Citation : 2021 Latest Caselaw 13019 Bom
Judgement Date : 13 September, 2021
Trupti wp-2076-2021.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 2076 OF 2021
Sai Agencies )
Through its Sole Proprietor Kiran Jagtap )
Its office at : )
Sangram Nagar, Behind Police Complex )
Jalna- 431 203 ) ...Petitioner
Versus
1. The State of Maharashtra )
Mantralaya, Mumbai )
2. Pimpri Chinchwad Municipal )
Corporation, through )
Municipal Commissioner, )
Mumbai - Pune Road, )
Pimpri - 411 018 )
And )
Yashwantrao Chavan Rose Garden )
Nehru Nagar, Bhosari - 411 026 )
3. Guruji Infrastructure Private Limited )
33, Suraj Plaza, Chandulwadi )
Opp. Dena Bank, Bhayander (W) )
Thane - 401 101 )
4. Ajit Swayam Rozgar Seva Sahakari)
Sanstha Maryadit )
Opp. Podar School, )
Kakde Park Chowk )
Chinchwad, Pune - 411 033 ) ...Respondents
.......
1
Trupti wp-2076-2021.doc
Mr. Shriram Kulkarni i/b. Mr. Pranjal Khatavkar for the Petitioner.
Mrs. R.M. Shinde, AGP for the Respondent -State.
Mr. G.H. Keluskar for Respondent No.2.
Mr. Ashok Dhanuka a/w. Mr.Ashish Jain and Ms. Vidhi Karia for
Respondent Nos. 3 and 4.
.......
CORAM : A.A.SAYED & S.G.DIGE, JJ.
RESERVED ON : 18th AUGUST, 2021.
PRONOUNCED ON : 13th SEPTEMBER,2021.
JUDGMENT : (PER : S.G.DIGE, J.)
1. The Petitioner, a sole proprietorship firm, is essentially
objecting to rejection of its tender at technical bid level and
allotment of tenders to the Respondent No. 3 -Guruji
Infrastructure Private Limited and Respondent No. 4- Ajit Swayam
Rozgar Seva Sahakari Sanstha Maryadit by Respondent No.2 as
successful bidders.
2. The present Petition relates to the Tender floated by
Respondent No.2- Pimpri Chinchwad Municipal Corporation (for
short, "Respondent No.2") in August, 2019 for maintenance and
protection of the gardens (for short, "the said Tender") situated
within the jurisdiction of the Respondent No.2.
Trupti wp-2076-2021.doc
3. Accordingly, the Petitioner submitted its technical bid
as well as financial bid along with all requisite documents for
garden works of Serial Nos. 10 to 14 of said Tender. Out of these
works, the Petitioner is objecting to allotment of work of two
gardens to Respondent Nos. 3 and 4. The Petitioner is also
challenging the validity of tender condition No. 3 of said Tender.
During pendency of this Petition, the Petitioner has amended the
Petition and sought some additional reliefs.
4. The scope of judicial review in the tender matters have
been considered by the Hon'ble Apex Court in the matter of Tata
Cellular v. Union of India1. It is held that judicial review of
Government contracts was permissible in order to prevent
arbitrariness or favoritism. In paragraph Nos. 77 and 94 of the
said judgment, the Apex Court has observed as under ;
"77. The duty of the court is to confine itself to the question of legality. Its concern should be :
1 (1994) 6 SCC 651 Trupti wp-2076-2021.doc
1. Whether a decision-making authority exceeded its powers?
2. Committed an error of law,
3. committed a breach of the rules of natural justice,
4. reached a decision which no reasonable tribunal would have reached or,
5. abused its powers.
Therefore, it is not for the court to determine whether a particular policy or particular decision taken in the fulfillment of that policy is fair. It is only concerned with the manner in which those decisions have been taken. The extent of the duty to act fairly will vary from case to case. Shortly put, the grounds upon which an administrative action is subject to control by judicial review can be classified as under:
(i) Illegality : This means the decision- maker must understand correctly the law that regulates his decision-making power and must give effect to it.
(ii)Irrationality, namely, Wednesbury unreasonableness.
(iii) Procedural impropriety.
The above are only the broad grounds but it does not rule out addition of further grounds in course of time. As a matter of fact, in R.V. Secretary of State for the Home Department, ex Brind, Lord Diplock refers specifically to one development, namely, the possible recognition of the principle of
Trupti wp-2076-2021.doc
proportionality. In all these cases the test to be adopted is that the court should, "consider whether something has gone wrong of a nature and degree which requires its intervention".
"94. The principles deducible from the above are (1) The modem trend points to judicial restraint in administrative action.
(2) The court does not sit as a court of appeal but merely reviews the manner in which the decision was made.
(3) The court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which itself may be fallible.
(4) The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract. Normally speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than not, such decisions are made qualitatively by experts.
(5) The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of Wednesbury principle of
Trupti wp-2076-2021.doc
reasonableness (including its other facts pointed out above) but must be free from arbitrariness not affected by bias or actuated by mala fides.
(6) Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure".
5. In Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn.
Ltd.2, it was held that a mere disagreement with the decision making
process or the decision of the administrative authority is no reason for
a constitutional Court to interfere. The threshold of mala fides,
intention to favour someone or arbitrariness, irrationality or perversity
must be met before the constitutional Court interferes with the decision
making process or the decision. The owner or the employer of a
project, having authored the tender documents, is the best person to
understand and appreciate its requirements and interpret its
documents. It is possible that the owner or employer of a project may
give an interpretation to the tender documents that is not acceptable to
the constitutional Courts but that by itself is not a reason for interfering
with the interpretation given.
2 (2016) 16 SCC 818, Trupti wp-2076-2021.doc
6. In ACC India Private Limited & Ors. V/s. State of
Maharashtra & Ors.3, the Division Bench of this Court has held that the
Court must be satisfied that there is some public interest involved in
entertaining such Petition and if the dispute is purely between the two
tenderers, the Court must be very careful to see if there is an element
of public interest involved in the litigation.
7. The principles emanating from the above judgments are
that the Courts shall not ordinarily test the opinion of the experts
unless their decision is totally arbitrary or unreasonable. The Courts
will only interfere to prevent arbitrariness, irrationality, bias, mala fides
or perversity. Considering these principles, we proceed to examine
matter at hand.
8. In the said tender, one of the condition was with
respect to the submission of the experience certificate from any
Government, Semi-Government authorities, having experience in
the work relating to garden, road dividers, tree plantation and
conservation. The contractor should have completed at least one
3WRIT PETITION (L) NO. 2321 OF 2018 DATED 30 JULY 2018
Trupti wp-2076-2021.doc
work in last five years having 30% of the Tender value.
Accordingly, the Petitioner while submitting the bid, also
submitted all documents including the experience certificate
issued by the Maharashtra Agro Industries Development
Corporation Limited (for short, " the MAIDCL"). According to the
Petitioner, the Respondent No.2 again demanded the experience
certificate, although one experience certificate was already
submitted by the Petitioner. In order to comply with the
requisition, the Petitioner again submitted the experience
certificate dated 8th November, 2019 issued by the MAIDCL that
the Petitioner has successfully completed the work with respect to
the garden maintenance etc., of amount of Rs. 2,95,29,911/-
(Rupees Two Crores Ninety Five Lakhs Twenty Nine Thousand
Nine Hundred and Eleven only).
9. The Respondent No.2 thereafter addressed a letter
dated 22nd November, 2019 to the MAIDCL to confirm the
issuance of certificate by them. As per the request of the
Respondent No.2, MAIDCL confirmed about issuance of certificate
Trupti wp-2076-2021.doc
to the Petitioner vide its letter dated 16 th December, 2019. The
Respondent No.2 again sent letter dated 17 th December 2019 to
MAIDCL and requested to send work order and photocopy of the
bills within two days. It is stated that although the MAIDCL had
confirmed the work done by the Petitioner vide its certificates
dated 8th November, 2019 and 16th December, 2019 the
Respondent No.2 again asked the information about work,
however, the MAIDCL refused to give the work order and bills
being their internal documents.
10. It is contended that inspite of submitting the
experience certificate as contemplated in the terms and conditions
of the said Tender to Respondent No.2, the Petitioner was not held
eligible to participate in financial bid of Tender. The list of eligible
and ineligible bidders was published on 28th January, 2020. By
the letter dated 29th January, 2020, the Petitioner brought to the
notice of the Municipal Commissioner of Respondent No.2 the
alleged malafide action of the Respondent No.2 in the allotment of
work under the said Tender. However, neither any action is taken
Trupti wp-2076-2021.doc
by the Municipal Commissioner nor the letter was replied.
11. It is further contended that the entire procedure of
allotting the aforesaid Tender was bogus and carried out only in
order to support the few bidders i.e. Respondent Nos. 3 and 4.
There were complaints against these bidders. As per the Tender
condition, the bidder should have experience of completion of
atleast one work having 30% of the said Tender value in last five
years. The Respondent No.4 has submitted the certificate for the
duration of the year 2012 to 2018. As per condition No. 2 (a), the
bidder must have in last 5 years turnover of 75% of the Tender
value. The documents in order to satisfy the aforesaid condition
submitted by the Respondent No.4 shows that the same is not
75% of the Tender value. As far as the Respondent No.3 is
concerned, to satisfy the condition No.2, it has submitted the work
order issued by Mira-Bhayandar Municipal Corporation (for short,
"Mira-Bhayander Corporation') which shows that the work
undertaken was not a single work but it was done in different
wards of Mira-Bhayander Corporation.
Trupti wp-2076-2021.doc
12. It is further contended that the condition No. 12.3 of
the said Tender states that the bidder will have to submit the
performance guarantee in terms of the said condition. Both the
above bidders have failed to submit the same. However, the
Respondent No.2, inspite of the aforesaid lacuna, held the
Respondent Nos. 3 and 4 as eligible. Respondent No.2 opened the
technical bid on 28th January, 2020 without giving any
opportunity to cure such discrepancies/ doubts to the bidders in
whose documents there was discrepancy/ doubt. Respondent No.2
opened the financial bid on very same day within a period of two
hours. The aforesaid act of Respondent No.2 is contrary to the
Government Resolution dated 17th September, 2019 and CVC
Guidelines. The Respondent No.2 was under an obligation to open
the bids in front of the bidders, however, without calling any of
the bidder, the Respondent No.2 hurriedly opened the technical as
well as financial bid. It shows that the Respondent No.2 has not
followed the procedure laid down by law.
13. It is further contended that the condition No.3 of the
Trupti wp-2076-2021.doc
said Tender restricts the successful bidder from getting more than
one work with respect to the work mentioned at serial Nos. 1 to 9
in the said Tender, though the said Tender list is of 14 gardens for
which the bids were invited. However, with respect to the gardens
mentioned at serial Nos.1 to 9, one bidder was entitled to get only
one work out of the work mentioned at serial Nos. 1 to 9. The said
restriction is not only unreasonable, arbitrary but also contrary to
the Government Resolution dated 17th September, 2019. The
aforesaid conduct of Respondent No.2 is brought to the notice of
the Municipal Commissioner but he has neither cancelled the
Tender nor granted stay on the further procedure of allotment of
the said Tender. The act of Respondent No. 2 is arbitrary,
unreasonable, restrictive and violative to the provisions of Article
14 of the Constitution of India and also violative to the provisions
of Article 19 (1) (g).
14. An Affidavit in Reply has been filed by the Respondent
No.2. In Affidavit in Reply, the Respondent No.2 has contended
that the technical bid was opened on 27 th September, 2019 and
Trupti wp-2076-2021.doc
financial bid was opened on 28th January, 2020. After opening
technical bid, the Respondent No.2 scrutinized the documents of
the Petitioner and other bidders. Shortfall was found in the
documents of Respondent Nos. 3 and 4 as well as the Petitioner.
Accordingly, the Respondent No.2 had informed the concerned
bidders about the shortfall of documents and requested them to
comply with the same on or before 10 th November, 2019. In
response thereto, the Petitioner furnished experience certificate
dated 8th November, 2019. The Tender Committee examined the
said certificate dated 8th November, 2019 when they found that
there is a discrepancy in respect of amount in earlier certificates
dated 27th August, 2019 and 8th November, 2019. Therefore, by
letter dated 22nd November, 2019 forwarded both certificates for
verification to MAIDCL.
15. On 16th December, 2019, the MAIDCL submitted a
copy of the "opinion letter" on whatsapp of one of the members of
the Tender Committee. Plain reading of the said "Opinion letter"
Trupti wp-2076-2021.doc
shows that the contract of the Petitioner is "not completed" but it
is "ongoing" which was not as per Condition No.2 of said contract.
16. It is further contended that the Tender was published
in August, 2019 and Petitioner's experience shown in the said
"Opinion letter" was from November, 2018 to October, 2019 which
was not as per Tender condition. The MAIDCL has not given reply
to the Respondent No.2's letter dated 17th December, 2019 in
respect of the experience certificate of the Petitioner hence
Petitioner was rightly held ineligible by the Tender Committee.
17. It is contended that Respondent No.4 submitted its
experience certificate and turnover for the period from 16th July,
2013 to 31st January, 2018. As per the certificate, the total period
of work is four years and 5.5 months and the yearly cost of the
work was Rs. 17,19,804/- (Rupees Seventeen Lakhs Nineteen
Thousand Eight Hundred Four only) which indicates monthly cost
of the work was Rs. 1,43,317/- (Rupees One Lakh Forty Three
Thousand Three Hundred Seventeen Only). Their experience was
Trupti wp-2076-2021.doc
counted from August 2014 to January 2018, total 42 months. So
the total work done was Rs. 60,19,314/- (Rupees Sixty Lakhs
Nineteen Thousand Three Hundred Fourteen only) (1,43,317 * 42
months). As per Tender condition No.2, the work experience
required was 30% of Tender cost i.e. Rs. 49,41,863/- (Rupees
Forty Nine Lakhs Forty One Thousand Eight Hundred Sixty Three
only). The work done amount fulfills the Tender condition.
18. It is further contended that the total Tender cost of
work in said tender was Rs.1,64,72,878/- (Rupees One Crore Sixty
Four Lakhs Seventy Two Thousand Eight Hundred Seventy Eight
only). The period for the said Tender was for two years, hence the
yearly cost was Rs. 82,36,439/-. As per Tender
condition No.2, the yearly turnover of the bidder must be 75% of
Tender cost. The turnover certificate of the Respondent No.4 was
duly signed by the Chartered Accountant. The amount fulfills the
Tender condition. As per the experience certificate submitted by
Respondent No.3, the work done in 2016-2017 was Rs. 3.12
Crores and in 2017-2018 it was Rs. 8.88 Crores. The amount
Trupti wp-2076-2021.doc
mentioned in certificate fulfills the Tender condition. As per
Tender condition No. 12, after opening an envelope No.2
(Financial Bid), the successful bidder must submit additional
performance security deposit in eight days to the Respondent
No.2. There was controversy in respect of tender condition Nos.
12 and 13 hence the Tender Committee decided to go with Tender
condition No. 12. For further Tender, this condition will be
included with proper correction with the consent of concerned
authority.
19. It is contended that the Respondent No.3 submitted
certificate for work undertaken by them with Mira Bhayandar
Corporation. This Respondent had enquired with Mira Bhayandar
Corporation about issuance of certificate, by letter dated 3 rd
December, 2019, the concerned authority informed Respondent
No.2 that the letter submitted by the Respondent No.3 is correct
and the same was issued by them.
Trupti wp-2076-2021.doc
20. It is further contended that the Government Resolution
dated 27th September, 2019 would not be applicable to present
case because said Tender was published on 5 th August, 2019. Due
to administrative reasons, the Respondent No.2 cancelled works
mentioned at Serial Nos. 1 to 9 of the said Tender.
21. In Affidavit in Reply, Respondent No.4 contended that
the Petitioner failed to qualify in the technical bid on the ground
of false certificate. Therefore, the Petitioner cannot seek any kind
of equitable reliefs. The Respondent Nos. 3 and 4 are held
qualified after complying all the formalities of bid and after
competing with various other eligible bidders.
22. It is contended that the Petitioner has suppressed
various facts from this Court including that the Tender process for
Garden Nos. 1 to 9 was cancelled by the Respondent No.2 and the
condition No.3 was only applicable to garden Nos. 1 to 9.
Therefore, the Petitioner has made an attempt to mislead this
Court.
Trupti wp-2076-2021.doc
23. It is further contended that as per Tender Conditions,
the Respondent No.4 submitted required certificates to
Respondent No.2, after opening of the technical and financial bids
and after competing with the other eligible bidders, the bid of
Respondent No.4 was declared as lowest quoted bid at the less
quoted percentage of -23.77% at Rs. 1,25,57,274.90 (Rupees One
Crore Twenty Five Lakhs Fifty Seven Thousand Two Hundred
Seventy Four and Ninety paise only) as compared to the other
bidders whose bids were at a higher price.
24. We have heard learned Counsel for the respective
parties.
25. Considering the facts and circumstances of the case,
two fold questions arise for our consideration :
(i) Whether the Petitioner had the requisite
experience certificate and that the allotment of bids to
Respondent Nos. 3 and 4 are not proper?
Trupti wp-2076-2021.doc
(ii) Whether Petitioner has suppressed material facts?
26. So far as first question is concerned, we have
considered the documentary material on record as well as
submissions of learned Counsels. According to Petitioner, its bid is
rejected at technical bid level without giving an opportunity to
submit a requisite experience certificate as per condition No.2 of
the said tender and though the certificates provided by Petitioner
are proper, they were not considered. Whereas Respondents state
that the Petitioner was not possessing requisite certificate as per
tender condition No. 2 hence Petitioner was not qualified for
financial bid. There were discrepancies in the experience
certificates submitted by Petitioner.
27. It would be appropriate, at this stage, to refer
condition No. 2 of the said Tender and qualification criteria
provided for it which reads as under :
"2) For the present work it is necessary to have experience of completing minimum one work of
Trupti wp-2076-2021.doc
30% amount of the Tender amount during last five years. It is necessary that during the said work contractor/ firm should have completed maintenance and protection works about gardens/ road divider/ tree plantation and tree conservation of Government Semi Government organization/ Civil Local bodies (excluding Grampanchayat and School). The independent works about the gardens/ road divider / tree cultivation and tree conservation protection and maintenance and renovation shall be considered valid.
A) The annual turnover during the last five years is required to be 75% of annual expenditure of the tender. It is necessary to submit certificate of Chartered Accountant.
B) It shall be compulsory for contractor/ firm to submit the certificate of Department head stating that the work giving complete details of work and expenditure of Government/ Semi Government/ Civil Local is completed satisfactorily.
C) It is necessary for the contractor/ firm to submit bid capacity certificate for tender filing of Chartered Accountant. The formula about the same is as
Trupti wp-2076-2021.doc
follows :
(A x N x 2) -B Where A= maximum turnover of last five years. N= Period of work awarded B= The cost of work in hand (during the work awarded)".
28. Perusal of condition No.2 of the said Tender shows
that the requirement is two-fold;
(1) Work Experience and
(2) Financial Capacity.
29. Thus, two certificates were required to be submitted to
the Respondent No.2, viz.
(1) Experience Certificate inter-alia to show
experience of at least one work of the amount equal
to amount of 30% of the present tender amount
being completed in the last five years.
(2) Turnover Certificate to show the financial
capacity of the bidder inter-alia by showing that the
Trupti wp-2076-2021.doc
annual turnover during the last five years shall be
75% of the annual tender cost of the tender.
30. Our attention was invited to the experience certificates
dated 27th August, 2019, 8th November, 2019 and 16th December,
2019 submitted by the Petitioner.
31. The experience certificate dated 27th August, 2019
shows that during period November, 2018 to July 2019 the
Petitioner had been supplying manpower and carrying out the
gardening work and house keeping work in the Head Office,
Mumbai of MAIDCL and in its 13 regional offices and nine
factories and amount of Rs. 3,85,18,634/- (Rupees Three Crores
Eighty Five Lakhs Eighteen Thousand Six Hundred Thirty Four
only) has been paid to Petitioner.
32. The experience certificate dated 8th November, 2019
shows that during the period November, 2018 to October, 2019,
the Petitioner had completed the gardening work in the Head
Trupti wp-2076-2021.doc
Office, Mumbai of MAIDCL and the amount of Rs. 2,95,29,911/-
(Rupees Two Crores Ninety Five Lakhs Twenty Nine Thousand
Nine Hundred Eleven only) has been paid to the Petitioner.
33. In response to letter dated 22nd November, 2019 sent
by Respondent No.2, MAIDCL sent "opinion letter" dated 16 th
December, 2019 and the said "opinion letter" shows that during
period November, 2018 to October 2019, the Petitioner's agency
has been supplying man power in the Head Office of MAIDCL and
in its 13 regional offices and nine factories and it included data
entry operator, assistant, assistant manager, peon, helper, driver
and Gardner, totaling 313 officers/ employees working on a
contract basis. It appears to us, on perusal of certificates dated 27th
August, 2019 and 8th November, 2019, that the work period of
certificate dated 27th August, 2019 shows November, 2018 to July
2019 and the work period of 8th November, 2019 certificate shows
November, 2018 to October 2019. It shows major discrepancy in
work period. The certificate dated 8th November, 2019 is not as
per Tender condition No.2 as Tender was published in August,
Trupti wp-2076-2021.doc
2019 whereas work period shows October, 2019, which is after
the tender period. Certificate dated 27th August, 2019 shows work
period from November, 2018 to July 2019, but the period was not
of a complete one year. Whereas "opinion letter" dated 16 th
December, 2019 shows work period November 2018 to October
2019, which is 'after' Tender period as well as this letter shows
that work is 'ongoing'. As per tender condition No.2, work should
be completed work.
34. There are discrepancies in the amount mentioned in
these certificates. Certificate dated 27th August, 2019 shows work
amount more than Rs. 3 Crores whereas 8 th November, 2019
certificate shows work amount more than Rs. 2 Crores. We do not
find merit in contention of learned Counsel for the Petitioner that
in certificate dated 27th August, 2019 the amount was in respect of
house keeping and gardening work, whereas in certificate dated
8th November, 2019 the amount was given in respect of only
gardening work. There is no mention of any amount in the
"opinion letter" dated 16th December, 2019 given by MAIDCL. Had
Trupti wp-2076-2021.doc
these amounts been given for different works, it would have been
mentioned in these certificates by mentioning separate works. So
it was not possible for Respondent No.2 to calculate 30% amount
of tender amount as there were different amounts mentioned in
two certificates whereas in "opinion letter" dated 16 th December
2019 no amount is mentioned. We are therefore of the view that
certificates submitted by Petitioner were not proper and were not
as per tender condition No.2 of said Tender. Hence, Petitioner was
rightly held ineligible for financial bid. The Government
Resolution dated 17th September, 2019 would not be applicable
retrospectively as tender was published in August, 2019.
35. In respect of the acceptance of bids of Respondent Nos.
3 and 4, we find that Respondent Nos. 3 and 4 are held eligible
after due scrutiny of documents and following proper procedure
by Evaluation Committee. As per Evaluation Committee Report,
the experience certificate and financial capacity certificates of
Respondent Nos. 3 and 4 are as per tender condition No.2. There
were other bidders who competed with Respondent Nos. 3 and 4.
Trupti wp-2076-2021.doc
Evaluation Committee was consisting of experts persons. When
such experts evaluates documents of participant bidders, the
Courts would be slow in interfering with the said decision unless it
is arbitrary or some favourism is pointed out. The view adopted
by experts should be given weightage. As has been held by the
Division Bench of this Court in the matter of Reliance Energy Ltd.
V/s. MSRDC Ltd. And Ors. 4 that, "....Suffice it to note that even on
interpretation of terms, there are divergent views. The treatment
to the Items is different at the hands of the officials and outside
Experts. Once the divergent views have been noted by the
Tendering Authority and it took the final decision after due
consideration of the same, we cannot substitute their views with
ours and thereafter alter their ultimate decision. That is not
permissible and would be beyond the parameters of judicial
review." The Respondent Nos.3 and 4 are held eligible after
proper scrutiny of documents by Evaluation Committee. The said
decision cannot be said to be manifestly incorrect or arbitrary or
malafide. In the circumstances, reconsideration of the decision of
4 (2007) 5 Mah. LJ 768
Trupti wp-2076-2021.doc
the Respondent Authority would tantamount to exercise the
Appellate powers by this Court and it may not be permissible. Hence,
we are of the view that the acceptance of bids of Respondent Nos. 3
and 4 are proper.
36. We may add that Petitioner had participated in tender
process of five garden works i.e. Sr. Nos. 10 to 14 of said tender but
Petitioner has challenged only tender process of two gardens, which
are allotted to Respondent Nos. 3 and 4. The Petitioner is held
ineligible in all five tender process on same ground i.e. not
possessing required experience certificate. As Petitioner is not
challenging other three tender processes, it indicates that Petitioner
is accepting that the Petitioner was not eligible for financial bids in
other three gardens tender process. When Petitioner claims right of
equity, Petitioner should have prayed to allow them in participation
of financial bids in all five tender process because in other three
tender process, the Petitioner is held ineligible on same ground.
Petitioner cannot differentiate challenge of tender process as per
their wish.
37. We do not find merit in contention of Petitioner that the
Trupti wp-2076-2021.doc
entire tender process was bogus and procedure of bidding was
carried in order to support to Respondent Nos. 3 and 4. There
were other bidders who had participated in financial bids along
with Respondent Nos. 3 and 4. After competing with all bidders,
Respondent Nos. 3 and 4 emerged as the successful bidders.
38. Now we examine second question, regarding
suppression of material facts by Petitioner. Considering the
material on record and submissions of learned Counsel, we deal
with it issue wise.
39. (1) Opportunity
According to Petitioner, technical bid was opened on
28th January, 2020 and after gap of two hours, financial bid was
opened on same day. No opportunity was given to Petitioner to
submit requisite experience certificate.
40. It appears to us from the record that the technical bid
was opened on 27th September, 2019 and opportunity was given
to the Petitioner and other bidders by Respondent No.2 to submit
the experience certificate as per Tender condition No.2.
Trupti wp-2076-2021.doc
Accordingly, Petitioner submitted certificate dated 8 th November,
2019, when shortfall was found in it, Respondent No.2 wrote
letter to MAIDCL dated 22nd November, 2019 in response to which
MAIDCL sent "Opinion letter" dated 16th December, 2019 and
another letter dated 17th December, 2019 was sent by Respondent
No.2 seeking more information. This letter shows that copy of it
was marked to Petitioner. The letters dated 27 th August, 2019, 8th
November, 2019 and 16th December, 2019 show that those were
given as per request of Petitioner. We thus find that after opening
technical bid on 27th September, 2019 opportunity was given to
Petitioner, however, the Petitioner has falsely stated that technical
bid was opened on 28th January, 2019. Petitioner has referred
submission of letters dated 8th November, 2019 and 16th December,
2019 in their Petition but not disclosed that an opportunity was
being given to them to cure the deficiency. We find that Petitioner
has suppressed these facts. Moreover, Petitioner states that
MAIDCL refused to give work order and bills being their internal
documents in response to letter dated 17 th December, 2019 of
Respondent No.2 but according to Respondent No.2, there is no
Trupti wp-2076-2021.doc
reply to said letter. Petitioner has not produced reply of MAIDCL
on record. It indicates that Petitioner has falsely stated that there
was a reply given by MAIDCL in response to letter dated 17 th
December, 2019.
41. (2)Validity
Petitioner has challenged the validity of condition No.
3 of said Tender. Petitioner states that this condition restricts the
successful bidder from getting more than one work with respect to
work Nos. 1 to 9 of said tender. After examining the material on
record, we find that condition No.3 was applicable to tender Nos.
1 to 9 and those tenders were cancelled by Respondent No.2 in its
meeting dated 20th August, 2019. Thereafter, Petitioner submitted
tender for tender work Nos. 10 to 14. It indicates that Petitioner
was aware about cancellation of tender Nos. 1 to 9. The Petitioner
has suppressed this fact. Even otherwise, it is well settled law that
a bidder who has participated in a tender cannot turn around and
challenge the terms and conditions of the tender and Tender
conditions are immune from judicial review.
Trupti wp-2076-2021.doc
42. (3) Condition No.2 of New tender.
Petitioner has filed Additional Affidavit in which
Petitioner has raised issue of acceptance of tender of some bidders
in a new tender process. According to Petitioner, Respondent
No.2 has published new tender in the year 2020 mentioning
condition No.2 similar to earlier tender of 2019 which is subject
matter of this Petition. As per this condition, the work should have
been completed, but in new tender, Respondent No.2 has accepted
tender of some bidders whose works are on going, whereas
Petitioner's tenders were rejected on same ground in tender of
2019 which demonstrates malafides on part of Respondent No.2.
The Petitioner has submitted the documents to show that in new
tender process of 2020, the tender of bidders have been accepted
whose works are ongoing.
43. It appears to us from record that Respondent No.2 vide
Corrigendum No.1 dated 2nd January, 2020 modified tender
Condition No. 2 of new tender to the extent of including even the
"ongoing work". It indicates that by said Corrigendum,
Respondent No.2 had permitted the bidders to participate in
Trupti wp-2076-2021.doc
tender process whose work was ongoing. Petitioner has submitted
the documents of the successful bidder along with their additional
Affidavit. It indicates that the Petitioner was aware of this fact but
Petitioner has suppressed this fact from this Court. We may add
that each tender is an independent contract in itself. If the
Respondent No.2 has chosen to lay down terms and conditions of
each tender with intent to achieve their objectives, then it is not
open for the Petitioner to pick and choose terms and conditions
from another tender to suit their convenience. We are therefore of
the view that Petitioner has suppressed above material facts from
this Court.
44. It is well settled that in exercising extraordinary
jurisdiction, a writ court must bear in mind the conduct of the
party who is invoking such jurisdiction and if the Petitioner does
not disclose full facts or suppresses relevant materials or is
otherwise guilty of misleading the court, the court may dismiss
the action without adjudicating the matter. The Hon'ble Apex
Court in the matter of the Silppi Constructions Contractors Versus
Trupti wp-2076-2021.doc
Union of India and Another 5 has held that, "attempts by
unsuccessful tenderers with imaginary grievances, wounded pride
and business rivalry, to make mountains out of molehills of some
technical/ procedural violation or some prejudice to self, and
persuade courts to interfere by exercising power of judicial review,
should be resisted. Such interference, either interim or final, may
hold up public works for years, or delay relief and succour to
thousands and millions and may increase the project cost
manifold".
45. Needless to state that in present case the Petitioner
has approached this Court to invoke writ jurisdiction under Article
226 of Constitution of India. Petitioner claims justice and equity,
but while claiming so the Petitioner has suppressed material facts
and has not come with clean hands. The person who claims
justice and equity must come with clean hands. We are of the view
that, the Petitioner was rightly held ineligible by Respondent No.2.
Tender of Respondent Nos. 3 and 4 were accepted after scrutiny of
5 (2020) 16 SCC 489
Trupti wp-2076-2021.doc
documents and by adopting proper procedure.
46. For the reasons recorded above, the Petition is devoid
of merit and is accordingly dismissed. No order as to cost.
47. On the request of learned Counsel for the Petitioner, we
direct that the ad-interim order of status quo shall continue to
operate for a period of four weeks from the date this order is
uploaded.
(S.G.DIGE,J.) (A.A.SAYED, J.)
Digitally signed
by TRUPTI
TRUPTI SADANAND
SADANAND BAMNE
BAMNE Date:
2021.09.24
23:40:37 +0530
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!