Citation : 2021 Latest Caselaw 1721 Bom
Judgement Date : 27 January, 2021
1 1-NMCD 1165-2019 in CARBP 485-2019.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
NOTICE OF MOTION NO.1165 OF 2019
IN
COMMERCIAL ARBITRATION PETITION NO.485 OF 2019
Digitally signed
Anjali by Anjali T.
Aswale
T. Date:
Essar Oil & Gas Exploration ]
2021.01.29
Aswale 17:36:55
+0530
& Production Limited. ] ... Applicant/
Original Petitioner
In the matter between :
Essar Oil & Gas Exploration ]
& Production Limited. ] ... Petitioner
Versus
UEM India Pvt. Ltd. ] ... Respondent
Mr. Pradeep Sancheti, Senior Counsel a/w Mr. Ganthan Raikar &
Pallavi Bali for Petitioner/Original Applicant.
Mr. Rahul Narichania, Senior Counsel a/w Mr. Vishal Muglikar, Mr.
Aniketh Nair & Mr. Shrikant Pillai i/b Mustafa Motiwala for
Respondent/Judgment Creditor.
CORAM :- B. P. COLABAWALLA, J.
DATE :- 27 JANUARY, 2021
P. C. :-
1. Leave to amend and correct the date of the award in
prayer clause 'a' of the Notice of Motion to substitute the year
'2019' with the year '2018' is granted. Amendment to be
carried out forthwith.
URS 1 of 7
2 1-NMCD 1165-2019 in CARBP 485-2019.odt
2. This Notice of Motion has been fled seeking stay of
the operation and efect of the Award dated 26 th November,
2018, passed by the sole Arbitrator. The amount due to the
Respondent under the impugned Award as on today is
approximately 2.23 Crores.
3. Mr. Sancheti, the learned Senior Counsel appearing
on behalf of the Petitioner, submitted that even though the
impugned Award is a money Award, an unconditional stay be
granted as the learned Arbitrator completely ignored a vital
term of the contract and awarded the claim contrary to the
express term of the contract. In this regard, Mr. Sancheti
brought my attention to Article 12 of the Agreement between
the Petitioner and the Respondent for Water Treating Facilities
Services in BLOCK RG(EAST)-CBM-2001/1 dated 14 th August,
2013. Relying upon Article 12, Mr. Sancheti submitted that
except to the extent otherwise agreed in writing, any and all
costs in connection with the performance of the work would be
to the contractor's account and shall be deemed to be included
in the fees specifed in the Appendix, unless the same are on
account of any change order. Mr. Sancheti brought my attention
to Contract Price Schedule (Exhibit-B to the Appendix, Page 379)
and submitted that the amount that was payable to the
URS 2 of 7 3 1-NMCD 1165-2019 in CARBP 485-2019.odt
Respondent for design, engineering, erection, testing,
commissioning and performance guarantee, test run etc. was a
lumpsum of Rs.75 Lakhs. This being the case, at the highest,
the Arbitrator, even if he found that the Respondent was entitled
to damages, he could not have awarded a sum larger than 75
lakhs. In other words, the Respondent could not get a larger
amount by way of damages, than the amount it would have got
if the agreement had been performed. Considering that the
Arbitral Tribunal has awarded the sum of approximately Rs.1.79
Crores towards compensation and damages for loss caused to
the Respondent, the award is wholly perverse and needs to be
set aside. He, therefore, submitted that more than a prima-
facie case is made out for an unconditional stay of the impugned
Award.
4. On the other hand, Mr. Narichania, the learned Senior
Counsel appearing on behalf of the Respondent, submitted that
as on 22/01/2021, the amount due and payable under the Award
is Rs.2.23 Crores. This being a money Award, no stay ought to
be granted without an order of deposit, unless extraordinary
circumstances are made out. Mr. Narichania submitted that,
frstly, it is very unfair to the Arbitral Tribunal to raise an
argument before this Court which was never raised and argued
URS 3 of 7 4 1-NMCD 1165-2019 in CARBP 485-2019.odt
before the Tribunal. Mr. Narichania submitted that the question
of interpretation of Article 12 was never in issue and was never
raised by the Petitioner before the Arbitral Tribunal. He
submitted that if this point was raised before the Arbitral
Tribunal, the Arbitral Tribunal, after reading the contract as a
whole, would have interpreted this Article and even if
interpreted erroneously, would not be amenable to challenge
under Section 34 unless the interpretation was wholly perverse.
He submitted that this being the case, it would be highly unfair
to let the Petitioner today canvass this point and call upon this
Court to interpret the said Article for the frst time. He,
therefore, submitted that no stay ought to be granted unless
and until the amount of Rs. 2.23 Crores is deposited in this
Court.
5. I have heard learned Senior Counsel for parties and
also perused the papers and proceedings. I must mention that
there appears to be some dispute as to whether this point was
raised or not before the Arbitral Tribunal. Though Mr.Narichania
was vehement in his arguments that this was never argued
before the Arbitral Tribunal, Mr. Sancheti contends otherwise.
However, this is an aspect that would be gone into in detail at
the time when petition under Section 34 is heard at the
URS 4 of 7 5 1-NMCD 1165-2019 in CARBP 485-2019.odt
admission stage. Assuming that the interpretation of Article 12
was never raised and argued before the Arbitral Tribunal, I will
then have to consider whether it can be raised for the frst time
before me.
6. Prima facie, today, considering this is a money Award
and the Respondent has succeeded before the Arbitral Tribunal, I
do not think that this would a ft case to grant any unconditional
stay of the impugned Award. In these circumstances, I think
that it will be in the ftness of things if the Petitioner is directed
to deposit a sum of Rs.1.85 Crores in this Court as a condition
precedent for stay of the impugned Award.
7. In view of the foregoing discussion, the following
order is passed :
ORDER
(i) In the event the Petitioner deposits in this Court a
sum of Rs.1.85 Crores or furnishes a bank guarantee
of any nationalized bank for the same amount within
a period of 6 weeks from today, the enforcement of
the impugned Award shall stand stayed.
(ii) In the event the Petitioner opts to furnish a bank
guarantee, the same shall be kept alive until further
URS 5 of 7 6 1-NMCD 1165-2019 in CARBP 485-2019.odt
orders by having the same renewed every year and
the bank guarantee shall also clearly state that as
and when encashed, the same shall be paid together
with interest of 10% p.a. from the date of furnishing
the bank guarantee till it's encashment.
(iii) In the event the bank guarantee is not renewed at
least 15 days prior to it's expiry, the Prothonotary and
Senior Master will be entitled to encash the bank
guarantee without any further orders of this Court.
(iv) In the event the money is not deposited as directed
above or the bank guarantee is not furnished, then,
necessarily, there will be no stay to the enforcement
of the impugned Award and the Respondent herein
shall be entitled to execute the same in accordance
with law.
8. At this stage, Mr. Narichania submitted that in the
event the Petitioner deposits in Court the sum of Rs.1.85 Crores
as mentioned above, the Respondent be allowed to withdraw
the same subject to the Respondent furnishing a bank
guarantee on the same terms and conditions as mentioned
earlier. Having heard the learned counsel for the parties on this
aspect, it is ordered that in the event the Petitioner deposits in
URS 6 of 7 7 1-NMCD 1165-2019 in CARBP 485-2019.odt
Court the sum of Rs. 1.85 Crores, the Respondent shall be
allowed to withdraw the same subject to the Respondent
furnishing a bank guarantee for the said amount which shall be
kept alive until further orders by having the same renewed
every year. The bank guarantee shall also clearly state that if
and when encashed, the same shall be paid together with
interest @ 10% p.a. from the date of furnishing the bank
guarantee till its encashment.
9. The above Notice of Motion is accordingly disposed
of. No order as to costs.
10. List Section 34 petition for admission on 10/03/2021.
11. This order shall be digitally signed by the Private
Secretory / Personal Assistant of this Court. All concerned shall
act on production by fax or e-mail of a digitally signed copy of
this order.
(B. P. COLABAWALLA, J.)
URS 7 of 7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!