                                                                              wp.7390.10.doc

Ajay/Amberkar
                           IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                     CIVIL APPELLATE JURISDICTION

                                    WRIT PETITION NO. 7390 OF 2010

                P. S.C. Pacific
                A Registered Partnership Firm having its
                registered office at PSC House,
                CTS No. 111 + 112, Anand Colony,
                Dr. Ketkar Road, Pune 411 004
                Through Partner,
                Paranjape Scheme Construction Ltd.
                A Registered Company, having its
                registered office at PSC House,
                CTS No. 111 + 112, Anand Colony,
                Dr. Ketkar Road, Pune 411 004
                through its Director
                Shri. Shrikant Purshottam Paranjape
                Address - PSC House,
                CTS No. 111 + 112, Anand Colony,
                Dr. Ketkar Road, Pune 411 004
                     [[
                                                                   ..   Petitioner
                          Versus
                1. The State of Maharashtra,
                   Through its Principal Secretary to thereafter
                   Ministry of Revenue, Mantralaya,
                   Mumbai - 400 032.

                2. The Divisional Commissioner, Pune
                   Division, Pune, having office
                   at Raj Bhavan, Pune.

                3. The Collector, Pune, having office
                   at Pune, Dist. Pune.

                4. Sub-Divisional Officer, Mulshi Subdivision,
                   Dist. Pune, having office at Mulshi.

                5. Tahsildar, Taluka - Mulshi, Dist. Pune.
                   having office at Mulshi.

                6. Circle Officer, Mulshi, Taluka Mulshi.
                   Dist. Pune.                                     ..    Respondents
                                               ...................

                                                                                     1 of 21
                                                                            wp.7390.10.doc


 Mr. Girish S. Godbole a/w. Drupad S. Patil for the Petitioner.
 Ms. M.P. Thakur, AGP for the Respondents - State.
                                   ...................

                           CORAM                         : S.J. KATHAWALLA &
                                                           MILIND N. JADHAV, JJ.


                           RESERVED ON   : 23 NOVEMBER, 2021
                           PRONOUNCED ON : 09 DECEMBER, 2021



JUDGEMENT (PER : S.J. KATHAWALLA & MILIND N. JADHAV, JJ.)

. By the present Writ Petition, the Petitioner has prayed for

the following reliefs:

"(a) That this Hon'ble Court may be pleased to issue a Writ of Mandamus or any other Writ, Order or direction in the nature of Mandamus thereby directing the Tahsildar, Taluka Mulshi Respondent No.5 herein to forthwith withdraw and / or cancel the impugned order 11/8/2010 issued to the Petitioner in purported exercise of powers conferred by section 48 of the M.L.R. Code, 1966 being Exhibit Q to this Writ Petition;

(b) That this Hon'ble Court may be pleased to issue a Writ of Certiorari or any other Writ, Order or Direction in the nature of Certiorari thereby quashing and setting aside the impugned order dated 11/8/2010 issued by the Tahsildar Mulshi, Respondent No.5 herein to the Petitioner in purported exercise of powers conferred under Section 48 of the M.L.R.Code, 1966; being Exhibit Q respectively to this Writ Petition;

(c) That it be held and declared that the Tahasildar, Taluka Mulshi, Respondent No.5 herein does not have any authority and jurisdiction to levy and demand royalty and / or penalty for the material excavated from the lands of Village Hinjewadi, Taluka Mulshi, District Pune for the purpose of laying down foundation and / or plinth and construction of basement when such work is being undertaken pursuant to the valid Development Permission issued by the Planning Authority u/s. 18 of the Maharashtra Regional & Town Planning Act, 1966 and after obtaining permission for NA use u/s. 44 of the M.L.R. Code, 1966 being permission dated 14/5/2008 which is at Exhibit 'L' to this Writ Petition.

2 of 21 wp.7390.10.doc

C(I) This Hon'ble Court may be pleased to issue a Writ of Certiorari and / or any other Writ, Order or direction in the nature of Writ of Certiorari thereby quashing and setting aside the impugned order purportedly dated 31.1.2011 passed by Circle Officer, Mulshi being Exh. "T" to this Writ Petition;

C(II) "This Hon'ble Court may be pleased to issue Writ of Mandamus and / or any other Writ, Order or direction in the nature of Writ of Mandamus thereby directing Respondent No. 6 herein, Circle Officer, Mulshi to forthwith withdraw and / or cancel the impugned order purportedly dated 31.1.2011 being Exh. "T" to this Writ Petition."

2. The Petitioner is challenging the show-cause notices dated

14.03.2009 and 23.12.2009 and order dated 11.08.2010 issued by the

Respondent No.5 - Tahsildar, Mulshi, inter alia, calling upon the

Petitioner to pay royalty and penalty of Rs. 1,36,33,194.00 for

excavating minor minerals while laying down foundation of the

building and construction of basement and plinth undertaken by the

Petitioner pursuant to valid development permission issued by the

planning authority. The Petitioner has also challenged the order dated

31.01.2011 passed by the Respondent No. 6 Circle Officer, Mulshi

cancelling Mutation Entry No. 7741 recording the name of the

Petitioner as owner of land which is the subject matter of the present

petition.

3. Briefly stated the facts are as under:

3.1. On 14.05.2008, the Collector, Pune being the planning

authority granted development permission under Section 18 of the

3 of 21 wp.7390.10.doc

Maharashtra Regional and Town Planning Act, 1966 (for short "the

said Act") to the Petitioner along with permission for Non-Agricultural

user under Section 44 of the Maharashtra Land Revenue Code, 1966

(for short "the MLR Code, 1966") in respect of lands bearing several

survey numbers totally admeasuring 35750 sq. mtrs. situated at village

Hinjewadi , Taluka Mulshi, District Pune (for short "the said lands").

3.2. On 13.08.2008, the Petitioner submitted an application

before the Tahsildar, Mulshi to seek permission for commencement of

excavation on the said lands in terms of the building permission

granted to the Petitioner. However, the Petitioner received no reply

from the Respondent No.5 - Tahsildar.

3.3. Petitioner commenced development / construction work

on the said lands in accordance with the development permission

granted on the said lands.

3.4. On 14.03.2009, Respondent No.5 - Tahsildar issued a

show-cause notice to the Petitioner stating that the Petitioner had

allegedly excavated minor minerals amounting to 12183 brass without

valid permission. This show-cause notice was based upon panchnama

dated 22.01.2009 prepared by the Circle Officer, Thergaon. The

Petitioner replied to the show-cause notice on 01.04.2009. On

4 of 21 wp.7390.10.doc

23.12.2009, Petitioner received a second show-cause notice dated

23.12.2009 for alleged excavation of minor minerals pursuant to

panchanama dated 01.09.2009 prepared by the Circle Officer, Male.

The Petitioner filed reply dated 22.02.2010 to the second show cause

notice. On 11.08.2010, after hearing the Petitioner, Respondent No.5

Tahasildar passed an order directing the Petitioner to pay an amount

of Rs. 1,36,33,194.00 towards royalty, penalty, TDS, education taxes

and rent for alleged excavation of minor minerals amounting to 12183

brass without valid permission.

3.5. On 06.09.2010, the Petitioner filed the present Writ

Petition to challenge the two show-cause notices and order.

3.6. On 31.01.2011, the Respondent No.6, Circle Officer,

Mulshi passed an order directing cancellation of Mutation Entry No.

7741 in the record of rights standing in the name of the Petitioner qua

the said lands.

3.7. On 13.04.2011, this Court admitted the present Petition

and granted ad-interim order in terms of prayer clause 'e' restraining

the Tahsildar from enforcing the impugned notices and order.

3.8. On 03.12.2014, the Apex Court allowed Civil Appeal No.

5 of 21 wp.7390.10.doc

10717 of 2014 filed by the Promoters and Builders Association, Pune

against the State of Maharashtra.

3.9. On 11.05.2015, the State Government notified an

amendment to the Maharashtra Minor Mineral Extraction

(Development and Regulation) (Amendment) Rules, 2015 by

introducing a proviso to Rule 46(a)(i), inter alia, providing that no

royalty shall be required to be paid on earth which is extracted while

developing a plot of land and if utilized on the very same plot for land

levelling or any work in the process of development of such plot.

4. Shri. G.S. Godbole, learned counsel appearing for the

Petitioner has submitted that in the present case the Petitioner has

excavated the minor minerals and used the same on the said lands for

development / while developing the said lands; Respondent No.5 -

Tahsildar, Mulshi has not disputed the above stand of the Petitioner in

his Affidavit-in-Reply; thus if the extracted minor minerals are used on

the same plot while developing the said plot, then no royalty is

payable by the Petitioner; hence the impugned show-cause notices /

demand order issued by the Tahsildar are bad in law and deserve to be

set aside. He submitted that the Supreme Court in the case of

Promoters and Builders Association of Pune vs. State of Maharashtra 1

1 (2015) 12 SCC 736

6 of 21 wp.7390.10.doc

has held that the purpose of excavation of minor minerals is required

to be looked into by the authority and if the excavation is merely for

construction / formation of plinth, it cannot be termed as mining

activity and the developer cannot be forced to pay royalty for the

same. He submitted that the Government of Maharashtra vide

notification dated 11.05.2015 amended the Minor Mineral Extraction

(Development and Regulation) Rules, 2013 and as per the amended

Rule No.46 royalty is not payable for excavation of earth while

developing a plot of land if the said earth is utilized on the very same

plot for land levelling or any work in the process of development of

such plot. He submitted that even though the impugned show-cause

notices were issued prior to the enactment of the above amended

Rule, by order dated 13.04.2011 this Court had stayed the impugned

action.

4.1. Shri. Godbole submitted that the impugned action of

levying royalty and penalty on the Petitioner for excavation of minor

minerals for the purpose of laying down the foundation / plinth and

construction of basement is clearly illegal in as much as the said

activity of construction was carried out pursuant to grant of valid

building permission under the provisions of the said Act by the

planning authority.

7 of 21 wp.7390.10.doc

4.2. Shri. Godbole further submitted that the applicability of

the provisions of Section 48(7) of the MLR Code, 1966 is in respect of

lands vested in the Government which are used for the purpose of

mining operations, similarly placed allied operations; excavation of

digging up of land for the purpose of laying down foundation of a

building and/or construction of plinth or basement cannot be

considered as mining activity if the said excavated material is used on

the same plot for levelling and development and consequently no

royalty is payable. Shri. Godbole submitted that Section 48 of the

MLR Code, 1966 deals with lands, the title of which is vested in the

Government and cannot apply to privately owned lands which are

developed under valid development permission granted by the

planning authority under the provisions of the said Act; the words

"......or such other place wherever situate......" as appearing in sub-

section 7 of Section 48 of the MLR Code, 1966 will have to be read

"ejusdem generis" with the words "Mines, quarries" etc.; the provisions

of Section 48 apply only in the case of excavation or disposal of any

minerals from such mines, quarries and not to excavation on the

surface of the land in the case of development / construction;

provisions of sub-section 2 of Section 48 clearly reflect the intention of

the legislature that the words "right to all mines and quarries" is

related to the principal activity of mining and quarrying; excavation of

land temporarily for the purpose of laying down foundation and

8 of 21 wp.7390.10.doc

development cannot amount to excavation of minor minerals

especially if the same are used on the same plot as in the present case

and there is no material evidence to show that there is any

transportation of minor minerals after excavation from the said lands

so as to pay the requisite royalty and penalty under the said Rules. He

submitted that after the Petition was filed, solely relying on the order

dated 11.08.2010, the Respondent No.6, Circle Officer, Mulshi by

order dated 31.01.2011 cancelled the Mutation Entry No. 7741

recording the name of the Petitioner as owner of the said lands; such

action of the Respondent No.6 being patently illegal and deserves to

be set aside.

5. Ms. M.P. Thakur, learned AGP appearing for the

Respondent(s) - State has referred to the affidavit-in-reply dated

04.09.2021 filed by Shri. Abhay Shivajirao Chavan, Tahsildar, Taluka

Mulshi, District Pune and contended that the Petitioner has illegally

excavated sand and murum to the extent of 12183 brass without prior

permission as can be seen from the panchnamas carried out by the

Circle Officers of Thergaon and Male on 27.01.2009 and 01.09.2009;

in view thereof, action under the provisions of sub-section 7 of Section

48 of the MLR Code, 1966 has been initiated.

9 of 21 wp.7390.10.doc

5.1. Advocate Ms. Thakur submitted that in the present case

the Petitioner has been heard by the appropriate authority and a

speaking order has been passed which is appellable under the MLR

Code, 1966; the Petitioner ought to exhaust the appellate remedy

available under the statute rather than press the present Petition under

Article 226 of the Constitution of India.

5.2. Advocate Ms. Thakur has referred to the judgment of the

Apex Court in the case of United Bank of India Vs. Satyawati Tondon

and Others2 and contended that the Petitioner can be directed to

exhaust the alternate remedy of going before the appellate authority.

She has also attempted to distinguish paragraph No.16 of the

judgment in the case of Promoters and Builders Association of Pune

(supra) passed by the Apex Court along with the provisions of sub-

section 7 of Section 48 of the MLR Code, 1966 and submitted that the

action initiated by the Respondent No.5 - Tahsildar under the said

provisions was correct in law. She has therefore prayed for dismissal

of the present Writ Petition.

6. We have perused the Writ Petition as well as the affidavit-

in-reply filed on behalf of the Respondent - State, considered the

submissions made by the learned Advocates for the parties and the 2 (2010) 8 SCC 110

10 of 21 wp.7390.10.doc

case law relied upon by them.

7. Admittedly in the present case, the Petitioner has been

granted a composite permission dated 14.05.2008 by the Collector,

Pune acting as Planning Authority under Section 18 of the said Act

whereby the Petitioner has been granted development permission and

permission for non-agricultural user under the provisions of Section 44

of the MLR Code, 1966. There is no dispute in respect of this

permission. Further in paragraph 3(a), the Petitioner has made the

following averments:-

" (a) 14/5/2008 - The Collector, Pune who acts as Planning Authority under 18 of MR & TP Act, 1966 granted a Development Permission to the Petitioner under section 18 of the MR & TP Act, 1966. Said permission is composite permission also granting permission for N.A. User under section 44 of Maharashtra Land Revenue Code 1966 in respect of an area admeasuring 35750 Sq mtrs. Hereto annexed and marked Exhibit 'L' is a copy of the said Order dated 14/5/2008. According to the said Development Permission the Petitioner has undertaken the work of Construction. For the purpose of the laying down foundation and / or plinth and for the purpose of construction of basement, the Respondent was required to excavate the plinth areas in the plot. Said work of excavation of plinth areas is done by using machineries / equipment without using any explosives or special mining machines upto the requisite depth, the foundation is laid by using steel and RCC and thereafter the excavated material remains, the said is used within the same plot or for the purpose of landscaping and / or land filling activity."

11 of 21 wp.7390.10.doc

7.1. In paragraph 5(a) of the Petition, the Petitioner has stated

thus:-

"5(a) The Petitioner states that Petitioner has been carrying on construction activities of laying down foundation and / or plinth and construction of basement after obtaining the requisite permission for non-agricultural use as contemplated by Section 44 of the M.L.R. Code, 1966 and Building / Development Permission u/s 18 of the Maharashtra Regional & Town Planning Act, 1966. The Petitioner states that pursuant to such valid Development Permission and for construction of Roads for the purpose of implementation of the sanctioned layout, Petitioner is required to excavate the surface of the land to some extent. The said activity does not involve any activity of mining and does not amount to "winning" or "mining" the minor minerals. The Petitioner has never sold the said excavated material. In any case, the activity of excavation of surface of land for the purpose of landscaping, levelling, laying down foundation and / or plinth and construction of basement, which amounts to the activity of Development of land pursuant to a valid permission can never be construed to be a mining activity nor can be construed as excavation of minor minerals u/s 48 of the M.L.R. Code, 1966 or Mines and Minerals Act, 1957 or Rules framed under the M.L.R. Code, 1966."

7.2. The case of the Petitioner in the aforesaid paragraphs of

the Writ Petition has not been controverted in the affidavit-in-reply

filed by the Tahsildar. It is also not the case of the Respondents that

the Petitioner is guilty of transportation of the excavated earth / minor

minerals and as such is therefore liable to pay royalty and penalty

under the provisions of sub-section (7) of Section 48 of the MLR Code,

1966 or Rules framed thereunder read with the Mines and Minerals

Act, 1957. The order dated 11.08.2010 does not refer to or gives any

12 of 21 wp.7390.10.doc

finding based on evidence that the Petitioner has transported the

excavated minor minerals from the site.

8. We may usefully quote the findings of the Supreme Court

in the case of Promoters and Builders Association of Pune (supra)

which squarely cover the facts of the present case. Paragraphs 12 to

15 of the said judgment are relevant and read thus:-

"12. It is not in dispute that in the present appeals excavation of ordinary earth had been undertaken by the appellants either for laying foundation of buildings or for the purpose of widening of the channel to bring adequate quantity of sea water for the purpose of cooling the nuclear plant. The construction of buildings is in terms of a sanctioned development plan under the MRTP Act whereas the excavation/widening of the channel to bring sea water is in furtherance of the object of the grant of the land in favour of the Nuclear Power Corporation. The appellant-builders contend that there is no commercial exploitation of the dug up earth inasmuch as the same is redeployed in the construction activity itself. In the case of the Nuclear Power Corporation it is the specific case of the Corporation that extract of earth is a consequence of the use of the land for the purposes of the grant thereof and that there is no commercial exploitation of the excavated earth inasmuch as "the soil being excavated for "Intake Channel" was not sent outside or sold to anybody for commercial gain".

13. None of the provisions contained in the MRTP Act referred to above or the provisions of Rule 6 of the Rules of 1968 would have a material bearing in judging the validity of the impugned actions inasmuch as none of the said provisions can obviate the necessity of a mining license/permission under the Act of 1957 if the same is required to regulate the activities undertaken in the present case by the appellants. It will, therefore, not be necessary to delve into the arguments raised on the aforesaid score. Suffice it would be to say that unless the excavation undertaken by the appellant-builders is for any of the purposes contemplated by the Notification dated 3.2.2000 the liability of such builders to penalty under Section 48(7) of the Code would be in serious doubt.

13 of 21 wp.7390.10.doc

14. Though Section 2(j) of the Mines Act, 1952 which defines 'mine' and the expression "mining operations" appearing in Section 3(d) of the Act of 1957 may contemplate a somewhat elaborate process of extraction of a mineral, in view of the Notification dated 3.2.2000, insofar as ordinary earth is concerned, a simple process of excavation may also amount to a mining operation in any given situation. However, as seen, the operation of the said Notification has an inbuilt restriction. It is ordinary earth used only for the purposes enumerated therein, namely, filling or levelling purposes in construction of embankment, roads, railways and buildings which alone is a minor mineral. Excavation of ordinary earth for uses not contemplated in the aforesaid Notification, therefore, would not amount to a mining activity so as to attract the wrath of the provisions of either the Code or the Act of 1957.

15. As use can only follow extraction or excavation it is the purpose of the excavation that has to be seen. The liability under Section 48(7) for excavation of ordinary earth would, therefore, truly depend on a determination of the use/purpose for which the excavated earth had been put to. An excavation undertaken to lay the foundation of a building would not, ordinarily, carry the intention to use the excavated earth for the purpose of filling up or levelling. A blanket determination of liability merely because ordinary earth was dug up, therefore, would not be justified; what would be required is a more precise determination of the end use of the excavated earth; a finding on the correctness of the stand of the builders that the extracted earth was not used commercially but was redeployed in the building operations. If the determination was to return a finding in favour of the claim made by the builders, obviously, the Notification dated 3.2.2000 would have no application; the excavated earth would not be a specie of minor mineral under Section 3(e) of the Act of 1957 read with the Notification dated 3.2.2000."

8.1. In the present case, it is clearly not in dispute that the

Petitioner has undertaken excavation of the earth on the said lands for

laying foundation of the buildings i.e. for development and

construction. The construction of buildings is in terms of the

14 of 21 wp.7390.10.doc

sanctioned development permission dated 14.05.2008 under the

provisions of Section 18 of the said Act read with permission for non-

agricultural user under the provisions of Section 44 of the MLR Code,

1966. The Respondents have also not alleged that there is commercial

exploitation of the excavated earth / minor minerals i.e. the earth

being excavated was sent outside or sold to anybody or transported by

the Petitioner. As held by the Supreme Court, the purpose of

excavation therefore needs to be considered. Any liability under the

provisions of Section 48(7) of the MLR Code, 1966 for excavation of

ordinary earth would truly depend on determination of the use /

purpose for which the excavated earth has been put to. An excavation

undertaken to lay the foundation of a building would therefore

ordinarily carry the intention to use the excavated earth / material for

the purpose of filling up or levelling as has been done in the present

case.

8.2. As observed by us, in the present case the excavated

material has been used by the Petitioner for the purposes of filling up

and levelling; digging of the earth is inbuilt in the course of building

operations; the activity so undertaken, therefore, cannot be

characterized as one of excavation of minor minerals as contemplated

under the Mines and Minerals (Development and Regulation) Act,

1957. We have considered and followed the decision pronounced by

15 of 21 wp.7390.10.doc

the Supreme Court in the case of Promoters and Builders Association

of Pune (supra) which has held that mere extraction of earth does not

invite the levy of royalty. In the said case, Promoters and Builders

Association of Pune had urged that the earth which is dug up for the

purposes of laying of foundation of buildings is intended for filling up

or levelling purposes as digging of the earth is inbuilt in the course of

building operations, the said activity cannot be characterized as one of

excavation of minor minerals and more particularly there was no

commercial exploitation of the excavated earth involved; neither there

was any sale or transfer of the excavated earth and the same was

incidental to the purpose of development / construction under a valid

development permission. The Supreme Court after analyzing the

provisions contained in Section 48(7) of the MLR Code, 1966 in

unequivocal terms held that the 'ordinary earth' used for filling or

levelling purposes in construction of embankments, roads, railways,

buildings though is a minor mineral, the liability under Section 48(7)

for excavation of ordinary earth would truly depend on a

determination of the use / purpose for which the excavated earth had

been put to. A blanket determination of liability merely because

ordinary earth was dug up, therefore, would not be justified; what

would be required is a more precise determination of the end use of

the excavated earth; a finding on the correctness would be required on

the stand of the builders that the extracted earth was not used

16 of 21 wp.7390.10.doc

commercially but was indeed redeployed in the building operations on

the same plot.

8.3. We may also state that the aforesaid decision of the

Supreme Court has been followed by a coordinate Bench of this Court

in the case of BGR Energy System Ltd, Khaparkheda Vs. Tahsildar,

Saoner 3 wherein the Petitioner had challenged the order of the

Tahsildar directing the Petitioner to pay royalty and penalty for illegal

excavation of earth while executing the work of construction of a

thermal power project at Khaparkheda. This Court after following the

decision in the case of Promoters and Builders Association of Pune

(supra), quashed and set aside the order of the Tahsildar holding, inter

alia, that use of the excavated earth to fill up the dug pits and any

construction of the project did not fall within the ambit of the

Notification dated 03.02.2000 and thus, the Tahsildar could not have

passed the order under Section 48(7) of the MLR Code, 1966. It is,

therefore, evident that the Supreme Court had enunciated in clear and

unambiguous terms that excavation of ordinary earth for construction

of building purposes / development would not attract levy of royalty

and penalty under the provisions of Section 48(7) of the MLR Code,

1966, especially when the excavated earth has been used for levelling

and development on the same plot.

3 2018(1) Mh.L.J. 332

17 of 21 wp.7390.10.doc

9. Respondent(s) have failed to place on record any

panchnama / evidence in order to justify the charge / claim made in

the notices dated 14.03.2009 and 23.12.2009 which state that the

Petitioner has unauthorizedly removed 12183 brass of earth, exploited

it commercially and transported the same. In the written submissions

filed on behalf of the State, the learned AGP in paragraph No.6 has

stated that the impugned notice dated 14.03.2009 clearly specified

that the Petitioner has not only excavated but also illegally transported

the excavated material which meant that the excavated soil / murum

was not utilized by the Petitioner to lay down the foundation of the

building. Therefore, according to the learned AGP, the ratio of the

Apex Court judgment in the case of Promoters and Builders

Association of Pune (supra) was not applicable to the Petitioner's case.

10. We have carefully perused the pleadings and annexures

placed before us by the parties. We do not find any evidence

pertaining to the Petitioner illegally transporting the excavated minor

minerals / materials from the construction site. Though it is alleged

that the Petitioner has excavated 12183 brass of minor minerals,

positive evidence is required to be placed on record to show that the

Petitioner has illegally transported the said minor minerals. The two

panchnamas dated 22.01.2009 and 01.09.2009 prepared by the Circle

Officer, Thergaon and the Circle Officer, Male have not been produced

18 of 21 wp.7390.10.doc

before us. There is no material evidence on record to show that the

Petitioner has transported or removed any earth / minor minerals

from the construction site. The Authorities, it appears have proceeded

on the premise that the very excavation of ordinary earth by the

Petitioner was subject to levy of royalty de-hors the use for which it

was put to. In view of the judgment of the Supreme Court in the case

of Promoters and Builders Association Pune ( supra) we are not

inclined to accept the submissions made on behalf of the

Respondent(s).

11. In so far as the grievance of the Petitioner in respect of

challenge to the impugned order dated 31.01.2011 is concerned,

though it may be stated that the Petitioner has alternate efficacious

remedy to challenge the said order passed by the Circle Officer, Mulshi

before the Appellate Authority under the MLR Code, 1966, according

to us no purpose shall be served to relegate the Petitioner to the

Appellate Authority in the facts and circumstances of the present case.

We have perused the order dated 31.01.2011 which is annexed at

Exhibit "T" to the Writ Petition. The said order has been passed solely

relying on the order dated 11.08.2010 passed by the Respondent No. 5

Tahsildar, Mulshi, inter alia, levying royalty, penalty and other charges

against the Petitioner despite the fact that the present petition was

pending on the date of passing of the said order. Though it is seen

19 of 21 wp.7390.10.doc

that ad-interim order was granted in the petition on 13.04.2011, the

act of cancellation of mutation entry by order dated 31.01.2011

recording the name of the Petitioner as owner of the said lands by

solely relying on the impunged order dated 11.08.2010 is not justified.

12. In view of the above discussion and findings, the

impugned show-cause notices dated 14.03.2009 and dated 23.12.2009

and the impugned order dated 11.08.2010 need to be interfered with

and deserve to be quashed and set aside. Since the order dated

11.08.2010 deserves to be quashed and set aside, the subsequent

order dated 31.01.2011 passed by the Respondent No.6 Circle Officer,

Mulshi solely relying upon the order dated 11.08.2010 also needs to

be interfered with and is required to be quashed and set aside.

Therefore, the Petition deserves to be allowed.

13. In view of the above, we pass the following order:

(i) The impugned show-cause notices dated

14.03.2009 and 23.12.2009 and order dated

11.08.2010 (being Exhibit Nos. "M", "O" and "Q" to

the Petition) issued / passed by the Respondent

No.5 Tahsildar, Taluka Mulshi, District Pune are

hereby quashed and set aside;

20 of 21 wp.7390.10.doc

(ii) The order dated 31.01.2011 (Exhibit "T" to the

Petition) passed by Respondent No.6 Circle Officer,

Mulshi is also quashed and set aside. The Mutation

Entry No. 7741 is directed to be restored in the

Record of Rights within a period of 4 weeks from

the date of this order being uploaded;

(iii) However, there shall be no order as to costs.

14. The above Writ Petition stands allowed in the above

terms.



 [ MILIND N. JADHAV, J. ]                              [ S.J. KATHAWALLA, J. ]

           Digitally signed
           by RAVINDRA
RAVINDRA   MOHAN
MOHAN      AMBERKAR
AMBERKAR   Date:
           2021.12.09
           14:31:45 +0530




                                                                              21 of 21
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter