Citation : 2021 Latest Caselaw 10186 Bom
Judgement Date : 3 August, 2021
(1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
SECOND APPEAL NO.263 OF 2021
1) The Maharashtra Housing and Area
Development Authority (MHADA)
Through its Secretary,
Mantralaya Mumbai & Ors. = APPELLANTS
VERSUS
M/s Shiva Enterprises,
Through its Partner -
Dhoopnarayan s/o Rajkara Singh = RESPONDENT
-----
Mrs.Renuka V.Ghule,Advocate for Appellants;
Mr.JN Singh and Mr. AS Kulkarni, Advocates, for
Respondent.
-----
CORAM : SMT.VIBHA KANKANWADI,J.
RESERVED ON : 15/07/2021 PRONOUNCED ON : 03/08/2021
PER COURT :-
1. Heard learned Counsel appearing for
respective parties.
2. At the outset, the ratio laid down in
Ashok Rangnath Magar Vs. Shrikant Govindrao
Sangvikar - (2015) 16 SCC 763, wherein the Hon'ble
Apex Court held as under, is considered.
"18. In the light of the provision contained in Section 100 Civil Procedure Code and the ratio decided by this Court, we come to the following conclusion:-
(i) ...........................................................................;
(ii) In cases where the High Court after hearing the appeal is satisfied that the substantial question of law is involved, it shall formulate that question and then the appeal shall be heard on those substantial question of law, after giving notice and opportunity of hearing to the respondent;
3. Though it is not necessary to hear the
respondent at this stage; yet, an opportunity was
given.
4. Present appellants are the original
defendants. Present Respondent is original
plaintiff, who filed Special Civil Suit No.43/2008
for recovery of amount of Rs.65,70,282/- towards
construction costs of residential houses under
MHADA Scheme. That suit was decreed by learned 3 rd
Joint Civil Judge, Senior Division, Dhule on
9.4.2012. The defendants were directed to pay the
said amount to the plaintiff together with future
interest @ 12% p.a. from the date of the order till
realisation of the decreetal amount. The said
judgment was challenged by the appellants-original
defendants before the District Court, Dhule by
filing Regular Civil Appeal No.213/2018. The
appeal was heard by learned District Judge, Dhule
and it came to be partly allowed. The decree was
modified and the defendants were directed to pay an
amount to the tune of Rs.37,51,784/- with interest
@ 12% p.a. from the date of filing of the suit till
the date of the decree and 6% p.a. from the date of
the decree till actual payment. Now. The MHADA and
other appellants are before this court.
5. It has been vehemently submitted on
behalf of the appellants that both the Courts below
have not properly considered the evidence and the
law points involved. The conduct on the part of the
plaintiff-respondent was not considered and every
blame was put on the defendants. It ought to have
been considered as to how the plaintiff was not
cooperating and the activities were not done as per
the Schedule. Exaggerated costs were levied
towards the labour charges and other items by the
plaintiff, though there was no ground work done by
the plaintiff as per the contract. In fact, the
defendants have paid all the RA bills from time to
time. Even the plaintiff had accepted amount of
Rs.6,93,185/-, vide RA Bill No.6 dated 27.6.2003
without any objection and thereafter action of
imposing penalty was revoked and extension was
granted without imposing the penalties up to
31.12.2003. Though the decree has been modified by
the learned Judge of the First Appellate court; yet
he has also not considered certain points. Certain
amount under different heads are levied as per the
whims without there being any ground or base.
Under such circumstance, when there was absolutely
no base much less legal, for the claim; yet the
decree has been granted which leads to substantial
question of law. Further, a fact has been missed
by the learned District Judge that the judgment and
decree passed by learned Civil Judge, Senior
Division, was challenged before the High Court
initially, as at that time, the jurisdiction was
with this Court.
6. In Civil Application No.5310/2014, the
then Bench of this Court had directed the
appellants to deposit an amount of Rs.35,16,570/-
and accordingly, that amount has been deposited in
two installments. That amount has been withdrawn by
the plaintiff. Thereafter, as the pecuniary
jurisdiction of District Courts was enhanced, the
First Appeal was transferred from this Court to the
District court and those payment has not been
considered by the learned District Judge while
modifying the decree. As substantial questions of
law are arising in the appeal and substantial
payment has been made, stay deserves to be granted
to the impugned decree till the Second Appeal is
decided.
7. Per contra, learned Advocate appearing
for the respondent supported the reasons given by
both the Courts below and submitted that no
substantial questions of law are arising in this
appeal. The plaintiff was a reputed partnership
firm, dealing in civil constructions. In view of
the tender, the plaintiff had taken the work of
construction of 200 tenements out of 350 on Survey
No.471, 477 at Chalisgaon Road, Dhule. Though the
estimated cost of the tender work was Rs.
77,67,500/-, but the plaintiff had accepted it at
the cost of Rs.63,69,427.67 ps. Thereafter, as the
defendants, who had committed breach of the terms
and conditions of the contract, the Work order was
itself issued belatedly. Further, due to rainy
season, there was no progress in the construction.
It was difficult to excavate black soil in rainy
season. Defendant No.5 had, in fact, issued the
order for 168 tenements only instead of
construction of 200 tenements. There was no
separate provision made for up-rooting of the
Babool trees from the spot and that was made by the
plaintiff at his cost. The plaintiff had submitted
running bills from time to time, however, they were
not cleared and, therefore, the plaintiff was
entitled to get an amount of Rs.65,70,282/-
together with interest. All the documentary
evidence and oral evidence has been considered
properly and, therefore, no substantial questions
of law is arising in this appeal.
8. At the outset, it can be said that there
is no concurrent finding by the Courts below. The
Trial Court had decreed the suit in its entirety;
whereas the first Appellate Court has modified it
and the amount that is awarded is almost 50% less.
The learned First Appellate Court has not granted
the amount under certain heads though it was held
that the defendants have committed breach of the
terms of the contract. This also requires
admission of the appeal. Further, it appears that
the fact, that certain amount was deposited by the
defendants in this Court in view of the order
passed by the Division Bench of this Court in CA
No.5310/2014 on 11.7.2014, was not communicated and
considered by the learned First Appellate Court.
In view of the said order passed by the Division
Bench of this Court, the defendants had deposited
an amount of Rs.35,16,576/- and the same has been
withdrawn by the plaintiff. That deduction ought
to have been considered and made by the learned
first Appellate court while passing the decree.
Therefore, on both these counts, definitely,
admission of the Second Appeal is required as it
involves substantial questions of law. Hence, the
Second Appeal is admitted on the following
substantial questions of law, -
i) Whether both the Courts below
were justified in holding that the
defendants have committed breach of the contract ?
ii) Whether the learned Judge of the First Appellate court erred in granting
arbitrary amount under different heads to the Respondent-plaintiff ?
iii) Whether the first Appellate Court ought to have been given due credit to the amount, which has been withdrawn by the present respondent-plaintiff when the amount was with this Court ? In other words, whether there is suppression of withdrawal of the amount by the present respondent - plaintiff before the first Appellate Court ?
9. Issue notice to the respondent. Learned
Advocate waives notice for the respondent.
10. Call R and P.
(SMT. VIBHA KANKANWADI) JUDGE
BDV
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!