Citation : 2022 Latest Caselaw 7834 Bom
Judgement Date : 11 August, 2022
6-SJ-3-20+.DOC
Sayali Upasani
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
SUMMONS FOR JUDGMENT NO. 3 OF 2020
IN
COMMERCIAL SUMMARY SUIT NO. 990 OF 2019
SANTOSH
SUBHASH
KULKARNI Sanjay Vaghji Rathod ... Plaintiff
Digitally signed by
SANTOSH
Versus
Government of India & Ors ...Defendants
SUBHASH
KULKARNI
Date: 2022.08.12
21:11:45 +0530
Mr. N.D. Jaywant, for Plaintiff.
Mr. Yogesh Bhate i/b Dharmesh Joshi, for Defendant Nos. 1
and 3.
Mr. Ashutosh Shukla, for Defendant No. 2.
CORAM: N. J. JAMADAR, J.
DATED : 11 AUGUST, 2022
ORDER:-
1. This Commercial Division Summary Suit is instituted for
recovery of a sum of Rs.12,51,73,033.77/-, comprising of
Rs.9,92,23,670.65/-, being outstanding amount of running bills
raised in respect of the works contract and Rs.2,59,49,363.12/-,
being the interest component.
2. The material averments in the plaint can be summarised as
under:
(a) The plaintiff deals in the business of construction
under the name and style of M/s Sanjay construction. The
6-SJ-3-20+.DOC
defendant Nos.2 and 3 are the instrumentalities of Government of
India, defendant no.1.
(b) The defendant No.2 had floated a tender on behalf of
defendant No.3 for structural repairs and allied civil work of SDF
Building Nos.1 to 6 and Gems & Jewellery Building Nos.1, 2 and 3
in the premises of defendant No.3. The plaintiff had submitted a
tender. On 17th February, 2017, the defendant No. 2 issued a letter
of intent, to award the contract for structural repairs to SDF
Building Nos.1, 2, 3 and 4 at the premises of defendant No.3, to
the plaintiff. Eventually, on 20th March, 2017, an agreement came
to be executed between the plaintiff and defendant No.2,
incorporating the terms and conditions. Vide communication
dated 15th November, 2017, the defendant No.2 revised the scope
of work order and the revised costs of the work was pegged at
Rs.25,33,93,331/-. The defendant No.3 appointed M/s Tekburo
Engineering Pvt. Ltd. as Structural Consultants and M/s Conspro
Management Services as Project Management Consultants for the
said work.
(c) The plaintiff claims that the plaintiff executed the work
in accordance with the terms of the contract and raised running
bills from time to time. As the payments of the running bills were
not forthcoming there was exchange of correspondence between
6-SJ-3-20+.DOC
the plaintiff and defendant No.2, on the one part, and defendant
No.2 and defendant No.3, on the other part. The plaintiff asserts
that the payments in respect of R.A. bills dated 20 th March, 2017,
19th April, 2017, 5th May, 2017, 6th June, 2017, 22nd August, 2017,
11th September, 2017 and 2nd December, 2017 (Exhibits-L to L6) to
the plaint remained outstanding. A final bill was raised by the
plaintiff on 23rd May, 2018, for a sum of Rs.18,76,619.59/-. It is
further averred that the Project Management Consultant has
certified that the work was satisfactorily executed. Even IIT,
Mumbai, who carried third party audit, certified that the
structural as well as non-structural repair work was satisfactorily
executed by the plaintiff.
(d) The plaintiff made repeated demands by addressing
series of communications. The defendant No.2 informed the
plaintiff that the approval was awaited from the concerned
Ministry of Government of India which controls the affairs of
defendant No.3, and the payment would be made after the
requisite approval. Since an amount of Rs.9,92,23,670.65/-,
remained outstanding, the plaintiff addressed notices to the
defendants including one under the provisions of Section 80 of
the Code of Civil Procedure, 1908. As the demand was not met
despite service of notice, the plaintiff was constrained to institute
6-SJ-3-20+.DOC
this suit for recovery of the aforesaid amount along with further
interest.
3. The defendants entered appearance upon being served with
the writ of summons. Thereupon, the plaintiff took out a
summons for judgment. The defendant Nos. 1 and 3 have resisted
the claim by filing an affidavit of Executive Assistant to the
Development Commissioner and Estate Manager in the office of
Development Commissioner, defendant No.3, and have sought an
unconditional leave to defend the suit.
4. At the outset, the tenability of the suit is assailed on the
ground that there is no privity of contract between the plaintiff
and defendant No. 3. The suit is thus stated to be bad for
mis-joinder of the parties. The defendant No.3 has thereafter
adverted to the circumstances in which the defendant No.2 came
to be appointed as a Project Management Consultant for
defendant No.3. The substance of the defence of defendant No.3 is
that the tender was floated by defendant No.2, works contract was
also executed by defendant No.2 and, at the instance of defendant
No.2, the defendant No.3 has released partial payment towards
the entire works contract. It later transpired that the appointment
of defendant No.2, by the then Development Commissioner of
6-SJ-3-20+.DOC
defendant No.3, was not in consonance with the rules and,
therefore, a vigilance enquiry was initiated.
5. On the merits of the claim, the defendant No.3 contends
that the third party inspection carried out by IIT, Mumbai has
revealed that there were several deficiencies in the work executed
by the plaintiff. Thus, the plaintiff cannot be said to have executed
the works contract in conformity with the terms and conditions of
the contract. Therefore, the question as to whether the plaintiff is
entitled to recover the amount of the bills raised by the plaintiff
for the works contract, the quality of which was found to be
inferior, raises a triable issue. Hence, unconditional leave to
defend the suit be granted.
6. The defendant No.2 has also filed an affidavit-in-reply and
sought an unconditional leave to defend the suit. It is contended
that the defendant No. 2 is a Multi State Co-operative Society
registered under the Multi-State Co-Operative Societies Act, 2002
and works under the aegis of the Ministry of Agriculture. The role
of defendant No.2 was only that of a Project Management
Consultant. The defendant No.2 was to receive a fee of 3% of the
project value for rendering the services as a Project Management
Consultant to defendant No.3. It had floated the tenders, executed
the agreement and issued work orders in the capacity of an agent
6-SJ-3-20+.DOC
of known principal. Therefore, the action against the defendant
No.2 is legally infirm.
7. I have heard Mr. Jaywant, the learned Counsel for plaintiff,
Mr. Yogesh Bhate, the learned Counsel for defendant Nos. 1 and
3, Mr. Ashutosh Shukla, the learned Counsel for defendant No.2,
at length.
8. To start with, it may be apposite to note uncontroverted
facts. The fact that the defendant No.2 was acting as a Project
Management Consultant for the defendant No.3 is
incontrovertible. The floating of the tender by defendant No. 2 for
structural repairs and allied civil work of SDF Building Nos. 1 to 6
and Gems & Jewellery Building Nos.1, 2 and 3 in the premises of
SEEPZ-SEZ, the defendant no.3, is incontrovertible. Nor is it in
dispute that the plaintiff's bid for structural repairs and allied
civil works of SDF 1, 2, 3 and 4 buildings came to be accepted,
under the letter of acceptance dated 17 th February, 2017 (Exhibit-
C). Indisputably, the said acceptance was preceded by the
approval granted by the defendant No.3 vide communication
dated 16th February, 2017 (Exhibit-B) addressed to the General
Manger of the defendant No.2. Armed with the said approval and
consequent to the acceptance conveyed by the plaintiff, it is
incontestable that, an agreement dated 20th March, 2017, came to
6-SJ-3-20+.DOC
be executed between the plaintiff and defendant No.2. Issuance of
the revised work order vide communication dated 15th November,
2017 (Exhibit-E) is also incontestable. Evidently, the parties are
not at issue over the fact that the plaintiff executed the work in
accordance with the agreement and revised work order. Raising
running bills and part payment therefor are also not much in
contest.
9. It seems that the disputes arose between the parties when
the amount covered by the running bills (Exhibit L to L6)
remained outstanding. The claim of the plaintiff that out of the
total costs of Rs.23,72,16,934.64/-,he was paid a sum of
Rs.12,72,69,206/-, and an amount Rs.9,92,23,670.65/-,
remained outstanding has not been seriously controverted.
10. In the aforesaid backdrop, the quality of the defences sought
to be raised by the defendants warrants consideration. At the
outset, it is interesting to note that both defendant Nos. 2 and 3
contend that there was no privity of contract between the plaintiff
and the respective answering defendant and the contract was
between the plaintiff and the defendant(s) other than the
answering defendant.
11. Mr. Ashutosh Shukla, the learned Counsel for the defendant
No.2 would urge that the defendant No.2 had merely acted as an
6-SJ-3-20+.DOC
agent of the defendant No.3. The defendant No.2 was a Project
Management Consultant and was to receive a consultancy fee of 3
% of the contract value. Mr. Shukla, invited the attention of the
Court to the provisions contained in Sections 194 and 195 of the
Indian Contract Act, 1872 to bolster up the submission that the
appointment of the plaintiff by the defendant No. 2 to execute the
work for defendant No.3 was of such a nature that the plaintiff
himself became an agent of defendant No.3. Emphasis was laid
on the illustration (a) appended to Section 194 of the Indian
Contract Act, 1872.
12. For a proper appreciation, Sections 194 and 195 of the
Indian Contract Act, 1872, are extracted below.-
"194. Relation between principal and person duly appointed by agent to act in business of agency.--Where an agent, holding an express or implied authority to name another person to act for the principal in the business of the agency, has named another person accordingly, such person is not a sub-agent, but an agent of the principal for such part of the business of the agency as is entrusted to him. --Where an agent, holding an express or implied authority to name another person to act for the principal in the business of the agency, has named another person accordingly, such person is not a sub-agent, but an agent of the principal for such part of the business of the agency as is entrusted to him.
Illustrations
(a) A directs B, his solicitor, to sell his estate by auction, and to employ an auctioneer for the purpose. B names C, an auctioneer, to conduct the sale. C is not a sub-agent, but is A's agent for the conduct of the sale.
(b) A authorizes B, a merchant in Calcutta, to recover the moneys due to A from C & Co. B instructs D, a solicitor, to take legal proceedings against C & Co. for the recovery of the money. D is not a sub-agent, but is solicitor for A.
Section 195: Agent's duty in naming such person. In selecting such agent for his principal, an agent is bound to exercise the same amount of discretion as a man of ordinary prudence would exercise in his own case; and, if he does this, he is
6-SJ-3-20+.DOC
not responsible to the principal for the acts or negligence of the agent so selected.
Illustrations
(a) A instructs B, a merchant, to buy a ship for him. B employs a ship-surveyor of good reputation to choose a ship for A. The surveyor makes the choice negligently and the ship turns out to be unseaworthy and is lost. B is not, but the surveyor is, responsible to A.
(b) A consigns goods to B, a merchant, for sale. B, in due course, employs an auctioneer in good credit to sell the goods of A, and allows the auctioneer to receive the proceeds of the sale. The auctioneer afterwards becomes insolvent without having accounted for the proceeds. B is not responsible to A for the proceeds."
13. At the outset, before adverting to appreciate the
aforesaid submission, it would be imperative to note that an
identical challenge raised by the defendant No.2 in Summons
for Judgment No.52 of 2019 in Commercial Summary Suit
No.1237 of 2019 and Summons for Judgment No.51 of 2019
in Commercial Summary Suit No.1230 of 2019 and
connected matter, instituted by the other contractors, arising
out of the very same approval granted by defendant No.3
dated 16th February, 2017, in respect of the same project, was
repelled by this Court. In fact, in the said suits, the
defendant No.2 herein was the sole defendant and the
defendant Nos. 1 and 3 herein were not impleaded as party
defendants to the said suits.
14. It is pertinent to note that the defence that there was no
privity of contract between the plaintiff and defendant No. 2
6-SJ-3-20+.DOC
did not see the light of the day till the affidavit-in-reply came
to be filed on behalf of the defendant No.2. Conversely, as is
evident from the undisputed facts noted above, the tender
was floated by the defendant No.2, the work orders were
issued by defendant No.2 and the agreement incorporating
terms and conditions of the contract was also executed by
defendant No. 2. The agreement between the plaintiff and
defendant No. 2 does not give an indication that the
defendant No. 2 was merely an executing agency. On the
contrary, from the perusal of the documents on record an
inference becomes sustainable that contract was executed by
the defendant No.2 in its own rights and authority.
15. For the foregoing reasons, I am afraid to accede to the
submission on behalf of the defendant No. 2 that it had
merely named an agency to act for the principal in the
business of agency and thus the plaintiff became an agent of
the principal. The jural relationship between the plaintiff
and defendants, especially, defendant no.2, does not seem to
be governed by the provisions contained in Sections 194 and
195, extracted above.
6-SJ-3-20+.DOC
16. The submission on behalf of the defendant Nos.1 and 3
that there was not privity of contract between the defendant
Nos.1 and 3 and the plaintiff is equally fallacious. As
indicated above, the defendant No. 2 after carrying out the
exercise of tendering the work had submitted the proposal to
award the contract to the agencies selected by it, to the
defendant no.3. Vide communication dated 16th February,
2017 (Exhibit-B), the defendant No.3 approved the said
proposal indicating the distinct projects to be entrusted to
different agencies and total costs of the works. Indisputably,
the work was executed by the plaintiff at the premises of
defendant No.3. In the circumstances, the claim of the
defendant Nos.1 and 3 that it had no concern with the
contract executed by defendant No. 2 with the plaintiff
cannot be said be a bona fide defence. What accentuates the
situation is the fact that the defendant Nos. 2 and 3 both
appear to be, in a sense, agencies of the State. Yet the
defendant Nos. 2 and 3 endeavoured hard to shift the onus
on each other.
6-SJ-3-20+.DOC
17. This take me to the second plank of the defence of
deficiency in the work executed by the plaintiff. It would be
contextually relevant to note that the defendant No. 2 does
not profess to contend that the work executed by the plaintiff
was either unsatisfactory or of inferior quality. In contrast
the defendant asserts that the work carried out by the
plaintiff was satisfactory and the Project Management
Consultant appointed by defendant No.3 had also certified
the said fact. Even IIT, Mumbai, the third party auditor, had
also found the work satisfactory.
18. Evidently, a cleavage emerges in the defences of
defendant Nos. 2 and 3. The aforesaid stand of defendant
No.2 that the work carried out by the plaintiff was in
conformity with the work order and terms of the contract
detracts materially form the endeavor of the defendant No.3
to seek leave to defend on the ground that there were
deficiencies in the work executed by the plaintiff.
19. Nonetheless, I am inclined to briefly appraise the worth
of the said defence sought to be urged on behalf of the
defendant No.3. First and foremost, the said defence did not
6-SJ-3-20+.DOC
see the light of the day till the affidavit-in-reply came to be
filed. Secondly, it is imperative to note that the M/s Conspro
Management Services, the Project Management Consultant
appointed by defendant No.3 had certified vide letter dated
23rd October, 2018, that the entire work was completed as per
scope of tender and the requirement of the client. The said
certificate reads as under.-
"It is certified that the work of above captioned work is satisfactorily (100%) completed. All test report are satisfactory and are in order the same have been already submitted to you. Additionally the quality of work and specification of work are found satisfactory. As the Tender conditions a third party audit for the quality was also carried out through IIT Mumbai and the report of satisfactory completion is also available with you.
We request to you please issue Work Completion Certificate to the contractor for the work "Structural Repairs and allied civil works of SDF 1 to 4 Buildings." Physically work has been completed as per scope & requirement of client in all aspects & full financially payment is balance as you well aware."
20. Satisfactory completion of the work has been certified
by the Project Management Consultant appointed by
defendant No.3 in clear and unambiguous terms. Moreover,
the Project Management Consultant has also adverted to the
fact that in accordance with the conditions of the contract,
IIT Mumbai, the third party auditor, carried out the audit
and found the work satisfactory.
6-SJ-3-20+.DOC
21. Mr. Bhate, the learned Counsel for the defendant Nos. 1
and 3 attempted to wriggle out of the situation by canvassing
a submission that the report of IIT Mumbai, the third party
auditor, points out defects in the work executed by the
plaintiff.
22. As the defendant Nos. 1 and 3 endeavored to cling to
the report of IIT Mumbai, to bolster up the defence of
deficiency in service it may be expedient to extract relevant
part of the concluding remarks and recommendations of IIT
Mumbai. They read as under.-
"1. The structural as well as non-structural repair work executed by the Agencies is found to be satisfactory, in general.
2. Comparing to the damage in the buildings, exhaustive structural and non- structural repairs of the buildings had been carried out by the agency.
3. The structural and non-structural repair works in the buildings had also been carried out at the places which were appearing to be good at the time of initial audit & inspection and were not considered in the initial estimate.
4. It is strongly recommended to execute Plaster work on top priority of the treated structural Elements, as keeping the treated Structural Elements open to atmosphere will result in failure of the treatment.
5. In order to enhance the life of the building, it is further strongly recommended to take up the balance Structural repair work of External and Internal faces of all buildings on top priority without further loss of time by using micro concrete, Epoxy Grouting, new reinforcement if required, shear keys and E-Glass fibre wrapping of 900 gsm, where loss of cover concrete is more than 25 mm and for loss of cover concrete up to 25 mm, the Structure shall be Repaired by using Polymer modified mortar and also execute the Plaster work on top priority of the treated surface, as keeping the treated surface open to atmosphere will result in failure of the treatment."
23. On a plain reading of the aforesaid remarks, I am
afraid, the defendant Nos. 1 and 3 can draw any support and
6-SJ-3-20+.DOC
sustenance from the aforesaid remarks to buttress the
defence that the third party auditor reported that there were
deficiencies in the work executed by the plaintiff. Clause 1
and 2, extracted above, unequivocally certify that the work
executed by the agencies was found to be satisfactory and
exhaustive structural and non-structural repairs of the
building had been carried out by the agencies. Clause 4
undoubtedly refers to the necessity to execute Plaster work,
on top priority. Clause 5 is of recommendatory nature.
However, it would be impermissible to read the aforesaid
remarks in such a fashion as to infer that the work executed
by the plaintiff was not found to be satisfactory.
24. Both the defences sought to be raised on behalf of the
defendants, in the circumstances of the case, can not be said
to be either a positive or a fair and reasonable defence. It
seems that the real reason for non payment of the bills raised
by the plaintiff was the inter se dispute between the
defendant Nos. 2 and 3, over the very appointment of the
defendant No. 2 as the Project Management Consultant. An
issue seems to have arisen regarding the validity of the
6-SJ-3-20+.DOC
appointment of defendant No.2, purportedly on account of
breach of GFR rules, and the said matter is being examined
from vigilance angle. This dispute is wholly irrelevant for the
determination of the controversy at hand, especially in the
context of the fact that the plaintiff had executed the entire
work under the terms of the contract and it has been duly
certified to be satisfactory by the Project Management
Consultant as well as third party auditor.
25. The conspectus of aforesaid discussion is that none of
defences sought to be raised by the defendants is of such
nature as to warrant an unconditional leave to defend the
suit. The claim of the plaintiff comprises outstanding amount
of the bills and interest thereon. It is pertinent to note that
there is no clause in the contract for payment of interest in
the event of delay in payment of the amount R.A. bills. The
rate at which the defendants are liable to pay interest would
thus be a matter for adjudication. Hence, it would be
appropriate to grant leave to the defendants to defend the
suit on the condition of deposit of the principal outstanding
amount.
6-SJ-3-20+.DOC
26. Hence, the following order.
ORDER
(i) Leave is granted to the defendant Nos. 1 to 3 to defend
the suit subject to the defendants depositing in this
Court a sum of Rs.9,92,23,670.65/-(Nine Crores
Ninety Two Lakhs Twenty Three Thousand Six
Hundred and Seventy and Sixty Five paisa only-)
within a period of eight weeks from today.
(ii) If the aforesaid deposit is made within the stipulated
period, this suit shall be transferred to the list of
Commercial Causes and the defendants shall file their
written statement within a period of 30 days from the
date of deposit;
(iii) If this conditional order of deposit is not complied with
within the stipulated period as mentioned earlier, the
plaintiff shall be entitled to apply for an ex parte
decree against the defendants after obtaining a non-
deposit certificate from the Prothonotary and Senior
Master of this Court.
The summons for judgment stands accordingly
disposed of.
[N. J. JAMADAR, J.]
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!