IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
INTERIM APPLICATION (ST.) NO. 92409 OF 2020
IN
FIRST APPEAL (ST) NO. 92406 OF 2020
Executive Engineer, Nandur
Madhyameshwar Project ... Applicant/Appellant
Vs.
Shivaji Laxman Shirsat & Ors. ... Respondents
-----
Ms. Chaitrali Deshmukh, Advocate for Applicant/Appellant. Mr. Yogesh Dabke, AGP for State-Respondent No.4.
-----
CORAM: ABHAY AHUJA J.
DATE : 18TH AUGUST, 2021 P.C.:
1. Heard learned counsel for the Applicant and learned AGP for
Respondent No.4.
2. Learned Counsel submits that by this application, Applicant is
seeking stay of the judgment and award dated 7 th August 2017 passed
by the Civil Judge, Senior Division, Nashik in LR No. 52 of 2010, with
respect to the Mukne Dam project in respect of which several other
Nikita Gadgil 1 of 2
32A. IAST 92409-20 in FAST 92406-20.odt
Appeals have also been filed in this Court.
3. Issue notice to Respondents, returnable on 17th September 2021.
4. Learned AGP waives service of notice on behalf of Respondent
No.4.
5. Applicant is permitted to serve by any legitimate mode of private
service and file affidavit of service with tangible proof thereof by the
next date.
6. List the matter on 17th September 2021.
(ABHAY AHUJA, J.)
Nikita Gadgil 2 of 2
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!