Executive Engineer, Bembla ... vs Chetan Narayan Mohakar And Others
2021 Latest Caselaw 16370 Bom

Citation : 2021 Latest Caselaw 16370 Bom
Judgement Date : 25 November, 2021

Bombay High Court
Executive Engineer, Bembla ... vs Chetan Narayan Mohakar And Others on 25 November, 2021
Bench: A.S. Chandurkar, G. A. Sanap
                              3A.CAF2332.21.odt                                                      1



                                            IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
                                                      NAGPUR BENCH : NAGPUR.
                                          CIVIL APPLICATION (F)NO. 2332/2021 IN F. A.NO.1062/2016
                                                    Executive Engineer, Bembla Project Division, Yavatmal
                                                                            Vs.
                                                            Chetan Narayan Mohakar and others.
                              ------------------------------------------------------------------------------------------------
                              Office Notes, Office Memoranda of                                                 Court's or Judge's Order
                              Coram, appearances, Court's Orders
                               or directions and Registrar's order
                              ------------------------------------------------------------------------------------------------------------------------------
                                       Shri Abhijit Parihar, Advocate for non-applicant/appellant.
                                       Shri S.U.Nemade, Advocate for applicants/respondent nos.1 to 3.
                                       Shri A.M.Kadukar, Assistant Government Pleader for non-applicants/respondent nos.
                                       4 and 5
                                         CORAM :-              A.S.CHANDURKAR AND G.A.SANAP, JJ.

DATED :- NOVEMBER 25, 2021.

The prayer made in this application is for permission to withdraw the amount of compensation as awarded by the Reference Court.

We have heard the learned counsel for the parties and we have perused the judgment of the Reference Court. It is seen that while staying the operation of the judgment of the Reference Court, the acquiring body was directed to deposit 60% of the amount as granted by the Reference Court.

Prima facie considering the nature of evidence on record, we are satisfied that the applicants have made out a case for withdrawal of the amount of compensation as deposited by the acquiring body. The applicants are permitted to withdraw the amount deposited by the acquiring body with accrued interest subject to filing of an undertaking in this Court that in case, the appeal filed by the acquiring body is allowed, the amount withdrawn by them shall be re-deposited along interest at such rate the Court may direct.

The civil application is disposed of.

Digitally Signed byJAYANT S ANDURKAR (G.A.SANAP, J.) (A.S.CHANDURKAR, J.) Personal Assistant Signing Date:

25.11.2021 17:06 Andurkar..

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter