Citation : 2021 Latest Caselaw 13804 Bom
Judgement Date : 24 September, 2021
WP-4801-2012 judg.odt
(1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO.4801 OF 2012
Anil S/o Shrikishan Agrawal,
Aged: 49 years, Occ: Business,
& Proprietor of M/s. Sudarshan
Solvent Industries,
C/o Radhe-Radhe Jewellers,
Bhusar Line, Latur,
Tq. &b Dist. Latur. ...Petitioner
Versus
1. The State of Maharashtra,
Through its Secretary,
Ministry of Industries,
Maharashtra State, Mantralaya,
Mumbai-32.
2. Maharashtra Industrial
Development Corporation,
(Govt. of Maharashtra Undertaking),
Through Regional Ofcer,
Maharashtra Industrial
Development Corporation,
Nanded. ...Respondents
...
Mr. Patil N.P. Jamalpurkar, Advocate for the Petitioner. Mr. S.G. Sangle, AGP for the Respondent No.1/State. Mr. S.S. Dande, Advocate for Respondent No.2.
...
CORAM : RAVINDRA V. GHUGE & S.G. MEHARE, J.J.
RESERVED ON : 06th SEPTEMBER, 2021
PRONOUNCED ON : 24th SEPTEMBER, 2021
JUDGMENT (PER S.G. MEHARE, J.) :-
1. The petitioner has impugned the communication of respondent
no.2 dated 10.05.2012 cancelling the allotment of the plot situated in
WP-4801-2012 judg.odt
MIDC Kalamnuri.
2. The facts giving rise to this petition are that plot no. 17-A
measuring 12344 square meters was allotted to the petitioner by letter
of allotment dated 03.02.2003. The petitioner executed a registered
agreement with the Regional Ofcer MIDC on 28.02.2003. The plot was
delivered in possession of the petitioner on 17.03.2003. The petitioner
had to construct the industry on the allotted plot within seven years from
the date of the agreement. Besides, according to the agreement terms,
he was to fence the plot, plant the trees and pay service charges
determined by the respondent.
3. The petitioner failed to comply with the terms of the agreement in
the given time. Hence a show cause dated 14.07.2010 was served on
him. The petitioner placed his reply dated 03.08.2010 and explained
that the water arrangement could not be made. Due to the defcit rainfall
for the last three years and the global economic crisis, he could not raise
the construction on the plot. Lastly, the petitioner requested the
extension of one year for obtaining the Building Commencement
Certifcate.
4. In response to his letter, respondent no.2, by its letter dated
19.11.2010, called upon the petitioner to submit the copy of the bank
loan application, copy of fre NOC proposal, and the copy of the building
map. By letter dated 1.12.2010, the petitioner submitted the copy of
loan proposal and fre NOC. He contended in the said letter that he tried
WP-4801-2012 judg.odt
to pay service charges of Rs. 52,664 at Parbhani Ofce, but that was
not accepted. By letter dated 01.12.2010, the petitioner objected to the
demand of Rs.01,02,455/- towards the service charges. By letter dated
11.01.2011, respondent no.2 informed the petitioner that he should clear
the arrears of service charges frst so he may take appropriate decision
on his request to extend the time to construct the factory. By letter dated
29.03.2011, it was informed to the petitioner that the service charges
were imposed after sanctioning the maps. Lastly, respondent no.2, by
impugned decision, cancelled allotment of his plot.
5. The petitioner challenged the impugned order mainly on the
ground that the petitioner could not construct the factory since the
respondent did not provide the water facility. The drastic action
cancelling the allotment of the plot was unwarranted when the dispute of
assessing the service charges was pending. The necessary facilities
were not available in the Kalamnuri Industrial Area. Therefore, the plot
holders could not construct the factory buildings. The water facility and
other amenities were lacking. No action was taken against similarly
situated plot holders, but the respondent took drastic action against him
only. Before issuing the impugned order, no hearing was given to him.
No show cause notice was served on him. Such conduct of respondent
no.2 violates the principles of natural justice and Article 14 of the
Constitution of India. The rules and guidelines for assessing the service
charges were never supplied to him. He went to deposit the amount of
Rs.52,664/-, but the Ofcer of the respondent has not accepted the
WP-4801-2012 judg.odt
money. He was not at fault for not paying the service charges. He was
willing to comply with all the conditions relating to the construction of the
factory building within two years, subject to the condition that the
respondent shall provide all basic amenities i.e., water supply,
road/street, lights, etc. The impugned order is arbitrary, illegal against
the principle of natural justice. Hence liable to be quashed and set
aside.
6. The contesting respondent no.2 fled his afdavit in reply. He did
not dispute the correspondence between them. However, he opposed
the petition contending that the petitioner has no legal right to insist the
respondent to extend the time to complete the construction and obtain a
Building Completion Certifcate. The petitioner was granted a
reasonable opportunity to construct the factory on the plot in question.
Though the building plans were approved, the petitioner did not build a
factory for about nine years. The inaction of the petitioner shows his
interest in not developing the plot in question. The petitioner has no
vested right for extension of time as prayed by him. The petitioner is a
mere licensee of the corporation, and the respondent has the power to
terminate the said agreement and restore the land allotted. The petition
is not liable to be entertained as it involves disputed questions of fact
and the dispute arising out of the agreement executed between the
parties. The petitioner has a statutory and efcacious remedy for the
dispute raised in this petition, and without availing the same, the present
petition is bad in law. The terms and conditions of the agreement bind
WP-4801-2012 judg.odt
the petitioner. The construction ought to have been completed within
seven years of delivering the possession of the plot in question. The
petition is on fimsy grounds. The petitioner took around three acres of
land without paying a single pie towards the service charges to the
respondent. From time to time, the correspondence was made, and the
facts were brought to the notice of the petitioner, but he did not take any
appropriate steps to follow the terms of the agreement. The time to
construct the building was reduced to four years from seven years,
which was also brought to his notice. The letters were sent from time to
time to the petitioner, seeking explanation. The petitioner has no
substantial grounds to seek extension.
7. To show the conduct of the petitioner, respondent no.2 has fled
an additional reply dated 31.08.2021 contending that the petitioner has
got various plots in MIDC at Latur, and instead of constructing the
factories or units, he has used the said plots for residential purposes.
By these facts, respondent no.2 tried to show that the petitioner had no
intention to develop the plot in question. To support such contentions,
he fled few photographs on record. He prayed to dismiss the petition.
8. Heard learned counsel Shri Patil for the petitioner at length and
learned counsel Shri Dande for respondent no.2 and learned AGP Shri
Sangle for respondent no.1-State.
9. Shri Patil, the learned counsel for the petitioner would argue that
the impugned order is arbitrary and against the principles of natural
WP-4801-2012 judg.odt
justice. He stressed his argument that neither many plots are developed
nor the factories are constructed in the Kalamnuri Mini Industrial Area.
However, the respondent deliberately chose the petitioner only and
made him a scapegoat. The required amenities like light, water, and the
road are still not available in the MIDC. The respondent failed to
discharge its duties to make such facilities and amenities available. The
respondent has no explanation how abruptly the service charges were
made double against the earlier demand of Rs.52,664/-.
10. He has further vehemently argued that the representation made
by the petitioner has not been considered in true perspective. The
overall conduct of the respondent reveals that it had made a mind to
evict the petitioner anyhow from the plot in question. The use of plots in
Latur MIDC is not the question before this Court in this petition; hence
the allegations of change of use of those plots have no relevance. He
would also argue that the petitioner was and even today ready and
willing to construct the factory on the plot in question, but he couldn't
comply with the terms of agreement for want of facilities. He would also
argue that the petitioner is ever ready to raise the unit/factory on the
plot, provided the respondent shall make all the amenities available. He
tried to make out a case that it is the respondent whose inaction to
develop the MIDC and provide necessary amenities and facilities cause
the failure of the construction of the factory not only by him but by many
other industrialists. Stressing his argument on not following the
principles of natural justice, he would pray to quash the impugned order.
WP-4801-2012 judg.odt
11. Per contra, Shri Dande, the learned counsel for respondent
no.2, taking the Court through the record and various correspondence
and communications between the petitioner and respondent no.2
pointed out, that the overall conduct of the petitioner is not bonafde.
Referring to clauses of the agreement, he would further argue that there
were specifc conditions in the agreement that the plot holder has to
construct the factory anyhow within seven years from the date of
possession. Admittedly, the petitioner has raised no construction as
such. The petitioner obtained the sanction for the construction of the
factory and went silent till the service of notice dated 14.07.2010. He
would further argue that the extension of time for completing the
construction of factory building is the discretion of the respondent. No
one can claim an extension of time as a matter of right. Referring to the
various notices and the reply given by the petitioner, he would point out
that the overall conduct of the petitioner is explicit that he never intended
to comply with the terms and conditions of the agreement and utterly
failed to use the plot in question for the purpose for which it was allotted.
He vehemently denied the allegations of no facilities as argued by the
petitioner's counsel in the MIDC area. He would say that till 2010, the
petitioner never whispered or complained about the non-availability of
the alleged facilities and amenities. On the contrary, all the necessary
facilities were available. The intention of the petitioner is clear from his
conduct that he was not interested in developing the industrial unit.
Hence, no extension as prayed can be permitted.
WP-4801-2012 judg.odt
12. He relies upon catena of judgments against the petitioner, which
held that violation of the terms of the agreement would not allow
extending the time. He relied on the following cases:
1. Dalip Singh and Ors Vs. State of Haryana and Ors, MANU/SC/
1210/2018.
2. Phatu Rochiram Mulchandani Vs. Karnataka Industrial Areas
Development Board and Ors, MANU/SC/0214/2014.
3. National Project Construction Corporation Ltd Vs. State of
Maharashtra, 2015 (1) Bom C.R. 22.
4. Ashok Sursingh Bhimani and Another Vs. The State of
Maharashtra and Others in Writ Petition No.8248 of 2017 dated
19/07/2017.
5. Surajagrah Steel & Mines Pvt. Ltd., Gadhchiroli Vs. The Chief
Executive Engineer, Maharashtra Industrial Development Corporation,
and another in Writ Petition No.4354 of 2012 dated 13.03.2013.
6. Abhay S/o Jayantilal Shah Vs. The State of Maharashtra and
others in Writ Petition No.5213 of 2013 dated 25.02.2016.
7. Sau. Chandrakala w/o. Suresh Mugdiya (Jain) Vs. Maharashtra
Industrial Development Corporation and others in Writ Petition No.8295
of 2006 dated 21.04.2009.
8. Orissa Industrial Infrastructure Development Corporation Vs.
MESCO Kalinga Steel Ltd and Ors, (2017) 5 SCC 86.
9. Sethi Auto Service Station and Ors Vs. Delhi Development
Authority and ors, AIR 2009 SC 904.
WP-4801-2012 judg.odt
13. The law is settled, that the parties are bound by the
terms of an agreement or the contract. The parties to the agreement
reciprocally bind each other according to the terms and conditions of the
agreement/contract.
14. The agreement dated 28.02.2003 is an agreement for seven
years. The petitioner had the license only to enter the piece of land for
building and executing work thereon. Respondent no.2, by the
impugned communication dated 10.05.2012, cancelled the letter of
allotment of plot no. 17-A which was issued in favour of the petitioner for
the following reasons that the petitioner;
i) had neither paid the annual rent nor fenced the plot.
ii) has made no development activities as per the sanctioned
map,
iii) has not constructed the factory within seven years as per
clause 3(c) of the agreement,
iv) the plot is lying unused,
v) he had not planted the trees.
vi) no service charges as contemplated in clause 3 (g) were paid,
vii) he did not submit a bank loan sanction order.
15. As per Clause 3(a) of the agreement dated 28.02.2003, the
petitioner was bound to submit the specifcation, plan elevations,
sections of the factory building to the Ofcer appointed by respondent
no.2 for approval within 84 months from the date of the agreement.
WP-4801-2012 judg.odt
Respondent no.2 has complete control over such maps, elevation, and
plans. For the said compliance, the Licensee may be called upon by the
authority appointed by respondent no.2. As per Clause (b), the plot
holder was bound to fence the plot granted to him at his or her expense.
Clause (c) speaks of the work that shall not begin until the plans are
approved. Until no objection certifcate is obtained from the
Maharashtra Pollution Control Board, no building work shall be
commenced following the building regulations. Clause 3(d), which is
most relevant to the issue involved in this case, is reproduced
hereunder;
"(d)That he shall within a period of seven years from the date of this agreement hereto commence, and within a period of seven years from the said date at his own expenses and in a substantial and workmanlike manner and with new and sound material and in compliance with all Municipal rules, bye-laws and regulations applicable thereto and in strict accordance with the plans, elevations, details and specifcations to the satisfaction of the Executive Engineer and conformably to the building lines marked on the plan hereto annexed and the building Regulations, set out in the Second Schedule hereunder written, build and completely fnish ft for occupation a building to be used as an industrial factory with all requisite drains and other proper conveniences thereto."
16. Clause (d) imposes responsibility on the plot holder to plant the
trees in the open space. Clause (g) speaks of the service charges and
other charges to be paid by the plot holder as may be prescribed by the
State Government under MIDC Act, 1961 in respect of amenities or
common facilities provided by the grantor.
WP-4801-2012 judg.odt
17. Clause 5(b) of the agreement empower the respondent to
resume the land allotted to the holder of the plot on the failure of the plot
holder to make construction on the plot within seven years from the date
of the agreement, the plot holder defaults to pay the service charges or
fails to observe the terms of the agreement. Upon resuming the land, the
agreement shall cease and terminate.
18. The above conditions mandate the plot holder to construct the
industrial factory anyhow within seven years from the date of the
agreement. Considering the date of the agreement, it was incumbent
upon the petitioner to build the factory unit on or before 27.02.2010.
Since the petitioner raised no construction on the plot, the respondent
issued him the frst notice dated 14.07.2010, calling upon him why the
action shall not be taken against him for breach of the terms of the
agreement. The petitioner, by way of reply dated 03.08.2010 submitted
the explanation as discussed above.
19. In addition to the above, Clause (6) of the agreement empowers
the respondent to extend the period for completion of the factory
building and the necessary work for the said period mentioned in clause
3(d), if it is satisfed that the building and works could not be completed
within the prescribed time for reasons beyond the control of the licensee.
20. The petitioner accepted, particularly vide Clause 3(d), the
responsibility to commence the construction of the factory building
within seven years from the date of the agreement. The petitioner also
WP-4801-2012 judg.odt
knew, by letter dated 16.11.2007, that the period of seven years was
reduced to four years. He never challenged such reduction of tenure. It
is not in dispute that till the frst show-cause notice dated 14.07.2010, no
action was taken to cancel the allotment of the plot after four years from
the date of the agreement. The respondents waited for seven years and
then initiated the action. The burden is on the petitioner to prove that
there were reasons for not raising the constructions within a given time.
Firstly he complained that the respondent did not make water facility
and infrastructure available, to any plot holder. He further explained that
there was defcit rainfall for the last three years and global economic
crisis. He has nothing to show that he ever complained of the lack of
water and infrastructural facilities. He tried to convince us that shortage
of rain for the last three years and a global economic crisis are the
reasons for not raising construction, and it was a situation beyond his
control. To believe his defence he placed no material that shortage of
rain and global economic crisis had a bearing on his project. He also
has no case; that for these reasons, the bank refused him the loan. He
never made any representation to respondent no.2 that he is facing
difculties as mentioned above in raising the construction until the show
cause notice dated 14.07.2010 was served on him. Indisputably, the
petitioner is in arrears of the service charges. He has a defense that he
went to pay the arrears, but the Ofcer refused. Had he intended to pay
the arrears, he could have paid by cheque or demand draft. On the
other hand, he went on disputing with the respondent about how the
charges were assessed. He could have paid the arrears under protest.
WP-4801-2012 judg.odt
That could throw light on his bonafde. Having regard to the
circumstances, we do not fnd substance in the arguments of the
petitioner that the situation was beyond his control which restrained him
from raising the construction of the factory within agreed time.
21. It is also the argument of the learned counsel for the petitioner
that the respondent was biased against the petitioner and took a drastic
step to evict him when numerous plot holders had not completed the
construction in the same MIDC area.
22. A person alleging bias against the authority has to place the
material or circumstances to believe the defense of bias. Bias is
inclination or prejudice for or against one person or group, especially in
a way considered unfair. It is a personal or sometimes unreasonable
judgment. The person alleging bias, shall prove instances of prejudice.
The petitioner has not placed a single example against respondent no.2
that he acted against his interest; he favoured others or did the acts with
malafde intention to evict the petitioner from the allotted plot. On the
contrary, no immediate action was taken within four years from the date
of agreement when the petitioner had not constructed the factory.
Respondent no.2 vide letter dated 11.01.2011, positively requested the
petitioner to clear the arrears frst so the appropriate decision may be
taken on his request to grant the extension. In the absence of material
that prejudiced respondent no.2 against the petitioner, the bare
allegations of bias have no meaning.
WP-4801-2012 judg.odt
23. The learned counsel Shri Dande for respondent by fling
additional reply, would argue that the plots in MIDC Latur were allotted
to the petitioner for construction of the factory, but instead of
constructing the factories, he constructed residential houses on those
plots. That shows his conduct that he never intended to use the land for
the purpose for which those were allotted. We are not impressed by his
arguments for the reasons that no issue of its change of user is before
us, and no material is placed in this case for what purpose those plots
were allotted to him. We are unaware what restrained respondent no.2
or the concerned Ofcer from taking action for the breach of agreement,
if any.
24. The learned counsel Shri Dande would argue that the plot
allotted under an agreement was subject to the terms and conditions
therein. Therefore, it could not be kept idle for stalling and stultifying
industrial growth of the area. To bolster his argument, he relied on the
case of National Project Construction Corporation Ltd (Supra). He
would also rely on the case of Ashok Sursingh Bhimani (Supra) and
argue that the properties of MIDC are public. Therefore in violation of
the terms of the agreement, the public property cannot be retained by
private persons. He also relied on the case of Abhay S/o Jayantilal
Shah (Supra), and argued that just applying for construction permission
would not mean taking the steps for the development of the property in
its real sense. In this case, the facts are that the petitioner has obtained
only the plan sanctioned from the concerned authority of the respondent.
WP-4801-2012 judg.odt
The above case law come to the aid of the learned counsel Shri Dande.
25. The facts and material placed on record indicates that the
petitioner breached the agreement terms. There were no circumstances
beyond the control of the petitioner that restrained him from constructing
the factory within the agreed time. Therefore nothing is there to believe
that the action cancelling the allotment of plot for the given reason is
arbitrary, perverse, and against the principle of natural justice.
26. In the light of the above, we do not fnd that judicial indulgence
is necessary in this case. Accordingly, the petition is devoid of merit;
hence dismissed. Thus, the interim orders stand vacated.
27. The learned counsel for the petitioner prayed to extend
the interim relief for eight weeks.
28. We have discussed the issues at length. The plot in
question is vacant and unused since 2003. It is a plot to be
commercially used. The MIDC is getting no revenue since then. The
petition was pending for about nine years. It would be improper to put
the MIDC at further loss. Hence, we reject the prayer.
(S.G. MEHARE, J.) (RAVINDRA V. GHUGE, J.) Mujaheed//
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!