Wednesday, 06, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The State Of Maharashtra Thr P.W.D ... vs Morya Infrastructure ...
2023 Latest Caselaw 1045 Bom

Citation : 2023 Latest Caselaw 1045 Bom
Judgement Date : 1 February, 2023

Bombay High Court
The State Of Maharashtra Thr P.W.D ... vs Morya Infrastructure ... on 1 February, 2023
Bench: Mangesh S. Patil, S. G. Chapalgaonkar
                                         1                            CA / 651 / 2023+


           IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                       BENCH AT AURANGABAD

                 CIVIL APPLICATON NO. 651 OF 2023 IN
          COMMERCIAL ARBITRATION APPEAL (ST.) NO. 1440 OF 2023

                                AND
                 CIVIL APPLICATON NO. 652 OF 2023 IN
          COMMERCIAL ARBITRATION APPEAL (ST.) NO. 1440 OF 2023

State of Maharashtra
Through Public Works Department,
Through its Executive Engineer,
Public Division, Beed Tq. & Dist. Beed                                 .. Appellant

        VERSUS

Morya Infrastructure Pvt. Ltd. Beed
Through its Director,
Bhaskar Tukaram Waghmare
R/o. Head Office at Shahunagar, Beed
Tq. & Dist. Beed                                                       .. Respondent

                                             ...
                 Mr. P.K. Lakhotiya, AGP for the applicant - State
                   Mr. J.N. Singh, Advocate for the respondent
                                        ...

                         CORAM                     : MANGESH S. PATIL &
                                                     S.G. CHAPALGAONKAR, JJ.

                         RESERVED ON   : 23 JANUARY 2023
                         PRONOUNCED ON : 01 FEBRUARY 2023



ORDER (MANGESH S. PATIL, J.) :

Civil application no. 651 of 2023 is filed by the Public Works

Department of the State of Maharashtra (hereinafter referred to as

"Department") seeking condonation of delay calculated as 187 days in

filing appeal under section 37 of the Arbitration and Conciliation Act,

1996 ("Arbitration Act") read with section 13 of the Commercial Courts

Act, 2015 ("Commercial Courts Act"), against the judgment and order

2 CA / 651 / 2023+

passed by the learned District Judge-2 & Commercial Court, Beed in a

proceeding bearing Civil Miscellaneous Application no. 87 of 2018

dated 06-05-2022 dismissing the department's application preferred

under section 34 of the Arbitration Act.

2. The learned Additional Government Pleader by referring to the

application and the additional affidavit filed by the department

submitted that the facts and circumstances leading to the filing of the

appeal are peculiar. The department manned by the personnel has

been made to suffer the award because of the misdeeds of its officers

and apart from the cause which the department is required to satisfy for

condonation of delay, all the happenings throughout this proceeding

right from the appointment of the arbitrator, are relevant factors for this

Court to exercise its discretion.

3. As regards the cause for the delay, Mr. P.K. Lakhotiya, learned

AGP would submit that though the department is not entitled to claim

any exception and the law of limitation has to be applied equally even

against it, there are sufficient circumstances which prevented it from

preferring the appeal in time. He would submit that some time was lost

to complete the administrative formalities and in seeking instructions

and documents. The delay is neither deliberate nor is it intentional.

The department was not to gain anything by causing the delay

particularly when it is intending to challenge the award which is passed

3 CA / 651 / 2023+

by the sole arbitrator in spite of a stipulation in the clause 3.4.17(iii)(a)

that the arbitral tribunal would comprise of three arbitrators; one to be

appointed by each of the sides and the third by the two such arbitrators

of the parties.

4. The learned AGP would submit that according to the Bombay

High Court Rules, this being an arbitration cum commercial appeal, it is

supposed to be filed online. An attempt was made to submit it on

14-12-2022 but for want of bill of costs, the system was not accepting

the registration and some time was lost therein till it was finally

registered on 11-01-2023. The application under section 34 of the

Arbitration Act was decided on 06-05-2022 and the appeal under

section 37 has been filed on 19-11-2022. The limitation for filing appeal

is 60 days. Five (5) days were required for obtaining certified copies

from the date of application till its receipt and there is 132 days delay.

5. Mr. Lakhotiya, the learned AGP would then refer to the decision

of the Supreme Court in the matter of Government of Maharashtrta

(Water Resources Department) represented by Executive

Engineer Vs. Borse Brothers Engineers and Contractors Pvt.

Limited; (2021) 6 SCC 460. He would submit that the department is

entitled to take benefit of this decision since the delay has occurred

bona fide and not in a negligent manner.

4 CA / 651 / 2023+

6. The learned advocate Mr. Singh for the claimant would strongly

oppose the application by referring to the affidavit in reply. He would

submit that there is no sufficient cause demonstrated by the

department for this Court to exercise the discretion. Even the

application for certified copy was not filed soon after pronouncement of

the judgment and order by the learned District Judge on 06-05-2022.

The calculation of delay is also incorrect. There is delay of 253 days.

He would submit that the department is under an obligation to

demonstrate sufficient cause and any reference to the merits of the

appeal is irrelevant. He would also place reliance in the judgment of

Borse Brothers (supra). The delay is enormous and the right which

by lapse of time has vested in the claimant may not be divested. He is

awaiting for the fruits of the award for years together. He had to sell

the properties since it was a project in the form of 'Built Operate and

Transfer' (BOT).

7. We have carefully considered the rival submissions and perused

the papers including the decision in the matter of Borse Brothers

(supra).

8. To begin with, after taking a thorough survey of catena of

judgments, following observations have been made in Borse Brothers

(supra) in paragraph no. 63 :-

5 CA / 651 / 2023+

"63. Given the aforesaid and the object of speedy disposal sought to be achieved both under the Arbitration Act and the Commercial Courts Act, for appeals filed under Section 37 of the Arbitration Act that are governed by Articles 116 and 117 of the Limitation Act or Section 13(1-A) of the Commercial Courts Act, a delay beyond 90 days, 30 days or 60 days, respectively, is to be condoned by way of exception and not by way of rule. In a fit case in which a party has otherwise acted bona fide and not in a negligent manner, a short delay beyond such period can, in the discretion of the court, be condoned, always bearing in mind that the other side of the picture is that the opposite party may have acquired both in equity and justice, what may now be lost by the first party's inaction, negligence or laches."

9. With respect, no further deliberation is necessary. If a sufficient

cause as contemplated under section 5 of the Limitation Act, 1963 can

be demonstrated coupled with the fact that the aspect of bona fides /

deliberate inaction also would be relevant.

10. There cannot be a dispute about the fact that the learned District

Judge pronounced the judgment and order in the proceeding under

section 34 on 06-05-2022 and the appeal is stated to have been filed

on 13-01-2023. As per the provisions of section 13(1-A) of the

Commercial Courts Act, the period of limitation for preferring an appeal

would be 60 days. The department ought to have filed the appeal on or

before 05-07-2022, of course excluding the time required for obtaining

the certified copy. However, the application for certified copy is stated

to have been filed on 07-09-2022 and it was obtained on 13-09-2022.

Since the application for certified copy itself was filed beyond the

6 CA / 651 / 2023+

period of limitation, the department would not be entitled to any benefit

of such time. Thus, the delay would come to 190 days.

11. Admittedly the appeal was required to be e-filed. The e-filing

history placed on record by the department has not been controverted

by the claimant. The history shows that the appeal was for the first

time presented on 14-12-2022 but it was not accepted on 16-12-2022.

Again it was pending acceptance till 26-12-2022 but was reported as

not accepted on 06-01-2023. Again an attempt was made for

acceptance on 11-01-2023. The scrutiny was undertaken on

13-01-2023 and it is this date which is being considered as the date of

filing. There is no law which would meet such an eventuality in case of

e-filing when a party is supposed to file it on-line on the requisite portal.

When it is a matter of physical presentation, the Registry accepts such

presentation even if it is deficient in any respect on the date of

presentation albeit it is not registered. Date of registration is never

considered as the date of presentation. The period while calculating the

delay abates on presentation of appeal. Further time required for

removing the office objections and registration is considered as

procedural delay and is never counted. In our considered view, in view

of the peculiar circumstances in e-filing of the appeals, the date of first

presentation, even if it is later on not accepted or is kept pending

acceptance should be regarded as the date of presentation and till that

date only the delay should be counted.

7 CA / 651 / 2023+

12. Resultantly, the delay in the present matter will have to be

counted only till 14-12-2022 and would be of 161 days.

13. The department has sought to explain the delay in following

words :-

"2. The Appellant most respectfully submit that impugned judgment is delivered by the Ld. District Judge-2/Commercial Court, Beed, District Beed, dated 06.05.2022 in Civil M.A. (Arbitration) No. 87/2018. The present appeal is preferred after getting proposal of appeal vide proposal dated 05.08.2022, issued Law & Judiciary Department, Aurangabad to the office of the Public Prosecutor, High Court Bench at Aurangabad which was received in the office on 10.08.2022. Thereafter the concerned file was allotted to the Additional Public Prosecutor for drafting on 11.08.2022, thereafter, immediately appeal is drafted and filed.

3. Appellant submits that this Appeal for condonation of delay may kindly be allowed in the interest of justice as it is a matter of serious nature and for such reasons the Appellant prays that, the delay of 169 days be condoned in the interest of justice.

4. The Appellant has a very good case based on sound legal grounds and hopes to succeed in the same. Delay caused in filing the Commercial Appeal (Arbitration) was caused due above mentioned circumstances which is neither intentional nor deliberate and the same is caused due to the administrative procedure. That, for obtaining some documents and also some instructions also there was some delay caused. As such, the delay caused in filing the Commercial First Appeal (Arbitration) deserves to be condoned in the larger interest of justice."

All these circumstances pleaded in the application have been

controverted by the claimant in his reply. However, in addition, the

department has filed an additional affidavit which inter alia reads as

under:-

"2. I say and submit that, thereafter, due to Court fees purpose and certified copy and bills of costs are not received by the Government Pleader Office, Aurangabad, hence appeal could not be filed. As the bills of costs of the impugned judgment was not ready and prepared at the District Court (commercial) Beed.

8 CA / 651 / 2023+

3. I say and submit that, by letter dated 23.08.2022 and 15.11.2022 requested to the Public Prosecutor as well as appellant to supply the bills of cost and same was intimated to the Public Prosecutor at Beed and on 17.11.2022 he intimated to the Government Pleader Office at Aurangabad that, bill of cost/decree is not ready in the District Court (commercial) Beed. Copy of letter dated 23.08.2022, 15.11.2022 and 17.11.2022 is annexed herewith and marked as EXHIBIT-A collectively.

4. The applicant say and submit that, as certified copy of the decree was not there, office of registry is not accepting the commercial appeal for registration and hence the Asst. Government Pleader on 13.12.2022 given undertaking that, as and when the bills of costs will be ready in the District Court immediately it will be filed. Copy of undertaking filed by the Asst. Government Pleader dated 13.12.2022 is annexed herewith and marked as EXHIBIT-B.

5. The applicant say and submit that, thereafter, immediately on 14.12.2022, the office accepted the filing of the present appeals but it could not be registered for the reasons best known to them and lastly on 13.01.2023 Stamp No. is given to the Commercial Appeal and thereafter, immediately matter was circulated before this Hon'ble Court for urgent hearing.

6. The applicant say and submit that, the above stated reasons were happened subsequently after drafting of delay condonation application and hence these additional grounds are not mentioned in the delay condonation application and as such by way of present additional affidavit these grounds are brought on record for kind consideration of this Hon'ble Court so that, it can be explained that the delay caused and calculated by the office is not intentional and deliberate but same was caused due to above mentioned facts and circumstances those are beyond control of present appellant."

Pertinently, the averments in this additional affidavit have not been

controverted by the claimant by filing any additional affidavit.

14. Though the State / Government departments are not entitled to

have any special treatment as regards the law of limitation is

concerned, which has to be applied rigoursly against the State as it is

applied against individuals, one cannot overlook the fact that the

9 CA / 651 / 2023+

certain decision making process has to be undertaken in every

department while taking any decision. It is in view of such peculiar set

up that it becomes imperative to ascertain if the delay is deliberate or

intentional or prompted by mala fides as has been laid down in the

matter of Collector, Land Acquisition Vs. Mst. Katiji ; (1987) 2

S.C.C. 107 and Ramlal, Motilal and Chhotelal Vs. Rewa Coalfields

Ltd.; AIR 1962 SC 361. However, nothing has been brought on record

by the claimant to demonstrate that there was deliberate inaction or

mala fides. In the absence of which we have no reason to doubt that

the delay has occasioned bona fide and is unintentional.

15. It is quite trite that while considering application for condonation

of delay, the Court must bear in mind the fact that a party is not to gain

anything by allowing its right to prefer an appeal is lost on

technicalities. It is in view of such principles that it was for the claimant

to bring on record circumstances to indicate that the delay has

occasioned mala fide. Not even allegations have been imputed to the

department in spite of filing of a lengthy reply by the claimant.

16. Apart from above state-of-affairs, in our considered view, there

are peculiar facts and circumstances which require this Court to

exercise the discretion in condoning the delay. We do not intend to

enter into the factual disputes, which could have a bearing on the

decision of the appeal, but we cannot overlook the fact that in spite of

10 CA / 651 / 2023+

the specific stipulation in the arbitration agreement in clause 3.4.17(iii)

(a) regarding composition of arbitral tribunal of three arbitrators, only an

arbitrator of the claimant who initially approached the department,

called upon it to appoint its arbitrator and in turn to enable appointment

of third arbitrator, the claimant's arbitrator solely proceeded to conduct

the arbitration proceeding and passed the award.

17. Mr. Singh for the claimant would strongly submit that there is a

scheme under the Arbitration Act provided under section 12, 13 and 16

for raising an objection to challenge appointment of arbitrator or

competence of arbitral tribunal but no recourse was taken by the

department to resort to these provisions and the fact of composition of

arbitral tribunal need not persuade this Court to exercise the discretion.

18. For the time being we do not want to deliberate in this regard.

We are only concerned about the fact that there is a serious issue

regarding the constitution of the arbitral tribunal which would go to the

root of the legality of award and the issue deserves to be addressed to,

particularly when it is a matter of public money.

19. Civil Application nos. 651 of 2023 and 652 of 2023 are allowed.

20. The delay is condoned subject to the department depositing cost

of Rs.10,000/- (Rs. Ten Thousand) in this Court within four weeks. On

such costs being paid in time, the appeal be registered and the cost be

11 CA / 651 / 2023+

paid over to the claimant. The execution of the award shall stand

stayed for a period of four weeks.

  [ S. G. CHAPALGAONKAR ]                     [ MANGESH S. PATIL ]
           JUDGE                                   JUDGE

arp/





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter