Citation : 2021 Latest Caselaw 8537 Bom
Judgement Date : 28 June, 2021
13. wpl 5516.21.doc
DDR
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION (L) NO. 5516 OF 2021
Perfect Alloys and Steel Limited and anr. ....Petitioners
Vs.
Union of India and ors. ..... Respondents
--------------
Mr.Shyam Kapadia, Mr.Suvaaankoor Das and Ms.Arushi Kaulaskar
i/b Krishnamurthy and Co., for the Petitioners.
Mr.Chandrakant N. Chavan, for Respondent No.1.
Mr.Javeed Hussein i/b Hussein & Co., for Respondents No. 2 & 3.
--------------
CORAM : S.C.GUPTE &
M. S.KARNIK, JJ.
RESERVED ON : JUNE 8, 2021
PRONOUNCED ON : JUNE 28, 2021
JUDGMENT (PER M.S. KARNIK, J.)
Rule. Rule is made returnable forthwith. Heard fnally with
the consent of the parties.
2. This Petition under Article 226 of the Constitution of India
takes exception to the tender conditions in the Notice inviting
tender dated November 8, 2019. Petitioner - Company has
prayed for further consequential reliefs.
13. wpl 5516.21.doc
3. Petitioner No. 1 - Company is engaged in the business of
manufacturing of diferent types of Liquid Processed Gas (LPG)
Cylinders. Respondent No.2 - Hindustan Petroleum Corporation
Limited ('HPCL' for short) is a Government of India Enterprise
engaged in refning and marketing of petroleum products
throughout the country.
4. Respondent No.2, on November 8, 2019, foated a tender
(hereafter referred to as 'NIT' for short) bearing No.1900789-HD-
10157 inviting bids for procurement of 89.87 lacs of 14.2 kg LPG
cylinders ftted with Self Closing Type LPG Cylinder Valves to
various LPG Bottling Plants. The bid of Petitioner No.1 was
rejected on the ground that Petitioner No.1 did not comply with
the essential terms and conditions of the tender as it did not
submit bid for ten States. The Petitioner decided to accept the
decision of Respondent No.2 rejecting the Petitioner's bid.
5. The letter of intent in favour of the successful bidder was
issued on January 10, 2020 and the tender was awarded in
favour of the successful bidder. It is the Petitioner's case that
upon expiry of the period of 12 months in terms of Clause 3 of
the NIT, HPCL is now considering extension of the period of
13. wpl 5516.21.doc
contract in favour of successful bidder for a further period of 12
months. By a letter dated February 10, 2021, the Petitioner
requested HPCL to consider empaneling Petitioner No.1 with
supply of 14.2 kg LPG Cylinders to HPCL on pan-India basis.
However, HPCL failed to respond to the same.
6. The Petitioner is aggrieved by the decision of HPCL in
extending the period of contract for further period of 12 months
in favour of the successful bidder without foating a fresh tender.
It is the submission of learned Counsel for the Petitioners that
though pursuant to NIT, the Petitioner participated in the tender
process and duly submitted its bid, however, due to inadvertence
and/or oversight and/or clerical mistake, Petitioner No.1
submitted a bid restricting the same for nine States. Learned
Counsel invited our attention to Clause 47.A.vii.b of the 'NIT'
which stated thus :
"Bidders quoting for any of the States, ie. Punjab, Himachal Pradesh, Uttarakhand, Uttar Pradesh have to necessarily quote for J&K"
It is submitted by learned Counsel that the Petitioner No.1 had no
other option but to abide by the decision of HPCL rejecting its
bid.
13. wpl 5516.21.doc
7. It is the submission of learned Counsel that it is not
rejection of the bid of Petitioner No.1 by HPCL which is impugned
in the present Petition but the decision of HPCL to extend the
period of contract under the tender for a further period of 12
months in favour of the successful bidder. Learned Counsel
submitted that the decision on the part of HPCL extending the
period of contract for a further period of 12 months tantamounts
to giving unfettered power to HPCL to take a decision with regard
to the extension of the contract and without ofering prospective
bidders to have their bids considered, in gross violation of the
principles of equality, fairness and non-arbitrariness. It is
contended by learned Counsel that though the Petitioners
accepted the decision of HPCL rejecting their bid, however, the
decision to grant an extension of one year is nothing but
providing an unfettered discretion and unrestricted power on
HPCL in contractual matters which according to him is capricious
and unreasonable. In the submission of learned Counsel, the
absolute discretion that the Respondent authority reserved for
itself in extending a contract of a vendor who emerged
successful in the tender process of November 2019, is both
unreasonable and contrary to public interest and such discretion
curtails the right of other empanelled vendors of HPCL who may
not have participated in the tender process or may have been
13. wpl 5516.21.doc
unsuccessful therein, to carry on their trade or business, and is
therefore in contravention of the fundamental right guaranteed
under Article 19(1)(g) of the Constitution of India. Learned
Counsel submits that the power under the tender document to
extend the contractual period by a period equivalent to the entire
original contractual period, i.e. efectively allowing it to double
the contractual period at its discretion, is vitiated by arbitrariness
and malafdes and is thus violative of Article 14 of the
Constitution of India.
8. Learned Counsel further urges that the tender process
denies fair competition amongst similarly placed persons for
performing the contract contemplated in the tender process. It is
vehemently urged by learned Counsel that instead of extending
the contractual period, a fair approach on the part of the
Respondent authority expected them to foat a fresh tender
allowing various persons who may have not bid in the tender or
been unsuccessful therein to participate in the process. It is
further submitted by learned Counsel that though HPCL has
sought to defend its action of extending the impugned tender as
being a policy decision, but have failed to disclose any policy
enacted by either Respondent No.1-Union of India permitting
13. wpl 5516.21.doc
extension of such tenders and in any case, no reasons for such
policy of extension are disclosed nor is it explained what
objective would be met by the arbitrary extending of tenders at
the whims and fancies of HPCL. It is thus a submission of learned
counsel that in the absence of any defned policy, the
Respondent authority is vested with uncontrolled discretion and
the same is contrary to well settled principles laid down by the
Hon'ble Supreme Court governing exercise of discretionary
powers by public authorities. In support of his submission that
the exercise of discretion should be fair and in public interest and
free from arbitrariness, learned Counsel relied upon the decision
of this Court in the case of Abdul Hassan Khan vs. State of
Maharashtra and another1.
9. On the other hand, learned Counsel for HPCL invited our
attention to the afdavit-in-reply fled on their behalf. Our
attention is invited to the various clauses of the tender document
dated November 8, 2019. Learned counsel submitted that the
tender document contained instructions to bidders of the tender
to study the tender document carefully and understand the
terms and conditions, specifcation of the tender before
submitting their bids. Learned counsel submitted that tender 1 2008(2) Mh.L.J. 373
13. wpl 5516.21.doc
terms specifcally provide that the contract in respect of the
successful bidders may be extended/repeated at the sole
discretion of Respondent No.2 for a further period of 12 months
including increasing the contract quantity on the same terms and
conditions. Learned Counsel submits that the Petitioners herein
are successful bidders with the IOCL and BPCL and supplying the
LPG Cylinders as per the tender norms, are also the benefciary
of the repetition/extension of the tender period for a further
period of 12 months in these two oil marketing companies. It is
therefore his submission that it is not open for the Petitioner to
raise the challenge as the one in the present Petition. It is thus
the contention of learned Counsel that when the tender
document itself provided for a condition of extending the
contract of the successful bidder for a further period of one year,
and when the Petitioner participated in the tender process by
submitting its bid without then challenging the tender condition
of extension, it is now not open for the Petitioner to raise any
grievance about extension of contract by a further period of one
year in favour of the successful bidder. It is the submission of
learned Counsel for Respondent Nos. 2 and 3 that the extension
of the contract in favour of the successful bidder in terms of the
contract will be only for 1 year and no further extension would
be granted.
13. wpl 5516.21.doc
10. We have perused the Petition, the Exhibits, the afdavit-in-
reply fled by Respondent Nos. 2 and 3 and the afdavit-in-
rejoinder. We have heard learned Counsel for the Petitioners and
learned Counsel for Respondents.
CONSIDERATION
11. It is an admitted fact that Respondent No. 2, on November
8, 2019, foated the subject tender. The bid of the Petitioner was
rejected as the Petitioner did not comply with the essential terms
and conditions of the tender by not submitting the bid for 10
States. It is an unequivocal stand in the Petition that it is not the
rejection of the bid of Petitioner No.1 by Respondent No.2 which
is impugned in the present Petition but the Petitioners are
aggrieved by the decision on the part of Respondent No.2 in
extending the contract for a further period of one year in favour
of the successful bidder without foating a fresh tender. It is the
Petitioners' case that though the tender document provides for
an extension upto 12 months including increasing the contract
quantity, the said provision for extension is arbitrary and confers
unfettered discretion on Respondent No.2, rendering such
extension contrary to the provisions of the Constitution of India.
13. wpl 5516.21.doc
12. To properly appreciate the controversy, relevant portion of
Clause 3 of the tender document is reproduced below, which
reads thus :-
"3. PERIOD OF CONTRACT :
The total requirement shown in this tender enquiry is for the period of 12 months from the date of placement of Order/Rate Contract/Purchase Order. The contract placed on successful bidders may be extended/repeated at sole discretion of Corporation for a further period of up to 12 months including increasing the contract quantity calculated on prorate basis on repeat order basis at the same terms and conditions.
13. It is thus seen that Notice inviting tenders contains a
specifc provision for extension of the contract by a further period
of up to 12 months at sole discretion of the Corporation. At the
cost of repetition, it may be stated that the Petitioners had
submitted their bid pursuant to the notice inviting tender and the
bid was rejected on the ground that the Petitioners did not fulfll
the eligibility condition. The Petitioners thus participated in the
tender process with full knowledge that the tender document did
provide for a clause for extension of contract in favour of the
successful bidder for a further period of upto 12 months. The
Petitioners did not raise any objection as regards Clause 3 while
submitting the bid or even thereafter when the Petitioners' bid
13. wpl 5516.21.doc
was declared unsuccessful. It is only at the stage when the
period of contract of 1 year was to expire that the Petition is fled
challenging the clause empowering Respondent Nos. 2 and 3 to
grant 12 months extension.
14. At this stage, we fnd it apposite to refer to some decisions
of the Hon'ble Supreme Court as regards the scope of judicial
review in the matter of grant of Government contracts. The
Hon'ble Supreme Court in the case of Tata Cellular vs. Union
of India2 has held that the principles of judicial review would
apply to the exercise of contractual powers by Government
bodies in order to prevent arbitrariness or favoritism. Their
Lordships have observed that it must be clearly stated that there
are inherent limitations in exercise of that power of judicial
review. It is expected to protect the fnancial interest of the
State. The right to refuse the lowest or any other tender is
always available to the Government. But, the principles laid down
in Article 14 of the Constitution have to be kept in view while
accepting or refusing a tender. There can be no question of
infringement of Article 14 if the Government tries to get the best
person or the best quotation. The right to choose cannot be
considered to be an arbitrary power. Of course, if the said power 2 (1994) 6 SCC 651
13. wpl 5516.21.doc
is exercised for any collateral purpose the exercise of that power
will be struck down. Judicial quest in administrative matters has
been to fnd the right balance between the administrative
discretion to decide matters whether contractual or political in
nature or issues of social policy; thus they are not essentially
justifable and the need to remedy any unfairness. Such
unfairness is set right by judicial review. The judicial power of
review is exercised to rein in any unbridled executive
functioning. Judicial review is concerned with reviewing not the
merits of the decision in support of which the application for
judicial review is made, but the decision-making process itself.
Their Lordships further observed that the duty of the court is to
confne itself to the question of legality. Their Lordships in
paragraph 94 held thus :-
"94.The principles deducible from the above are :
(1) The modern trend points to judicial restraint in administrative action.
(2) The court does not sit as a court of appeal but merely reviews the manner in which the decision was made.
(3) The court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which itself may be fallible.
(4) The terms of the invitation to tender cannot be open to
13. wpl 5516.21.doc
judicial scrutiny because the invitation to tender is in the realm of contract. Normally speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than not, such decisions are made qualitatively by experts.
(5) The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of Wednesbury principle of reasonableness (including its other facts pointed out above) but must be free from arbitrariness not afected by bias or actuated by mala fdes.
(6) Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure.
(emphasis supplied by us)
15. A reference to what is observed by the Hon'ble Supreme
Court in the case of Sterling Computers Limited vs. M/s. M &
N Publications Limited and others3 in paragraph 12 is
pertinent. Paragraph 12 reads thus :-
"12. At times it is said that public authorities must have the same liberty as they have in framing the policies, even while entering into contracts because many contracts amount to implementation or projection of policies of the Government. But it cannot be overlooked that unlike policies, contracts are legally binding commitments and they commit the authority which may
3 (1993) 1 SCC 445
13. wpl 5516.21.doc
be held to be a State within the meaning of Article 12 of the Constitution in many cases for years. That is why the Courts have impressed that even in contractual matters the public authority should not have unfettered discretion. In contracts having commercial element, some more discretion has to be conceded to the authorities so that they may enter into contracts with persons, keeping an eye on the augmentation of the revenue. But even in such matters they have to follow the norms recognised by Courts while dealing with public property. It is not possible for Courts to question and adjudicate every decision taken by an authority, because many of the Government Undertakings which in due course have acquired the monopolist position in matters of sale and purchase of products and with so many ventures in hand, they can come out with a plea that it is not always possible to act like a quasi judicial authority while awarding contracts. Under some special circumstances a discretion has to be conceded to the authorities who have to enter into contract giving them liberty to assess the overall situation for purpose of taking a decision as to whom the contract be awarded and at what terms. If the decisions have been taken in bona fde manner although not strictly following the norms laid down by the courts, such decisions are upheld on the principle laid down by justice Holmes, that Courts while judging the constitutional validity of executive decisions must grant certain measure of freedom of "play in the joints" to the executive."
16. Based on these principles we will examine the facts of the
present case. Pursuant to the notice inviting tenders the
Petitioner submitted its bid. The bid is rejected on the ground
that the Petitioner did not fulfll the eligibility condition. The
13. wpl 5516.21.doc
Petitioner decided to abide by the decision of Respondent No.2
rejecting the bid of the Petitioners having not fulflled the
eligibility condition. Clause 3 of the tender document clearly
provided for an extension upto 12 months in favour of the
successful bidder in the sole discretion of Respondent No.2.
Petitioner No.1 participated in the tender process with full
knowledge that there exists a condition of extension of contract
by one year in favour of the successful bidder at the sole
discretion of HPCL. In our considered opinion, the challenge to
tender condition regarding extension cannot be entertained at
this belated stage at the instance of the Petitioner who
participated in the tender process and was the unsuccessful
bidder. No doubt, it was always open for the Petitioner to
challenge the rejection of its bid on the grounds available of
judicial review of the decision as spelt out by the Hon'ble
Supreme Court. The Petitioner. however, decided to abide by the
decision of HPCL rejecting his bid. It is trite that even in
contractual matters, public authority should not have unfettered
discretion. The decision in the present case to extend the
contract has been taken in terms and conditions of the tender
document. It is not as if Respondent No.2 unilaterally at its
discretion granted extension sans any clause in terms of the
notice inviting tenders. It is well settled that the terms of the
13. wpl 5516.21.doc
invitation to tender cannot be open to judicial scrutiny because
the invitation to tender is in the realm of contract. The extension
is in terms of the tender conditions. It is not the case that the
condition was incorporated to favour a particular bidder. It
cannot be said that the tender condition is unreasonable or
afected by bias or actuated by malafde. It is not possible for us
to sit in appeal over the decision of HPCL incorporating the
condition of extension of contract upto 12 months in the 'NIT'.
This is a matter purely within the domain of HPCL and in the
realm of contract. So long as the decision in bonafde and not
actuated with any malafdes, it is not open for this Court to
interfere with the tender conditions.
17. Learned counsel for HPCL was at pains to point out that in
respect of IOCL and BPCL companies where the Petitioner was a
successful bidder, similar term of extension in the tender existed
and the Petitioners have been benefciaries of the extended
purchase orders. Though we see the point which learned Counsel
for the Respondent is trying to make out, we do not wish to
comment on this aspect, as even otherwise for the reasons
stated above we do not fnd any merit in the submissions of
learned Counsel for the Petitioners.
13. wpl 5516.21.doc
18. We do not fnd any merit in the submission of learned
Counsel for the Petitioner that the clause empowering
Respondent No.2 to extend the contract by a further period of 12
months confers unfettered discretion on HPCL. The clause was
very much part of 'NIT' of which the Petitioner had full knowledge
and despite which he participated in the tender process. The
Petitioner having sufered the consequence of his bid being
rejected on the ground that he does not fulfll the eligibility
condition, in our opinion, the Petitioner is not justifed in raising a
challenge to the impugned tender condition, that too when HPCL
is on the verge of considering the extension of contract. The
Respondent Authority has acted completely in consonance with
the terms and conditions of the 'NIT'.
19. We do not fnd this to be a ft case where the judicial
intervention is necessary in the decision of the authority granting
an extension, as the impugned decision cannot be said to be
capricious, unreasonable, irrational or arbitrary.
20. In our considered opinion, the decision relied upon by
learned Counsel for the Petitioner in Abdul Hassan Khan
13. wpl 5516.21.doc
(supra) has no application in the present facts. This Court in
Abdul Hassan Khan, unlike the present case, was not
concerned with a clause in the 'NIT' empowering the authority to
grant an extension at its discretion. The decision in Abdul
Hassan Khan thus proceeds on an entirely diferent set of facts.
21. At this juncture, we record the statement made on behalf
of Respondent No.2 that no further extension will be granted to
the successful bidder in respect of instant tender. Statement is
accepted.
22. We, therefore, do not see any reason to interfere with the
decision of Respondent No.2 in granting extension of the contract
by a further period of 12 months in favour of the successful
bidder. Consequently, the Petition fails and is accordingly
dismissed.
23. Rule is discharged with no order as to costs.
(M.S.KARNIK, J.) (S.C.GUPTE, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!