Citation : 2021 Latest Caselaw 11767 Bom
Judgement Date : 25 August, 2021
16. wp 3540.21.doc
Urmila Ingale
Digitally
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
URMILA
signed by
URMILA
PRAMOD
CIVIL APPELLATE JURISDICTION
PRAMOD INGALE
INGALE Date:
2021.08.27
20:28:29
+0530
WRIT PETITION NO. 3540 OF 2021
WITH
INTERIM APPLICATION NO. 1657 OF 2021
Rupesh Dhirwani .... Petitioner
Vs.
The Electricity Ombudsman, Mumbai and ors. ..... Respondents
Mr.Mayur Faria, for the Petitioner.
Mr.S.M. Gorwadkar, Senior Advocate a/w Mr.Yogesh Morbale,
Ms.Vaishnavi Gholave i/b Mr.Vinod P. Sangvikar, for Respondent
No.2 and for Applicant in IA/1657/2021.
Mr.Sandeep S. Jinsiwale, for Respondent No.3.
CORAM : M. S.KARNIK, J.
DATE : 25th AUGUST, 2021
P.C. :
. Heard learned Counsel for the Petitioner. The
Petitioner by this Petition fled under Article 227 of the
Constitution of India challenges an order passed by the Electricity
Ombudsman, Mumbai appointed under the Maharashtra
Electricity Regulatory Commission under Section 42(6) of the
Electricity Act, 2003. It is the contention of the Petitioner that
originally a Company by name Asian Electronics was functioning
16. wp 3540.21.doc
in the plot no. 68 in MIDC area, Nashik. The power to the factory
was supplied through the switchgear provided by Maharashtra
State Electricity Distribution Company Limited (for short
'MSEDCL') which is situated in the said plot. It is the Petitioner's
contention that the Petitioner entered into the conducting
agreement sometime in the year 2013 with the Asian Electronics.
The electricity was being supplied through the switchgear which
is in the said plot no. 68. There is dispute about the sub-division
of the said plot according to the Petitioner. It is the contention of
the Petitioner that their factory is situated in the sub-divided plot
no. 68/4, but he has an agreement with Asian Electronics about
the electricity being supplied through said switchgear situated in
plot no. 68. It is the contention of the Petitioner that by virtue of
the agreement entered into with Asian Electronics, it is the
Petitioner who is entitled to utilize the electricity from the said
connection.
2. There is no dispute that Asian Electronics went in
liquidation. In proceedings fled before this Court in Company
Petition, plot no. 68 over which Asian Electronics was situated
was purchased by Respondent No.2 approximately for a sum of
Rs.11 crores. They therefore applied to Maharashtra State
Electricity Distribution Co. Ltd. (for short 'MSEDCL') for
16. wp 3540.21.doc
transferring electricity connection of Asian Electronics situated on
plot No. 68 in their name which was granted.
3. The Petitioner then approached the Consumer
Grievance Redressal Forum, MSEDCL when injunction was
granted in favour of the Petitioner on 09/08/2019. Then a
representation came to be made by the Respondent No.2 vide
Representation No. 162 of 2019 before the Ombudsman. The
said representation has been allowed and electricity connection
in the name of Respondent No.2 came to be confrmed. This
order is challenged by way of this Petition.
4. There is no dispute that so far as plot no. 68 is
concerned, the same stands in the name of Respondent No.2.
Further, so far as sub-divided plot no. 68/4 is concerned, in that
plot, the Petitioner is conducting its business pursuant to the
agreement entered into between them and Asian Electronics.
Now a dispute is being raised by the Petitioner that the plots are
never sub-divided. Factually, it is seen that there are factories
situated in the sub-divided portions in 68/1, 68/2, 68/4. Plot no.
68/3 is shown to be vacant. The Petitioner is carrying on its
activities in plot No. 68/4.
16. wp 3540.21.doc
5. I have gone through the fndings recorded by the
Ombudsman. A fnding of fact has been recorded that the
switchgear electricity connection is situated in plot no. 68 which
has been purchased by the Respondent No.2. By a reasoned
order and after considering the matter in detail, the Ombudsman
has made the following observations in paragraph 17 which
reads thus :
"17. My observations from the above discussion is as follows:
(i) The Appellant is the lawful owner/ occupier of Plot No. 68.
(ii) The agreement is executed between Arun Babulal Shah on behalf of Asian Electronics Ltd. as the owner, and Mohanlal K. Pahuja and Rupesh Dhirwani together as Conductor ( Respondent No.2) on 14.05.2013. Company Petition No. 492 of 2011 is admitted on 27.04.2012 and its judgment is dated 13.11.2014. Therefore, the said agreement is during the litigation period of the Company Petition No. 492 of 2011.
(iii) The second Lease Deed dated 09.01.1992 is between MIDC and Asian Electronics Ltd. which mentions subdivision of Plot No. 68 admeasuring 20780 sq. mtr. into fve plots at the request of Lessee (Asian Electronics Ltd.). This being so, how the agreement dated 14.05.2013 between Asian Electronics Ltd. and the Respondent No.2 can be for a Plot admeasuring 20780 sq. mtr. when it has already been subdivided into fve plots. Moreover, this agreement is neither registered nor notarized. I am of the opinion, that, such agreements/transfer requires permission from MIDC. However, no such permission from MIDC Authority seems to have been taken before execution of such agreement. Neither any separate permission
16. wp 3540.21.doc
letter is submitted before this Authority by the Respondent No.2. The original owner, Asian Electronics Ltd. appears to have created third party interest in the said property without valid permission from MIDC which is not allowed. Therefore, this agreement dated 14.05.2013 prima facie appears to be bad in law.
(iv) The Respondent No.2 submitted that power cable does not crossroad as no road as such exists. However, from the above table, it is clear that area of 1746 sq. mtr. has been surrendered for the access road by Asian Electronics Ltd. from 11970 sq. mtr. Therefore, the submission of Respondent No.2 is incorrect."
(emphasis supplied)
6. Having regard to the materials on record, it further
appears that there is a road passing between plot no. 68 and plot
No. 68/4. It is not as if an application was made by the
Petitioner for electricity connection and that the said switchgear
standing in the plot no. 68 was transferred in their favour. It is
the contention that pursuant to the conducting agreement that
the Petitioner had with the Asian Electronics, the Petitioner was
authorised to use the electricity which they have been utilising
all these years. The Petitioner has not placed any material to
show that they ever applied for electricity connection or that the
switchgear was transferred in their name. It is also seen from the
location map produced that the switchgear is in plot No. 68 and
16. wp 3540.21.doc
there is an internal road separating plot No. 68 (purchased by
Respondent No.2) & 68(4) (which belongs to the Petitioner). Now
it is tried to contend that the sub-division itself is illegal. This is a
claim made by the Petitioner on the basis of a conducting
agreement with Asian Electronics. The second lease deed
between MIDC & Asian Electronics mentions sub-division of plot
No. 68 into 5 plots. It is therefore not open for the Petitioner to
take this stand contrary to the stand of Asian Electronics from
under whom the Petitioner claims by virtue of conducting
agreement. It is obvious that the said stand is taken to
demonstrate that there is no sub-division, resultantly the
switchgear situated in undivided plot No. 68 can be claimed by
the Petitioner on the strength of the conducting agreement.
7. I see no perversity in the order passed by the
Ombudsman so as to warrant interference. The Petition is
dismissed. However, in the interest of justice, it is clarifed that
in the event the Petitioner makes an application for grant of
electricity connection for plot no. 68/4, the same be considered
expeditiously by MSEDCL preferably within a period of 8 weeks
from the date of the application. Further on the condition that
the Petitioner clears all the electricity dues within one week from
today, the Petitioner is permitted to utilise the electricity
16. wp 3540.21.doc
connection for a period of 8 weeks from today to enable the
Petitioner to make alternate arrangement and even learned
Senior Advocate for the Respondent No.2 does not object to this
arrangement. Learned Counsel for Respondent No.3 - MSCDCL
assures this Court that if an application for grant of electricity
connection is made by the Petitioner in the prescribed form, the
same will be considered expeditiously in accordance with Rules.
8. In view of dismissal of the Petition, nothing survives
for consideration in the interim application and the same stands
disposed of.
(M.S.KARNIK, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!