-WP.4022.2021-J.doc


                            IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                    CIVIL APPELLATE JURISDICTION

                                       WRIT PETITION NO.4022 OF 2021


                 Manik Chandru Deokar,
                 Age 78 years, Occupation : Agriculturist,
                 Residing at : Sugaon Khed Bhose,
                 Taluka : Pandharpur, District : Solapur.              ...Petitioner

                             Versus

                 1.        State of Maharashtra,
                           Through the Secretary,
                           The Ministry of Revenue and Forest,
                           Mantralaya, Mumbai.
                           (Summons to be served on the Learned
                           Government Pleader appearing for
                           State of Maharashtra under Order XXVII,
                           Rule 4, of the Code of Civil Procedure, 1908)

                 2.        The Divisional Commissioner,
                           Pune Division, Pune.
                           (Summons to be served on the Learned
                           Government Pleader appearing for
                           State of Maharashtra under Order XXVII,
                           Rule 4, of the Code of Civil Procedure, 1908)

                 3.        The District Rehabilitation Officer,
                           Solapur, District - Solapur.
                           (Summons to be served on the Learned
                           Government Pleader appearing for
                           State of Maharashtra under Order XXVII,
                           Rule 4, of the Code of Civil Procedure, 1908).

                 4.        The Additional Collector and Deputy Director
                           (Rehabilitation), Solapur,
                           District - Solapur.



                                                      1 of 15
 Tauseef                                                     22-WP.4022.2021-J.doc


          (Summons to be served on the Learned
          Government Pleader appearing for
          State of Maharashtra under Order XXVII,
          Rule 4, of the Code of Civil Procedure, 1908).

5.        Dattatray Mohan Deokar,
          Age: Adult, Occupation: Business and Agriculturist,
          Residing at: Post Sugaon Bhose,
          Taluka: Pandharpur, District: Solapur.    ...Respondents
                                   ********
Mr. Sandeep M. Pathak for the Petitioner.
Mr. Sachin H. Kankal, AGP for the Respondent (State).
Mr. Sandeep S. Salunkhe for Respondent No.5.

                                   ********

                CORAM                     :    G. S. KULKARNI,
                                               JITENDRA JAIN, J.J.

                RESERVED ON               :    13th SEPTEMBER, 2023.
                PRONOUNCED ON             :    30th OCTOBER, 2023.


JUDGMENT (Per Jitendra Jain, J.):

1. By this petition under Article 226 of the Constitution of India,

the Petitioner prays for quashing of the orders dated 17 th December

2019 and 24th November 2015 passed by Respondent No. 4, by which

allotment of land No.82 admeasuring 2500 sq.ft. is sought to be

cancelled. He further prays for issuance of writ of mandamus for

allotment of balance land of 1500 sq.ft., as the Petitioner is entitled for

8000 sq. ft. land and he has been allotted only 6500 sq.ft. till date, in

lieu of the Petitioner's land acquired long back.





                                     2 of 15
 Tauseef                                                    22-WP.4022.2021-J.doc


2.         Narrative of the relevant events :-


(i) The Petitioner's land and residential house situated at village

Sugaon, Khed Bhose, Taluka Pandharpur, District Solapur was

acquired for Ujjani Dam Project. The family of the Petitioner

consisted of 15 persons. The Petitioner, therefore, was entitled to

alternate land admeasuring 8000 sq.ft. under the Maharashtra

Resettlement of Project Displaced Persons Act, 1976 as further

replaced by the 1989 Act and 1999 Act (for short "Resettlement

Act").

(ii) In the year 1976, the Petitioner was first allotted plot, being Plot

No.82 admeasuring 2,500 sq.ft. at village Sugaon, Khed-Bhose,

Taluka Pandharpur, District Solapur, but possession of this plot was

handed over in the year 1989, i.e., after 13 years. The official

translation of relevant extracts of letter dated 6th February 1976

allotting Plot No.82 imposing conditions reads thus:

"Conditions:

(1) The price for getting possessory right of the said plot which will be determined as per Government Resolution, General Administration Department No. R.P.A.1070 Occupancy/ Ra-1, dated 4-9-71, shall be paid in lump-sum, within 30 days from the date of its demand.

(2) The agreement should be executed in the format prescribed in the Government Resolution, General Administration Department No. R.P.A./1067 / Ra-1, dated 11-1-71.

(3) The Occupant shall not transfer plot allotted to him in the gaothan area, without obtaining prior permission from the

3 of 15 Tauseef 22-WP.4022.2021-J.doc

Collector, Solapur.

(4) The Occupant should construct house within a period of one year.

(5) If it is found that the Occupant is not dam affected person, the plot which is allotted to him, will be withdrawn.

(6) The loan taken for the house in the new gaonthan area situated at Sugaon in Taluka Indapur as per the above mentioned Government Order, will be transferred to the plot being allotted under this Order and recovery thereof shall be made as per the Rules.

If any of the aforesaid conditions is violated and if the compliance in respect thereof, is not made, the Collector, Solapur shall take further action as per the provisions prescribed in the Law and shall revoke the right, title and interest to the said plot."

(emphasis supplied)

(iii) In the year 1996, the Petitioner was allotted second plot, being Plot

No.12, admeasuring 4,000 sq.ft. at village Sugaon Khed Bhose,

Taluka Pandharpur, District Solapur. The second allotment in the

year 1996 was almost after 20 years from the date of acquisition of

the Petitioner's land.

(iv) However, the balance 1,500 sq.ft. land (8000-2500-4000) still

remains to be allotted to the Petitioner as of today, which is one of

the prayers made in the present petition.

(v) On 14th May 2015, Respondent No.5-Shri. Dattatray Mohan

Deokar (not related to the Petitioner in any manner as we are

informed that most of the people residing in that area have similar

4 of 15 Tauseef 22-WP.4022.2021-J.doc

surname) filed a complaint with Respondent Nos. 3 and 4, alleging

that the Petitioner has not constructed the house on Plot No.82,

admeasuring 2,500 sq. ft. and, therefore, the said allotment of

2,500 sq. ft. should be cancelled.

(vi) On 24th November 2015, Respondent Nos.3 and 4 passed an order

cancelling the allotment of Plot No.82, admeasuring 2,500 sq. ft.

on the ground that the Petitioner has not constructed house on Plot

No.82 admeasuring 2500 sq. ft. and thereby violated condition

no.4 of order dated 6th February 1976.

(vii) The aforesaid order was challenged in review application filed by

the Petitioner and was also a subject matter of Writ Petition

No.2161 of 2018. However, the said writ petition was withdrawn

since the Petitioner had availed the remedy of review.

(viii) On 6th July 2019, the Divisional Commissioner, Pune, in review,

remanded the proceedings back and directed Respondent No.4 to

make inquiries in respect of the following three issues, namely:-

(a) The number of family members of the Petitioner on the

date of publication of Notification under Section 4 of the

Land Acquisition Act, 1894.

(b) Permissible plot area as per G.R. dated 12 th July 1978 to

which the Petitioner would be entitled, and;

(c) Reconsideration of order passed on 24th November 2015.





                                   5 of 15
 Tauseef                                                   22-WP.4022.2021-J.doc


(ix) Pursuant to above, Respondent No.4 passed the impugned order

dated 17th December 2019 by giving following findings on each of

the above three issues:-

(a) On the date of Notification under Section 4 of the Land

Acquisition Act, 1894, the family of the Petitioner

comprised of 15 persons.

(b) The Petitioner is entitled to 8,000 sq. ft. in lieu of the

acquisition of the land.

(c) The Petitioner has violated condition no.4 of order dated

6th February 1976 which required the Petitioner to

construct the house on Plot No.82, admeasuring 2,500

sq.ft. within one year of its allotment and, therefore, the

allotment of 2,500 sq.ft. land stands cancelled.

3. It is on such backdrop that the present petition is filed

challenging the order dated 17th December 2019 cancelling the

allotment made in the year 1976 of Plot No.82, admeasuring 2,500

sq.ft. for violation of condition No.4 of the order of allotment dated 6 th

February 1976.

4. Heard Mr. Pathak, learned counsel for the Petitioner, Mr.

Kankal, learned AGP and Mr. Salunkhe, learned counsel for respondent

no. 5 and with their assistance, we have perused the documents

annexed to the petition.




                                      6 of 15
 Tauseef                                                   22-WP.4022.2021-J.doc


                   Submission of the Petitioner :-


5. At the outset, the Petitioner submitted that as per Condition

No.4 of the order dated 6th February 1976, the occupant should

construct the house within a period of one year and failing, which the

right, title and interest to the said plot would be revoked, is arbitrary,

unconstitutional and without jurisdiction, since such power is not

conferred by the Maharashtra Project Affected Persons Rehabilitation

Act, 1976 as replaced in the years 1989 and 1999. Secondly, the

Petitioner's family consisted of more than 15 persons and, therefore, the

plot area of 2,500 sq.ft. was not sufficient to construct a house to

accommodate all these members, who were living under one roof. The

Petitioner, therefore, constructed house on the second plot, i.e., Plot

No.12, admeasuring 4,000 sq.ft., which was allotted in the year 1996.

Furthermore, where Plot No.82 admeasuring 2500 sq.ft. was allotted, it

was not having basic civic amenities as also essential facilities like,

education, transport, water, etc. and, therefore, they could not construct

a house on the said plot. The Petitioner submitted that had the State

allotted one full plot of land admeasuring 8,000 sq. ft. in that event, it

would have been possible for the Petitioner to construct the required

house on such plot to accommodate all the members of the family

under one roof. The Petitioner also contended that as against the

entitlement of 8,000 sq. ft., the Petitioner was allotted only 6,500 sq.ft.





                                  7 of 15
 Tauseef                                                    22-WP.4022.2021-J.doc


and, therefore, the Petitioner is still deprived of 1,500 sq.ft. of land till

today. The Petitioner also contested the locus of Respondent No.5 and it

is his submission that the impugned action smacks of malafides at the

behest of Respondent No.5, who has no locus to make a complaint.

Submission of the Respondents :-

6. Respondent No.5 contended that the Petitioner has violated

Condition No.4 of the order dated 6th February 1976 by not constructing

house on plot no.82 admeasuring 2,500 sq.ft. and, therefore, the

allotment should be cancelled. Respondent No.5 further stated that this

fact of non-construction of house was not brought to the notice of

Respondent Nos.3 and 4 at the time of allotment of 4,000 sq.ft. and,

therefore, there is a fraud played by the Petitioner in getting allotment

of Plot No.12, admeasuring 4,000 sq.ft.

7. Learned counsel for the State adopted the submissions made

by Respondent No.5 and prayed that the cancellation of allotment of

Plot No.82, admeasuring 2,500 sq. ft. is justified and in accordance with

law. Respondents have also relied upon the affidavit-in-reply in support

of their aforesaid contentions.

8. On the above conspectus, the question which would fall for

determination are:-

8 of 15 Tauseef 22-WP.4022.2021-J.doc

(1) Whether order of cancellation dated 17 th December 2019 of Plot

No.82 admeasuring 2500 sq.ft. on the ground of violation of

Condition No.4 of order dated 6 th February 1976 is illegal, unfair,

arbitrary, unreasonable and without jurisdiction and more

particularly in case of beneficial allotment to project affected

persons?

(2) Whether Respondent-State is justified in not allotting balance 1500

sq. ft. of land?

Analysis and Conclusion :-

9. On Question No.1 :- Insofar as the cancellation of Plot No.82

admeasuring 2500 sq. ft. is concerned, whether Respondent No. 4 was

justified in cancelling the allotment of Plot No.82 admeasuring 2500 sq.

ft., the only reason given in the impugned order is that the Petitioner

had not constructed the house on the said plot within one year from the

date of allotment and therefore, there has been a violation of Condition

No.4 specified in the order dated 6th February 1986.

10. The object and purpose in rehabilitating a person like the

Petitioner by allotting him the alternate land in lieu of his land being

acquired for a public project is purely on special and humanitarian

considerations and not merely to compensate him as in a normal case of

land acquisition. It is for such beneficial reason and only with such

9 of 15 Tauseef 22-WP.4022.2021-J.doc

intention that the person who stands uprooted from his land is

rehabilitated by allotment of land, is sought to be achieved. The object

being to mitigate the extreme hardship which was faced by such

persons whose lands have been taken away. This would certainly not

contemplate imposing of a condition which would take away the

benefits of such rehabilitation, and in fact would subject such person to

a coercive taking away of the alternate land allotted to him. In short,

such condition imposed in allotment of land, to the project affected

persons so as to expropriate the land allotted to a person, to rehabilitate

him would certainly not stand the test of reasonableness, when tested

on the anvil of Article 14 of the Constitution. This apart we wonder as

to how it can be reasonable for any person as a mandate to construct a

house within one year. This has to be subjective. It may not be possible

for everyone to construct a house within one year. Further the State-

Respondent has not been able to show any policy or any provision

under the Rehabilitation Act which empowers the State to impose such

condition in the context of rehabilitation. Therefore, imposition of such

condition in the allotment order issued by the Collector was without

jurisdiction. Moreover, having any such condition and revoking the

allotment on such condition would not only be draconian but also

arbitrary, unfair, unreasonable and contrary to the object of the

Resettlement Act. Thus, in our considered opinion, imposing a

10 of 15 Tauseef 22-WP.4022.2021-J.doc

condition to foist on the Petitioner to undertake construction within one

year of the allotment, would be on the face of it arbitrary and

unreasonable condition. In any case, such a condition could not have

been implemented after 40 years of allotment of the land and that too

on a complaint of Respondent No.5, who in no manner was concerned

with the allotment of the land to the Petitioner. Acting on such

complaint itself, was a colourable exercise of power, discriminatory,

unjust and arbitrary action on the part of the Respondent No.4. In fact

by resorting to such action, the very object and purpose of resettlement/

rehabilitation would stand defeated and destroyed in the facts of the

present case.

11. Be that as it may, the Respondent-State in the first place for a

period of 40 years, never bothered to implement any such condition. It

could not have been implemented. The Respondents have also not

disputed the reasons given by the Petitioner for non-construction of a

house on the Plot No.82 admeasuring 2500 sq.ft., that is, on account of

lack of basic amenities, the plot size being small, considering the

number of family members, the name could not be constructed. For

such reason the Petitioner has constructed house on Plot No.12

admeasuring 4000 sq.ft., which was not questioned by the Respondents

in any manner and therefore it cannot be said that the Petitioner had

not complied the condition of construction of a house or there was non-

11 of 15 Tauseef 22-WP.4022.2021-J.doc

compliance of condition no.4 as contained in the order dated 6

February, 1976, moreso when the Petitioner has not been allotted a

continguous (single) plot of 8000 sq.ft.

12. We also do not agree with the reasons as set out by

Respondent No.4 for cancellation of the Petitioner's allotment of Plot

No.82 admeasuring 2500 sq. ft., that while getting allotted Plot No.12

admeasuring 4000 sq. ft., the Appellant has not disclosed non-

compliance of the condition of non-construction of house on Plot No.82.

The impugned order itself records that it is not clear whether the

Petitioner has given false information to the Government for allotment

of Plot No.12. In view of what is observed hereinabove, Plot No.82 was

not sufficient to accommodate all the family members of the Petitioner

as also it lacked the basic civic amenities and as held by us such

condition therefore was not applicable. Thus, one cannot say that there

is any false information given by the Petitioner at the time of getting

allotment of Plot No.12 admeasuring 4,000 sq. ft.

13. We may state that the genesis of the present proceedings

initiated against the Petitioner appears to be at the behest of

Respondent No.5, who appears to be the architect behind the initiation

of the impugned action. It is only after the complaint of Respondent

No.5 that the officer (Respondent No.4) of the Respondent-State, who

12 of 15 Tauseef 22-WP.4022.2021-J.doc

had not taken any action for a period of almost four decades on this

issue, happened to have woken up. We fail to understand the locus of

Respondent No.5 to make a complaint, though he is not related to the

Petitioner nor he claims any entitlement to the land in question which

is allotted to the Petitioner. The intention of Respondent No.5 to make

such complaint does not appear to be bonafide or in any public cause.

As to how the State and its officers could act upon and succumb to

Respondent No.5's complaint and that too after almost 4 decades is a

mystery. It is not the case that the State Government and in the manner

known to law had suo-moto initiated action, which if at all would

certainly include an action to be taken within a reasonable time. Thus,

as to how such drastic action could not have been initiated against the

Petitioner at the behest of Respondent No.5.

14. On Question No.2 :- Insofar as the claim of the Petitioner for

allotment of 1500 sq. ft. is concerned, it is an admitted fact as evident

from paragraph 2 of the order dated 17 th December 2019 passed by the

Collector, Solapur that the Petitioner is entitled to 8000 sq.ft. of the land

in lieu of the acquisition. It is also an admitted fact that as of today, the

Petitioner has been allotted two different plots of the land aggregating

6500 sq.ft. (Plot No.82 admeasuring 2500 sq.ft. and Plot No.12

admeasuring 4000 sq.ft.). Therefore, as of today, against the

entitlement of 8000 sq.ft., the Petitioner has been allotted only 6,500

13 of 15 Tauseef 22-WP.4022.2021-J.doc

sq.ft. There is no reason given in the reply affidavit of the Respondent-

State as to what is the justification for not allotting balance land of

1500 sq.ft. The entitlement of the Petitioner to the allotment of balance

1500 sq. ft. of land is not in dispute. It cannot be indefinitely

postponed without any justification by the State, which itself is unfair

and unreasonable. The Respondent-State have admitted the entitlement

of the Petitioner to 8000 sq.ft. of land. The Respondent State has acted

upon the same by allotting two plots aggregating 6500 sq.ft., however

there is no reason given for withholding balance allotment of land of

1500 sq.ft. Therefore, the Petitioner is justified based on doctrine of

legitimate expectation to seek allotment of the balance land. The

Petitioner is entitled for allotment of balance plot area admeasuring

1500 sq. ft. as prayed for in prayer clause (b) of the petition.

15. In the light of the above discussion, we allow the writ petition

in terms of the following order.

ORDER

(i) The impugned order dated 17th December 2019 is as

much as it cancels allotment of Plot No.82 admeasuring

2500 sq. ft. for non-compliance of Condition No.4 of 6th

February 1976 order is quashed and set aside;

(ii) The State-Respondent is directed to allot 1500 sq. ft.




                                   14 of 15
                                Tauseef                                                  22-WP.4022.2021-J.doc


balance plot area to the Petitioner within a period of 12

weeks from today;

(iii) Petition is disposed of in terms of the above order. No

costs.

                               [JITENDRA JAIN, J.]                              [G. S. KULKARNI, J.]




Signed by: Tauseef Farooqui
Designation: PA To Honourable Judge
Date: 30/10/2023 11:41:34
                                                                 15 of 15
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter