Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Dsl Enterprises Pvt. Ltd vs Maharashtra State Electricity ...
2018 Latest Caselaw 1271 Bom

Citation : 2018 Latest Caselaw 1271 Bom
Judgement Date : 13 March, 2018

Bombay High Court
Dsl Enterprises Pvt. Ltd vs Maharashtra State Electricity ... on 13 March, 2018
Bench: G.S. Patel
    DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd
                             916-CHSCDL246-18.DOC




 Arun



                                                              REPORTABLE


    IN THE HIGH COURT OF JUDICATURE AT BOMBAY
           ORDINARY ORIGINAL CIVIL JURISDICTION
                     IN ITS COMMERCIAL DIVISION
             CHAMBER SUMMONS (L) NO. 246 OF 2018
                                       IN
           EXECUTION APPLICATION NO. 422 OF 2018
                                       IN
             ARBITRATION PETITION NO. 374 OF 2004


DSL Enterprises Private Limited                                       ...Claimant

         ~ versus ~

Maharashtra State Electricity Distribution                      ...Respondent/

Company Ltd. Applicant

Mr Chirag Mody, with Mr Rahul Sinha i/b Lex Global Legal Consultant for the Applicant-Respondent. Mr RA Dada, Senior Advocate, with Mr Mukul Taly and Ms S Sridhar, i/b Mohamedbhai & Company, for the Claimant.

CORAM: G.S. PATEL, J DATED: 13th March 2018 ORAL JUDGMENT:

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

1. The Chamber Summons is filed by the Maharashtra State Electricity Distribution Company Limited ("MSEDCL"), the unsuccessful respondent to an arbitral award. These are the prayers in the Chamber Summons:

(a) That upon the Applicant depositing a sum of Rs.46,89,16,396/- this Hon'ble Court be pleased to declare that the arbitration award dated 18th June 2004 stands fully satisfied and the Applicant stands discharged therefrom;

(b) That this Hon'ble Court be pleased to raise attachment of Applicant's bank account being Schedule as attached in the Warrant of attachment dated February 22, 2018 vide warrant of attachment (Exhibit "A" hereto);

(c) That pending the hearing and final disposal of the Chamber Summons Applicant may be allowed to deposit an amount of Rs.46,89,16,396/- through Demand Draft no 977411 dated 6th February 2018 (Bank of Maharashtra) in satisfaction of the award dated 18th June 2004 and attachment of Applicant's Bank account being 0239256010710, Canara Bank, Tamarind Lane branch be raised;

2. The Chamber Summons was first moved on 24th February 2018. As I was unavailable that day, MSEDCL moved before AK Menon J. It cited 'grave urgency', and actually applied after court hours, saying that the attachment in execution of its bank accounts needed to be raised immediately. Given the time when it was moved, Menon J directed it be placed before the regular Bench on 26th February 2018. On that day, 26th February 2018, at the request of Mr Dada for the decree holder, DSL Enterprises Pvt Ltd ("DSL"), it was stood over by a day. On 27th February 2018, I passed an ad-

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

interim order. I will return to the details of this order presently, but in sum, since MSEDCL (a) deposited in Court (i) an amount of Rs.46,89,16,396 admittedly due to DSL; and (ii) an amount of Rs.98,54,06,315 claimed by DSL; and (b) made a statement in regard to a potential deduction of tax at source, I ordered the raising of the attachment of MSEDCL's bank accounts.

3. The parties then completed their filings, to the stage of a sur- rejoinder. I have now heard Mr Mody for MSEDCL and Mr Dada for DSL at some length. In my view, and for the reasons that follow, this entire application is not just untenable in law and unsupported by facts; it is purely dilatory, certainly vexatious and has resulted in a quite unforgivable waste of judicial time.

4. An abbreviated statement of facts is thus. On 18th June 2004, MSEDCL suffered an award in the amount of Rs.179 crores in an arbitration claim brought by DSL. The arbitral tribunal (Mr Justice VD Tulzapurkar, Mr Justice SC Pratap and Mr Justice ML Pendse) awarded interest at 10% per annum from the date of the award until payment. MSEDCL was also held liable to pay costs. These were quantified at Rs.1 crore, a very significant sum by any standards, and especially in 2004. There was no separate award of interest pendente lite.

5. MSEDCL filed a challenge Petition under Section 34 of the Arbitration Act. There were certain intervening events and proceedings, but these are not of immediate relevance to the present considerations. That challenge Petition was ultimately dismissed by

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

a learned single Judge of this Court (Mrs RS Dalvi J) on 18th March 2009. She imposed costs of Rs.1,00,000/- on MSEDCL.

6. DSL moved in execution and proceeded to attach MSEDCL's bank accounts. The single Judge hearing Execution Applications (SC Dharmadhikari J) directed MSEDCL to furnish a bank guarantee in the amount of Rs.75 crores and raised attachment on MSEDCL's bank accounts subject to fulfilment of that condition.

7. MSEDCL appealed under Section 37 of the Arbitration Act. On 2nd May 2009, a Division Bench ( JN Patel J, as he then was, and Mrs Mridula Bhatkar J) stayed the execution of the decree subject to two conditions; (i) that MSEDCL would deposit Rs.179 crores in Court before 29th June 2009; and (ii) that MSEDCL would furnish a bank guarantee for Rs.86 crores and would keep this alive until final disposal of the Appeal.

8. Both parties went to the Supreme Court against the 2nd May 2009 order. On 15th May 2009, the Supreme Court modified the High Court order. It directed MSEDCL to deposit Rs.65 crores in this Court and granted DSL the liberty to withdraw this upon DSL furnishing a bank guarantee. It also directed MSEDCL to furnish a bank guarantee for Rs.200 crores to the satisfaction of the Prothonotary and Senior Master of this Court. This bank guarantee was to be kept alive during the pendency of the Appeal.

9. A good four years went by until, on 19th October 2013, another Division Bench of this Court (VM Kanade and KR Shriram,

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

JJ) dismissed MSEDCL's Appeal under Section 37 of the Arbitration Act. The Division Bench also imposed costs on MSEDCL.

10. This was, therefore, the third order of costs against MSEDCL so far.

11. MSEDCL moved the Supreme Court in a Special Leave Petition against the order dismissing its Section 37 Appeal. On 28th November 2013, the Supreme Court passed an interim order directing MSEDCL to furnish bank guarantee of Rs.100 crores to the satisfaction of the Prothonotary and Senior Master; directing it to deposit Rs.100 crores in this Court; giving to DSL to withdraw this against a bank guarantee; and directing DSL to keep alive its bank guarantee previously furnished to the High Court while withdrawing Rs.65 Crores.

12. Early this year, on 18th January 2018, the Supreme Court dismissed MSEDCL's SLP against the High Court Division Bench order dismissing MSEDCL's Section 37 appeal. This dismissal was also accompanied by an order of costs. This is therefore the fourth order of costs against MSEDCL.

13. This Chamber Summons was then filed sometime in February 2018. On 27th February 2018, I passed the order I referred to earlier. Paragraphs 1, 2, 3 and 4 of that order read:

1. Mr Mody has two Demand Drafts. Both Demand Drafts are in favour of the Prothonotary and Senior Master.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

The first Demand Draft is in the amount of Rs.46,89,16,396/-. This is admittedly due by the Respondent to the Petitioner. This Draft will be deposited with the Prothonotary and Senior Master in the course of morning and will be deposited immediately in the course of the day. The Prothonotary and Senior Master will issue an instrument in favour of the Petitioner in this exact amount by the end of day tomorrow, 28th February 2018. Alternatively, payment may be made by the Prothonotary and Senior Master by RTGS to an account nominated by the Decree Holder.

2. The second Demand Draft is in the amount of Rs.98,54,06,315/-. This will also be encashed by the Prothonotary and Senior Master and will be invested initially for a period of 15 days. Further renewal will be subject to the orders of the Court.

3. Mr Mody states that an amount of Rs.15,12,50,893.09/- has been deducted as tax at source. Mr Dada submits that no TDS can be deducted on an award for damages. For the present I will record the undertaking by the Judgment Debtor to pay the amount in to the revenue as TDS within time. The amount of TDS will be retained by the Judgment Debtor on the understanding that specific undertaking that the question of whether or not tax is deductible at source will also be decided at the next hearing. In any case the Judgment Debtor has one month or 30 days to pay the amount to revenue. The matter will be listed before then. The undertaking is accepted as an undertaking to the Court.

4. In view of the foregoing, all bank accounts of the Judgment Debtor, The Maharashtra State Electricity Distribution Company Limited, are released from attachment or orders of freezing with immediate effect. An

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

authenticated copy of this order will be communicated to the Managers of the respective branches. They are directed to act on production of an authenticated copy of this order.

14. One further fact must be noted. On 3rd June 2009, DSL recorded partial satisfaction of the Arbitral Award or decree and it did so by showing that it had appropriated the amounts withdrawn (from the MSEDCL deposits made in Court) first towards interest and costs. It is actually this point that is at the heart of Mr Mody's case today on behalf of MSEDCL. His submission is that when the Division Bench ( JN Patel & Mrs Bhatkar JJ) directed a deposit of the principal amount and separately interest, this necessarily meant that the DSL was first required to make appropriations towards principal and then to interest, and could not do it the other way around. Mr Mody draws my attention to paragraph 9 of the order dated 2nd May 2009:

9. This contention is strongly opposed by the respondents on the ground that the respondents have been deprived of the amount for the last ten years which has led them to approach BIFR to get itself declared as a sick industrial unit as they were not paid their dues by the appellants under the contract which was the subject matter of arbitration proceedings till passing of the award in their favour and, therefore, the Court should direct the appellants to deposit the amount along with interest for which the order of attachment has already been passed by the Prothonotary and the award has been confirmed by the learned Single Judge. We are inclined to grant stay in favour of the appellants on the condition that the appellants shall deposit the principal amount which is in the sum of Rs.179 crores in this Court on or before

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

29th June 2009 and furnish a bank guarantee for the balance amount i.e. 86 crores and the bank guarantee may be kept alive till the appeal is heard finally and disposed of. Failure to deposit the amount and furnish the bank guarantee as directed would result in vacation of the stay order. On the amount being so deposited by the appellants, the Prothonotary & Sr Master would invest it in any nationalised bank as per the usual directions of this Court in respect of such investment of monies deposited by the parties in a term deposit initially for a period of one year. The appeal be listed before the Second Court on 29th June 2009 for hearing.

15. On the face of it the submission is untenable in law. How to appropriate an amount paid under or in partial satisfaction of a decree is always the sole prerogative of the decree holder. It is subject to only two exceptions: (i) where a court otherwise directs (either in the decree or in execution), or (ii) where the parties agree on the mode and manner of appropriation. Barring a judicial order directing a particular form, manner or mode of appropriation, or an agreement inter-partes, it is always for the decree holder to decide how he wishes to appropriate a payment made towards the decretal debt. As a general rule, the first thing almost always sought to be satisfied is the decree for interest and costs. The reason is plain. A decree that awards interest on a principal amount necessarily implies that interest keeps running on the base principal amount until the entirety of the decree is satisfied. Unless the decree so provides, there is no possibility of the judgment creditor on his own capitalising interest or compounding it, for that would amount to recovering interest on interest. It is for this reason that a prudent judgment creditor will always first apply any funds received towards

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

interest. If those are left unsatisfied or without appropriation they will remain in that amount and will not earn further interest. There is therefore a logical reason why appropriations are first made towards interest and costs. This is a well settled position in law.1

16. Second, the submission that once a deposit is made as a condition for stay on execution, the decree is automatically satisfied and interest stops running is prima facie incorrect. An order of deposit as a conditional stay is to provide security to the judgment creditor. It is only when the amount deposited is allowed to be withdrawn and it is actually applied towards satisfaction of the debt that there is a reduction of the decretal claim to the extent of that appropriation. If the amount of the appropriation is wholly consumed by being applied towards interest and costs, interest on the principal amount will continue to run. The situation will be slightly different, if after appropriating towards interest and costs there is an application towards a part of the principal claim. Then interest will run on the reduced principal debt.2

17. In PSL Ramanathan Chettiar & Ors v ORMPRM Ramanathan Chettiar,3 the Supreme Court enunciated the legal principle thus:

1 Industrial Credit & Development Syndicate v Smithaben H Patel & Ors, (1999) 3 SCC 80 (paras 6, 7 and 14); V Kala Bharathi & Ors v Oriental Insurance Company Ltd, (2014) 5 SCC 577 (paras19, 20, 26); Jet Airways (India) Ltd v Sahara Airlines Ltd & Ors, (2011) 113 (3) BLR 1725 (paras 49-51).

2 PSL Ramanathan Chettiar & Ors v ORMPRM Ramanathan Chettiar, AIR 1968 SC 1047 (paras 12, 13,15); Jet Airways, supra, (paras 44, 45,46); Sino Ocean Ltd v Salvi Chemical Industries ltd, 2017 SCC Online Bom 9401 (paras 23, 24), per KR Shriram J.

 3       AIR 1968 SC 1047.



                                  13th March 2018



DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

12. On principle, it appears to us that the facts of a judgment-debtor's depositing a sum in court to purchase peace by way of stay of execution of the decree on terms that the decree-holder can draw it out on furnishing security, does not pass title to the money to the decree-holder. He can if he likes take the money out in terms of the order; but so long as he does not do it, there is nothing to prevent the judgment debtor from taking it out by furnishing other security, say, of immovable property, if the court allows him to do so and on his losing the appeal putting the decretal amount in court in terms of Order 21 Rule 1 CPC in satisfaction of the decree.

13. The real effect of deposit of money in court as was done in this case is to put the money beyond the reach of the parties pending the disposal of the appeal. The decree-holder could only take it out on furnishing security which means that the payment was not in satisfaction of the decree and the security could be proceeded against by the judgment-debtor in case of his success in the appeal. Pending the determination of the same, it was beyond the reach of the judgment-debtor.

(Emphasis added)

This, I believe, is the principle to be applied.

18. The pronouncement of law by a three-Judge bench of the Supreme Court in V Kala Bharathi & Ors v Oriental Insurance Company Ltd4 is the clearest possible enunciation of the principle applicable.

 4       (2014) 5 SCC 577



                                  13th March 2018



DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

1. The short question to be answered in this appeal is whether the amount deposited by the judgment-debtor in a decree is to be adjusted first towards interest or towards principal decretal amount.

... ... ...

19. In Mathunni Mathai [Mathunni Mathai v. Hindustan Organic Chemicals Ltd., (1995) 4 SCC 26] , it was held that: (SCC p. 29, para 3)

"3. The right of the decree-holder to appropriate the amount deposited by the judgment-debtor, either in court or paid outside, towards interest and other expenses is founded both on fairness and necessity."

It was observed that: (SCC pp. 29-30, para 3)

"3. ... The courts and the law have not looked upon favourably where the judgment-debtor does not pay or deposit the decretal amount within the time granted as one cannot be permitted to take advantage of his own default. Therefore, the normal rule that is followed is to allow the deposit or payment, if it is in part to be adjusted towards the interest due, etc."

20. In Industrial Credit and Development Syndicate Ltd. [(1999) 3 SCC 80] , it has been held that in cases where the trial court has not prescribed any mode for payment of decretal amount, except fixing the instalments, in the absence of agreement between the parties, regarding the mode of payment of decretal amount, the general rule of appropriation of payments towards decretal

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

amount is that the said amount is to be adjusted firstly strictly in accordance with the directions contained in the decree and in the absence of such direction, it is to be adjusted firstly towards interest and costs and thereafter towards principal amount. This is, of course, subject to the exception that the parties can agree to the adjustment of payment in any other manner despite the decree. In that case, the Supreme Court had an occasion to consider the method of appropriation and after noticing various decisions of the English courts and the Privy Council, followed the judgment in Meghraj case [(1969) 2 SCC 274] .

26. In view of above and more particularly keeping in view the ratio of the Constitution Bench judgment in Gurpreet Singh [(2006) 8 SCC 457] , where considering an identical question in respect of Order 21 Rule 1 CPC, it was held that if the amount deposited by the judgment- debtor falls short of the decretal amount, the decree- holder is entitled to apply the rule of appropriation by appropriating the amount first towards interest, then towards costs and subsequently towards principal amount due under the decree; we are of the opinion that the appellants herein are entitled to the amount awarded by the executing court, as the amounts deposited by the judgment-debtor fell short of the decretal amount. After such appropriation, the decree- holder is entitled to interest only to the extent of unpaid principal amount. Hence, interest be calculated on the unpaid principal amount.

(Emphasis added)

19. If there is the slightest doubt about this principle, and I do not for a moment believe there is, it is buried by the emphatic

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

delineation of the law on the subject -- the precise question of appropriation absent a judicial direction or an agreement inter partes

-- by the Supreme Court's decision in Industrial Credit & Development Syndicate v Smithaben H Patel & Ors,5 referenced, as noted, in V Kala Bharathi. This is what the Supreme Court said in Industrial Credit & Development Syndicate:

6. In Venkatadri Appa Row v. Parthasarathi Appa Row [(1920-21) 48 IA 150 : AIR 1922 PC 233] the Judicial Committee of the Privy Council had held that upon taking an account of principal and interest due, the ordinary rule with regard to payments by the debtor unappropriated either to principal or interest is that they are first to be applied to the discharge of the interest. This Court in Meghraj v. Bayabai [(1969) 2 SCC 274 : (1970) 1 SCR 523] reiterated the position of law and held that the normal rule was that in the case of a debt due with interest, any payment made by the debtor was in the first instance to be applied towards satisfaction of interest and thereafter to the principal. It was for the debtor to plead and prove the agreement, if any, that the amounts paid or deposited in the Court by him were accepted by the creditor/decree-holder subject to the condition imposed by him. In that case the judgment-

debtor had urged that when the amount was finally submitted by the mortgagee they were aware of the fact that certain amounts had been paid conditionally and the withdrawal of the amounts deposited in the court amounted to acceptance of the conditions subject to which the amounts were deposited. In the facts and circumstances of that case this Court observed thus: (SCC p. 277, para 7)

5 (1999) 3 SCC 80.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

"But the account submitted by the mortgagees shows clearly that they had given credit for the amounts deposited towards the interest and costs in the first instance and the balance only towards the principal. The account submitted by the mortgagees clearly negatives the plea of the mortgagors."

The same is the position in the instant case as earlier noticed and evident from the statement of accounts (Annexure 'C') admittedly furnished to the judgment-debtor immediately after payment of the amounts consequent upon the passing of the decree. To the same effect is the letter (Annexure 'E') and statement of account accompanying it.

7. Order 21 Rule 1 of CPC provides the mode of paying money under the decree. Payments made to the decree- holder out of court are required to be certified for adjustment in terms of Rule 2 of Order 21 CPC. Where any money payable under a decree is paid out of court or is otherwise adjusted in whole or in part to the satisfaction of the decree, the decree-holder is to certify such payment and adjustment towards the court whose duty is to execute the decree. The judgment-debtor or any person who has become surety for the judgment-debtor has also a right to inform the court of such payment or adjustment applying to the court for the issuance of a notice to the decree- holder to show cause as to why such payment or adjustment be not recorded as certified and if, after service of such notice, the decree-holder fails to show cause why the payment or adjustment should not be recorded as certified, the court is obliged to record the same accordingly. No payment or adjustment can be recorded at the instance of the judgment-debtor unless it is made in

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

the manner provided under Rule 1 or the payment or adjustment is proved by documentary evidence or the payment or adjustment is admitted by, or on behalf of the decree-holder in a reply to the notice given to him under sub-rule (2) of Rule 1 Order 21 of CPC. In the absence of payment having been made in accordance with the mode prescribed or the satisfaction recorded under Rule 2, the judgment-debtor cannot claim the benefit of adjustment in the manner insisted upon by him.

8. In order to overcome the legal obstacles in their way, the judgment-debtors have sought refuge under the cloak of alleged protection provided by Section 60 of the Indian Contract Act, 1872. It is further submitted that in view of the later judgments of this Court in Mathunni Mathai v. Hindustan Organic Chemicals Ltd. [(1995) 4 SCC 26] and in Prem Nath Kapur v. National Fertilizers Corpn. of India Ltd. [(1996) 2 SCC 71] the law laid down in Meghraj case [(1969) 2 SCC 274 : (1970) 1 SCR 523] has to be held as no good law.

9. We are of the opinion that such a plea is far- fetched and begged only for the purpose of putting an imaginary defence to the claim of the appellant-decree- holder. Section 59 of the Indian Contract Act deals with the application of payment where debt to be discharged is indicated and Section 60 where debt to be discharged is not indicated. The aforesaid Sections 59 and 60 are reproduced below:

"59. Application of payment where debt to be discharged is indicated.--Where a debtor, owing several distinct debts to one person, makes a payment to him, either with express intimation, or under circumstances implying, that the payment is to be applied to

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

the discharge of some particular debt, the payment, if accepted, must be applied accordingly.

60. Application of payment where debt to be discharged is not indicated.--Where the debtor has omitted to intimate, and there are no other circumstances indicating to which debt the payment is to be applied, the creditor may apply it at his discretion to any lawful debt actually due and payable to him from the debtor, whether its recovery is or is not barred by the law in force for the time being as to the limitation of suits."

A perusal of Section 59 would clearly indicate that it refers to several distinct debts payable by a person and not to the various heads of one debt. The principal and interest due on a single debt or decree passed on such debt carrying subsequent interest cannot be held to be several distinct debts. A Full Bench of the Lahore High Court in Jia Ram v. Sulakhan Mal [AIR 1941 Lah 386 : ILR 1941 Lah 740] dealt with the scope of Section 59 to Section 61 of the Indian Contract Act and held:

"Sections 59 to 61, Contract Act, embody the general rules as to appropriation of payments in cases where a debtor owes several distinct debts to one person and voluntarily makes payment to him. They do not deal with cases in which principal and interest are due on a single debt, or where a decree has been passed on such a debt, carrying interest on the sum adjudged to be due on the decree.

These sections are based upon the rule of English Law, well settled since Clayton case

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

[(1816) 1 Mer 608 : 14 RR 166] that where a debtor, owing several distinct debts to one person, makes a payment to him intimating that the payment is to be applied in discharge of particular debt, the creditor, if he accepts the payment, must apply it accordingly. If, however, the debtor has omitted to intimate and there are no circumstances indicating to which debt the payment is to be applied the creditor may, at his discretion, apply it to any debt actually due and payable to him by the debtor at the time. In case neither party makes the appropriation, the payment is to be applied in discharge of the debts in order of time; and if the debts are of equal standing the payment is made in the discharge of each of them proportionately. It will be seen that these rules have no application to a case in which only one debt is due and at the time of payment, besides the principal sum secured, interest has also accrued due. In such cases, the rule of English Law, laid down as far back as 1702 in Chase v. Box [(1702) 2 Freeman 261 : 22 ER 1197] is that

'if a man is indebted to another for principal and interest and payeth the money generally, it shall be applied in the first place to sink the interest before any part of the principal should be sunk'.

In Parr's Banking Co. Ltd. v. Yates [(1898) 2 QB 460 : 67 LJQB 851 : 79 LT 821 : 47 WR 42 : (1895-99) All ER Rep Ext

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

1592] Lord Rigby, J. described it as 'the old and well-settled rule' that where both

'principal and interest are due the sums paid on account must be applied first to interest. That rule, where it is applicable is only common justice. To apply the sums paid to principal where interest has accrued upon the debt, and is not paid, would be depriving the creditor of the benefit to which he is entitled under his contract, and would be most unreasonable as against him'.

Fisher in his standard work on the Law of Mortgages (Edn.

7), p. 620, while dealing with the question of appropriation of payments towards a mortgage debt, states the law as follows:

'Where the debtor claims to be discharged by reason of payments which were not specially made in respect either of the principal or the interest of the mortgage, the rule is that a general payment shall be applied in the first place to sink the interest, before any part of the principal is discharged.' "

The judgment of the Lahore High Court is based upon sound principle and has kept in mind the intention of the legislature in enacting Sections 59 to 61 of the Act. We do not agree with the learned counsel for the respondents that Section 60 of the Contract Act has to be read independently excluding the provisions of Section 59. Accepting such an argument would amount to doing violence to the language employed in the section and the purpose sought to be achieved by it. Besides, it would also be contradictory in terms. Section 60, if applied

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

independently, cannot be held to be conferring any right upon the judgment-debtor as it confers a discretion in favour of the creditor to apply such deposited amount to any lawful debt actually due and payable by the debtor when such debtor omits to intimate the discharge of the debt in the manner envisaged under Section 59. We are of the opinion that Sections 59 and 60, Contract Act, would be applicable only in pre-decretal stage and not thereafter. Post-decretal payments have to be made either in terms of the decree or in accordance with the agreement arrived at between the parties though on the general principles as mentioned in Sections 59 and 60 of the Contract Act. As and when such an agreement either express or implied is relied upon, the burden of proving it would always be upon its propounder. The judgment-debtors, in the instant case, are proved to have failed in discharging such an onus. There does not appear to be any obligation on the decree-holder to intimate the judgment-debtor that the amount paid to him had not been accepted in the manner specified by him in the letter accompanying the payment. Insisting upon such a course would result in unnecessary burden upon the financial institutions and conferment of unwanted unilateral discretion in favour of the defaulters. Acceptance of the plea that the amount paid first should be adjusted in the principal amount would not only be against the provision of law but against the public policy as well. To provide security, continuity and certainty in business transaction, the legislature has been making specific provisions in that regard which may be found in various provisions of the Negotiable Instruments Act, 1881 or Order 37 Code of Civil Procedure and other statutory provisions.

14. In view of what has been noticed hereinabove, we hold that the general rule of appropriation of payments towards a decretal amount is that such an amount is to

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

be adjusted firstly, strictly in accordance with the directions contained in the decree and in the absence of such direction, adjustments be made firstly in payment of interest and costs and thereafter in payment of the principal amount. Such a principle is, however, subject to one exception, i.e., that the parties may agree to the adjustment of the payment in any other manner despite the decree. As and when such an agreement is pleaded, the onus of proving is always upon the person pleading the agreement contrary to the general rule or the terms of the decree schedule. The provisions of Sections 59 to 61 of the Contract Act are applicable in cases where a debtor owes several distinct debts to one person and do not deal with cases in which the principal and interest are due on a single debt.

(Emphasis added)

20. Mr Mody relies on the decision in Himachal Pradesh Housing and Urban Development Authority & Anr v Ranjit Singh Rana6 and Union of India & Anr v MP Trading & Investment RAC Corporation Ltd.7 I do not believe either of these cases assists MSEDCL. In Ranjit Singh Rana the entire amount due under the award was deposited in the Himachal Pradesh High Court even before the challenge petition was dismissed, i.e. before the award became enforceable and could be put into execution. The deposit was specifically towards satisfaction of the award (paragraph 15). In the present case, the deposits were ad hoc amounts. The amount of Rs.65 crores deposited by MSEDCL pursuant to the 15th May 2009 Supreme Court order was less even than the interest by then due,

6 (2012) 4 SCC 505.

 7       (2016) 16 SCC 699.



                                  13th March 2018



DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

about Rs.80 crores. Further, the deposits were not of the decretal debt or the amount of the award but were pre-conditions to stay of execution; there was no such issue in Ranjit Singh Rana. There was, therefore, no 'payment of the decretal debt' or 'payment under the decree' within the meaning of the formulation in Ranjit Singh Rana. Indeed, this is why Ranjit Singh Rana does not reference the three- Judge bench decision in Ramanathan Chettiar.

21. MP Trading is on similar lines, for here, too, the entire amount of the award was deposited before the Section 34 petition was dismissed, i.e. before the award could be put into execution. The direction for deposit was by the Section 34 court, and was not ordered as a pre-condition to stay of execution. it could not have been; because, before the Section 34 court, so long as that petition was pending, there was nothing to execute, and therefore no execution of which any stay could be sought. In any case, MP Trading is said to have been decided on its facts (paragraph 5), and it therefore has no discussion about 'appropriation' of any amount towards interest or principal; again, there could not have been, because the award holder made no withdrawal at all.

22. The argument that MSEDCL advances today is, therefore, contrary to nearly four centuries of settled law. Viewed from this perspective, the submission that because of the Division Bench order, DSL ought to have first appropriated such amounts as it was allowed to withdraw (against a bank guarantee) towards satisfaction of the principal is a submission that is entirely without legal foundation. This in itself is sufficient to warrant a dismissal of the Chamber Summons.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

23. The order of 2nd May 2009 ( JN Patel and Mrs Mridula Bhatkar JJ), set out above, in terms says that the matter was being considered only on the question of stay (of execution and of the award). Here is the relevant passage again:

We are inclined to grant stay in favour of the appellants on the condition that the appellants shall deposit the principal amount which is in the sum of Rs.179 crores in this Court on or before 29th June 2009 and furnish a bank guarantee for the balance amount i.e. 86 crores and the bank guarantee may be kept alive till the appeal is heard finally and disposed of.

It simply cannot be argued that the deposit was required for payment of the decretal debt. It was clearly only as a pre-condition to stay of execution, a very different thing. To say otherwise is to deliberately twist the words of the Appeal Court. Second, the mere mention of the words 'principal' and 'interest' do not and cannot amount to a direction to pay the amount. They are used only to compute or reckon the amount of the deposit required in order to grant stay. Third, this order was modified by the Supreme Court's order of 15th May 2009. In that order, the Supreme Court granted leave (in DSL's Special Leave Petition). It modified the order of deposit, again as a pre-condition to a stay of execution. Paragraph 5 of the 15th May 2009 order says:

"5. Having regard to the facts and circumstances, we are of the view that the terms subject to which a stay has been granted require modification."

In paragraph 6, the modified terms are set out; and these make no reference to the principal and interest at all. MSEDCL's deposit was

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

fixed at Rs.65 crores. It had to give an unconditional bank guarantee of Rs.200 crores. Stay was granted on that basis. It is, therefore, futile to refer to the High Court Division Bench order in support of a case for appropriation, when that order was entirely modified and substituted, with no mention of either principal or interest, by the Supreme Court in appeal.

24. At no point, therefore, did any court require any deposit in payment of the decretal debt or direct appropriation of withdrawals in any particular mode or manner. There was also, clearly, no agreement between the parties about the mode of appropriation. Neither of the two exceptions to the general rule are met.

25. Therefore, in regard to the principal argument that MSEDCL's deposits pursuant orders of the Division Bench and the Supreme Court were either clearly directed towards payment of the principal or must be deemed to have so been, it is sufficient to note that in every one of those orders the only question before the Court was in regard to a stay of execution of the decree. The fact that one or the other Court specified deposit of some amount in cash and some amount as a bank guarantee makes no difference. This is only a matter of convenience and to lessen the execution burden on the judgment creditor. None of these orders, I note, prescribed any mode of satisfaction of the decree. None of these orders said that the amount or amounts withdrawn by DSL were to be appropriated in any particular fashion. Consequently, the general rule giving primacy to the decree holder to decide how best to effect that appropriation was never even touched by any of the orders of the Division Bench or of the Supreme Court.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

26. Mr Dada makes a further point. He says it is on account of the non-recovery of this debt and MSEDCL's frivolous objections to DSL's claim that DSL was run into the ground. The amounts in question, he submits, are not trivial. They materially and directly affected DSL's cash flow. It had to seek BIFR protection. One of the consequences was that it had difficulty for a great period of time in even effecting the necessarily withdrawals, thus pushing into a further downward spiral. The submission undermines what little remains of MSEDCL's case today. The necessary implication is that any amount that DSL withdrew was on a purely ad hoc basis without there even being a notional break up between principal and interest; and, in any case, the withdrawal was against security furnished by DSL in the form of a bank guarantee, i.e. a withdrawal with a condition attached of guaranteed restitution. The decree was always one, of principal and continuing interest. There was no distinction between how much DSL could, on withdrawal, apply towards principal and how much towards interest. That clearly left DSL at large to make appropriations of these ad hoc withdrawals in such manner as it thought fit.

27. What Mr Mody asks of me is to read into the orders of the Appeal Court and the Supreme Court words not there, and to arrive at a conclusion entirely tailored to MSEDCL's convenience -- rather than law -- by a process of interpolating alternative meanings into those very clear orders. That is something I will not and cannot do.

28. Finally, this: the entire application is nothing more than a latter-day epiphany. If what MSEDCL says today is correct, then it

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

must explain why, at no point in time before this application, has it ever sought a clarification or a direction from the Court or Courts that made orders of deposit and withdrawal in regard to the appropriation of the withdrawals. MSEDCL was aware of its liability under the arbitral award. It knew of the decree it faced. It knew what it had to deposit, and what DSL was allowed to withdraw. It had enough opportunities to seek a clarification. MSEDCL never did. It sat by. It is only when everything is over bar the shouting that it comes up with this quite extraordinary sophistry. We should not mistake the singular purpose of the application: to evade, by any means at all, even at the risk of raising an argument solidly against established legal principle, a portion of its decretal liability. As we shall shortly see, this runs to a pattern that marks MSEDCL's conduct from the time of the contract in question, even before the arbitral award.

29. There is one further aspect to be addressed. Mr Mody has a concern that MSEDCL must deduct tax at source on the decretal interest awarded. Again, this is incorrect. We should not be misled by the mere use of the word 'interest'. For the purposes of the Income Tax Act, this is not interest "earned" as it might be on a fixed deposit or an investment. This is interest in the form of mitigation of a loss. When interest is awarded on a decree it forms part and parcel of the decree itself. It no longer retains its character as 'interest'. We use word interest only as a term of art, for convenience, or of want of a better expression. A decree that awards interest for a past period is actually only compensating the decree holder for that which he might have earned had he not been put to the loss. It represents an opportunity cost. There is therefore no

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

question of MSEDCL having any liability to the revenue to deduct income at source. It must pay the amount to the Decree Holder. The tax liability of the Decree Holder, DSL, is a matter that DSL itself will address and it is of no concern of MSEDCL.8

30. In my view there is absolutely no substance to this Chamber Summons. It deserves to be dismissed. It is.

31. The only question that remains is whether there should be another -- a fifth in sequence -- order of costs. In this, I do not believe I have any choice in the matter at all. This is an Execution Application in the Commercial Division. The Commercial Courts, Commercial Division and Commercial Appellate Division of High Courts Act, 2015 ("the Commercial Courts Act"), effected sweeping changes to the Code of Civil Procedure 1908 ("CPC"). Among those changes were significant changes to Section 35 of the CPC. The Commercial Courts Act substituted an entirely new Section 35 applicable to commercial matters covered by the new Act.

32. In its 253rd Report, the Law Commission of India, then under the chairmanship of Mr Justice AP Shah, former Judge of this Court and former Chief Justice of the Delhi High Court, in regard to the Bill proposing the Commercial Courts Act said:9

8 Madhusudan Shrikrishna v Emkay Exports & Ors, 2010 (2) BCR 38;

Islamic Investment v Union of India, 2002 (4) BCR 685; Sino Ocean, supra, paras 27 and 28.

9 Law Commission of India, 253rd Report, January 2015, Section F(ii), pp. 45-47.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

3.21.1 As recommended by the Supreme Court of India and the Law Commission, costs will have to follow the event as a meaningful deterrent against frivolous litigation. In the Sahara judgment [Subrata Roy Sahara v Union of India, (2014) 8 SCC 470, at para 150], the Court observed:

He [the innocent suffering litigant] spends invaluable time briefing counsel and preparing them for his claim. Time which he should have spent at work, or with his family, is lost, for no fault of his. Should a litigant not be compensated for, what he has lost, for no fault? The suggestion to the legislature is, that a litigant who has succeeded, must be compensated by the one, who has lost. The suggestion to the legislature is to formulate a mechanism, that anyone who initiates and continues a litigation senselessly, pays for the same. It is suggested that the legislature should consider the introduction of a "Code of Compulsory Costs.... The effort is only to introduce consequences, if the litigant's perception was incorrect, and if his cause is found to be, not fair and legitimate, he must pay for the same.

3.21.2 In Rameshwari Devi v Nirmala Devi [(2011) 8 SCC 249, at para 55], the Supreme Court noted that another factor to be considered while imposing costs is "for how long the defendants or respondents were compelled to contest and defend the litigation in various courts."

3.21.3 Therefore, the proposed 2015 Bill shall also contain a clause ensuring that costs shall necessarily follow the event in all cases, except where the court gives reasons in writing explaining why costs should

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

not follow. The model of costs proposed in the amendments to the A&C Act, 1996 by the Law Commission in its 246th Report will also be adopted in this Bill. This will entail amendments to Section 35 and Section 35-A of the CPC, which govern the award of costs.

3.21.4 As proposed in the amendments to the A&C Act, 1996 in awarding costs, the court/arbitral tribunal will have regard to all circumstances including-

                  a)       The conduct of all parties;

                  b)     Whether a party has succeeded in part of

its case, even if the party has not been wholly successful;

c) Whether the party had made a frivolous counter claim leading to delay in the disposal of the case;

d) Whether any reasonable offer has been made by a party to settle; and

e) Whether the Party had made a frivolous claim and instituted a vexatious proceeding wasting the time of the Court.

3.21.5 "Costs" here will mean reasonable costs relating to:

a) fees and expenses of the arbitrators, courts and witnesses;

                  b)       Legal fees and expenses; and

                  c)     Any other expenses incurred in connection
                  with the proceedings.

3.21.6 It is proposed to adopt the above model with suitable changes, to empower the Commercial Divisions

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

and Commercial Courts to award costs along the above lines, and to also make it mandatory to give reasons for not awarding costs. This, it is intended, will deter parties from making frivolous claims or engaging in vexatious litigation, thereby adding to the burden of pendency and delays.

(Emphasis added)

33. Amended Section 35 reads thus:

Costs.

35.(1) In relation to any commercial dispute, the Court, notwithstanding anything contained in any other law for the time being in force or Rule, has the discretion to determine:

(a) whether costs are payable by one party to another;

                  (b)      the quantum of those costs; and

                  (c)      when they are to be paid.

Explanation. For the purpose of clause (a), the expression costs shall mean reasonable costs relating to

(i) the fees and expenses of the witnesses incurred;

(ii) legal fees and expenses incurred;

(iii) any other expenses incurred in connection with the proceedings.

(2) If the Court decides to make an order for payment of costs, the general rule is that the

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

unsuccessful party shall be ordered to pay the costs of the successful party:

Provided that the Court may make an order deviating from the general rule for reasons to be recorded in writing.

Illustration

The Plaintiff, in his suit, seeks a money decree for breach of contract, and damages. The Court holds that the Plaintiff is entitled to the money decree. However, it returns a finding that the claim for damages is frivolous and vexatious.

In such circumstances the Court may impose costs on the Plaintiff, despite the Plaintiff being the successful party, for having raised frivolous claims for damages.

(3) In making an order for the payment of costs, the Court shall have regard to the following circumstances, including--

(a) the conduct of the parties;

(b) whether a party has succeeded on part of its case, even if that party has not been wholly successful;

(c) whether the party had made a frivolous counterclaim leading to delay in the disposal of the case;

(d) whether any reasonable offer to settle is made by a party and unreasonably refused by the other party; and

(e) whether the party had made a frivolous claim and instituted a vexatious proceeding wasting the time of the Court.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

(4) The orders which the Court may make under this provision include an order that a party must pay

(a) a proportion of another party's costs;

(b) a stated amount in respect of another party's costs;

                  (c)      costs from or until a certain date;

                  (d)    costs incurred before proceedings have
                  begun;

(e) costs relating to particular steps taken in the proceedings;

(f) costs relating to a distinct part of the proceedings; and

(g) interest on costs from or until a certain date. .

Amendment of section 35A.

3. In section 35A of the Code, sub-section (2) shall be omitted.

(Emphasis added)

34. The amended CPC clearly says that the general rule is that the unsuccessful party will be ordered to pay the costs of the successful party. There is a proviso. It says that I may make an order deviating from this general rule, but I can only do so for reasons to be recorded in writing. The amended Section also tells us that in making an order of costs I must have regard to the conduct of the parties and whether, inter alia, the party made a frivolous claim or instituted a vexatious proceedings wasting the time of the Court.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

The restriction in Section 35-A(2) is removed; Section 35-A(1), for compensatory costs, remains. Section 35(4) then says that the order of costs would include an order that the party must pay a proportion of the other sides costs, a stated amount in respect of the other party's costs, cost from a given date and so on. There is also a provision for interest on costs in Section 35(4)(g). The amended Section 35 of the CPC also says that it prevails over any other law for the time being in force or any other rules. It would thus prevail over any other provisions in the CPC as also any provisions in the Bombay High Court Original Side Rules.

35. I am actually unable to even envision any reasons that might fall within the proviso to the general rule. The only submission from Mr Mody, somewhat predictably, is that MSEDCL is a government company and these are public funds. The second submission is that the entire Chamber Summons is based on orders of the Court, and therefore no costs should be imposed.

36. I do not believe these are even remotely compelling. The application from MSEDCL is, if anything, too clever by half. It is an application that ought never to have been made. There is no basis for this in law. It is contrary to centuries-old settled law. The fact that MSEDCL has pursuant to the orders of this Court including my order of 28th February 2018 deposited amounts in Courts is not an excuse. This matter has today consumed over a fifth of the court working day for no good reason. Time has been spent before as well. Mr Dada submits that through out from the very beginning and going back to the stage of the arbitral proceedings, the conduct of MSEDCL was to take every conceivable, and, very often, even

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

inconceivable defences only to obstruct. Mrs Justice Dalvi observed that MSEDCL's Petition under Section 34 was an attempt to escape liability for fundamental breaches. The Arbitral Tribunal (of three eminent and generally conservative judges on questions of costs) were moved to impose costs of Rs. 1 crore (though DSL sought much more) -- and that was 14 years ago, in 2004. The arbitrators said, even then, that MSEDCL raised 'untenable and unsustainable defences which led to considerable delay in concluding the proceedings'. A Division Bench of this Court imposed further costs. Even the Supreme Court had occasion to comment adversely on the conduct of MSEDCL. If the argument is that MSEDCL is a custodian of public funds, then that actually warrants a direction that the costs I now award ought to be recovered from the salaries of its officers who authorised the filing of this Chamber Summons. It is not a reason to make an exception to the general rule. As a custodian of public funds, MSEDCL was duty bound to be more circumspect and cautious in the applications that it made.

37. The Arbitral Tribunal imposed costs of Rs.1 crores. That was in 2004 well before the Commercial Courts Act. Mrs Justice Dalvi imposed cost of Rs.1,00,000/-, a significant amount in those days and also prior to the present Act. In this context, some observations by the Supreme Court in its order dated 18th January 2018 in paragraph 42 may be usefully reproduced. Here, the Supreme Court culled out the salient findings in the arbitral award.10

42) Reasoning contained in the Award reveals following salient findings returned by the Arbitral Tribunal:

10 MSEDCL was the appellant before the Supreme Court.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

(i) The appellant prevented respondent No.2 from performing the contract.

(ii) Respondent No.2 was ready and willing to perform the contract all throughout.

(iii) The appellant chose not to examine any of its Superintending Engineers who were in- charge for giving DTC locations to respondent No.2 and as found by the Arbitral Tribunal, they were the kingpins of each circle for performance of the contract.

(iv) There is considerable merit in the submission of respondent No.2 that the Minutes of the Meeting dated 24th June 1998 is a fabricated document.

(v) It is not possible to accede to the submission of the appellant that respondent No.2 had adequate lists of locations available and still failed to install the contract objects.

(vi) It is obvious that there is something seriously wrong in the working of the appellant. Once a letter is listed in the affidavit of documents, it is surprising how the letter was not traceable. Be that as it may, the fact remains that prior to the date of termination of contract, at least in three Circles, the appellant had directed stoppage of installation work.

(vii) It is unfortunate that the Head Office of the appellant lacked control over the field offices and which ultimately led to the failure of the project. It is futile to even suggest that the breach was not a fundamental one.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

(viii) Respondent No.2 was ready and willing to perform their part of the contract while the appellant committed a breach by failure to supply DTC locations as per the terms of the contract.

(ix) Respondent No.2 invested Rs. 163 crores in the project.

(x) The appellant failed to prove that deductions effected in the Performance Certificates were proper.

(xi) The appellant indulged in tampering the commissioning reports produced on record. The attempt does not behove a statutory body and requires to be deprecated. The attempt made by the appellant by producing documents which are tampered with and which are not genuine indicates that the appellant was willing to go to any extent to make allegations against respondent No.2.

(xii) The appellant did not make available large number of documents disclosed in the affidavit of documents on the ground that the same are not available.

(xiii) Counter claim of the appellant is misconceived and is nothing short of counter blast to the claim made against respondent No.2.

(xiv) It was the appellant and appellant alone who had committed fundamental breaches of the terms of the work order.

(xv) The appellant has raised untenable and unsustainable defences which led to

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

considerable delay in concluding the proceedings.

These are finding of facts base upon the material evidence that emerged on the record of the case.

(Emphasis added)

38. These findings were approved by the Supreme Court. It found no merit at all in MSEDCL's appeal, which it dismissed. The arbitral findings culled out in the Supreme Court decision, and quoted above, are oddly prescient: those findings pre-dated the Commercial Courts Act by a full decade or more, and yet the wording of those findings is echoed in the Commercial Courts Act: untenable and unsustainable defences, a frivolous defence, and a frivolous counter-claim. And yet more: there are factual findings, now having attained finality, of tampering, fabrication and falsification -- all against the very body that claims it is a 'custodian of public funds', and therefore, presumably, in some way sanctified if not actually canonized. But that 'custodian' has been found to be wholly remiss in discharging its public duties. This brings to bear the provision in the amended Section 35, and its sub-clauses, set out fully above. There is no doubt at all in my mind that this application is entirely frivolous and is just another attempt to delay the inevitable. I believe it is time that we sent out a signal that these practices must stop and the Government authorities must take responsibility for their actions. Further, the Commercial Courts act has only deleted the restriction in Section 35-A(2), not the provision for compensatory costs in Section 35-A(1).

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

39. Having regard to the provisions of substituted Section 35, there will be an order of costs against MSEDCL in the amount of Rs.30,00,000/-. The amount is, in my view, not unreasonable. I have had to hear the parties on at least three occasions. The filings have gone to the stage of a sur-rejoinder. These costs are not merely compensatory. That is why I have set out the recommendations of the Law Commission and, in extenso, the provisions of the amended CPC. The statutory intent is to use costs, which are the general rule of "you lose you pay", as a deterrent to prevent frivolous litigation. That kind of litigation, as the Supreme Court itself said, is an unacceptable clog and burden on the judiciary. A party must know before it embarks on any judicial misadventure that if it puts up a case found to be useless, it will have to pay a price, and a steep price at that.

40. In Dnyandeo Sabaji Naik v Pradnya Prakash Khadekar,11 the Supreme Court said:

14. Courts across the legal system--this Court not being an exception--are choked with litigation. Frivolous and groundless filings constitute a serious menace to the administration of justice. They consume time and clog the infrastructure. Productive resources which should be deployed in the handling of genuine causes are dissipated in attending to cases filed only to benefit from delay, by prolonging dead issues and pursuing worthless causes. No litigant can have a vested interest in delay. Unfortunately, as the present case exemplifies, the process of dispensing justice is misused by the unscrupulous to the detriment of the legitimate. The

11 (2017) 5 SCC 496.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

present case is an illustration of how a simple issue has occupied the time of the courts and of how successive applications have been filed to prolong the inevitable. The person in whose favour the balance of justice lies has in the process been left in the lurch by repeated attempts to revive a stale issue. This tendency can be curbed only if courts across the system adopt an institutional approach which penalises such behaviour. Liberal access to justice does not mean access to chaos and indiscipline. A strong message must be conveyed that courts of justice will not be allowed to be disrupted by litigative strategies designed to profit from the delays of the law. Unless remedial action is taken by all courts here and now our society will breed a legal culture based on evasion instead of abidance. It is the duty of every court to firmly deal with such situations. The imposition of exemplary costs is a necessary instrument which has to be deployed to weed out, as well as to prevent the filing of frivolous cases. It is only then that the courts can set apart time to resolve genuine causes and answer the concerns of those who are in need of justice. Imposition of real time costs is also necessary to ensure that access to courts is available to citizens with genuine grievances. Otherwise, the doors would be shut to legitimate causes simply by the weight of undeserving cases which flood the system. Such a situation cannot be allowed to come to pass. Hence it is not merely a matter of discretion but a duty and obligation cast upon all courts to ensure that the legal system is not exploited by those who use the forms of the law to defeat or delay justice. We commend all courts to deal with frivolous filings in the same manner.

(Emphasis added)

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

Therefore, in imposing costs as I do, I am following a mandate directed by the Supreme Court. In my reading of it, the decision tells us that we have no choice at all. If we do not deal with frivolous cases most firmly, then the structure of our judiciary and its functioning are imperilled.

41. The Law Commission Report and the amendment both say the costs must be reasonable. But what is 'reasonable' must be governed not by some misplaced sense of awe of money, or a terror of large amounts. Our hands must be guided by the dictum of the Supreme Court in decisions like Dnyandeo Sabaji Naik, especially in commercial matters where the stated legislative intent is to use costs, as a general rule, to discourage litigation frivolities. None should be able to 'take a chance on' or gamble in courts. No one has a vested right to delay a case or the enforcement of a decree. The costs regime, as re-engineered by the Commercial Courts Act, has several components. Costs are to function as a deterrent. They are to be realistic, not illusory (and most certainly not the price of a couple of coconuts and a cup of coffee). They may also be exemplary or punitive, as the Supreme Court says, especially when a court finds, as I have, that the case of the party made to suffer costs is thoroughly without merit. I have, here, not the slightest doubt that MSEDCL's only attempt is to persist in the dishonesty and illegality that seem to have stamped its conduct from the get-go. The words of the Supreme Court summarizing the arbitral findings are enough to alarm even the most jaded judicial conscience. That a public body should be found guilty on evidence of fabrication and manipulation is unthinkable. What remains of public governance if this is how statutory bodies conduct themselves? Despite all that has gone

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

before, MSEDCL still claims 'rights' in regard to its decretal debt. It has none. The costs I award today are, in my view, not unreasonable having regard to the costs that DSL must have incurred, the waste of judicial time, and the utter lack of substance in the MSEDCL's application, and the frivolous and speculative nature of the application. This order of costs therefore combines elements of amended Section 35, Section 35-A(1) and the mandate of the Supreme Court in Dynandeo Sabaji Naik.

42. There will be interest on the amount of costs computed at 10% from today.

43. Mr Mody is instructed to say that MSEDCL deposited the entire debt and therefore there should be no order of costs. That deposit was too little too late. It was made only after my order of 27th February 2018. It was also a pre-condition to hearing this application, one that comes so very late in the day. There was no deposit of the entire decretal debt at any time before, and, as we have seen, there is a marked difference between this case and authorities cited by Mr Mody. This argument is of no avail in any context.

44. The amount deposited pursuant to my order dated 27th February 2018 will be allowed to be withdrawn with all accrued interest. The Prothonotary and Senior Master will make payment to DSL either by a physical instrument or by RTGS to an account that it designates. The Prothonotary and Senior Master will act on production of an authenticated copy of this order.

13th March 2018

DSL Enterprises Pvt Ltd v Maharashtra State Electricity Distribution Co Ltd 916-CHSCDL246-18.DOC

45. Mr Dada makes a statement that the DSL will give MSEDCL credit for the interest earned on the deposit made by MSEDCL upon receipt of the amount from the Prothonotary and Senior Master. That statement is noted and accepted.

46. Order accordingly.

(G. S. PATEL, J)

13th March 2018

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter