Citation : 2022 Latest Caselaw 942 Bom
Judgement Date : 27 January, 2022
1 1-arbpl 1665-22.odt
Prajakta Vartak
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION (L.) NO.1665 OF 2022
M/s. Moonline Express Cargo Pvt. Ltd. ..Petitioner
Vs.
Union of India through Divisional
Railway Manager (Commercial) ..Respondent
-----
Mr. Mutahhar Khan i/b. Mr. Rajesh Gupta for Petitioner.
Mr. T. J. Pandian with Mr. T. C. Subramanian and Mr. Dheer Sampat for
Respondent.
-----
CORAM : G.S. KULKARNI, J.
DATE : JANUARY 27, 2022.
P.C.:
1. This is a petition filed under Section 9 of the Arbitration and
Conciliation Act, 1996 (for short, "the Act") whereby the petitioner has
prayed for interim reliefs pending the arbitral proceedings. The disputes
between the parties have arisen under a contract entered by the
respondent -Railways with the petitioner, awarded in pursuance of a
tender floated by it on 03 March, 2021, for grant of leasing rights in
respect of a "3.9 Ton parcel space in Train No. 03202 (FL WLRRM) LTT-
PNBE Spl Ex. Operating between Lokmanya Tilak Terminus and Patna"
for a period of five years.
2. It is also necessary to note the date on which petitioner,
participated in such tender which was on 26 March, 2021. The dates of
issuance of the tender and the date on which the petitioner submitted its
bid, according to the petitioner are indicative of quite a normal period
2 1-arbpl 1665-22.odt
after the first wave of the Covid 19 pandemic. The petitioner has
contended that in April 2021 the second wave of Covid-19 had
commenced, consequent to which lockdown restrictions were imposed
in Mumbai as also in Patna.
3. On 17 May 2021, the respondent having accepted the petitioner's
bid, issued a 'Letter of Allotment' in favour of the petitioner. This was
during the time when the lockdown restrictions were imposed. As per
the letter of allotment the respondent called upon the petitioner to
commence loading within 15 days of issuance of the letter of allotment.
4. It is the petitioner's case that due to the circumstances created by
the lock down , it was not possible for the petitioner to comply with the
requirement of immediate loading as contained in the letter of
allotment. On the issue of commencement of the loading there was
correspondence between the parties. By its letters dated 31 May, 2021,
29 June, 2021 and 19 July, 2021 the petitioner informed the respondent
about the lockdown restrictions in Mumbai as also in Patna and due to
which it had become difficult for the petitioner to comply with such
conditions as contained in the letter of allotment.
5. The petitioner's request however was not accepted by the
respondent and a show cause notice dated 26 July, 2021 came to be
issued to the petitioner calling upon the petitioner to start loading with
effect from 01 August, 2021, failing which the petitioner was put to a
notice that its allotment would stand terminated. It is the petitioner's
3 1-arbpl 1665-22.odt
case that the show cause notice did not refer and /or contain any
intimation or a threat that the petitioner would be debarred or
blacklisted from submitting its bid in future tenders.
6. The petitioner responded to the show cause notice of the
respondent by its letter dated 28 July, 2021 interalia setting out the
circumstances which were prevailing. The petitioner categorically
pointed out that when the tender in question was floated by the
respondent as also when the petitioner submitted its bid, the
circumstances of a lockdown were not existing, that is in March 2021.
The petitioner has contended that the respondent although considered
the petitioner's reply to the show cause notice, however, the reasons as
pointed out by the petitioner were not accepted by the respondent,
inasmuch as the respondent on 8 September, 2021 issued a termination
letter to the petitioner, terminating the award of the said contract and
forfeiting the earnest money deposit of Rs.1 Lakh, as also, debarring the
petitioner from participating in the future tenders of the respondent for
a period of two years. Such termination letter dated 8 September, 2021
was received by the petitioner on 16 October, 2021.
7. The petitioner being aggrieved by such action of the respondent to
debar the petitioner from participating in future tenders, approached
this Court by filing Writ Petition No.3581 of 2021, which came to be
filed on 28 October, 2021. However, as an alternate remedy was
available to the petitioner including resorting to arbitration, a Division
4 1-arbpl 1665-22.odt
Bench of this Court by an order dated 17 January, 2022 permitted the
petitioner to withdraw such petition, with liberty to pursue the available
alternate remedy including arbitration keeping open all contentions.
Accordingly, the petitioner has filed this petition on 19 January, 2022.
8. Mr. Khan, learned counsel for the petitioner at the outset would
submit that the grievance of the petitioner in the present proceedings is
on the action of the respondent to debar the petitioner from
participating in any tender of the respondent for two years. Mr. Khan,
would submit that the relief in regard to such a condition has become
necessary, in as much as, the respondent has floated tender for leasing
rights in respect of certain trains. Such tenders would be opened on 28
January, 2022. It is submitted that the petitioner, who is desirous to
participate in such tender, would lose an opportunity of participating in
such tender in view of the arbitrary condition of debarment imposed by
the respondent in the termination letter dated 8 September, 2021.
9. Mr. Khan submits that to debar the petitioner for any period, was
not the case of the respondent, in the show cause notice issued to the
petitioner. It is submitted that an action of debarring the petitioner was
certainly an action involving civil consequences and if such action was to
be taken against the petitioner, in that event, the respondent ought to
have followed the due procedure, as known to law and a specific show
cause notice ought to have been issued to the petitioner, and thereafter
following the principles of natural justice, by granting the petitioner an
5 1-arbpl 1665-22.odt
opportunity of being heard on such show cause notice, an appropriate
order could have been passed by the respondent. It is submitted by Mr.
Khan that such lawful procedure has been given a complete go-bye by
the respondent in imposing on the petitioner, a drastic consequence of
debarment for a period of two years. Mr. Khan has submitted that the
action to debar is an action of blacklisting the petitioner for a period of
two years and in a manner completely unknown to law. To support such
contentions, Mr. Khan placed reliance on the decisions of the Supreme
Court in Erusian Equipment & Chemicals Ltd. v. State of West Bengal 1,
Gorkha Security Services v. Government (NCT of Delhi) and Ors. 2,
Southern Painters versus Fertilizers & Chemicals Travancore Ltd. & Anr. 3
and in a recent judgment of Supreme Court in UMC Technologies Private
Limited Versus Food Corporation of India and Another 4 to submit that
this is a clear case where the lawful procedure of adherence to the
principles of natural justice in blacklisting a contractor has not been
followed by the respondent which would render the respondent's action,
as assailed, totally non est in law. In these circumstances, it is his
submission that the petitioner has become entitled to the reliefs as
prayed for in prayer clause (c), wherein the petitioner has prayed for
stay to the effect and operation of the condition as contained in the
termination letter dated 8 September, 2021, to the extent it seeks to
1 . (1975) 1 SCC 70.
2. (2014) 9 SCC 105
3 1994 Supp (2) Supreme Court Cases 699
4 (2021) 2 Supreme Court Cases 551
6 1-arbpl 1665-22.odt
debar the petitioner from participating in any tenders floated by the
respondent for a period of two years.
10. On the other hand, Mr. Pandian, learned counsel for the
respondent in opposing the reliefs as prayed by the petitioner, has placed
reliance on the reply affidavit of Mr. Dhirendra Singh, Divisional
Commercial Manager, Central Railway, Mumbai CSMT. In the
arguments as advanced by Mr. Pandian, his principal contention is that
the petitioner would not be entitled to any reliefs, as in the tender
documents under which the petitioner was issued an allotment letter, a
provision for an appeal has been made in clause 1.6 interalia against
cancellation of registration or termination of lease contracts, which
would lie with the Chief Commercial Manager of Zonal Railways. It is
his submission that in view of such condition, it was not correct for the
petitioner to invoke the jurisdiction under Section 9 of the Act. Mr.
Pandian however does not dispute that clause 1.5 of the tender
condition which also forms part of the contract confers an authority on
the respondent , in a manner as specifically set out in the said condition
to debar the contractor from fresh registration for a period of five years,
which was not invoked by the respondent against the petitioner. Mr.
Pandian is not in a position to support the action of the respondent to
debar the petitioner on the basis of the show cause notice which was
issued to the petitioner. Thus, the only contention of Mr. Pandian is that
7 1-arbpl 1665-22.odt
the petitioner ought to have availed the remedy of appeal as set out in
clause 1.6 of the tender.
11. Having heard Mr. Khan and Mr. Pandian, learned counsel for the
parties, in my opinion, there is much substance in the contention as
urged by Mr. Khan, that an action to debar the petitioner for any period,
was certainly not in contemplation of the respondent, when the
respondent issued to the petitioner, the show cause notice dated 26 July,
2021. Such show cause notice was conspicuously silent on any action of
a debarment/blacklisting to be taken against the petitioner. Thus, no
opportunity was available to the petitioner to defend an action of
debarment being resorted by the respondent against the petitioner. The
petitioner could not have been taken by a surprise by the respondent. If
the respondent wanted to initiate any action against the petitioner by
invoking clause 1.5 of the tender condition which according to Mr.
Pandian would confer a contractual authority on the respondent to
debar the petitioner, then necessarily the law would require issuance of
a specific show cause notice on debarment, when such cause to debar
stems under the contract between the parties, as in the present case.
12. Adherence to the principles of natural justice which would include
issuance of a show cause notice and an effective hearing to be given to
the person against whom a debarment action is proposed are a sine qua
non, as clear from decisions of the Supreme Court which hold the field
for more than last 46 years (see: Erusian Equipment & Chemicals Ltd.
8 1-arbpl 1665-22.odt
(supra)) and several other decisions as rendered by the Supreme Court
after such decision. Mr. Khan's reliance on a recent decision of the
Supreme Court in UMC Technologies Private Limited (supra) is well
founded. The facts of the said case are quite similar to the facts of the
case in hand. Under the bids invited by the respondent-FCI, the
appellant had submitted its bid and was declared to be a successful
bidder for undertaking the tender work of conducting recruitment of
watchman for the FCI. On certain materials gathered by the FCI against
the appellant a show cause notice was issued to the appellant which was
completely silent on any action of blacklisting to be taken against the
appellant. The proceedings of the show cause notice however resulted in
the FCI terminating the appellants contract as also blacklisting the
appellant from participating in any future tenders for a period of five
years. The appellant failed before the High Court in its writ petition
challenging such action of the FCI. Allowing the appellants appeal the
Supreme Court referring to several earlier decisions held, that it is the
first principle of civilized jurisprudence that a person against whom any
action is sought to be taken or whose right or interests are being
affected should be given a reasonable opportunity to defend himself. It
was observed that the basic principle of natural justice, is to the effect
that, before an adjudication starts, the authority concerned should isue a
notice to the affected party putting up the case against him, so that he
can defend himself. It was observed that blacklisting of a person or of
an entity by the State or a State Corporation, the requirement of a valid,
9 1-arbpl 1665-22.odt
particularized and unambiguous show cause notice was crucial due to
the severe consequences of blacklisting and the stigmatization that
accrues to the person/entity being blacklisted. It was observed that
blacklisting has the effect of denying a person or an entity the privileged
opportunity of entering into government contracts. Such privilege arises
because it is the State who is the counter party in government contracts
and as such, every eligible person is to be afforded an equal opportunity
to participate in such contracts, without arbitrariness and
discrimination. The Court held that not only does blacklisting takes
away this privilege, it also tarnishes the blacklisted person's reputation
and brings the person's character into question. It was observed that
blacklisting also has long-lasting civil consequences for the future
business prospects of the blacklisted person. The Court referring to the
decision in Erusian Equipment & Chemicals Ltd. (supra) observed that
the severity of the effects of blacklisting and the resultant need for strict
observance of the principles of natural justice before passing an order of
blacklisting, made it mandatory that the principles of natural justice are
followed as blacklisting casts a slur. It creates a barrier between the
persons blacklisted and the Government in the matter of transactions. It
was observed that black list are instruments of coercion. The Court also
referred to its decision in Gorkha Security Services (supra) wherein the
Supreme Court had observed that blacklisting was equivalent to a civil
death of a person, because blacklisting was stigmatic in nature and
10 1-arbpl 1665-22.odt
which debars a person from participating in government tenders. These
principles of law are aptly applicable in the facts of the present case.
13. Considering the aforesaid principles of law, in my clear opinion,
prima-facie the respondent appears to have acted in complete
derogation of its dominant contractual position in debarring the
petitioner for a period of two years under the termination order.
Although for justifiable reasons even assuming that such a right was
available to the respondent under the contract in question, however, it
could not have been exercised in a manner alien to the well settled
principles of law as laid down by the Supreme Court as noted above. A
party to the contract like the respondent was under a more solemn
obligation to adhere to the principles of law in imposing a debarment on
the petitioner acting under the contract. It is also significant that the
petitioner's registration has not been cancelled, a consequence of which
is that the petitioner continuous to be a panel contractor. However, by
issuing a debarment and that too illegally, the respondent has meted out
to the petition a consequence of a civil death. The action on the part of
the respondent is thus prima facie not only perverse to the contractual
conditions, but also illegal affecting the legal and constitutional rights of
the petitioner as held by the Supreme Court.
14. In the aforesaid circumstances, in my opinion a strong prima facie
case has been made out by the petitioner for grant of interim measures
pending the arbitral proceedings to the extent it debars the petitioner for
11 1-arbpl 1665-22.odt
a period of two years. It is would be the requirement of law for the
Court to stay the effect of such illegal condition being inserted in the
termination letter dated 8 September, 2021, as such condition is prima
facie void ab initio being contrary to the settled principles of law as laid
down in the decisions as discussed above.
15. In so far as the prayers as made in clauses (a) and (b) are
concerned, I am not inclined to grant any relief to the petitioner, as
prayed for in such prayers, as these reliefs are in the nature of reliefs,
which can be granted only on final adjudication of the disputes, in the
proposed arbitral proceedings. The petition is accordingly disposed of
by the following order:-
ORDER
i. The respondent is directed not to act upon the condition of
debarring the petitioner for a period of two years as contained in the
termination letter dated 8 September, 2021. Consequently, the
petitioner is permitted to participate in the tenders which may be issued
by the respondent.
ii. In the event the respondent intends to initiate any action of
blacklisting/debarring the respondent for any reason, it is open for the
respondent to follow the procedure as known to law.
iii. The petitioner is directed to invoke arbitration. As the present
proceedings are filed before invocation of the arbitral proceedings, the
provisions of sub-section (2) of Section 9 of the Act would become
12 1-arbpl 1665-22.odt
applicable making it incumbent upon the petitioner to commence the
arbitral proceedings within a period of 90 days.
iv. If the petitioner does not commence the arbitral proceedings as
provided for under sub-section (2) of section 9, it would be open for the
respondent to apply for vacating of the protection granted to the
petitioner by this order.
v. All contentions of the parties in the arbitral proceedings are
expressly kept open.
vi. Disposed of in the above terms. No costs.
[G.S. KULKARNI, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!