Citation : 2023 Latest Caselaw 1045 Bom
Judgement Date : 1 February, 2023
1 CA / 651 / 2023+
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
CIVIL APPLICATON NO. 651 OF 2023 IN
COMMERCIAL ARBITRATION APPEAL (ST.) NO. 1440 OF 2023
AND
CIVIL APPLICATON NO. 652 OF 2023 IN
COMMERCIAL ARBITRATION APPEAL (ST.) NO. 1440 OF 2023
State of Maharashtra
Through Public Works Department,
Through its Executive Engineer,
Public Division, Beed Tq. & Dist. Beed .. Appellant
VERSUS
Morya Infrastructure Pvt. Ltd. Beed
Through its Director,
Bhaskar Tukaram Waghmare
R/o. Head Office at Shahunagar, Beed
Tq. & Dist. Beed .. Respondent
...
Mr. P.K. Lakhotiya, AGP for the applicant - State
Mr. J.N. Singh, Advocate for the respondent
...
CORAM : MANGESH S. PATIL &
S.G. CHAPALGAONKAR, JJ.
RESERVED ON : 23 JANUARY 2023
PRONOUNCED ON : 01 FEBRUARY 2023
ORDER (MANGESH S. PATIL, J.) :
Civil application no. 651 of 2023 is filed by the Public Works
Department of the State of Maharashtra (hereinafter referred to as
"Department") seeking condonation of delay calculated as 187 days in
filing appeal under section 37 of the Arbitration and Conciliation Act,
1996 ("Arbitration Act") read with section 13 of the Commercial Courts
Act, 2015 ("Commercial Courts Act"), against the judgment and order
2 CA / 651 / 2023+
passed by the learned District Judge-2 & Commercial Court, Beed in a
proceeding bearing Civil Miscellaneous Application no. 87 of 2018
dated 06-05-2022 dismissing the department's application preferred
under section 34 of the Arbitration Act.
2. The learned Additional Government Pleader by referring to the
application and the additional affidavit filed by the department
submitted that the facts and circumstances leading to the filing of the
appeal are peculiar. The department manned by the personnel has
been made to suffer the award because of the misdeeds of its officers
and apart from the cause which the department is required to satisfy for
condonation of delay, all the happenings throughout this proceeding
right from the appointment of the arbitrator, are relevant factors for this
Court to exercise its discretion.
3. As regards the cause for the delay, Mr. P.K. Lakhotiya, learned
AGP would submit that though the department is not entitled to claim
any exception and the law of limitation has to be applied equally even
against it, there are sufficient circumstances which prevented it from
preferring the appeal in time. He would submit that some time was lost
to complete the administrative formalities and in seeking instructions
and documents. The delay is neither deliberate nor is it intentional.
The department was not to gain anything by causing the delay
particularly when it is intending to challenge the award which is passed
3 CA / 651 / 2023+
by the sole arbitrator in spite of a stipulation in the clause 3.4.17(iii)(a)
that the arbitral tribunal would comprise of three arbitrators; one to be
appointed by each of the sides and the third by the two such arbitrators
of the parties.
4. The learned AGP would submit that according to the Bombay
High Court Rules, this being an arbitration cum commercial appeal, it is
supposed to be filed online. An attempt was made to submit it on
14-12-2022 but for want of bill of costs, the system was not accepting
the registration and some time was lost therein till it was finally
registered on 11-01-2023. The application under section 34 of the
Arbitration Act was decided on 06-05-2022 and the appeal under
section 37 has been filed on 19-11-2022. The limitation for filing appeal
is 60 days. Five (5) days were required for obtaining certified copies
from the date of application till its receipt and there is 132 days delay.
5. Mr. Lakhotiya, the learned AGP would then refer to the decision
of the Supreme Court in the matter of Government of Maharashtrta
(Water Resources Department) represented by Executive
Engineer Vs. Borse Brothers Engineers and Contractors Pvt.
Limited; (2021) 6 SCC 460. He would submit that the department is
entitled to take benefit of this decision since the delay has occurred
bona fide and not in a negligent manner.
4 CA / 651 / 2023+
6. The learned advocate Mr. Singh for the claimant would strongly
oppose the application by referring to the affidavit in reply. He would
submit that there is no sufficient cause demonstrated by the
department for this Court to exercise the discretion. Even the
application for certified copy was not filed soon after pronouncement of
the judgment and order by the learned District Judge on 06-05-2022.
The calculation of delay is also incorrect. There is delay of 253 days.
He would submit that the department is under an obligation to
demonstrate sufficient cause and any reference to the merits of the
appeal is irrelevant. He would also place reliance in the judgment of
Borse Brothers (supra). The delay is enormous and the right which
by lapse of time has vested in the claimant may not be divested. He is
awaiting for the fruits of the award for years together. He had to sell
the properties since it was a project in the form of 'Built Operate and
Transfer' (BOT).
7. We have carefully considered the rival submissions and perused
the papers including the decision in the matter of Borse Brothers
(supra).
8. To begin with, after taking a thorough survey of catena of
judgments, following observations have been made in Borse Brothers
(supra) in paragraph no. 63 :-
5 CA / 651 / 2023+
"63. Given the aforesaid and the object of speedy disposal sought to be achieved both under the Arbitration Act and the Commercial Courts Act, for appeals filed under Section 37 of the Arbitration Act that are governed by Articles 116 and 117 of the Limitation Act or Section 13(1-A) of the Commercial Courts Act, a delay beyond 90 days, 30 days or 60 days, respectively, is to be condoned by way of exception and not by way of rule. In a fit case in which a party has otherwise acted bona fide and not in a negligent manner, a short delay beyond such period can, in the discretion of the court, be condoned, always bearing in mind that the other side of the picture is that the opposite party may have acquired both in equity and justice, what may now be lost by the first party's inaction, negligence or laches."
9. With respect, no further deliberation is necessary. If a sufficient
cause as contemplated under section 5 of the Limitation Act, 1963 can
be demonstrated coupled with the fact that the aspect of bona fides /
deliberate inaction also would be relevant.
10. There cannot be a dispute about the fact that the learned District
Judge pronounced the judgment and order in the proceeding under
section 34 on 06-05-2022 and the appeal is stated to have been filed
on 13-01-2023. As per the provisions of section 13(1-A) of the
Commercial Courts Act, the period of limitation for preferring an appeal
would be 60 days. The department ought to have filed the appeal on or
before 05-07-2022, of course excluding the time required for obtaining
the certified copy. However, the application for certified copy is stated
to have been filed on 07-09-2022 and it was obtained on 13-09-2022.
Since the application for certified copy itself was filed beyond the
6 CA / 651 / 2023+
period of limitation, the department would not be entitled to any benefit
of such time. Thus, the delay would come to 190 days.
11. Admittedly the appeal was required to be e-filed. The e-filing
history placed on record by the department has not been controverted
by the claimant. The history shows that the appeal was for the first
time presented on 14-12-2022 but it was not accepted on 16-12-2022.
Again it was pending acceptance till 26-12-2022 but was reported as
not accepted on 06-01-2023. Again an attempt was made for
acceptance on 11-01-2023. The scrutiny was undertaken on
13-01-2023 and it is this date which is being considered as the date of
filing. There is no law which would meet such an eventuality in case of
e-filing when a party is supposed to file it on-line on the requisite portal.
When it is a matter of physical presentation, the Registry accepts such
presentation even if it is deficient in any respect on the date of
presentation albeit it is not registered. Date of registration is never
considered as the date of presentation. The period while calculating the
delay abates on presentation of appeal. Further time required for
removing the office objections and registration is considered as
procedural delay and is never counted. In our considered view, in view
of the peculiar circumstances in e-filing of the appeals, the date of first
presentation, even if it is later on not accepted or is kept pending
acceptance should be regarded as the date of presentation and till that
date only the delay should be counted.
7 CA / 651 / 2023+
12. Resultantly, the delay in the present matter will have to be
counted only till 14-12-2022 and would be of 161 days.
13. The department has sought to explain the delay in following
words :-
"2. The Appellant most respectfully submit that impugned judgment is delivered by the Ld. District Judge-2/Commercial Court, Beed, District Beed, dated 06.05.2022 in Civil M.A. (Arbitration) No. 87/2018. The present appeal is preferred after getting proposal of appeal vide proposal dated 05.08.2022, issued Law & Judiciary Department, Aurangabad to the office of the Public Prosecutor, High Court Bench at Aurangabad which was received in the office on 10.08.2022. Thereafter the concerned file was allotted to the Additional Public Prosecutor for drafting on 11.08.2022, thereafter, immediately appeal is drafted and filed.
3. Appellant submits that this Appeal for condonation of delay may kindly be allowed in the interest of justice as it is a matter of serious nature and for such reasons the Appellant prays that, the delay of 169 days be condoned in the interest of justice.
4. The Appellant has a very good case based on sound legal grounds and hopes to succeed in the same. Delay caused in filing the Commercial Appeal (Arbitration) was caused due above mentioned circumstances which is neither intentional nor deliberate and the same is caused due to the administrative procedure. That, for obtaining some documents and also some instructions also there was some delay caused. As such, the delay caused in filing the Commercial First Appeal (Arbitration) deserves to be condoned in the larger interest of justice."
All these circumstances pleaded in the application have been
controverted by the claimant in his reply. However, in addition, the
department has filed an additional affidavit which inter alia reads as
under:-
"2. I say and submit that, thereafter, due to Court fees purpose and certified copy and bills of costs are not received by the Government Pleader Office, Aurangabad, hence appeal could not be filed. As the bills of costs of the impugned judgment was not ready and prepared at the District Court (commercial) Beed.
8 CA / 651 / 2023+
3. I say and submit that, by letter dated 23.08.2022 and 15.11.2022 requested to the Public Prosecutor as well as appellant to supply the bills of cost and same was intimated to the Public Prosecutor at Beed and on 17.11.2022 he intimated to the Government Pleader Office at Aurangabad that, bill of cost/decree is not ready in the District Court (commercial) Beed. Copy of letter dated 23.08.2022, 15.11.2022 and 17.11.2022 is annexed herewith and marked as EXHIBIT-A collectively.
4. The applicant say and submit that, as certified copy of the decree was not there, office of registry is not accepting the commercial appeal for registration and hence the Asst. Government Pleader on 13.12.2022 given undertaking that, as and when the bills of costs will be ready in the District Court immediately it will be filed. Copy of undertaking filed by the Asst. Government Pleader dated 13.12.2022 is annexed herewith and marked as EXHIBIT-B.
5. The applicant say and submit that, thereafter, immediately on 14.12.2022, the office accepted the filing of the present appeals but it could not be registered for the reasons best known to them and lastly on 13.01.2023 Stamp No. is given to the Commercial Appeal and thereafter, immediately matter was circulated before this Hon'ble Court for urgent hearing.
6. The applicant say and submit that, the above stated reasons were happened subsequently after drafting of delay condonation application and hence these additional grounds are not mentioned in the delay condonation application and as such by way of present additional affidavit these grounds are brought on record for kind consideration of this Hon'ble Court so that, it can be explained that the delay caused and calculated by the office is not intentional and deliberate but same was caused due to above mentioned facts and circumstances those are beyond control of present appellant."
Pertinently, the averments in this additional affidavit have not been
controverted by the claimant by filing any additional affidavit.
14. Though the State / Government departments are not entitled to
have any special treatment as regards the law of limitation is
concerned, which has to be applied rigoursly against the State as it is
applied against individuals, one cannot overlook the fact that the
9 CA / 651 / 2023+
certain decision making process has to be undertaken in every
department while taking any decision. It is in view of such peculiar set
up that it becomes imperative to ascertain if the delay is deliberate or
intentional or prompted by mala fides as has been laid down in the
matter of Collector, Land Acquisition Vs. Mst. Katiji ; (1987) 2
S.C.C. 107 and Ramlal, Motilal and Chhotelal Vs. Rewa Coalfields
Ltd.; AIR 1962 SC 361. However, nothing has been brought on record
by the claimant to demonstrate that there was deliberate inaction or
mala fides. In the absence of which we have no reason to doubt that
the delay has occasioned bona fide and is unintentional.
15. It is quite trite that while considering application for condonation
of delay, the Court must bear in mind the fact that a party is not to gain
anything by allowing its right to prefer an appeal is lost on
technicalities. It is in view of such principles that it was for the claimant
to bring on record circumstances to indicate that the delay has
occasioned mala fide. Not even allegations have been imputed to the
department in spite of filing of a lengthy reply by the claimant.
16. Apart from above state-of-affairs, in our considered view, there
are peculiar facts and circumstances which require this Court to
exercise the discretion in condoning the delay. We do not intend to
enter into the factual disputes, which could have a bearing on the
decision of the appeal, but we cannot overlook the fact that in spite of
10 CA / 651 / 2023+
the specific stipulation in the arbitration agreement in clause 3.4.17(iii)
(a) regarding composition of arbitral tribunal of three arbitrators, only an
arbitrator of the claimant who initially approached the department,
called upon it to appoint its arbitrator and in turn to enable appointment
of third arbitrator, the claimant's arbitrator solely proceeded to conduct
the arbitration proceeding and passed the award.
17. Mr. Singh for the claimant would strongly submit that there is a
scheme under the Arbitration Act provided under section 12, 13 and 16
for raising an objection to challenge appointment of arbitrator or
competence of arbitral tribunal but no recourse was taken by the
department to resort to these provisions and the fact of composition of
arbitral tribunal need not persuade this Court to exercise the discretion.
18. For the time being we do not want to deliberate in this regard.
We are only concerned about the fact that there is a serious issue
regarding the constitution of the arbitral tribunal which would go to the
root of the legality of award and the issue deserves to be addressed to,
particularly when it is a matter of public money.
19. Civil Application nos. 651 of 2023 and 652 of 2023 are allowed.
20. The delay is condoned subject to the department depositing cost
of Rs.10,000/- (Rs. Ten Thousand) in this Court within four weeks. On
such costs being paid in time, the appeal be registered and the cost be
11 CA / 651 / 2023+
paid over to the claimant. The execution of the award shall stand
stayed for a period of four weeks.
[ S. G. CHAPALGAONKAR ] [ MANGESH S. PATIL ]
JUDGE JUDGE
arp/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!